Citation : 2022 Latest Caselaw 8093 Bom
Judgement Date : 20 August, 2022
- Judgment A.A.No.03.2022.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR
ARBITRATION APPEAL NO. 03 OF 2022
1 National Highways Authority of India
(Ministry of Road Transport and Highways)
Through its Project Director,
Project Implementation Unit - 1, Nagpur,
Office at Hill Top, Nagpur, Tah. & Dist. Nagpur.
.. Appellants
2 Secretary, Government of India
(Ministry of Road Transport and Highways),
Dwarka, New Delhi.
Versus
1. The Additional Commissioner, Nagpur and .. Respondents
Arbitrator under the National Highways
Act,1956.
Having office at Old Secretariat Building,
Civil Lines, Nagpur - 440 001.
2. The Deputy Collector, Land Acquisition
(General)
and Competent Authority, National Highway
Authority, Collector Compound, Nagpur.
3. Shri Nareshchandra Maheshchandra Agrawal,
Aged about 60 years, Occ.: Business,
R/o. Plot No.150, Agrawal Bhavan,
Ravi Nagar Square, Amravati Road, Nagpur.
4. Smt. Nirnjana Haridas Wasani
Aged about 68 years, Occ.:Agriculturist,
R/o. Plot No.26, Athwa Mile, Amravati Road,
Behind Bank of India, Dawalamethi, Nagpur.
5. Mrs. Neeta Hetal Kariya,
Aged about 40 years, Occ.: Housewife,
R/o. B-405, Sai Shivam, Cabin Road,
Behind National Diary, Sai Nagar,
Thane - 401105
PAGE 1 OF 25
- Judgment A.A.No.03.2022.odt
6. Mrs. Bharti Kamlesh Thakkar
Aged about 44 years, Occ.: Housewife,
R/o.13/4, Dr. P.K.B. Road, Hora Corporation,
Hora, West Bengal - 711101.
7. Mrs. Heena Ajay Baraliya
Aged about 47 years, Occ.: Housewife,
R/o. Raghukul, Small Ayachit Mandir,
Kumbharpura, Mahal, Nagpur.
8. Shri Hitesh Haridas Wasani
Aged about 42 years, Occ.: Agriculturist,
R/o. Plot No.26, Athwa Mile,
Amravati Road, Behind Bank of India,
Dawalamethi, Nagpur.
Mr.A.A.Kathane, Advocate for appellants.
Ms.T.H.Khan, AGP for respondent Nos.1 & 2.
Mr.C.S.Kaptan, Senior Advocate assisted by Mr.A.V.Khare,
Advocate for respondent Nos.3 to 8.
CORAM : MANISH PITALE, J.
RESERVED ON : 30/06/2022
PRONOUNCED ON : 20/08/2022
JUDGMENT
Heard. Admit. Heard finally with the consent of the
learned counsel for the rival parties.
PAGE 2 OF 25
- Judgment A.A.No.03.2022.odt
(2) By this appeal, National Highways Authority of
India and the Government of India, through the Ministry of Road
Transport and Highways(appellants) have challenged judgment and
order dated 21/12/2020, passed by the Court of Principal District
Judge, Nagpur (PDJ) in arbitration application filed by the appellants
under Section 34 of the Arbitration and Conciliation Act, 1996 (Act of
1996). By the said judgment and order, the PDJ has partly allowed the
application and set aside Award passed by the Arbitrator, only to the
extent of granting additional 10% amount on total compensation to
the contesting respondent Nos.3 to 8 for loss of easementary rights, as
per Section 3-G(2) of the National Highways Act, 1956 (Act of 1956).
(3) The appellants undertook the process of acquisition
of lands of respondent Nos.3 to 8 through the respondent No.2 - Land
Acquisition Collector and Competent Authority, under the provisions of
the Act of 1956, pertaining to the land located in village Ketapar, Tah.
Kalmeshwar, Dist. Nagpur. The said land was acquired for Saoner-
Dhapewada-Kalmeshwar-Gondkhairi section of National Highway
No.7. Pursuant to the proceedings of acquisition undertaken by the
respondent No.2 under the provisions of said Act, on 31/03/2018, the
PAGE 3 OF 25
- Judgment A.A.No.03.2022.odt
said respondent pronounced Award/Order, offering compensation to
respondent Nos.3 to 8. Aggrieved by the same, the said respondents
invoked Section 3-G (5) of the said Act, as a consequence of which,
arbitration proceeding was initiated before the respondent No.1 -
Additional Commissioner/Arbitrator.
(4) The respondent Nos.3 to 8 raised various grounds in
their application seeking enhancement of compensation. They relied
upon the ready reckoner concerning the said lands and also asserted
that the land had non-agricultural potential, being located adjacent to
the highway. The respondent Nos.3 to 8 also referred to relevant
guidelines pertaining to the ready reckoner and stated the basis for
their claims towards enhanced compensation. The appellants opposed
the claims of respondent Nos.3 to 8 before the Arbitrator.
(5) The respondent No.1 Additional Commissioner/
Arbitrator considered the material placed on record by the rival parties
and by Award/Order dated 30/11/2019, partly allowed the application
of the claimants i.e. respondent Nos.3 to 8. The operative portion of
the Award/Order of the Arbitrator reads as follows: -
PAGE 4 OF 25
- Judgment A.A.No.03.2022.odt
"Order
i. The application is partly allowed.
ii. The non-applicants are directed to pay to the applicants an amount of Rs.2630/- per Sq. Mt. for the acquired lands of 0.4530 H.R., 0.0720 H.R. & 0.0870 H.R. i.e. total 0.6120 H.R., i.e. 6120 Sq.Mtrs which comes to Rs.1,60,95,600/-.
iii. The non-applicants are directed to pay 100% solatium to the applicants on the amount of total compensation, less the amount already granted/received by the applicants towards land component.
iv. The non-applicants are also directed to pay to the applicants an additional amount of 10% of the total compensation amount for the loss of easement rights as per section 3-G(2) of the National Highways Act, 1956, if not already paid.
v. The non-applicants are further directed to pay the applicants an interest @9%p.a. on the enhanced compensation w.e.f. the date of notification under section 3-D of the said Act till the date of payment of the enhanced compensation.
vi. The non-applicants are directed to pay to the applicants additional component @12% per annum of the enhanced component as per the RFCTLARR Act, 2013.
vii. Order may be communicated to all the parties concerned."
(6) Aggrieved by the said Award/Order passed by the
respondent No.1 - Additional Commissioner/Arbitrator, the appellants
filed application invoking Section 34 of the Act of 1996. Various
grounds of challenge were raised, claiming that the Award deserved to
PAGE 5 OF 25
- Judgment A.A.No.03.2022.odt
be set aside on the parameters specified in Section 34 of the Act of
1996. The respondent Nos.3 to 8 filed their replies and opposed the
said application.
(7) By the impugned judgment and order dated
21/12/2020, the PDJ rendered findings in favour of respondent Nos.3
to 8 on all the aspects of the matter, except the aspect of payment of
additional amount of 10% on the total compensation for loss of
easementary rights as per Section 3-G (2) of the Act of 1956. It was
found that the Arbitrator failed to appreciate that there was no
evidence placed on record on behalf of respondent Nos.3 to 8, to
demonstrate that due to acquisition of part of their lands, they were
finding it difficult in developing the same. Accordingly, the PDJ partly
allowed the application filed by the appellants and partly set aside the
Award of the Arbitrator to the aforesaid extent.
(8) Aggrieved by the impugned order, the appellants
filed the present appeal in which notice for final disposal was issued on
10/04/2022. The respondent Nos.1 and 2 were represented by the
Additional Government Pleader, while learned counsel having
instructions waived service on behalf of respondent Nos.3 to 8. Upon
replies being filed, the appeal was taken up for final disposal.
PAGE 6 OF 25
- Judgment A.A.No.03.2022.odt
(9) Mr. Kathane, learned counsel appearing for the
appellants submitted that the PDJ committed a grave error in partly
setting aside the Award passed by the Arbitrator. It was submitted that
when the PDJ found that a ground was made out by the appellants for
setting aside the Award, the same could not have been partly set aside
and the Award in its entirety ought to have been set aside, leaving the
parties to go for arbitration afresh, if so advised. It was submitted that
partial setting aside the Award was not contemplated and the same
amounted to modifying the Award of the Arbitrator. The learned
counsel for the appellants further submitted that the PDJ, while
exercising power under Section 34 of the Act of 1996, having found
that the Award did deserve interference, the entire Award ought to
have been set aside.
(10) In this regard, the learned counsel for the appellants
relied upon the judgments of the Hon'ble Supreme Court in the case of
National Highways Authority of India(NHAI) Vs. M. Hakeem and
another (2021) 9 SCC 1, State of Chhattisgarh and others vs. Sal
Udyog Private Limited (2022) 2 SCC 275, Dakshin Haryana Bijli Vitran
Nigam Limited vs. Navigant Technologies Private Limited, (2021) 7
PAGE 7 OF 25
- Judgment A.A.No.03.2022.odt
SCC 657 and Mcdermott International Inc. Vs. Burn Standard Co. Ltd.
& Ors. (2006) 11 SCC 181.
(11) Apart from the aforesaid contention, the learned
counsel for the appellants submitted that sufficient material was
placed before the PDJ to demonstrate that the entire Award passed by
the Arbitrator was vitiated, because the guidelines pertaining to the
ready reckoner, particularly guideline No.16(b) was not appreciated in
the correct perspective by the Arbitrator. It was submitted that a slab
system was contemplated under the said guidelines, which ought to
have been applied to the facts of the present case, but the Arbitrator
failed to apply the same, resulting in exorbitant compensation paid to
respondent Nos.3 to 8.
(12) It was further submitted that the direction to pay
interest @9% p.a. on the enhanced compensation was granted from
incorrect date, because it was payable from the date of taking over
possession and not from the date of the notification. On this basis, it
was submitted that the entire Award was vitiated on the touchstone of
the grounds available under Section 34 of the Act of 1996, for
interference in arbitral Awards. It was submitted that therefore, the
PAGE 8 OF 25
- Judgment A.A.No.03.2022.odt
entire Award ought to have been set aside, which the PDJ completely
failed to appreciate while passing the impugned judgment and order.
(13) On the other hand, Mr. C. S. Kaptan, learned Senior
Counsel appearing for respondent Nos.3 to 8 submitted that the
impugned order passed by the PDJ under Section 34 of the Act of
1996, could not be said to be modification of the Award of the
Arbitrator and therefore, there was no substance in the contention
raised on behalf of the appellants that the parties ought to be relegated
to arbitration afresh. By referring to order dated 26/08/2021, passed
by this Court in Arbitration Appeal No. 28 of 2019 ( Shri Sarjuprasad
s/o Sangmlal Gupta vs. National Highways Authority of India and
others) and connected appeals, it was submitted that even applying
the law laid down by the Hon'ble Supreme Court in the case of NHAI
vs. M. Hakeem (supra), as also other judgments indicated by the
learned counsel for the appellants, it could not be said that the
impugned order passed by the PDJ amounted to modification of the
arbitral Award.
(14) Insofar as the merits of the matter are concerned,
the learned counsel submitted that the basis for enhanced
PAGE 9 OF 25
- Judgment A.A.No.03.2022.odt
compensation granted by Award/Order of the Arbitrator was
reasonable and sound. It was based on public document in the form
of ready reckoner. The limited scope available under Section 34 of the
Act of 1996 to interfere in an arbitral Award, indicated that the
appellants had failed to make out sufficient grounds for interference
with the Award on merits. The Arbitrator had taken into consideration
the ready reckoner, as well as guidelines, including guideline No.16(b),
while holding that respondent Nos.3 to 8 were entitled to
compensation @Rs.2630/- per square meter for the acquired lands and
the conclusions rendered therein could not be said to be perverse or
open to interference in the limited scope available under Section 34 of
the Act of 1996. On this basis, it was submitted that the appeal
deserved to be dismissed.
(15) Heard learned counsel for the rival parties and
perused the material placed on record. The foremost contention raised
on behalf of the appellants pertains to the aspect of scope and extent
under Section 34 of the Act of 1996, to interfere with an arbitral
Award. The contention of the learned counsel for the appellants is that
once the Court, under Section 34 of the Act of 1996, finds that there is
PAGE 10 OF 25
- Judgment A.A.No.03.2022.odt
a ground made out for interference in the arbitral Award, the entire
Award must be set aside and the parties can be relegated for
arbitration afresh, if so advised. Much emphasis was placed on the
aforementioned judgments, to claim that the manner in which the
impugned order was passed by the PDJ, it amounted to modification of
the arbitral Award, which was wholly impermissible.
(16) This Court is aware that the Supreme Court in
various judgments, including Mcdermott International Inc. Vs. Burn
Standard Co. Ltd. (supra) and judgments thereafter, culminating in the
aforesaid judgment in the case of NHAI vs. M. Hakeem (supra) has
categorically held that the Court exercising power under Section 34 of
the Act of 1996, does not have power to modify an arbitral Award. It
is specifically held that the Court does not consider an appeal under
Section 34 of the Act of 1996 and that it performs a supervisory role,
wherein it cannot correct the errors of the Arbitrators. The Court can
only quash the Award, leaving the parties to go for arbitration afresh,
if so advised. In the case of NHAI vs. M.Hakeem (supra), in this
context, it has been held as follows :-
"48. Quite obviously if one were to include the power to modify an award in Section 34, one would be crossing the
PAGE 11 OF 25
- Judgment A.A.No.03.2022.odt
Lakshman Rekha and doing what according to the justice of a case, ought to be done. In interpreting a statutory provision, a Judge must put himself in the shoes of Parliament and then ask whether Parliament intended this result. Parliament very clearly intended that no power of modification of an award exists in Section 34 of the Arbitration Act, 1996. It is only for Parliament to amend the aforesaid provision in the light of the experience of the courts in the working of the Arbitration Act, 1996, and bring it in line with other legislations the world over."
(17) There can be no quarrel with the aforesaid
proposition, but the question that arises for consideration in this case
is, whether the impugned order passed by the PDJ amounts to
modification of the arbitral award or that the Award is partially set
aside. The operative portion of the impugned order passed by the PDJ
reads as follows: -
"O R D E R
i. The application is partly allowed.
ii. The Award passed by learned Arbitrator in Arbitration Case No.95/ARB/2018-19, Mauza Ketapar, Tahsil Kalmeshwar, District Nagpur, dated 30th November 2019 is partly set aside to the extent granting the additional amount of 10% of total compensation amount for the loss of easement rights as per Section 3G(2) of the National Highways Act, 1956.
iii. The non-applicant Nos.3 to 8 to bear the costs of the applicants.
iv. R & P be returned to the learned Arbitrator.
Dictated and delivered in open court."
PAGE 12 OF 25
- Judgment A.A.No.03.2022.odt
(18) A perusal of the above quoted portion of the
impugned judgment and order clearly shows that the PDJ has partly
set aside the Award passed by the Arbitrator. Therefore, the question
that really arises for consideration is, as to whether the Court,
exercising power under Section 34 of the Act of 1996, can partially set
aside an Award of the Arbitrator. In other words, even when the Court
is convinced that the Arbitrator has erred only on specific issues and
the Award is otherwise sustainable, is the Court mandatorily required
to set aside the entire Award, leaving the parties for fresh round of
arbitration, if so advised.
(19) None of the counsel brought to the notice of this
Court the relevant judgments or the position of law in this regard.
While the learned counsel appearing for the appellants emphasized
upon the aforementioned judgments of the Supreme Court starting
from Mcdermott International Inc. Vs. Burn Standard Co. Ltd. (supra)
and NHAI vs. M. Hakeem (supra) which pertain to the question of
power of the Court under Section 34 of the said Act to modify an
Award of the Arbitrator, the learned Senior Counsel appearing for
respondent Nos.3 to 8 only referred to the said order dated
PAGE 13 OF 25
- Judgment A.A.No.03.2022.odt
26/08/2021 passed by this Court in Arbitration Appeal No.28/2019,
(in the case of Sarjuprasad s/o Sangmlal Gupta Vs. National Highways
Authority of India and others) with connected appeals. The said order
of this Court also pertained to the aspect of modification of the Award
by the Court. On facts, in that case it was found that the Court while
exercising power under Section 34 of the Act of 1996 had, in fact, not
set aside the Award, but modified the same on certain aspects. But,
none of these judgments could be said to be directly relevant for the
issue sought to be raised on behalf of the appellants, to the effect that
while exercising power under Section 34 of the Act of 1996, the Court
cannot partly set aside the Award and or that the Award must be
wholly set aside.
(20) The said question had been engaging attention of
this Court and it was found that there were divergent views of Division
Benches of this Court, leading to the question being referred to a Full
Bench of this Court in the case of R.S. Jiwani (M/S.) Vs. Ircon
International Ltd., (2010) 1 Mh.L.J. 547 . The Full Bench of this Court
framed following questions for consideration : -
"(1) Whether doctrine of severability can be applied to an award while dealing with a Petition under section 34 of the Arbitration and Conciliation Act, 1996?
PAGE 14 OF 25
- Judgment A.A.No.03.2022.odt
(2) What is the scope of proviso to section 34(2)(iv) and whether its application is restricted to clause (iv) alone or it applies to the whole of section 34(2) of the Act?"
(21) After referring to various precedents and discussing
the law in detail, the Full Bench of this Court in the aforesaid case held
as follows: -
"36. We may now revert back to the facts of the present case which itself is a glaring example of what devastating results can be produced by accepting the contention which has been raised on behalf of the respondent in the present appeal. Undisputedly claims were adjudicated upon on merits. Parties led evidence, documentary as well as oral, argued the matter before the Arbitrator whereafter the Arbitral Tribunal allowed some claims of the claimants and rejected all remaining claims of the claimants and the counter-claim filed by the company. The claimant was satisfied with the award. An enforceable right by way of decree accrued to the claimant in terms of sections 32,35 and 36 of the Act. The company approached this court by filing a petition under section 34 which partially allowed in the sense that out of 15 claims allowed by the Arbitrator in favour of the claimant, held that other claims were not payable to the claimants but still did not make any observation that the award in so far as it rejects the remaining claims and the counter-claim were unsustainable. However, to conclude, the learned Single Judge despite having upheld the claims in favour of the claimants, set aside the entire award in view of the Division Bench judgment in the case of Ms.Pushpa Mulchandani (supra).
Could there be a greater perversity of justice to a party which has succeeded before the Arbitral Tribunal as well as in the court of law but still does not get a relief. Is that what is contemplated and was the purpose of introduction of the Act of 1996. An Act which was to provide expeditious effective resolution of disputes free of court interference would merely become ineffective
PAGE 15 OF 25
- Judgment A.A.No.03.2022.odt
statute. Would not the canon of civil jurisprudence with the very object of the Arbitration Act, 1996 stand undermined by such an approach. The effective and expeditious disposal by recourse to the provisions of the 1996 Act would stand completely frustrated if submissions of the respondent are accepted. Partial challenge to an award is permissible then why not partial setting aside of an award. In a given case, a party may be satisfied with major part of the award but is still entitled to challenge a limited part of the award. It is obligatory on the court to deal with such a petition under section 34(1)(2) of the Act. We may further take an example where the Arbitral Tribunal has allowed more than one claim in favour of the claimant and one of such claim is barred by time while all others are within time and can be lawfully allowed in favour of the claimant. The court while examining the challenge to the award could easily severe the time barred claim which is hit by law of limitation. To say that it is mandatory for the court without exception to set aside an award as a whole and to restart the arbitral proceeding all over again would be unjust, unfair, inequitable and would not in any way meet the ends of justice.
37. The interpretation put forward by the respondents is bound to cause greater hardship, inconvenience and even injustice to some extent to the parties. The process of arbitration even under 1996 Act encumbersome process which concludes after considerable lapse of time. To compel the parties, particularly a party who had succeeded to undergo the arbitral process all over again does not appear to be in conformity with the scheme of the Act. The provisions of section 34 are quite pari materia to the provisions of Article 34 of the Model Law except that the proviso and explanation have been added to section 34(2)(iv). The attempt under the Model Law and the Indian Law appears to circumscribe the jurisdiction of the court to set aside an award. There is nothing in the provisions of the Act and for that matter absolutely nothing in the Model Law which can debar the court from applying the principle of severability provided it is otherwise called for in the facts and circumstances of the case and in accordance with law. The courts will not get
PAGE 16 OF 25
- Judgment A.A.No.03.2022.odt
into the merits of the dispute. Thus, the interpretation which should be accepted by the court should be the one which will tilt in favour of the Model Laws, scheme of the Act and the objects sought to be achieved by the Act of 1996.
38. For the reasons afore-recorded, we are of the considered view that the dictum of law stated by the Division Bench in the case of Ms.Pushpa Mulchandani (supra) is not the correct exposition of law. We would predicate the contrary view expressed by different Benches of this court for the reasons stated in those judgments in addition to what we have held hereinabove. It is difficult to prescribe legal panacea which, with regard to the applicability of the principle of severability can be applied uniformally to all cases. We find that the principle of law enunciated by us hereinabove is more in comity to object of the Act, legislative intent, UNCITRAL Model Law and will serve the ends of justice better. Thus, we proceed to record our answers to the questions framed as follows :
1. The judicial discretion vested in the court in terms of the provisions of section 34 of the Arbitration and Conciliation Act, 1996 takes within its ambit power to set aside an award partly or wholly depending on the facts and circumstances of the given case. In our view, the provisions of section 34 read as a whole and in particular section 34(2) do not admit of interpretation which will divest the court of competent jurisdiction to apply the principle of severability to the award of the Arbitral Tribunal, legality of which is questioned before the court. The Legislature has vested wide discretion in the court to set aside an award wholly or partly, of course, within the strict limitations stated in the said provisions. The scheme of the Act, the language of the provisions and the legislative intent does not support the view that judicial discretion of the court is intended to be whittled down by these provisions.
PAGE 17 OF 25
- Judgment A.A.No.03.2022.odt
2. The proviso to section 34(2)(a)(iv) has to be read ejusdem generis to the main section, as in cases falling in that category, there would be an absolute duty on the court to invoke the principle of severability where the matter submitted to arbitration can clearly be separated from the matters not referred to arbitration and decision thereupon by the Arbitral Tribunal."
(22) Thus, it becomes clear that in a given case, the
Court, while exercising power under Section 34 of the Act of 1996, can
set aside an Award partly, depending upon the facts and circumstances
of the case. In this context, reference can also be made to the
judgment of the Supreme Court in the case of J.G. Engineers Pvt. Ltd.
Vs. Union of India and another (2011) 5 SCC 758.
(23) In the said case also, the doctrine of severability was
invoked and it was held that when the Award deals with several claims
that can be said to be separate and distinct, the Court can segregate
the Award on items that do not suffer from any infirmity and uphold
the Award to that extent. Thus, it becomes clear that the contention
raised on behalf of the appellants in the present case, that the PDJ
ought to have set aside the arbitral Award in its entirety, is not
justified.
PAGE 18 OF 25
- Judgment A.A.No.03.2022.odt
(24) The aspect of grave inconvenience highlighted in
the aforesaid full bench judgement of this Court in the case of R.S.
Jiwani (M/S.) Vs. Ircon International Ltd. (supra), if parties are
required to go for arbitration afresh in its entirety, even when the
arbitral award is only partly set aside, becomes more relevant in
situations like in the present case, which concern statutory arbitration,
involving an acquiring body on the one hand and private individuals
(claimants) on the other. If such a recourse to go for arbitration afresh
is to be adopted on every occasion that the arbitral award is found
liable to be set aside on some issues, it would lead to multiple rounds
of litigation, going against the very purpose of alternative dispute
redressal mechanisms like arbitration. The claimants would be forced
to pursue numerous rounds of proceedings before the arbitrator and
Courts, which cannot be countenanced, thereby indicating that the
contention raised in this regard on behalf of the appellants is
unsustainable.
(25) This Court is of the opinion that in the present case,
each of the issues decided by the Arbitrator were separate and distinct,
particularly the issue pertaining to additional amount to be awarded
PAGE 19 OF 25
- Judgment A.A.No.03.2022.odt
for loss of easementary rights and therefore, it cannot be said that the
PDJ while passing the impugned order, erred in partly setting aside the
Award to that extent.
(26) As regards the contentions raised on behalf of the
appellants with regard to the merits of the calculations undertaken by
the Arbitrator to ascertain the quantum of enhanced compensation
payable, suffice it to say that the PDJ considered the said aspect, being
conscious of the limited jurisdiction available under Section 34 of the
Act of 1996. The scope and extent of interference in an arbitral Award
by the Court, while exercising power under Section 34 of the Act of
1996, has been considered and elaborated in numerous judgments of
the Supreme Court, including the judgment in the case of Delhi
Development Authority Vs. M/s. R.S. Sharma and Company (2008) 13
SCC 80. After referring to earlier precedents on the said aspect of the
matter, the Supreme Court in the said judgment held as follows: -
"21. From the above decisions, the following principles emerge :
(a) An Award, which is
(i) contrary to substantive provisions of law; or
(ii) the provisions of the Arbitration and Conciliation Act, 1996;
PAGE 20 OF 25
- Judgment A.A.No.03.2022.odt
or
(iii) against the terms of the respective contract; or
(iv) patently illegal; or
(v) prejudicial to the rights of the parties;
is open to interference by the court under Section 34(2) of the Act.
(b) The award could be set aside if it is contrary to :
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality.
(c) The award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court.
(d) It is open to the court to consider whether the award is against the specific terms of contract and if so, interfere with it on the ground that it is patently illegal and opposed to the public policy of India.
With these principles and statutory provisions, particularly, Section 34(2) of the Act, let us consider whether the arbitrator as well as the Division Bench of the High Court were justified in granting the award in respect of Claims 1 to 3 and Additional Claims 1 to 3 of the claimant or the appellant DDA has made out a case for setting aside the award in respect of those claims with reference to the terms of the agreement duly executed by both parties."
(27) Applying the said principles to the facts of the
present case, it is found that the Arbitrator while determining the
quantum of enhanced compensation payable to respondent Nos.3 to 8,
took into consideration the ready reckoner, as well as the relevant
guidelines, including the guideline on which the appellants have
placed much emphasis. The grounds of challenge raised in the
PAGE 21 OF 25
- Judgment A.A.No.03.2022.odt
application filed under Section 34 of the Act of 1996, on behalf of the
appellants on the said aspect of the matter do not make out any of the
grounds on which the Court of the PDJ could have exercised power in
favour of the appellants. As laid down in a series of judgments by the
Supreme Court and this Court, the Court while exercising power under
Section 34 of the Act of 1996, does not exercise appellate jurisdiction
and findings rendered in the arbitral Award can be interfered with only
on the touchstone of the principles enumerated in the above quoted
judgments. Applying the said principles to the facts of the present
case, this Court is not satisfied that a case is made out by the
appellants for interference in the Award on the said aspect of the
matter. To that extent, the contentions raised on behalf of the
appellants cannot be accepted.
(28) But, there is another aspect of the matter and it
concerns the direction given in the arbitral Award for payment of
interest @9% p.a. on enhanced compensation to respondent Nos.3 to
8, from the date of the notification under Section 3-D of the Act of
1956. The learned counsel for the appellant invited attention of this
Court in this context to Section 3-H (5) of the Act of 1956, which reads
PAGE 22 OF 25
- Judgment A.A.No.03.2022.odt
as follows: -
"Section 3-H(5) - Where the amount determined under section 3-G by the arbitrator is in excess of the amount determined by the competent authority, the arbitrator may award interest at nine per cent. per annum on such excess amount from the date of taking possession under section 3-D till the date of the actual deposit thereof."
(29) A perusal of the above quoted operative portion of
the arbitral Award shows that while granting relief to respondent
Nos.3 to 8 relatable to Section 3-H (5) of the Act of 1956, the
Arbitrator directed as follows: -
"(v) The non-applicants are further directed to pay the applicants an interest @9% p.a. on the enhanced compensation w.e.f. the date of notification under Section 3D of the said Act till the date of payment of the enhanced compensation."
(30) The said direction could be said to be illegal
inasmuch as under Section 3-H (5) of the Act of 1956, interest @9%
p.a. can be granted by the Arbitrator on the excess amount from the
date of taking possession under Section 3-D of the Act of 1956. But,
in the above quoted direction given in the arbitral Award, the
Arbitrator has directed such amount of interest @9% p.a. to be paid
from the date of the notification under Section 3-D of the Act of 1956
PAGE 23 OF 25
- Judgment A.A.No.03.2022.odt
and not from the date of taking possession.
(31) But, in this regard amendment of Section 34 of the
Act of 1996 w.e.f. 23/10/2015, whereby sub Section (2A) stood added
thereto, assumes significance. Section 34(2A) of the Act of 1996,
reads as follows: -
"Section 34(2-A) :- An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award:
Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by re- appreciation of evidence."
(32) The proviso to sub Section (2A) of Section 34 of the
Act of 1996, clearly indicates that an Award shall not be set aside
merely on the ground of erroneous application of law. In the present
case, the appellants cannot dispute the entitlement of the respondent
Nos.3 to 8, towards payment of interest @9 % p.a. on the excess
amount, as Section 3-H(5) of the Act of 1956, clearly provides for the
same, but, while granting such relief in clause (v) of the arbitral
Award, the Arbitrator has directed payment of such amount from the
date of notification under Section 3-D of the Act of 1956, instead of
the date of taking possession. This can be said to be, at worst, an
PAGE 24 OF 25
- Judgment A.A.No.03.2022.odt
erroneous application of the law, covered under proviso to sub Section
(2A) of Section 34 of the said Act. Therefore, this Court is of the
opinion that on this ground also the appellants have failed to make out
a case in their favour.
(33) In view of the above, this Court is of the opinion
that the appellants have failed to make out any case in their favour
under Section 37 of the Act of 1996, for this Court to exercise
jurisdiction in order to interfere with the impugned judgment and
order passed by the Court of PDJ.
(34) Accordingly, the appeal is dismissed. No order as to
costs. Pending applications, if any, stand disposed of.
[ MANISH PITALE J. ]
KOLHE
Digitally signed byRAVIKANT CHANDRAKANT KOLHE Signing Date:20.08.2022 14:46 PAGE 25 OF 25
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!