Citation : 2022 Latest Caselaw 4517 Bom
Judgement Date : 28 April, 2022
CORRECTED-Judgment in WP2981.2021.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR
WRIT PETITION NO. 2981 OF 2021
1. National Highways Authority of India
Through its Project Director, Project
Implementation Unit, Yavatmal Having its
office at Chandan Niwas, Plot No.13,
Kolhe Layout Part-2, Darwha Road,
.. Petitioners
Yavatmal
2. Government of India through Secretary,
Ministry of Road Transport & Highways,
New Delhi
Versus
1. Sub-Divisional Officer cum Land
Acquisition Officer, Yavatmal
2. Shyamsundar Shribhagwan Jaipuria,
Aged about : major, r/o : 404, Krushna
Apartments, Gadge Nagar, Yavatmal
3. Saurabh Nandkishore Jaipuria
Aged about : major, through its Power of
Attorney Holder : Shyamsundar
Shribhagwan Jaipuria r/o : 404, Krushna
Apartments, Gadge Nagar, Yavatmal
.. Respondents
4. Naman Naval Agrawal
Aged about : major, through its Power of
Attorney Holder : Shyamsundar
Shribhagwan Jaipuria r/o : 404, Krushna
Apartments, Gadge Nagar, Yavatmal
5. Manjushri Nilesh Tibedwal,
Aged about : major, through its Power of
Attorney Holder : Shyamsundar
Shribhagwan Jaipuria r/o : 404, Krushna
Apartments, Gadge Nagar, Yavatmal
PAGE 1 OF 18
CORRECTED-Judgment in WP2981.2021.odt
6. Purvi Sanjay Agrawal,
Aged about : major, through its Power of
Attorney Holder : Shyamsundar
Shribhagwan Jaipuria r/o : 404, Krushna
Apartments, Gadge Nagar, Yavatmal
Mr. Saurabh A. Choudhari, Advocate for petitioners.
Mr. H. D. Dubey, A.G.P. for respondent No.1.
Mr. S. P. Khirsagar, Advocate for respondent Nos.2 to 6.
CORAM : MANISH PITALE, J.
RESERVED ON : 07/04/2022
PRONOUNCED ON : 28/04/2022
JUDGMENT
Rule. Rule made returnable forthwith. Heard finally
with consent of the learned counsel appearing for the rival parties.
(2) The National Highways Authority of India and the
Government of India through the Ministry of Road Transport and
Highways have filed the present petition challenging order dated
16.03.2021, passed by the respondent No.1 - Sub-Divisional Officer
cum Land Acquisition Officer, Yavatmal. By the said order an
application filed by respondent Nos.2 to 6 i.e. land owners, under
Section 3C of the National Highways Act, 1956, has been allowed and
PAGE 2 OF 18 CORRECTED-Judgment in WP2981.2021.odt
specific directions have been given to the petitioners in the context of
0.88 HR land located in Gut No.4, Mouza Madkona, Tahsil and District
- Yavatmal.
(3) The petitioners undertook a project for constructing
National Highway No.361 passing through Gut No.4, Mouza Madkona,
and for that purpose provisions of the aforesaid Act were invoked for
acquisition of land. Petitioner No.2 issued declaration under Section
3A of the aforesaid Act, declaring intention to acquire 1.8261 HR of
land from Gut No.4, in Mouza Madkona. Respondent Nos.2 to 6 raised
objections under Section 3C of the said Act in respect of the acquisition
proposed to be undertaken for construction of the aforesaid National
Highway. It was the case of respondent Nos.2 to 6 that 0.62 HR and
0.26 HR lands from the aforesaid Gut No.4, Mouza Madkona, were
utilized by the petitioners for construction of the said National
Highway No.361, but in the process no steps were taken for follow-up
action regarding acquisition under the provisions of the said Act.
(4) It was claimed that there were documents on record
to show that joint measurement was undertaken, identifying the
aforesaid lands admeasuring 0.62 and 0.26 HR i.e. total 0.88 HR from
PAGE 3 OF 18 CORRECTED-Judgment in WP2981.2021.odt
Gut No.4, Mouza Madkona, belonging to respondent Nos.2 to 6, that
was utilized during construction of the said National Highway and yet,
the petitioners had not taken appropriate steps for compensating
respondent Nos.2 to 6. In this backdrop, the said application under
Section 3C of the aforesaid Act was filed, which was allowed by the
impugned order dated 16.03.2021.
(5) The petitioners filed the present petition, wherein
notice was issued for final disposal by order dated 17.08.2021. The
respondent No.1 entered appearance through the Assistant
Government Pleader and respondent Nos. 2 to 6 were also represented
by counsel.
(6) Mr.Saurabh Choudhari, learned counsel appearing
for the petitioners submitted that the impugned order dated
16.03.2021, passed by respondent No.1 was without jurisdiction in the
light of law laid down by the Hon'ble Supreme Court as regards the
nature of objections that could be entertained under Section 3C of the
aforesaid Act. It was submitted that the findings rendered in the
impugned order were well beyond the scope of Section 3C of the said
Act and the direction given in the impugned order for rendering Award
PAGE 4 OF 18 CORRECTED-Judgment in WP2981.2021.odt
and disbursing compensation to respondent Nos. 2 to 6, was clearly
beyond the jurisdiction of respondent No.1. It was claimed that
although declaration under Section 3A of the said Act was issued,
there was no follow-up action as expected under Section 3D of the said
Act pertaining to the aforesaid pieces of land and therefore, there was
no question of rendering a land acquisition Award and disbursing
compensation to respondent Nos.2 to 6.
(7) It was further submitted that 0.26 HR land
concerned a service lane and insofar as 0.62 HR land was concerned,
the same was never acquired by the petitioners and an earlier litigation
initiated by respondent No.2 against the Public Works Department of
the State Government claiming that the said piece of land was utilized
for construction of State highway, had met with failure before this
Court. Attention of this Court was invited to order dated 29.06.2010,
passed in Writ Petition No.2282 of 2009, wherein this Court had
dismissed the writ petition filed by respondent No.2 concerning the
very same piece of land admeasuring 0.62 HR in Gut No.4, Mouza
Madkona. The respondent No.2 had claimed that the said piece of
land was utilized for construction of State highway and that therefore,
the State Government through the Public Works Department ought to
PAGE 5 OF 18 CORRECTED-Judgment in WP2981.2021.odt
be directed to complete acquisition proceedings in respect of the same
and to pay compensation. The writ petition was dismissed on the
ground that disputed questions of fact were involved, which could not
be decided in writ jurisdiction. On this basis, it was submitted that the
respondent No.1 had erred in passing the impugned order.
(8) The learned counsel for the petitioners further
submitted that due to the direction given in the impugned order, land
acquisition Award dated 31.05.2021 was passed, determining
compensation payable to respondent Nos.2 to 6 for the aforesaid
pieces of land, but since the Award was consequential to the impugned
order and the impugned order was itself unsustainable, the Award
passed by respondent No.1 also deserved to be set aside.
(9) The learned counsel for the petitioners relied upon
judgment of the Hon'ble Supreme Court in the case of Competent
Authority Vs. Barangore Jute Factory and Others (2005) 13 SCC 477
and judgment of the Karnataka High Court in the case of Dr.
V.S.Shukal and Ors Vs. National Highways Authority of India (Ministry
of Road Transport and Highways) and Ors. AIR 2013 Karnataka 65.
PAGE 6 OF 18 CORRECTED-Judgment in WP2981.2021.odt
(10) On the other hand, Mr.S.P. Kshirsagar, learned
counsel appearing for respondent Nos.2 to 6 opposed the contentions
raised on behalf of the petitioners. It was submitted that a joint
measurement report on record and the order passed in an appeal
preferred by petitioner No.1, as regards the said aspect of the matter
had met with dismissal at the hands of the Deputy Superintendent of
Land Records, Yavatmal and the said order had attained finality. In the
said order, it was specifically recorded that the joint measurement of
the land in question taken place in the presence of the representative
of petitioner No.1 and that it was found, as a matter of fact, that both
pieces of land admeasuring 0.26 HR and 0.62 HR in Gut No.4, Mouza
Madkona, belonging to respondent Nos.2 to 6 were utilized in
construction of National Highway No.361. This material was
specifically appreciated by respondent No.1 while passing the
impugned order and therefore, the said finding of fact could not be
interfered with in the present petition. It was submitted that the
petitioners were unable to deny the fact that 0.88 HR land in Gut
No.4, Mouza Madkona, was indeed utilized for construction of
National Highway No.361 and therefore, it could not lie in the mouth
of the petitioners that since there was no order/declaration issued
PAGE 7 OF 18 CORRECTED-Judgment in WP2981.2021.odt
under Section 3D of the aforesaid Act, the direction to pay
compensation could not be claimed by respondent Nos.2 to 6. It was
submitted that the material on record was correctly appreciated by
respondent No.1 while passing the impugned order.
(11) Insofar as the aspect that respondent No.1 had
exceeded jurisdiction under Section 3C of the said Act, it was
submitted that the petitioners could not support their claims on facts
before the said authority and it was on the basis of material brought
on record that the respondent No.1 correctly exercised jurisdiction in
favour of respondent Nos.2 to 6. It was submitted that challenge to
the Award at the behest of the petitioners for whose benefit the
acquisition proceedings were undertaken, was unheard of and totally
unsustainable.
(12) Mr.H.D. Dubey, learned Assistant Government
Pleader appeared on behalf of respondent No.1 and defended the
impugned order.
(13) Before dealing with contentions raised on behalf of
the petitioners concerning findings on merits rendered by respondent
PAGE 8 OF 18 CORRECTED-Judgment in WP2981.2021.odt
No.1, it would be appropriate to first deal with the contention
regarding the scope of jurisdiction under Section 3C of the said Act.
The learned counsel for the petitioners relied upon the judgment of the
Supreme Court in the case of Competent Authority Vs. Barangore Jute
Factory and Others (supra) and that of the Karnataka High Court in
the case of Dr. V.S. Shukla Vs National Highways Authority of India
(supra). A perusal of the aforesaid judgments would show that it has
been laid down that the scope of jurisdiction under Section 3C of the
said Act, is not as wide as the jurisdiction exercised under Section 5A
of the Land Acquisition Act, 1894. It is laid down that the land owner
has a very limited right to object under Section 3C of the aforesaid Act
and such an objection can only be limited to the question of use of the
land under acquisition for the purposes other than those declared
under Section 3A of the said Act. It is laid down that Section 3C of the
said Act confers no right to object to the acquisition as such. This
position has been followed by the Karnataka High Court and it is laid
down that the land owners are not entitled to get the acquisition
proceedings invalidated on the ground that some of their objections
were not considered.
(14) Thus, it becomes clear that under Section 3C of the
PAGE 9 OF 18 CORRECTED-Judgment in WP2981.2021.odt
said Act, the nature of objections that can be raised is limited and the
very acquisition cannot be challenged. In the present case, respondent
Nos.2 to 6 as owners of the aforesaid pieces of land, together
admeasuring 0.88 HR in Gut No.4, Mouza Madkona, raised detailed
objections under Section 3C of the said Act. A perusal of the
objections raised on behalf of respondent Nos.2 to 6 along with the
documents placed on record before respondent No.1 would show that
they raised serious concerns about being deprived of the aforesaid
pieces of land, without being compensated for the same. In fact, the
tenor of the entire objections was that they ought to be compensated,
not only for possession of the said pieces of land being taken for
construction of Highway No.361, but also for the reason that the
remaining area of land belonging to the said respondents had been
rendered either unmarketable or inaccessible, thereby diminishing the
utility of the remaining area of land belonging to them.
(15) It was also indicated that fair compensation was due
to them and it was claimed that the whole designing of the National
Highway was "eccentric" thereby indicating that the said pieces of land
need not have been utilized for construction of National Highway
No.361. A number of documents were annexed with the said
PAGE 10 OF 18 CORRECTED-Judgment in WP2981.2021.odt
objections in support of the issues raised therein. This Court is
convinced that the nature of objections raised on behalf of respondent
Nos.2 to 6, did fall within the scope and jurisdiction of respondent
No.1 under Section 3C of the said Act. Therefore, the contentions
raised on behalf of the petitioners that respondent No.1 exceeded its
jurisdiction while passing the impugned order, cannot be accepted.
(16) The petitioners have also vehemently contended
that the observations made in the impugned order were uncalled for
and the direction to pay compensation by preparing land acquisition
Award for having utilized the aforesaid pieces of land could not have
been granted, particularly when proceedings under Section 3D of the
said Act were not undertaken in respect of the said two pieces of land
in Gut No.4, Mouza Madkona.
(17) A perusal of the impugned order shows that the
respondent No.1 has stated in great detail, the rival contentions and
specific issues raised by the parties. In the context of the material
placed before respondent No.1, it was found as a matter of fact that
both pieces of land i.e. 0.26 HR and 0.62 HR in Gut No.4, Mouza
Madkona, belonging to respondent Nos.2 to 6 had been indeed utilized
PAGE 11 OF 18 CORRECTED-Judgment in WP2981.2021.odt
for construction of National Highway No.361. The report pursuant to
exercise of joint measurement, where the representative of petitioner
No.1 was present and so were respondent Nos.2 to 6, was placed on
record before respondent No.1. It was appreciated in the context of
the map on record and order dated 04.10.2018, passed by the Deputy
Superintendent of Land Records, Yavatmal, wherein specific findings
were given, that both the aforesaid pieces of land were indeed utilized
for construction of National Highway No.361.
(18) The respondent No.1 found that the petitioners
could not dispute such documents on record and it was clear that both
the aforesaid pieces of land belonging to respondent Nos.2 to 6 had
indeed been utilized for construction of National Highway No.361 and
that the said respondents had been deprived of the said pieces of land.
In fact, the respondent No.1 found from the documents on record that
the petitioner No.1 was collecting toll for construction of the said
stretch of National Highway No.361, in respect of which respondent
Nos.2 to 6 stood dispossessed from 0.62 HR of land in Gut No.4,
Mouza Madkona. On the basis of such finding of fact, the respondent
No.1 concluded that since the two pieces of land belonging to
respondent Nos.2 to 6 had been undisputedly utilized for construction
PAGE 12 OF 18 CORRECTED-Judgment in WP2981.2021.odt
of National Highway No.361, the objections and apprehensions
expressed by the said respondents were justified. It is in this context
that the direction was given by respondent No.1 for rendering land
acquisition Award and suitably compensating respondent Nos.2 to 6
for utilization of the said two pieces of land. It is also undisputed that
declaration under section 3A of the said Act was issued for acquisition
of the said pieces of land. Hence, this Court is of the opinion that the
findings of facts rendered by respondent No. 1 on the basis of material
on record cannot be found fault with.
(19) This Court also perused the documentary material
placed on record. It clearly shows that the joint measurement report
and the map prepared pursuant thereto undeniably establish the fact
that the aforesaid two pieces of land belonging to respondent Nos.2 to
6 were indeed utilized in the said project of the petitioners. The
respondent Nos.2 to 6 stood dispossessed and deprived of the said
pieces of land. There can be no dispute about the fact that the said
respondents deserved to be suitably compensated for the same. The
order dated 04.10.2018 passed by the Deputy Superintendent of Land
Records, Yavatmal, shows that the appeal filed by petitioner No.1 as
regards the joint measurement report was dismissed and it was
PAGE 13 OF 18 CORRECTED-Judgment in WP2981.2021.odt
specifically recorded that the aforesaid pieces of land admeasuring
0.26 HR and 0.62 HR from Gut No.4, Mouza Madkona, belonging to
respondent Nos.2 to 6, were indeed utilized for the project concerning
National Highway No.361. The said order was admittedly not
challenged any further by petitioner No.1, thereby showing that the
same attained finality.
(20) Much emphasis was placed on behalf of the
petitioners on order dated 29.06.2010, passed by this Court whereby
Writ Petition No.2282 of 2009 filed by respondent No.2 was dismissed.
A proper appreciation of the said order passed by this Court would
show that the respondent No.2 had claimed that the State Government
through the Public Works Department had encroached upon 0.62 HR
land from Gut No.4, Mouza Madkona, for construction of the State
highway and that no compensation was paid for the same. The State
Government had denied the aforesaid claim of respondent No.2. A
Division Bench of this Court while considering the writ petition under
Article 226 of the Constitution of India found that in the light of the
rival claims made by the parties, disputed questions of fact were
involved, which could not be gone into in the said writ petition. On
this basis, the writ petition was dismissed.
PAGE 14 OF 18 CORRECTED-Judgment in WP2981.2021.odt
(21) Even if the said writ petition filed by the respondent
No.2 was dismissed, the effect of the same was that the respondent
No.2 failed to establish the fact that the State Government through the
Public Works Department had utilized 0.62 HR land from Gut No.4,
Mouza Madkona, for construction of the State highway. But, the same
would not result in any finding that could be positively rendered in
favour of the petitioners in the present case. It appears from the tenor
of the contentions raised on behalf of the petitioners before this Court
that it was the State Government, which may have utilized 0.62 HR
land from Gut No.4, Mouza Madkona, which thereafter, may have
been subsumed or utilized in construction of National Highway
No.361, and that therefore, the petitioners could not be held
responsible for payment of compensation for utilization of said pieces
of land. The aforesaid contention and approach adopted by the
petitioners, cannot be accepted, particularly because when this Court
put pointed queries to the learned counsel for the petitioners, he could
not demonstrate that National Highway No.361 did not run through
the aforesaid pieces of land belonging to respondent Nos.2 to 6. On the
contrary, respondent Nos. 2 to 6 proved that the said pieces of land
were indeed utilized for construction of the said highway, as per the
PAGE 15 OF 18 CORRECTED-Judgment in WP2981.2021.odt
joint measurement report and the order of the Deputy Superintendent
of Land Records.
(22) By the said order, the Deputy Superintendent of
Land Records found that the aforesaid pieces of land were utilized for
construction of National Highway No.361. In fact, on the basis of joint
measurement report, wherein the representative of petitioner No.1 was
also present and he signed the same, it was recorded as a matter of
fact that the aforesaid pieces of land belonging to respondent Nos.2 to
6 were indeed utilized for construction of National Highway No.361
and this material was appreciated by the Deputy Superintendent of
Land Records while dismissing the appeal filed by petitioner No.1. In
the face of such material available on record, it becomes clear that
dismissal of Writ Petition No.2282 of 2009, by the Division Bench of
this Court cannot be of any assistance to the petitioners in this case.
(23) Having appreciated the material available on record,
the respondent No.1 in the impugned order correctly allowed the
application/objection filed by respondent Nos.2 to 6. Having come to
specific finding of facts that the aforesaid pieces of land belonging to
respondent Nos.2 to 6 were indeed utilized for construction of
PAGE 16 OF 18 CORRECTED-Judgment in WP2981.2021.odt
National Highway No.361, it was a logical corollary for respondent
No.1 to have directed payment of appropriate compensation to
respondent Nos.2 to 6. The petitioners cannot hide behind the excuse
that appropriate proceeding under Section 3D of the Act was never
undertaken regarding the said pieces of land and therefore, there was
no question of rendering an Award for payment of compensation to
respondent Nos.2 to 6.
(24) In fact, it is an admitted position that Award dated
31.05.2021, was passed by the respondent No.1 determining the
compensation payable to respondent Nos.2 to 6 for utilization of the
aforesaid two pieces of land admeasuring 0.26 HR and 0.62 HR from
Gut No.4 in Mouza Madkona. A copy of the said Award was not
placed before this Court with the writ petition on behalf of the
petitioners and it was respondent Nos.2 to 6 who placed the same on
record. It is surprising that the petitioner,s having utilized the
aforesaid pieces of land for construction of National Highway No.361,
have challenged the very Award determining compensation payable to
respondent Nos.2 to 6. The petitioner No.1 is the authority for whom
the entire exercise of acquisition and utilization of the lands in
question took place and when the material on record undeniably
PAGE 17 OF 18 CORRECTED-Judgment in WP2981.2021.odt
demonstrated that the said two pieces of land were indeed utilized for
construction of National Highway No.361, the petitioners could not
have challenged the Award dated 31.05.2021, in the present writ
petition.
(25) In view of the above, this Court is convinced that
there is no substance in the contentions raised on behalf of the
petitioners. Land owners whose lands are acquired ought to be suitably
compensated for the same. It is the right of respondent Nos.2 to 6, for
being suitably compensated and the said right is guaranteed under
Section 300-A of the Constitution of India. Hence, the petition is
found to be without any merit.
(26) Accordingly, the writ petition is dismissed. Rule is
discharged. No costs.
[ MANISH PITALE J.]
KOLHE
Digitally signed byRAVIKANT CHANDRAKANT KOLHE Signing Date:28.04.2022 14:44 PAGE 18 OF 18
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!