Citation : 2021 Latest Caselaw 15428 Bom
Judgement Date : 27 October, 2021
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
INTERIM APPLICATION (L) NO. 23237 OF 2021
IN
COMMERCIAL ARBITRATION PETITION NO. 483 OF 2021
Konkan Railway Corporation Ltd. ... Applicant/ Petitioner
vs.
Maytas-Rithwik (JV) ... Respondent
Mr. Simil Purohit a/w. Mr. Saket Mone, Mr. Subit Chakrabarti and Mr.
Devansh Shah i/b. M/s. Vidhii Partners for the Applicants.
Mr. Gaurav Joshi, Senior Advocate a/w. Dr. Birendra Saraf, Senior Advocate,
Mr. Purvesh Buttan, Mr. Bharat Jain, Mr. Tejas Agarwal and Mr. Varun Nair i/
b. IC Legal for the Respondent.
CORAM : A. K. MENON, J.
DATED : 27th OCTOBER, 2021
P.C. :
1. By this IA, the applicant-original petitioner seeks a direction against
the respondent to renew 32 bank guarantees described in paragraph 9 of the
application of a total value of Rs.38,37,39,785/- for the period during which
the Commercial Arbitration Petition no.483 of 2021 remains pending in this
court and for three months thereafter and by renewing the bank guarantees
one month prior to the expiry. Failing such renewal leave is sought to encash
the bank guarantees. The claimant also seeks a direction to the respondent to
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai submit further unconditional bank guarantees of a sum of Rs.24,94,37,614/-
to secure interest upto 31st December, 2022 on the mobilization advance paid
by the petitioner to the respondent.
2. As and by way of background, I may point out that the present IA has
occasioned by virtue of an order passed on 3 rd August, 2021 by this court
while admitting the arbitration petition filed under Section 34 of the
Arbitration and Conciliation Act ("the Act").
3. At the time of admission, the petitioner was put to terms, staying the
operation of the award on deposit of Rs.6,06,51,846/-. In addition, the
petition under Section 34 had sought a mandatory order seeking fresh bank
guarantees to be issued to cover the demobilization advance. Liberty was
granted to the applicant to file a separate IA for this purpose and in the
meantime, the court directed the petitioner not to invoke the bank guarantees
without leave of the court. Today it is pointed out by the applicant that the
amount has been deposited and pursuant to the liberty granted, the present IA
has been filed.
4. Mr. Purohit, the learned counsel appearing in support of the
application submitted that the applicant had paid a mobilization advance paid
to the respondent in three stages as set out in paragraph 5 of the application
return of which was to be secured by the aforesaid bank guarantees. A
Subsidiary Agreement was then executed between the parties on 26 th Novem-
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai ber, 2012 whereby the scope of work was reduced, certain items were
deleted from the scope of work. The contract was thereafter cancelled by
executing a Foreclosure Agreement dated 22 nd November, 2013. The
respondent was not therefore required to carry out any work of the
non-scheduled items mentioned in the Subsidiary Agreement as on the date
of foreclosure. In the meantime, mobilization advance along with interest
amounting to Rs.38,37,39,785/- was outstanding. According to the applicant,
this amount is to be repaid by the respondent to the claimant and is therefore
secured by the bank guarantees.
5. Mr. Purohit submitted that the bank guarantees are now valid till 31 st
October, 2021. The amount secured by the bank guarantees are the amounts
of mobilization advance as aforesaid which guarantees are required to be
renewed one month prior to their expiry. The bank guarantees must
therefore be kept alive till the Arbitration Petition is disposed. He states that
unless this relief is granted, the applicant is likely to lose more than Rs.30
crores and hence the bank guarantees may be ordered to be renewed.
6. In the alternative, Mr. Purohit submitted that if the court was not
inclined to order renewal, the applicant may be permitted to encash these
guarantees since the order dated 3 rd August, 2021 provides that the bank
guarantees will not be encashed without the leave of the court. He therefore
seeks leave as contemplated in the order dated 3 rd August, 2021.
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai
7. The application is opposed on behalf of the respondent by Mr. Joshi
who has raised a preliminary objection as to maintainability. He submits that
the application is not maintainable in view of the legal position that the relief
under Section 9 cannot be sought by a losing party and in the instant case the
applicant has failed in its attempt to secure an award for the mobilization
advance. The claim of the applicant had been rejected by the tribunal and
hence there is no occasion to secure this amount by way of bank guarantee.
Subject to the objection of maintainability, Mr. Joshi has invited my attention
to some of the provisions of the Subsidiary Agreement and has contended
that there is no occasion to renew the bank guarantees. According to Mr.
Joshi this is a case where the applicant after having failed to get any award in
its favour, is seeking to secure the amount of a counter claim which was
rejected by the arbitral tribunal. As an unsuccessful counter claimant, there is
no question of renewing the bank guarantees upon expiry nor is there any
occasion to permit the encashment of the bank guarantee.
8. What the applicant seeks to achieve is to secure the claim which has
been rejected by the tribunal and which cannot be allowed even if the peti-
tioner were to succeed in the challenge under section 34. Mr. Purohit while
acknowledging the legal position has submitted that the present set of facts
will justify the relief that is sought. According to him the tribunal had re -
jected the claim in a summary fashion without any justification and therefore
the mobilization advance is due to be repaid to the applicant.
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai
9. Mr. Joshi submitted that the law as laid down in Dirk India Private
Limited vs. Maharashtra State Electricity Generation Company Limited 1 is
clear on this aspect and an application made for interim reliefs after
arbitration can only be made by a successful party to enjoy the fruits of the
award and not by a party who has failed to secure an award in its favour. Mr.
Joshi further submitted that the judgment of this court in Dirk India(supra)
has been consistently followed in numerous other matters and therefore
considering the state of the law the present application is not competent.
10. Inviting my attention to the observations of the Division Bench in Dirk
India (supra). Mr. Joshi submitted that in Hindustan Construction Company
Limited vs. Union of India2 the Supreme Court has referred the judgment of
this court in Dirk India(supra) in aid of interpretation of the objects of
section 9. He further submitted that in yet another judgment of this court in
Evonik India Pvt. Ltd vs. Reliable Spaces Pvt. Ltd. 3 Dirk India (supra) has been
followed repeatedly different. Reliance is also placed on the decision of Wind
World (India) Ltd vs. Enercon GmbH 4 in which the Court held that an
unsuccessful party under section 9 will not have the occasion to seek and be
granted interim relief. Such a party will not be entitled to seek enforcement
of the award under section 36. Inviting my attention to the decision of the
single judge of this court in the case of ONGC vs Consortium of Sime Darby
1 2013 SCC Online Bom 481 2 2019 SCC OnLine SC 1520
4 2017 SCC OnLine Bom 1147
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai Engineering5, in Notice of Motion (L ) no. 733 of 2018 in Commercial
Arbitration Petition (L) No. 327 OF 2018 Mr. Joshi submitted that in an
almost identical case, where the applicant had suffered partial rejection of
the claim, a prayer seeking a direction against the respondent to extend the
period of bank guarantees was refused. This view of the learned single
judge was then upheld by the Division Bench in Commercial Appeal (L) No.
166 of 2018 along with connected matters. Mr. Joshi therefore submitted
that the application is devoid of merit and deserves to be dismissed.
11. Incidentally it is revealed that the respondent had already filed a
petition under section 9 of the Arbitration and Conciliation Act being
Commercial Arbitration Petition (L)No. 19900 of 2021 seeking the very same
relief that is sought in this interim application and that petition came to be
withdrawn albeit with liberty to file this interim application. This interim
application was then listed before the appropriate Court when the Court felt
that the order dated 3rd August, 2021 needed clarification. This Interim
Application has since been assigned to this Court by an administrative order
and hence I have proceeded to hear the parties .
12. Mr. Purohit persisted with his contention that the respondent was
duty bound to renew the bank guarantees and keep the same renewed and
alive for at least six months after the award was communicated and in this
behalf he has relied upon the consent minutes of order dated 5 th October,
5 2018 SCC OnLine Bom 6034
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai 2020 passed in Commercial Arbitration Petition (L) No. 3014 of 2020 and
Petition LDVC No. 90 of 2020. Vide clause 10 of those minutes, the applicant
herein had agreed not to invoke the bank guarantees till declaration and
communication of the award by the tribunal and for further period provided
in a Subsidiary Agreement dated 22nd November, 2013 (SA No.3). The
respondent was required to continue to extend and renew the bank
guarantees one month prior to expiry as stipulated in the SA No. 3 and
continuously till six months after the communication of the Award passed by
the Arbitral Tribunal. It was also clarified that if the respondent failed to
renew the bank guarantees and keep them valid and operative as aforesaid,
the applicant would be entitled to invoke and encash the bank guarantees.
13. Relying on this provision, Mr. Purohit submitted that the order dated
3rd August, 2021 prevents the applicant from encashing the bank guarantees
without leave of this court. He therefore sought leave of this court to encash
the bank guarantees as an alternative to a direction to the respondent to
renew the same. He submitted that unless the bank guarantees are renewed
they would expire on 31st October, 2021 and valuable security would be then
lost to the applicant Corporation. In the absence of such renewal he
submitted that the applicants would be entitled to invoke and encash the
guarantees.
14. Reference to Clause 10 of the minutes has led me to consider the
contents of the SA No. 3. SA No. 3 was required to be executed because the
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai contract was brought to a close and to draw up the financial statements
both parties had agreed to execute this subsidiary agreement. It records that
a total sum of Rs.22,79,08,104/- had been paid as mobilisation advance.
Interest accrued thereon amounted to Rs.15,58,38,681/- and it provided for
the contractor, namely the respondent herein, to keep the bank guarantees
valid and operative by keeping it extended till the finalisation of the
arbitration award. The said agreement also provided that till such time the
arbitral award is pronounced and subsequently as agreed in the minutes of
meeting dated 3rd September, 2013, the applicant would not invoke the bank
guarantees provided the extension was forthcoming. It further provided that
upon the award being declared, the applicant would be entitled to deduct the
outstanding amount of advances given to the contractor and interest
accrued there on from amounts, if any, payable to the contractor under the
award. If the Arbitration award was insufficient then the respondent would
pay balance including applicable interest in equal installments from the date
of the award failing which the applicant was entitled to invoke the bank
guarantees.
15. On a query from the court, the parties have produced a copy of the
minutes of the meeting referred to in clause 10 and those minutes reveal that
the applicant had requested the respondent to refund the entire advances
(mobilisation advance) along with interest due and the respondent had stated
that they were unable to remit the amount but would await the outcome of
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai the arbitration. They had thus expressed their willingness to renew the
guarantees prior to its expiry but till the award was pronounced. It is under
these circumstances that the bank guarantees came to be extended.
16. After the last extension of 12 months, the bank guarantees are now
scheduled to expire on 31 st October, 2021 and read in this light it does appear
that the obligation to renew the bank guarantees was only till the award was
published. If the award was in favour of the applicant to the extent it
concerns the claim for reimbursement of mobilisation advances, there would
have been merit in the submission of Mr. Purohit that loss of more than 30
crores is likely to be caused to the applicant if the bank guarantees were not
encashed. The submission of the counsel proceeds on the basis that they were
a successful party in the arbitration. indeed they were partly successful in the
arbitration but net of claims and counter claims, it is the applicant that owed
more than Rs. 6 crores to the respondent. The claim for repayment of
mobilisation advance was clearly rejected and in no uncertain terms.
17. Having considered the rival contentions, I am of the view that the
present application cannot succeed. Firstly an application for interim reliefs
was filed under section 9 which came to be withdrawn. The very same relief
are now sought in this interim application. The question is whether the
reliefs for interim protection after an Arbitral award is passed and filed via a
petition under section 9 can be, or should be treated differently if an identical
prayer is made in an Interim Application filed in the pending petition under
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai section 34. In my view the answer must be in the negative. Relief that
cannot be sought or granted under Section 9 cannot in the facts of the case be
granted under this IA in the Section 34 petition. The law as it stands and as
been reiterated after the judgment of this court in Dirk India is that only
successful party would be entitled to seek interim reliefs post arbitral award
in order to ensure that enforcement of the award is meaningful. A successful
party in arbitration therefore must be provided all assistance in enforcing
that award and it is to this end that the decision in Dirk India has considered
the second facit of section 9. As recorded in paragraph 13 of the judgment
in Dirk India the Court was required to consider the proximate nexus
between the orders that were sought in the arbitral proceedings. That when a
interim measure of protection is sought after an arbitral award is made but
before it was enforced, the intention was to safeguard the fruits of the
proceedings until the award was enforced. The measure of protection is only
a step in aid of enforcement and to ensure that the fruits of arbitration are
realized and that the award is not rendered illusory.
18. Dirk India also holds that the scheme of section 9 postulates an
application for grant of interim protection after making the award but before
its enforcement for the benefit of the parties which seeks enforcement of the
award. Furthermore it holds that a party whose claim has been rejected
cannot seek to have the award enforced under section 36 and the purpose of
considering interim measures after passing of an award but before its
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai enforcement is only to secure the property for the benefit of party seeking
enforcement.
19. Dirk India goes on to hold that the court exercising jurisdiction under
section 34 not being court of Appeal does not have the same powers as that
of Appellate Court and the Court hearing section 34 does not pass the order
decreeing a claim. In a case where a claim has been rejected by arbitral
tribunal the Court under section 34 can uphold or set aside the award. Setting
aside of an award does not necessarily result in a claim that was rejected
being allowed. The applicants case is that the mobilisation advance was
repayable to it. The bank guarantees seek to secure that mobilisation advance.
The claim for payment of mobilisation advance has been rejected by the
arbitral tribunal and to that extent there is no question of the applicant
enforcing the award to recover the mobilisation advance. Since the applicant
is not entitled to enforce the award in those terms there is no question of
securing the amount of mobilisation advance.
20. Mr. Purohit had contended that under the award the bank guarantees
were directed to be released to the claimants. This Mr. Purohit submits is an
aspect that is relevant since the operation of the award having been stayed
and the petition under section 34 admitted, the bank guarantees are not
required to be released to the claimants. This argument in my view overlooks
the fact that the applicant is not the successful party as far as this claim for
repayment of mobilisation advance is concerned. The claim for payment of
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai mobilisation advance has been rejected and even assuming the applicant
succeeds in the section 34 challenge, the mobilisation advance will not be
automatically repayable. Succeeding in the section 34 petition thus will only
entail that the objections to the award are upheld and award set aside in part
or in full, but it will not result in the claim of the applicant for payment of
the mobilisation advance being allowed. Thus viewed, the operation of the
Award including the direction to release the bank guarantees having been
stayed is in my view of no consequence.
21. The bank guarantees were in place and were required to be kept in
place in anticipation of the publication of an award. If the award was in
favour of the applicant the guarantees would have to be kept alive as
contemplated in the Minutes of order dated 5 th October, 2020 in the earlier
round litigation . In the second round the award passed by the freshly
constituted tribunal has found in favour of the respondent. It has rejected the
applicants claim for repayment of mobilisation advance. The bank guarantees
therefore need not be kept alive and are to be returned. In fact, if these bank
guarantees are allowed to be encashed it would amount to grave injustice to
the respondents which has succeeded in the arbitral proceedings.
22. In the event the arbitration petition under Section 34 succeeds, it will
only result in the award being set aside to the extent it awards the claim as
against the applicant. That however will not result in the mobilisation
advance being ordered to be refunded to the applicants. In my view therefore
3-IAL-23237-2021-CARBP-483-2021.odt wadhwa/ rrpillai no case whatsoever is made out for either directing the respondent to renew
the bank guarantees or permitting their encashment. For all the aforesaid
reasons I pass the following order :
(i) Interim Application is dismissed.
(ii) No costs.
(A. K. MENON, J.)
Digitally
signed by
RAJESHWARI
RAJESHWARI RAMESH
RAMESH PILLAI
PILLAI Date:
2021.10.27
17:45:09
+0530
3-IAL-23237-2021-CARBP-483-2021.odt
wadhwa/ rrpillai
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!