Citation : 2021 Latest Caselaw 14489 Bom
Judgement Date : 5 October, 2021
1/3 47 IA-3734-20.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
INTERIM APPLICATION NO.3734 OF 2020
IN
FIRST APPEAL (ST) NO.5919 OF 2O2O
Pune Municipal Corporation through the
Commissioner .. Applicant/
Appellant
Versus
Surmilan Singh Soiban and Ors. .. Respondents
...
Mr.Vishwanath Patil with Mr.Kewal Ahya and Mr.Ankit Lodha
for the Applicant/Appellant.
...
CORAM: BHARATI DANGRE, J.
DATED : 05th OCTOBER, 2021
P.C:-
1. By the present application, the Applicant/Appellant., Pune Municipal Corporation, seeks condonation of delay in instituting the First Appeal.
2. The Appellant is aggrieved by the Judgment and Award dated 18/09/2019 passed by the MACT, Pune in MACP No.581 of 2014, directing the Appellant to pay compensation to the claimants as determined by the impugned Judgment and Award.
M.M.Salgaonkar
2/3 47 IA-3734-20.doc
The First Appeal is instituted by the Appellant on 07/08/2020. According to the Appellant, there is a delay of 62 days in fling the First Appeal whereas the Registry of this Court has noted the delay to be of 207 days. When an explanation was sought from the Registry as to how delay of 207 days has been arrived at, the calculation which has been placed on record is to the effect that from the date of the judgment i.e. 18/09/2019, the total period counted till fling of the First Appeal is 179 days, out of which 90 days limitation has been excluded alongwith period of 27 days consumed for obtaining certifed copy. A period of 145 days is thereafter added to 62 days as the period counted from the date from which the limitation came to be extended in terms of the order of the Hon'ble Apex Court in suo motu Special Leave Petition on account on the Covid pandemic. Therefore, 145 days are counted from 15/03/2020. In fact, the period of limitation for the Appellant expired prior to the said date i.e. 15/03/2020 and that is how the Appellant is calculating the delay as of 62 days. According to the Registry, the delay is of 207 days by adding the period of 145 days counted from 15/03/2020.
3. In any case, in the wake of the Covid pandemic, the Hon'ble Apex Court has issued directions, which stopped the running of period of limitation from 15/03/2020, on account of the closure of the Courts and the fling being not accepted on account of the Covid pandemic. The Appellant is surely entitled to get the beneft of the said period.
M.M.Salgaonkar
3/3 47 IA-3734-20.doc
4. The reasons for delay are explained in paragraphs 5 to 9 of the application, which in my considered opinion, are justifable. In any case, since the fling of proceeding was not accepted from 15/03/2020 and the Appeal could not have been fled till the fling in the Registry was resumed in August, 2020. The beneft has to be extended for the said period to the Appellant, since the period of limitation itself was extended during pandemic. Recording that suffcient cause has been shown by the Appellant in not fling the Appeal within the period of limitation, which expired before 15/03/2020, the delay of 207 days, calculated by the Registry, deserves to be condoned.
5. The Interim Application is made absolute in terms of prayer clause (a).
( SMT. BHARATI DANGRE, J.)
M.M.Salgaonkar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!