Citation : 2021 Latest Caselaw 14207 Bom
Judgement Date : 1 October, 2021
904.ITXA.1313.17.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
INCOME TAX APPEAL NO. 1313 OF 2017
The Pr. Commissioner of Income Tax-2 .... Appellant
V/s.
M/s Prathamesh Constructions .... Respondent
----
Mr. Vineet Sawant a/w Ms. Lizna Namawati i/b Mr. Charanjeet Chanderpal for appellant.
Mr. Aniket Malu i/b Mr. Akshay Petkar for respondent.
----
CORAM : K.R.SHRIRAM &
R.I. CHAGLA JJ.
DATED : 1st OCTOBER, 2021
P.C. :
1 Respondent carried on business as builders and
developers and developed a project named "Amrut Kalash" consisting
of 7 buildings 'A', 'B', 'C', 'D', 'E', 'H' and 'I' and parking slab of building
'G' having total 174 flats and 4 shops. No residential flats were
planned at plot 'G'. For assessment year 2008-2009 Respondent
claimed deduction of Rs.3,89,07,405/-under Section 80IB (10). The
project was first approved on 31.03.2001 and as per the provisions of
Section 80IB (10) the same should have been completed on or before
31.03.2008. The assessee - Respondent, as recorded in the order of
CIT(A), submitted a completion certificate dated 28.03.2008. Even on
Waghmare 1/7
904.ITXA.1313.17.doc
28.03.2008, the building 'G' was marked to be parking only is
undisputed. Therefore, upto 31.03.2008, respondent had not
contemplated any residential units in the building 'G'. Subsequently,
on 19.04.2011 respondent got the plan approved after purchase of
TDR whereby the plan for said building 'G', which contemplated
parking only, was revised and the same was approved as a building
with ground plus 6 floors comprising of 48 residential units.
According to appellant as the completion certificate issued on
29.03.2008 did not show building 'G' with ground plus 6 floors, the
certificate issued by the Pune Municipal Corporation was a part
completion certificate and hence, respondent was not entitled to the
deductions under Section 80IB (10). The Assessing Officer rejected
the deduction claimed and passed the assessment order dated
28.03.2013. Aggrieved by this order, respondent preferred an appeal
before Commissioner of Income Tax (Appeals). The CIT (A) allowed
respondent's appeal relying on his own decision in the case of
respondent for asessment year 2009-2010 as identical issues were
involved and held that respondent qualifies for deduction under
Section 80IB (10). Aggrieved by this order, appellant preferred an
appeal before the Income Tax Appellate Tribunal (ITAT). ITAT
dismissed the appeal of the appellant and confirmed the conclusions
Waghmare 2/7
904.ITXA.1313.17.doc
arrived at by CIT (A). Shri Sawant, the learned counsel for appellant
submitted that the tribunal erred in allowing the deduction under
Section 80IB (10) of the Act without appreciating that since the
housing project was approved on 31.03.2001, it was liable to be
completed by 30.03.2008 and the assessee had not completed the
entire project by 30.03.2008. Shri Sawant further submitted that the
stipulated completion certificate issued by the Pune Municipal
Corporation was also in respect of only buildings 'A', 'B', 'C', 'D', 'E', 'H'
and 'I' and not in respect of building 'G'. Even though the sanctioned
project was for buildings 'A', 'B', 'C', 'D', 'E', 'H' and 'I' and 'G' as parking
slab, Shri Sawant submitted that the plan which got sanctioned in
2001, ought to be seen as a whole and it had contemplated building
'G' to be parking. Shri Sawant submitted that respondent had taken
part completion certificate only before 31.03.2008 and the completion
certificate of building 'G' was obtained from respondent in which it
clearly mentioned that building 'G' was completed on 12.05.2011
along with the parking. Shri Sawant submitted that as per the
provisions under Section 80IB (10), the amount of deduction in the
case of an undertaking developing and building housing projects
approved before 31.03.2008 by a local authority shall be 100% of the
profits derived in the previous year from such housing project if, the
Waghmare 3/7
904.ITXA.1313.17.doc
housing project has been approved by the local authority before
01.04.2004 and the assessee completes such construction of housing
project on or before 31.03.2008. Shri Sawant submitted that the date
of completion of the housing project shall be taken to be the date on
which the completion certificate in respect of housing project is issued
by the local authority and as respondent had only a part completion
certificate on 20.03.2008 and the completion certificate for building
'G' was only issued much later, respondent was not entitled to claim
deduction under Section 80IB (10).
2 Shri Malu for respondent opposed the appeal and
submitted that the plan for constructing building 'G' was itself
conceived much later after 31.03.2008. Shri Malu submitted that
when the original plan was sanctioned in 2001 only the 7 buildings 'A',
'B', 'C', 'D', 'E', 'H' and 'I' were under reckoning and only after the
purchase of TDR on 19.04.2011, a fresh plan for building 'G' was
prepared as a building with ground plus 6 floors comprising of 48
residential units. Relying upon the judgment of this Court in the
matter of CIT vs. Vandana Properties1, Shri Malu submitted that
building 'G' constituted a separate project and cannot be considered as
an extension of the original project.
1 2012 SCC OnLine Bom 474
Waghmare 4/7
904.ITXA.1313.17.doc
3 We have heard learned counsel and in our view the
appeal requires to be rejected.
4 The substantial questions of law proposed are as under :
(i) "Whether on the facts and circumstances of the
case and in law, the Hon'ble Income Tax Appellate Tribunal was justified in allowing the deduction u/s 80IB(10) of the Act, without appreciating that since the housing project was approved on 31.03.2001, it was liable to be completed by 31.03.2008, whereas, the assessee had not completed the entire project by the stipulated date, i.e. 31.03.2008 and the stipulated completion certificate issued by the Pune Municipal Corporation was also in respect of only Buildings A, B, C, D, E, H and I and not in respect of Building 'G', even though the sanctioned project was for Buildings A, B, C, D, E, G, H and I ?
(ii) "Whether on the facts and circumstances of the case and in law, the Hon'ble Income Tax Appellate Tribunal was justified in allowing the deduction u/s 80IB(10) of the Act without appreciating the ratio of the decision of the Hon'ble Apex Court in Sarkar Builders which envisages deduction u/s 80IB(10) in respect of the entire project as a whole ?"
Waghmare 5/7
904.ITXA.1313.17.doc
5 In our view whether the assessee had not completed the
entire project by the stipulated date as observed by the Assessing
Officer or whether the assessee had completed the stipulated project
as held by CIT (A), are questions of fact.
6 In any event, we would agree with the view expressed by
CIT (A) and ITAT. This is because the original plan that was
sanctioned in 2001 had contemplated building 'G' to be only parking
slab and the revised plan dated 20.3.2008 also showed building 'G' to
be parking only. Therefore, upto 31.03.2008, respondent had not
even contemplated any residential units in the said building 'G'. It was
only subsequently that respondent got the plan approved after the
purchase of TDR on 19.04.2011 whereby the plan for said building 'G'
which contemplated only parking was revised and the same was
approved as a building with ground plus 6 floors comprising of 48
residential units. What is pertinent to also note is that respondent has
not claimed any deduction under Section 80IB (10) on the said
building 'G'. A question that was considered was whether the housing
project should be considered to be completed without the parking of
building 'G' as approved by the local authority. Undisputably the
entire project excluding building 'G' has been completed within the
stipulated period and the completion/ occupancy certificate was also Waghmare 6/7
904.ITXA.1313.17.doc
received within the time limit prescribed under Section 80IB (10). As
TDR for building 'G' was not available upto 2011, appellant could not
have constructed the said building. As held in Vandana Properties
(supra), the expression housing project is not defined under the Act
and the expression housing project in common parlance should be
accepted, which would mean constructing a building or group of
buildings consisting of several residential units.
7 In our view, the building 'G' cannot be part and parcel of
the housing project because the TDR for constructing building 'G' itself
was purchased on 19.04.2011. Consequently, in our view, respondent
was entitled to claim of deduction under Section 80IB (10) of the Act.
8 In our view, ITAT has not committed any perversity or
applied incorrect principles to the given facts and when the facts and
circumstances are properly analyzed and correct test is applied to
decide the issue at hand, then, we do not think that question as
pressed raises any substantial question of law.
9 The appeal is devoid of merits and it is dismissed with no
order as to costs.
Digitally signed by WAISHALI WAISHALI SUSHIL SUSHIL WAGHMARE
(R.I. CHAGLA, J.) (K.R. SHRIRAM, J.) WAGHMARE Date:
2021.10.08 03:05:06 +0530
Waghmare 7/7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!