Citation : 2021 Latest Caselaw 16258 Bom
Judgement Date : 24 November, 2021
9.wp.7955-21
PMB
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.7955 OF 2021
Madhukar Sukdeo Sangale and Ors. ..Petitioners
vs.
Union of India and ors. ..Respondents
Mr. Rahul Walia for petitioners.
Mr. T.J. Pandian a/w T.C. Subramanian and Dheer Sampat
for respondents.
CORAM : DIPANKAR DATTA, CJ &
M. S. KARNIK, J.
DATE: NOVEMBER 24, 2021 P.C.:
1. This writ petition, at the instance of the original
applicants in Original Application No. 557 of 2021 on the file
of the Central Administrative Tribunal, Mumbai Bench,
Mumbai (hereafter "the Tribunal"), is directed against an
order dated November 16, 2021. By such order, the Tribunal
vacated interim protection granted to the original applicants
(hereafter "the petitioners") on September 22, 2021 and
thereby allowed the application (Miscellaneous Application
No. 579 of 2021) filed by the respondents seeking vacation
of the interim order.
9.wp.7955-21
2. The only question that we are tasked to decide is,
whether the Tribunal acted legally on facts and in the
circumstances to vacate the interim order dated September
22, 2021.
3. With the consent of the parties, this writ petition is
taken up for final hearing at this stage.
4. The petitioners are employed as 'khalasi' under the
Central Railway. They were empaneled pursuant to a
selection process and on lateral movement, transferred
from Mumbai to Nashik in 2013. On the basis of a vigilance
report hinting at mal-practices in preparation of the panel in
which they figured, the petitioners were sought to be re-
transferred to Mumbai by orders dated November 15, 2014
and January 16, 2015. Aggrieved thereby, the petitioners
had the occasion to approach the Tribunal by instituting
Original Application No. 83 of 2015. By an order dated
February 5, 2015, the Tribunal stayed the operation of the
impugned orders. Ultimately, by a judgment and order
dated May 1, 2019, the Tribunal allowed O.A. No. 83 of
2015 in part by setting aside the impugned orders.
9.wp.7955-21
However, the respondents were granted liberty to proceed
in the matter after serving a copy of the relevant vigilance
report, based whereon the orders impugned before the
Tribunal were issued, to the petitioners. In terms of the
liberty granted by the Tribunal, a fresh exercise was
undertaken to re-transfer the petitioners to Mumbai.
Apprehending re-transfer to Mumbai from Nashik, the
petitioners instituted O.A. No. 557 of 2021. A specific
statement appears to have been made in the application
that copy of the vigilance report, despite the directions of
the Tribunal, have not been made over to the petitioners.
5. O.A. No. 557 of 2021 was moved before the Tribunal
on September 9, 2021. A Single Bench of the Tribunal,
comprised of the Member (Administrative), declined ad-
interim relief as prayed for but issued notice to the
respondents with direction to file a short reply on interim
relief by September 21, 2021. The Tribunal intended to hear
the petitioners on the question of interim relief on
September 22, 2021.
6. While O.A. No. 557 of 2021 was pending before the
9.wp.7955-21
Tribunal, two orders dated September 18, 2021 and
September 20, 2021 were issued by the Chief Workshop
Manager, Traction Machine Workshops, Nashik Road, Nashik
(Exhibit 'U'). By such orders, it was sought to be conveyed
that empanelment of the petitioners as 'khalasi' stood
cancelled by an order of the competent authority.
7. On September 21, 2021, two applications were filed
by the petitioners. First, Miscellaneous Application No. 540
of 2021 was filed being an application for amendment of
O.A. No. 557 of 2021; whereas the second application,
being Miscellaneous Application No. 541 of 2021, prayed for
stay of operation of orders, inter alia, dated September 18,
2021 and September 20, 2021. A prayer was also made for
direction on the respondents to permit the petitioners to
continue to render services at Nashik.
8. The Tribunal heard Mr. Walia, learned advocate for the
petitioners on September 22, 2021 and by the order passed
on that date, proceeded to stay the operation of the orders
dated September 18, 2021 and September 20, 2021.
Despite notice having been served on the respondents, they
9.wp.7955-21
were not represented before the Tribunal.
9. On October 4, 2021, M.A. No. 579 of 2021 came to be
filed by the respondents urging that the ex-parte ad-interim
order dated September 22, 2021 ought to be vacated.
10. We may record at this stage that although none of the
two miscellaneous applications filed by the petitioners [M.A.
Nos. 540 of 2021 and 541 of 2021] were listed on
November 16, 2021, the application of the respondents
being M.A. No. 579 of 2021 came to be listed on that date,
and the impugned order, as noted above, was passed by the
Tribunal upon hearing the parties.
11. The primary reasons for which the Tribunal proceeded
to vacate the order dated September 22, 2021 are that (i)
interim relief came to be granted erroneously without
hearing M.A. No. 541 of 2021 and (ii) the Chief Workshop
Manager, Traction Machine Workshops, Nashik Road, Nashik,
who issued the impugned orders dated September 18, 2021
and September 20, 2021, had not been impleaded as
respondent in the original application.
12. We have failed to comprehend as to why these
9.wp.7955-21
reasons were considered sufficient by the Tribunal to vacate
the interim order that was passed on September 22, 2021,
without even attempting to hear and pass orders on M.A.
Nos. 540 of 2021 and 541 of 2021. It is not the case of any
of the parties that the orders dated September 18, 2021
and September 20, 2021, which were issued subsequent to
institution of O.A. No. 557 of 2021, were not sought to be
challenged by the petitioners at all. It is not also the case
that the petitioners made no attempt to bring on record the
Chief Workshop Manager, Traction Machine Workshops,
Nashik Road, Nashik as a respondent. Since M.A. Nos. 540
of 2021 and 541 of 2021 had been filed and must have
been there in the records of O.A. No. 557 of 2021, the
Tribunal ought not to have taken a hyper-technical view of
the matter for the purpose of vacating the interim order by
recording that it had erroneously passed the same. That
apart, absence of the Chief Workshop Manager was also not
crucial, in the sense that although the Chief Workshop
Manager had issued the orders dated September 18, 2021
and September 20, 2021, perusal thereof would reveal that
9.wp.7955-21
he merely sought to convey the decision of the competent
authority canceling the empanelment of the petitioners. The
Central Railway and the General Manager, Central Railway
being on record, we are of the view that mere absence of
the Chief Workshop Manager was not fatal so as to warrant
vacation of the interim order dated September 22, 2021.
13. That apart, the Tribunal also seems to have erred in
failing to notice that the respondents, despite being put on
notice that the Tribunal intended to consider the prayer for
ad-interim relief on September 22, 2021, went
unrepresented. Indeed, the order dated September 22,
2021 was passed after hearing only Mr. Walia, but it is an ex
parte order passed on notice. The petitioners ought not to
suffer if the respondents did not choose to appear and
oppose the prayer for ad-interim relief. The reason assigned
in the application for vacating interim order, being M.A. No.
579 of 2021, is that the name of the advocate was not
printed on the board. Having regard to the admission in
such application that the number of the original application
together with the names of the parties were rightly
9.wp.7955-21
described on the board, the absence could not possibly be
justified; more so, when one finds a statement in the said
application that only a couple of days before, the advocate
engaged by the respondents had filed his memo of
appearance before the Tribunal.
14. Be that as it may, while considering a prayer for
interim relief, the Courts/Tribunals are required to consider
whether the three factors of a prima facie case for
consideration having been set up, the balance of
convenience/inconvenience being in favour of grant of
interim relief and the possibility of irreparable loss, injury
and prejudice being suffered by the party, if interim relief
were not granted, are satisfied or not. We are of the
considered view that the Tribunal while vacating the interim
order overlooked that the harm and injury that the
petitioners are likely to suffer if ad-interim relief were
declined/vacated would be much more than the harm and
injury that is likely to be caused to the respondents if their
prayer had not been granted. All the factors were
overwhelmingly in favour of continuance of the interim
9.wp.7955-21
order.
15. Over and above this, having regard to the fact that the
petitioners had filed M.A. Nos. 540 of 2021 and 541 of 2021
on September, 2021, nothing prevented the Tribunal from
taking such applications on board before considering M.A.
No. 579 of 2021.
16. We are, thus, satisfied that the Tribunal has exercised
its jurisdiction illegally. While setting aside the order dated
November 16, 2021 and restoring the interim order passed
on September 22, 2021, which we direct would continue till
the end of December, 2021 or until further orders to the
contrary are passed by the Tribunal, we direct that M.A.
Nos. 540 of 2021 and 541 of 2021 shall be heard at the first
instance as early as possible but not later than two weeks
from date of receipt of a copy of this order. After
consideration of M.A. Nos. 540 of 2021 and 541 of 2021,
the Tribunal may proceed to hear M.A. No. 579 of 2021
afresh. After the prayer for grant of interim relief and/or its
vacation is considered in accordance with law, we would
expect the Tribunal to fix an early date of hearing of O.A.
9.wp.7955-21
No. 557 of 2021 bearing in mind the fact that the dispute
has its origin in a process initiated in 2013 as well as in the
light of the specific allegation made by the petitioners that
despite the Tribunal's earlier order dated May 1, 2019, the
respondents are yet to supply the vigilance report to the
petitioners.
17. The writ petition stands allowed for the reasons
mentioned above. No costs.
18. Reasons assigned/observations made above are only
for the purpose of disposal of this writ petition and may not
influence the Tribunal while it proceeds to hear the parties
in terms of this order. All contentions are left open for the
parties to urge before the Tribunal for a proper decision by
it.
(M. S. KARNIK, J.) (CHIEF JUSTICE)
Digitally
signed by
PRADNYA
PRADNYA MAKARAND
MAKARAND BHOGALE
BHOGALE Date:
2021.11.25
11:09:48
+0530
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!