Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Maharashtra State Electericity ... vs Lustre Engineering Corporation ...
2021 Latest Caselaw 6962 Bom

Citation : 2021 Latest Caselaw 6962 Bom
Judgement Date : 3 May, 2021

Bombay High Court
Maharashtra State Electericity ... vs Lustre Engineering Corporation ... on 3 May, 2021
Bench: A. K. Menon
               IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                           CIVIL APPELLATE JURISDICTION

                    ARBITRATION PETITION NO. 116 OF 2018

                                     ALONGWITH

                    ARBITRATION PETITION NO. 117 OF 2018

                                     ALONGWITH

                    ARBITRATION PETITION NO. 118 OF 2018

                                     ALONGWITH

                    ARBITRATION PETITION NO. 119 OF 2018

                                     ALONGWITH

                    ARBITRATION PETITION NO. 120 OF 2018



Maharashtra State Electricity                        ...    Petitioner
Transmission Company Ltd through
Its Superintending Engineer
       Vs.
Lustre Engineering Corporation and Anr.              ...    Respondents


Mr. Anil Sakhare, Senior Advocate a/w. Mr. Rohan Mirpuri i/b. Mr. Ashok
Gade and Mr. Sagar Jadhav for the Petitioner.
Mr. Nigel Quraishy i/b. Mr. Dushyant Krishnan for Respondent no. 1.


                                     CORAM : A. K. MENON, J.
                                     RESERVED ON : 25th FEBRUARY, 2021
                                     PRONOUNCED ON : 3rd MAY, 2021




                                                                        1/60
ARP-116-2018-CONNECTED MATTERS.odt
            JUDGMENT :

1. Called for final hearing and disposal. These are petitions under Section

34 of the Arbitration and Conciliation Act, 1996 ["the Arbitration Act"]

seeking to challenge an Arbitral Award dated 23 rd May, 2018 passed by an

Arbitral Tribunal appointed pursuant to Section 18 (3) of the The Micro,

Small and Medium Enterprises Development Act, 2006 ["MSME Act"].

2. The petitioners are aggrieved by the Award dated 23 rd May, 2018

which according to the petitioners was passed without following due process

of law. No issues were framed nor was any evidence led. No opportunity was

offered to the petitioner to meet the case against them and thus it is contended

that the Award is in violation of the principles of natural justice. Before

dealing with the contentions of parties briefly put the facts are as follows :

3. The petitioner is engaged in the transmission of electricity. Respondent

no. 1 had filed five petitions petition before the Micro and Small Enterprises

Facilitation Council ["the Facilitation Council" / "the Council" ] under Section

18(1) of the MSME Act. In all these petitions the claims arise out of different

Work Orders. All of them are identical in nature and hence by consent the

facts relating to the impugned order in the first of these petitions being

Arbitration Petition no. 116 of 2018 is taken up for consideration. rrpillai

ARP-116-2018-CONNECTED MATTERS.odt

4. The claim pertains to alleged delay in payment in respect of work of

construction of a Transformer, Gantry and Equipment Foundation T/F oil soak

pit, cable trench, earthing pits, pipe line and metal spreading work for a 50

MVA, 100/22 KV 4th T-F @ Vasai S/Stn. The claims were for principal sums

and interest. Similar claims have been lodged in other cases as well. It

transpires that the petitioner had invited offers from interested parties to

carry out work as defined above and the respondent had made an offer

which came to be accepted on terms and conditions specified by the petitioner

in an enquiry number 4600 dated 20 th September, 2010 and the acceptance

which was communicated on 24th September, 2010.

5. Pursuant to an application filed by the respondent on 1 st April, 2017

under Section 18 of the MSME Act and the Maharashtra Micro and Small

Enterprises Facilitation Council Rules 2007 ("MSME Rules") the Facilitation

Council passed an order to initiate Arbitration on 14 th February, 2018 in

Petition no. 38 of 2017. The claim in the petition was for delayed payment of

a sum of Rs. 17,03,735 /- towards principal and a sum of Rs. 8,52,775/-

towards interest. Thus a total of Rs. 25,56,510/- was claimed as on date of

filing the petition. The order to initiate arbitration recorded that the

Facilitation Council held conciliation meetings between the parties on two

occasions after due notice to all. The respondent in the application viz. the

petitioner herein had not responded to the attempts at settlement and was not

interested in conciliation and hence conciliation proceedings were terminated

and arbitration proceedings were initiated. The Council ordered that it

ARP-116-2018-CONNECTED MATTERS.odt would act as the Arbitral Tribunal. Notices were accordingly issued to the

parties.

6. The basis of the claim is a purchase/work order copy of which is at

Exhibit D to the petition dated 24 th September, 2010. It is addressed by the

petitioner to the respondent and sets out the scope of work i.e. erection of an

additional transformer including supply of required material and civil works

at Mahape Sub-station, Kalwa. The work order was of a value of

Rs.3,88,64,583/-. It provided for security deposit of 5% of the order value

and it contained numerous other terms and conditions. It interalia provided

for packing, forwarding and transportation, watch and ward, bringing of

material on site, supervision of the work to be carried out at site subject to the

approval of the Executive Engineer.

7. Reference is also made to the general conditions of contract included

by reference in clause no. 55. A payment schedule was also provided for

according to which 70% of the total cost of the material was to be released

after supply of material at site, balance 30% of the cost of material after

successful commissioning. The bills against the labour component were to

be paid first and others in running account bills and a final bill. After

meeting certain initial objections to the maintainability, the respondents

insisted that the petition was maintainable before the Council. Subsequently

pursuant to an order of the Council a conciliation meeting was held on 19 th

December, 2018 and after discussions it was noted that the respondent had

ARP-116-2018-CONNECTED MATTERS.odt revised their claim. These claims were so revised in view of the fact that the

petitioner had already paid the total amount of the bills and retention money

in all those cases and no dues were pending. It is the case of the petitioner

that all bills and retention amounts had been already settled and the

respondent was requested to withdraw the claim for interest. The respondent

however acting through its partner was not agreeable to withdraw the claim

for interest and thus the reference proceeded.

8. On or about 24th February, 2018 the respondent in response to a query

from the Facilitation Council submitted that the total amount outstanding is

an interest component of Rs.10,47,031/-. The principal amount was shown

as "Nil". This communication was in response to direction by the Council to

submit detailed statements giving particulars of payment and receipt of

payments. However what was submitted by the respondent is just a single

page letter mentioning the total amount due as Rs. 10,47,031/-. An annexure

to the letter sets out nine bill numbers, bill amounts, due dates, balance

amounts, date of payments and number of days delay. On this basis interest

was computed from 6th July, 2016 to 14th February, 2018. The reason for

claiming interest from 6th July, 2016 is not understood since the tabulated

statement itself shows that payments of the nine bills were made between

17th June, 2015 to 29th May, 2017. Interest was then computed on the bill

amounts to arrive at a total of Rs. 10,47,031/-.

ARP-116-2018-CONNECTED MATTERS.odt

9. In an affidavit in reply, the petitioner contended that the reference was

not maintainable under the provisions of the Act. That the requirement under

the Act was that an applicant would have investment in plant and machinery

not exceeding Rs. 5 crores, whereas the schedule of assets disclosed by the

respondent in their petition disclosed an investment of Rs.11,96,22,322/-.

From the record available with the petitioner- Corporation the amounts due

to the respondent - contractor had already been paid as of 13 th June, 2017

and nothing was then due. Moreover it was contended that the work

involved was that of erection of a transformer. The time limit had also

expired. The work site was handed over to the respondent on 21 st January,

2015 and the contract contemplated completion of work by 20 th May, 2016

excluding the monsoon period. The total civil work done was of a value of Rs.

77,97,538. 62 and of which the applicant had completed the work on 20 th

May, 2016 for an amount of Rs. 77,93,035.09. While dealing with the

merits of the claim the petitioner contended that the six bills submitted by the

respondent had all been paid within reasonable time and there was no

occasion to charge any interest. It was contended that the payments could be

made only after getting necessary sanctions and approvals and that itself took

up a reasonable amount of time.

10. On behalf of the petitioner Mr. Sakhare submitted that the sixth and

final bill was delayed since there was quantity variations in various items of

the work order. The final bill was then processed and clubbed with others i.e.

ARP-116-2018-CONNECTED MATTERS.odt the electrical and civil work bills were clubbed and submitted to the

competent authority. The quantity variation required modification of the

purchase order in the SAP system failing which the payment would not have

been cleared. After requisite approvals, Purchase Order modification was

required to be carried out in the SAP system and following these changes

payments were processed. It is therefore contended that on behalf of the

petitioners there was no delay in paying the principal sum and hence no

justification in claiming interest. Without prejudice it was contended that in

view of the fact that the principal amount had already been paid no

reference could have been filed under Section 18 to claim only interest.

11. It is also contended that the MSME Act does not contain any provision

to claim only interest when principal sums have already been paid, especially

because there was no clause for payment of interest on delayed payments in

the contract in question. Mr. Sakhare therefore submitted there was no merit

in the claim filed by the respondent before the Facilitation Council despite

which at a hearing described as a final hearing on merit on 23 rd May, 2018 a

four member Council consisting of the Ex-officio Chairperson, Joint Director

of Industries, a Member Secretary who was the Deputy Director of Industries

and two members of the Council observed on facts that both civil and

electrical works had been undertaken pursuant to the work order of erection

of an additional transformer which included the supply of requisite materials

and civil work.

ARP-116-2018-CONNECTED MATTERS.odt

12. The Award noted that there was delay in the work and which were

caused due to the petitioners constraints. Delay in the work did not result in

any penalty being levied on the respondent. The case of the respondent was

that having completed the activity of "electrical contracting, overhauling /

repairs of power transformers" they were entitled under the work order to

certain payments in the sum of Rs. 17,03,735/- at the time of filing the

petition. The respondent had submitted its revised claim along with interest

on delayed payment. According to the respondent the delay was between one

month and eleven months. In the case of nine bills several of these amounts

were paid in installments resulting in delays.

13. The Award records the contention of the petitioner being a

Government undertaking a Work Order had been placed during the

financial year 2014-15 and it was contended that being a work order the

provisions of the MSME Act 2006 were not applicable. The work was

completed on 20th May, 2016 and the entire principal sum had been paid

within the reasonable time taken for passing of the bills. The respondent had

not acceded to the requests of withdrawing the claim for interest. The

Council proceeded then to hold that after taking into considering the records,

documentary evidence submitted by the respondent it had decided on merits

and passed an order on 23rd May, 2018 which is reproduced below :

ORDER

1. The reference Petition No. 38/2017 is allowed in terms of

prayer.

ARP-116-2018-CONNECTED MATTERS.odt

2. The Respondent is required to pay to the Petitioner a

principal amount of "Nil" along with interest as per the Section 16A

of the MSMED Act, 2006 on each and every due amount of the

invoice when become payable after deduction of 30 days, till the

realization of the amount to the Petitioner.

3. The Principal and interest amount are to be paid by the

Respondent to the Petitioner within a period of one month from the

date of receipt of this Award.

4. No Order as to costs.

5. The case is disposed off and closed.

6. This order is issued on this 23 day of May, 2018.

The order records that the petition was allowed as prayed. It required the

petitioner to pay no amounts towards principal but directed payment of

interest under Section 16A of the MSME Act on every invoice amount when

payable after a deduction of 30 days till realisation of the amount to the

petitioner. The operative order in clause 2 therefore requires to be analysed

to understand the true meaning and effect of the order.

14. Mr. Sakhare submitted that the order lacked clarity and it was not

possible to understand the scope of the order from a plain reading of the

operative portion or even considering the findings of the Facilitation Council.

Being aggrieved by the order the above petitions came to be filed. At the

hearing of the petition for admission the Advocates on both sides agreed that

the matter be sent back to the Facilitation Council for providing

ARP-116-2018-CONNECTED MATTERS.odt clarifications without which the award was not meaningful. After the matter

was remanded to the Facilitation Council pursuant to the consent minutes

signed between the parties which were made order of the Court, the

Facilitation Council made what is described as an "Additional award as per

the order dtd. 07.12.2018 by the "Hon'ble High Court, Bombay". By this

Additional Award the Facilitation Council proceeded to calculate the interest

payable in addition to the Award issued by the Facilitation Council on 23 rd

May, 2018 while recording that "other terms and conditions" of the Award

issued by the Council remained the same. A tabulated statement was

thereafter appended to the additional Award listing out the nine invoices

forming subject matter of Petition. 38 of 2017, Bill nos, Bill dates, Due dates,

Amounts due, Amounts paid, Dates of payment, Bank interest rate multiplied

three times, the delay in the number months and computation of interest till

date of receipt of payments. In this manner a computation was arrived at

unilaterally.

15. One other interesting factor is that the original award was made by a

Council consisting of four members whereas the additional award is made by

five members, two of whom were entirely new to the dispute. The five

member Council therefore consisted of three members from the original

Facilitation Council which passed the Award and two new incumbents who

had not participated in the hearing prior to the first and main award.

ARP-116-2018-CONNECTED MATTERS.odt

16. The petitioner is aggrieved by the original Award and the Additional

Award passed pursuant to the limited remand in terms of the Consent

Minutes of Order. Mr. Sakhare representing the petitioner submitted that the

original Award does not quantify any amount payable. The principal amount

already having been paid there was no question of payment of interest. Even

assuming that the petitioner had liability to pay interest the said amount is not

been quantified in co-relation to the principal sum. My attention was invited

to the order dated 7 th December, 2018 passed by this Court which required

the Facilitation Council to convey to the High Court the corrections in the

Award, their interpretation of the Award and an Additional Award and in

terms the amount payable under the decree. Mr. Sakhare submitted that this

was not done within the time of 12 weeks granted by the order or even

thereafter. He submitted that the period of 12 weeks expired on 6 th March,

2019 despite which the Council had not conveyed the decretal amount to the

High Court.

17. In the meanwhile in view of the Additional Award having been passed

an interim application was filed by the petitioner seeking amendment to the

petition to incorporate a challenge to the Additional Award. This amendment

is being opposed as being barred by limitation since according to the

respondent the original Award had merged with the Additional Award as a

result of which the Arbitration petition pending in this Court became

infructuous. Mr. Sakhare submitted the Court had remanded the matter

ARP-116-2018-CONNECTED MATTERS.odt under Section 34(4) of the Arbitration Act. He submitted that the order

erroneously refers to Section 33 in the minutes. He contended that the

remand was at all times contemplated as one under Section 34(4) since these

petitions under Section 34 have been kept pending. He then submitted that

the Council did not communicate its decision to this Court nor did it decide

within the allocated 12 weeks as required by the order of the High Court. The

petitioners have filed the interim application in the pending Arbitration

Petition on their own after having coming to learn of the decision of the

Council. He therefore submitted there was no fresh cause of action that had

arisen. The interim application is therefore not barred by the law of

limitation. According to Mr. Sakhare there was no question of any merger as

pleaded by the respondent.

18. Mr. Sakhare then submitted that reference to Section 33 is erroneous

because under Section 33(1) a party could approach the Tribunal for

correction of errors, clerical or otherwise or to interpret any aspect of the

Award. The Tribunal is then empowered to entertain such a request and

provide its interpretation and/or correct errors on its own within thirty days.

Section 33(4) provides an option to a party to make request to make an

additional award in the event -of any claim being omitted and the tribunal is

authorised to make such an Award within 30 days of receipt of such a

request. The Tribunal also has the power to extend time to ensure compliance

with the appropriate Sections. According to Mr. Sakhare the decision of the

Tribunal rendered on 25th May, 2018 was not under Section 33 and was

ARP-116-2018-CONNECTED MATTERS.odt under Section 34(4) since the Arbitration petition continued to be pending.

According to him the minutes incorrectly made reference to Section 33. Thus

he submitted that the interim application for amendment is not barred either

by limitation or on account of merger of the original Award with the latter

Award. He submitted that the Tribunal had failed to comply with the order of

the High Court and hence any order passed beyond the period of 12 weeks

would be vitiated as without authority.

19. Mr. Sakhare submitted that if the Council had communicated its

decision within twelve weeks as directed by this Court, the petitioner would

be entitled to file its objection in law. In this behalf reliance is placed on the

decision of the Supreme Court in Kinnari Mullick and Anr. vs. Ghanshyam

Das Damani1 by contending that the Court had only two options after the

Award was pronounced. One was to set aside the Award under Section 34

and the second option to adjourn proceedings to enable tribunal to take

suitable action to eliminate grounds for challenge under Section 34.

According to Mr. Sakhare this Court had exercised the second option to

eliminate grounds for challenge and that is the reason why reference to

Section 33 in the minutes is incorrect. He then submitted that the Arbitral

Tribunal had failed to comply with the order of this Court within time and

not having done so, the petitioners on its own filed the interim application.

The amendment was required in view of the Award dated 25th April, 2019

and it is not a fresh application under Section 34.

1 (2018)11 SCC 328

ARP-116-2018-CONNECTED MATTERS.odt

20. Reliance is placed on the decision of the Supreme Court in S tate of

Maharashtra vs. Hindustan Construction Co. Limited 2 (2010) 4 SCC 518 in

this respect Mr. Sakhare submitted that without prejudice to the aforesaid in

the event the order passed by the Tribunal of 25th April, 2019 is treated as

Additional Award under Section 33(5) the doctrine of merger would not

apply since these petitions under Section 34 can still be prosecuted and can

be decided on merits. The Additional Award can therefore form subject

matter of challenge in the present petition itself. Reliance is placed on the

decision of Delhi High Court in Prakash Atlanta Jv & Ors. vs National

Highways Authority of India & Ors. 3 in support of the contention that the

concept of merger will not apply in the case of an Additional Award.

21. The next submission on behalf of the petitioner is on the aspect of

compliance, if any, required with Section 19 of the MSME Act. In support of

his contention that Section 19 of the Act would not be attracted Mr.Sakhare

submitted that the requirement of depositing 75% of the amount of the

Award will not be attracted since the principal sum is described as Nil. Since

the principal sum was Nil when the Award was passed the question is

whether there was any requirement of deposit as contemplated under Section

19. Even otherwise the Award as originally passed did not quantify any

amount. It was not therefore an executable Award which is the reason why

the parties agreed to have the matter sent back under orders of this Court.

2 (2010) 4 SCC 518 3 (2016) SCC online Delhi 743

ARP-116-2018-CONNECTED MATTERS.odt Even thereafter the computation is not forthcoming as contemplated and

provisions of Section 19 would not be attracted since it is only interest that is

sought to be awarded, that too when the contract did not provide for interest.

22. The third ground of challenge canvassed by Mr. Sakhare is the

improper constitution of the tribunal as being in violation of Section 10 of the

Arbitration Act. It is contended that the MSME Act contemplates a tribunal of

not less then three members and not more than five. The Arbitration Act on

the other hand contemplates parties having the freedom to decide on the

number of Arbitrators, provided that the number of arbitrators shall not be

an even number. Provisions of Section 10 are said to be applicable to the

instant case and there was no consent sought from the petitioner to constitute

this new tribunal upon remand. Mr.Sakhare contended and in my view

correctly that when the Award was initially passed on 23 rd May, 2018 the

Tribunal consisted of four persons whereas when the further order /

Additional Award dated 25th April, 2019 came to be passed upon remand the

Tribunal consisted of five members, two out of these five were new and were

not part of the tribunal when the original Award dated 23 rd May, 2018 was

passed.

23. Reliance is placed on affidavit filed by the petitioners Advocate Mr.

Mukund Rao Kadam which sets out that some of the hearings took place

before three arbitrators and some before four. The contents of the affidavit

ARP-116-2018-CONNECTED MATTERS.odt are not controverted. The Supreme Court had in the case of M. K. Global

Financial Services Limited vs. Girdhar Sondhi 4 observed that if there are

matters not contained in the record of the Tribunal but were relevant for

determining issues arising under Section 34(2)(a) such fact should be

brought on record by filing affidavits. Not having controverted the contents of

the affidavit Mr. Sakhare submitted that the contents of Kadam's affidavit

dated 29th January, 2020 will have to be considered as true.

24. Mr. Sakhare then submitted that notwithstanding any of the above the

Award is bad in law in terms of Section 34(2)(a)(iii) & (v) because the

petitioner had no notice of constitution of the Tribunal or the composition of

the Tribunal. The Tribunal is constituted without consent of the petitioner.

Last but not the least, the petitioner was deprived of an opportunity to present

its case including by raising objection to the constitution of the Tribunal. He

therefore submitted that the Award suffers from a patent illegality having

been contrary to the fundamental policy of Indian Law and failure to adopt a

judicial approach thus amenable to challenge under Section 34(2)(b)(ii) of

the Arbitration Act.

25. Mr. Sakhare placed reliance on the decision of the Supreme court in

Associate Builders vs. Delhi Development Authority 5 . It is also contended that

following Associate Builders (supra) a judicial approach was required to be

followed by the Tribunal which it has not. Mr. Sakhare submitted that there

4 (2018) 9 SCC 49 5 (2015) 3 SCC 49

ARP-116-2018-CONNECTED MATTERS.odt were no pleading to support the alleged delay in payment. The work order

provides for stages for submission of bills, verification of bills and their

certification. No pleadings are to be found on these aspects. Dealing with

these aspects that clause 28 of the work order specifies the verification

process by three authorities. There was no challenge to this in the Arbitral

Reference. Delay in payments was not one of the reasons for filing the

petitions under Section 18(3) of the MSME Act. The principal sum had by

then been paid over albeit after filing the claim but in the absence of any

evidence or contractual provisions for payment of interest the award

represents a patent illegality. The Award is passed without application of

mind and lacks judicial approach. The Tribunal has framed no issues and

called for no evidence. The respondent made no attempt to lead any evidence.

No documents were proved by the respondent. The Award being a non

speaking Award containing no reasons there is no application of mind.

26. The contention on behalf of the petitioner is that the respondent

neither produced any evidence to establish how there was delay in the first

place nor the entitlement to interest in the event of there being delay. In

respect of each bill, delay had to be proved and liability had to be established.

It is not in doubt that principal sums had been paid over and therefore it was

incumbent upon respondent to establish these facts prior to seeking interest.

It is therefore reiterated that the Award suffers from a patent illegality being

in contravention of Section 31(3) of the Arbitration Act, thus susceptible to

setting aside under Section 34(2A).

ARP-116-2018-CONNECTED MATTERS.odt

27. Mr. Sakhare submitted that even otherwise. the respondent had filed

copy of letter dated 24 th November, 2016 referring to the final bill which

clarifies that no other claims will be raised in respect of the work. He

therefore submitted that there are similar letters in all cases forming subject

matter of these petitions. Thus in the absence of any specific claim there was

no occasion to pass any further award. Mr. Sakhare also relied upon the

decision in M/S Dyna Technologies Pvt.Ltd. vs M/S Crompton Greaves Ltd. 6

and submitted that reasoning of the tribunal should be adequate and

intelligible. In the present case the Award satisfies neither requirement and

is therefore liable to be set aside. When the principal amount was admittedly

"Nil" there was no question of making any payment of interest.

28. The next point urged by Mr. Sakhare is that the mandate of the tribunal

came to an end upon expiry of 90 days from the letter dated 14 th February,

2018 viz. on 13th May, 2018. Whereas the award was made only on 23 rd

May, 2018. Thus having been passed after expiry of the mandate the award

is void ab intio. Mr. Sakhare submitted that the petitioner had not consented

to extension of time nor was such a request made by the Council or the

respondent. The matter was remanded to the Council by the Court to

complete the specified exercise within 12 weeks which expired on 6 th March,

2019 and an additional award is seen to have been passed on 25 th April,

2019. Once again after the expiry of time granted. Thus without authority of

law.

6 2019 SCC OnLine SC 1656.

ARP-116-2018-CONNECTED MATTERS.odt

29. Reliance is placed on the decision of the Delhi High Court in Bata

India Limited vs Avs International Private Limited 7 in support of the

contention that Section 18 of the MSME Act would have overriding effect

over other laws including the Arbitration Act and therefore the period of 90

days was not negotiable and could not have been extended. Provisions of

Section 18(5) are to be held to be binding and therefore an Award passed

beyond the period of 90 days would not be good in law and therefore would

have to be set aside. The Delhi High Court had also placed reliance on the

decision of the Gujarat High Court in Principal Chief Engineer Vs.Manibhai

and Brothers (Sleeper) and Ors. 8 . Manibhai (supra) was subject matter of SLP

17434 of 2017 which came to be rejected upholding the decision of the

Gujarat High Court. Thus the period of 90 days is said to be sacrosanct and

any order passed beyond that period would be invalid. Furthermore upon

remand by the High Court, the Council was granted 12 weeks' time (which is

about 84 days). However the additional award was not made till 25 th April,

2019. On this basis Mr. Sakhare contended that the Award is likely to be set

aside.

30. The petitions are opposed by Mr. Quraishy on behalf of the

respondents. He submitted that under Section 19 of the MSME Act, deposit of

75% of the amount awarded was a pre-condition and this Court could not

entertain this petition without such a deposit. He relied upon a summary of

7 (2019) SCC Online Delhi 9801 8 AIR 2005 SC 3549,

ARP-116-2018-CONNECTED MATTERS.odt claims under the six petitions and contended that the principal amount due

was Rs.2,75,684/- and interest amounted to Rs.2,16,58,476.61 as of 30 th

April, 2019 and Rs.2,98,67,411.14 as on 12 th October, 2020. According to

Mr. Quraishy unless 75% of these amounts were deposited this petition could

not be entertained. He demanded strict compliance with Section 19.

31. The next plank of opposition was limitation. According to him the

remand was under Section 33(1)(a) of the Arbitration Act and not under

Section 34(3). Inviting my attention to a tabulated statement containing

dates of various work orders, completion dates, the dates of references and

part amounts received prior to conciliation, he submitted that all payments

had not been received when reference were filed. The balance payment of

the principal sums was received after the references were made and it was

for this reason that the principal sum payable was shown to be "Nil" in some

of the cases. Nevertheless without prejudice to the bar under Section 19 Mr.

Quraishy submitted that when the parties agreed to approach the Facilitation

Council they so agreed under Section 33 for correction, interpretation and for

an additional award and not under Section 34(4). The question that arises is

whether the High Court remanded the matter under Section 33 or Section

34(4).

32. Mr. Quraishy further submitted that since the petition was filed

without fulfilling the pre-condition of deposit / payment of 75% the petitions

cannot be entertained. He therefore called for summary rejection of these

ARP-116-2018-CONNECTED MATTERS.odt petitions. According to him the remand could not be under Section 34(4)

since the Minutes signed by the parties referred to the requirement of

interpretation of the amount payable. The parties were to approach the

Council under Section 33 and the Council was to correct / interpret the

award under Section 33. The High Court had not passed any order on the

merits of the case to take any action to eliminate grounds for setting aside. If

the High Court had remanded the matter under Section 34(4) it would be

seen in the order of the High Court which would have considered the effect of

the Award and the need for eliminating grounds for setting aside of the

Award. No such order has been passed.

33. In my view unless the Court was satisfied that there were grounds for

setting aside the award the occasion for remand would not have arisen.

However this aspect would have to be considered in more detail after I deal

with all the points raised by Mr. Quraishy.

34. According to Mr. Quraishy the Arbitration Act does not invite

intervention of the Court and even when it does it is required to be kept at the

bare minimum. It is therefore contended that the contention of the petitioners

that pendency of Section 34 petitions would imply that the remand was made

pursuant to Section 34(4) cannot be sustained since correction of the Award

and interpretation of the Award falls within the scope of Section 33 and the

parties had, by consent, agreed to go back to the tribunal under Section 33

and that being the case the consequences of Section 33 would apply. Mr.

ARP-116-2018-CONNECTED MATTERS.odt Quraishy canvassed the point that the High Court had not found it

appropriate or requested a party to go back to the tribunal on the basis that it

would eliminate ground for setting aside the Arbitral Award and especially

since the statute expressly prohibits a challenge to the Award unless a deposit

is made. For ease of reference Section 19 of the MSME Act is reproduced

below :

19. Application for setting aside decree, award or order. --No

application for setting aside any decree, award or other order made

either by the Council itself or by any institution or centre providing

alternate dispute resolution services to which a reference is made by

the Council, shall be entertained by any court unless the appellant

(not being a supplier) has deposited with it seventy-five per cent. of

the amount in terms of the decree, award or, as the case may be, the

other order in the manner directed by such court:

Provided that pending disposal of the application to set aside the

decree, award or order, the court shall order that such percentage of

the amount deposited shall be paid to the supplier, as it considers

reasonable under the circumstances of the case, subject to such

conditions as it deems necessary to impose.

Absence of a deposit/payment of an amount equal to 75% would

automatically bar prosecution of the petition.

35. Mr. Quraishy then submitted that the petition would be barred under

the law of limitation since the period of limitation under Section 34(3) would

ARP-116-2018-CONNECTED MATTERS.odt run only from the date when an application under Section 33 has been

disposed. That disposal occasioned on 25 th April, 2019 and no fresh petition

had been filed. Mr. Quraishy disputed the petitioners contention that the

correction of the Award must relate back to the original challenge in the

pending petition. There being no separate petition filed challenging the

Additional Award he contended that any challenge would now be barred by

the law of limitation and that the present set of petitions would not be of any

assistance. The amendment itself is barred.

36. Mr. Quraishy submitted the Supreme Court in the case of Ved

Prakash Mithal and Sons vs. Union of India 9 (2018) online SCC 3181 upheld

the interpretation of a single judge of the Delhi High Court that the period

of limitation under Section 34(3) would run only when the application

under Section 33 is disposed. Whether or not the Award is modified,

computation of limitation must begin from the date that the application

under Section 33 is disposed. This would entail that the present petitions are

infructuous and that the petitioners ought to have filed a fresh petition. Not

having been filed the challenge is not maintainable in its current form. Mr.

Quraishy then submitted that limitation does not stop running upon

remand. He submits that in the absence of any provision under the

Arbitration Act or the Limitation Act and considering Section 19 of the MSME

Act, there is no occasion to hold that limitation had stopped running or

that the correction to the Award relates back to the earlier award. According

9 (2018) online SCC 3181

ARP-116-2018-CONNECTED MATTERS.odt to him there are two different awards which are subject matter of challenge

and the challenge to the additional award was not filed within time. Thus the

awards become executable. The challenge to the Award dated 25th

May,2018 cannot be entertained in view of the bar under Section 19 and

the only option for the petitioner is to challenge the additional award by

depositing 75% of the amount awarded.

37. Mr. Quraishy then adverted to certain arguments on the merits of the

case. He submitted that the petitioners contention that the impugned award

is violative of Section 31 has no merit. That the work contemplated under the

works order having been carried out and no objection having been raised,

payment should have been made within 45 days failing which interest was

liable to be paid under Section 16. Thus even if any other period was to be

agreed upon, liability under Section 16 had not been waived. The Award

according to Mr. Quraishy was a reasoned one and there is no occasion to

fault it. The Award inasmuch as it is issued after an expiry of 90 days, Mr.

Quraishy contends is not relevant because the period of 90 days is not

mandatory and coupled with "reality and practicality of the situation" the

period of 90 days is to be treated as directory.

38. Alluding to the challenge to the constitution of the tribunal, Mr.

Quraishy submitted that the conciliation having been failed it was open to

the Council to take up the arbitration itself. There is no question of any

further consent required from the petitioner. He submitted that consent may

ARP-116-2018-CONNECTED MATTERS.odt have been necessary under provisions of the Arbitration Act and in particular

Section 11(2) but in view of Section 18(3) of the MSME Act which has an

overriding effect over the Arbitration and Conciliation Act there is no merit

in the challenge. The Council is required to be of not less than three

members and not more than five and that is for the Council to decide. It is

not open to the parties to decide the constitution of the Council. Mr. Quraishy

submitted that while it is true that the Council which heard the matter in the

first instance was of four members and the one heard that heard the matter

upon remand consisted of five members, this is not an aspect that the parties

are contesting and the appointment of the members of the Facilitation

Council was actually challenged by the petitioner and hence the composition

cannot be faulted.

39. Mr. Quraishy submitted that the change of the constitution of the

tribunal and increase in the number of members of the Council from four to

five is no ground for challenging an otherwise reasoned Award. Reasons

being that interest was payable by the petitioners under the Act and that had

been computed. There is no other dispute that had been adjudicated which

required any detailed reasons. On this basis he submitted that the

constitution of the Council with five members is not to be faulted. According

to Mr. Quraishy the members of the Council had arrived at a unanimous

decision upon remand and there is no challenge to that.

ARP-116-2018-CONNECTED MATTERS.odt

40. On the aspect of absence of due process Mr. Quraishy submitted that

the Council was not bound by rules of Civil Procedure Code or the Evidence

Act and therefore there was no occasion for the petitioners to mount any

challenge on that count. According to Mr. Quraishy the Award is a reasoned

award and it speaks for itself and is passed within the framework of law. The

Award of interest is in accordance with Section 16 of the Act and the

Arbitrator could not have decided a different rate. The Council is required to

Award interest at three times bank rate notified by the Reserve Bank of India

and that is how the interest was computed. He submitted that none of the

grounds of challenge were valid. The calculation of interest has been

provided by the tribunal in a tabular form and reasons are obvious from that

table. Mr. Quraishy therefore submitted that all petitions are liable to be

rejected.

CONCLUSIONS

41. The learned counsel for the both the parties have taken me through the

impugned Awards, relevant pleadings, the factual aspects involved and the

law on the subject. At the outset it would be appropriate to describe the scope

of this challenge. There are in all five Arbitration petitions which are being

considered. For the sake of convenience the factual aspects in Arbitration

Petition no. 116 of 2018 are being dealt with. Both sides agree that in the

remaining petitions i.e. Arbitration Petition nos. 117 of 2018, 118 of 2018,

119 of 2018 and 120 of 2018 the facts are all identical. It all pertains to

work done, principal sums have been paid and the claim survives to the

ARP-116-2018-CONNECTED MATTERS.odt extent it concerns interest. A birds eye view of the Awards in the five

petitions is given in the table below:

Arbitration      Petition                Claim Amount                 Amount granted as per
Petition No      No.                                                  Award dated 23.05.2018
                             Principal     Interest         Total

ARP/116/2018     38/2017 17,03,735.00 8,52,775.50       25,56,510.50 Principal amount- Nil


                                                                      Along with Interest per
ARP/117/2018     39/2017 9,16,921.00     18,37,811.00 27,54,732.00
                                                                      S.16(A) of MSMED Act,
                                                                2006 on each and every
ARP/118/2018     36/2017 14,95,869.00 18,19,207.00 33,15,076.00 due amount Invoice
                                                                      when became payable
ARP/119/2018     40/2017 2,53,681.00     4,04,640.85    6,58,321.85   after deduction of 30
                                                                      days, till the realisation
                                                                      of   amount      to     the
ARP/120/2018     41/2017 5,33,586.00     3,09,140.70    8,42,726.70




Perusal of this table indicates the basis of the Award. The principal sums in

all the five cases have been paid. Interest has been claimed under Section 16A

on the amount of each of the invoices from the date they became payable

after giving credit for a period of 30 days.

42. Before I proceed to examine the Award and the Additional Award it

will be appropriate to consider what the parties agreed to when the Award

was sent back to the Council and in that respect we must refer to the order

dated 7th December, 2018. The order was passed by consent. It transpires

that the parties had attempted to arrive at amount payable under the Award

and despite their efforts there was no consensus emerging or interpreting the

award or ascertaining the amounts payable under the Awards. The parties

found he Award unintelligible. The parties therefore agreed to approach the

ARP-116-2018-CONNECTED MATTERS.odt Facilitation Council for correction and interpretation of the Award and

passing of the Additional Awards. They agreed to submit in writing all their

queries with documentation. Thus the Council was required to correct and

interpret the Award and make Additional Awards by calculating the amount

payable and draw up a decree within 12 weeks and then convey the

correction and interpretation and additional award and the amount payable

under the decree to the High Court. Thus the scope of the inquiry was to

conclude upon drawing up a decree and communicating it to the Court. All

contentions of the parties were kept open. This was agreed to in clause 6 of

the Consent Minutes. The matter was then adjourned . The Minutes are

signed by the respective Advocates and parties. Thus when so presented the

Court passed an order in terms thereof. The Minutes did refer to Section 33

of the Act. One of question is whether this application was sent to the

tribunal under Section 33 or Section 34(4). For that matter it would be

appropriate to examine the two Sections. Section 33 and 34(4) are

reproduced for ease of reference:

33. Correction and interpretation of award; additional award.--

(1) Within thirty days from the receipt of the arbitral award, unless

another period of time has been agreed upon by the parties--

(a) a party, with notice to the other party, may request

the arbitral tribunal to correct any computation errors,

any clerical or typographical errors or any other

errors of a similar nature occurring in the award;

ARP-116-2018-CONNECTED MATTERS.odt

(b) if so agreed by the parties, a party, with notice to

the other party, may request the arbitral tribunal to

give an interpretation of a specific point or part of the

award.

(2) If the arbitral tribunal considers the request made under

Sub-Section (1) to be justified, it shall make the correction or give

the interpretation within thirty days from the receipt of the request

and the interpretation shall form part of the arbitral award.

(3) The arbitral tribunal may correct any error of the type

referred to in clause (a) of Sub-Section (1), on its own initiative,

within thirty days from the date of the arbitral award.

(4) Unless otherwise agreed by the parties, a party with notice to the

other party, may request, within thirty days from the receipt of the

arbitral award, the arbitral tribunal to make an additional arbitral

award as to claims presented in the arbitral proceedings but

omitted from the arbitral award.

(5) If the arbitral tribunal considers the request made under Sub-

Section (4) to be justified, it shall make the additional arbitral award

within sixty days from the receipt of such request.

(6) The arbitral tribunal may extend, if necessary, the period of time

within which it shall make a correction, give an interpretation or

make an additional arbitral award under Sub-Section (2) or Sub-

Section (5).

ARP-116-2018-CONNECTED MATTERS.odt (7) Section 31 shall apply to a correction or interpretation of the

arbitral award or to an additional arbitral award made under this

Section.

Section 34(4) : On receipt of an application under Sub-Section (1), the Court may, where it is appropriate and it is so requested by

a party, adjourn the proceedings for a period of time determined by

it in order to give the arbitral tribunal an opportunity to resume the

arbitral proceedings or to take such other action as in the opinion of

arbitral tribunal will eliminate the grounds for setting aside the

arbitral award.

Consideration of this aspect is necessary to determine the scope of the

challenge and whether the challenge as originally filed would survive or

whether the challenge in the petitions would be rendered infructuous in

view of the Additional Award passed by the Tribunal upon remand.

43. Under Section 33 the parties are entitled to request the Arbitral

tribunal to correct clerical, typographical or computational or other similar

errors after notice to the other parties. The parties may also request the

tribunal to give an interpretation of a specific point or part of the Award and

if the tribunal considers it justified, it shall make a correction or provide an

interpretation within 30 days from receipt of the request and such

interpretation would form part of the Arbitral Award. Under Sub-Section 3

the tribunal may carry out these corrections on its own initiative, but within

ARP-116-2018-CONNECTED MATTERS.odt 30 days from the date of the Award. This Sub-Section does not arise for

consideration in the present case since the tribunal has not adopted this

course. Under sub Section 4 the tribunal may be requested within 30 days

from the receipt of the Award to make an additional award as to the claims

presented, but omitted from the Arbitral Award and if such request is found

justifiable, an additional award shall be made within 60 days of receipt of the

request. The tribunal is also empowered to extend the duration of time within

which the correction, interpretation or additional award is to be issued and all

such corrections, interpretations and additional award shall be subject to

provisions of Section 31 as regards the form and content of the arbitral

award.

44. Sub Section (2) of Section 31 is material inasmuch as it provides that

in an Arbitral proceeding with more than one arbitrator, signature of

majority of the members shall be sufficient so long as the reason for omission

of any signature is stated. In the instant case the original award was passed

by four arbitrators and the revised Award by five arbitrators, two of whom

are new and were not part of the Council which passed the main award.

Section 31 also provides for payment of interest of 2% higher than the current

rate prevailing. Thus on analysing Section 33, the following becomes clear

viz. correction, interpretation and additional award can be carried out only

upon one of the parties making a request to the tribunal. The 30 days period

within which such an application is to be made may be enlarged by parties

by consent. As a result request for correction interpretation and additional

ARP-116-2018-CONNECTED MATTERS.odt award can be made beyond 30 days period but the essential part is that

under Section 33 it is for one or the other or both parties to apply. The

Tribunal also is empowered to carry out corrections, offer an interpretation

or an additional award of its own initiative. Thus Section 33 operates at the

request of a party or parties or by the initiative of the tribunal itself. It does

not contemplate the Court stepping in .

45. Section 33 forming part of Chapter VI deals only with making of

arbitral award and termination of the proceedings. Section 34 falls under

Chapter VII which deals with recourse against an arbitral award. Under the

scheme of the Act therefore, recourse against an arbitral award is considered

only after termination of proceedings. Thus under Section 34(1) an

application can be made to Court to set aside the Award which the Court may

do only if the party applying establishes on the basis of the record of the

tribunal that it was either under any incapacity or the arbitration

agreement was not valid, the applicant did not have proper notice of the

appointment of the arbitrator or of the proceedings or if the award dealt with

the dispute not in contemplation of the parties or it was beyond the scope of

submission to arbitration. If matters submitted are separable from those not

submitted, only that part which was not subject matter to submission of

arbitration can be set aside.

46. The other ground for setting aside the award is composition of the

tribunal or procedure adopted not being in accordance with the agreement

ARP-116-2018-CONNECTED MATTERS.odt between the parties. Once again, if such agreement was in conflict with Part

I of the Arbitration Act this ground would not be available. Under Section

34(2)(b) the award could be set aside if the Court found that the subject

matter was not capable of settlement by arbitration or if the award is in

conflict with public policy of India. The explanation deals with what public

policy would entail. Under the amended provisions an award could also be

set aside if the Court finds the award vitiated by patent illegality appearing

on the face of the Award and not merely on the ground of erroneous

application of law or by re-appreciation of evidence. Sub Section (3) sets

time limit for seeking setting aside of an award at three months after the date

on which an applicant receives the arbitral award or within three months

from date of disposal of a request under Section 33. The period of three

months is extendable by another 30 days if the Court finds sufficient cause

for not applying within time. Under Sub-Section (4) the Court may on an

application by the party adjourn the proceedings for some time to give an

opportunity to the tribunal to either resume the arbitral proceedings or adopt

measures to eliminate grounds of setting aside the award.

47. Thus in the case at hand one of the aspects that has arisen for

consideration is whether the application to the tribunal for correction,

interpretation and additional award was made pursuant to Section 34(4) and

I am of the view in facts of the case the matter referred was clearly pursuant

to Section 34(4). As stated earlier, if I have to accept Mr. Quraishy's

submission that the application was one made under Section 33 alone, the

ARP-116-2018-CONNECTED MATTERS.odt respondent must demonstrate that the parties, any one or both of them

requested the tribunal to correct errors contemplated under Section 33(1)(a)

and that the parties agreed and requested tribunal to give an interpretation or

correct the award. The tribunal has not in the present case done so of its own

initiative. In the case at hand however, all that the parties have done is to

agree that the Award is incapable of interpretation and therefore request

correction and interpretation and seek issuance of an additional award after

termination of proceedings under Chapter VI and after presentation of a

petition seeking recourse against an arbitral award. Once the matter crosses

the threshold of Chapter VII and an application for setting aside an arbitral

award is filed in a Court, the parties would not be in a position to apply for

correction without leave of the Court. It is possible that an application for

correction may be filed by one party to the arbitral proceeding and an

application for setting aside under Section 34 has been filed by another party.

In such a situation the correction ensuing from such application may well be

one under Section 33. For instance a party who has not challenged the

award, but has applied for correction will be entitled to contend that the

order passed by the arbitral tribunal was one under Section 33. However, if a

party seeks correction after challenge petition is filed, an application could

only be made under Section 34(4) and a party would not be able to make an

application under Section 33 without leave of the Court under Section 34(4).

This becomes clear on a plain reading of the aforesaid two Sections.

ARP-116-2018-CONNECTED MATTERS.odt

48. In the present case I am of the firm view that it is only after the filing

of the petitions challenging the award that the parties deemed it appropriate

to approach the tribunal to seek interpretation, correction and renewed

application of award. The order of the Court does not specify that this is

under Section 33 although the Minutes did and indeed it could not since it is

the Court which has adjourned the proceeding under Section 34(3) in order

to enable a determination by the Arbitral Tribunal to either resume

proceedings or take such measures so as to eliminate grounds of challenge.

This is an indication that the challenge was not mature or that the challenge

was possibly premature since the tribunal is being given an opportunity to

either resume proceeding or take action to eliminate grounds for setting aside

the award. In the first option the tribunal may be expected to incorporate its

decision on the subject matter of arbitration after resuming arbitral

proceedings for it is possible it may have omitted to do so in the first round.

In the second scenario there is a presumption that grounds for setting aside

arbitral award exist. Failing such presumption a party would not be

expected to agree to submit to the tribunal under Section 33 or to request a

Court to adjourn the proceeding in order to approach the tribunal under

Section 34.

49. There is a distinction between an application under Section 33 and that

under Section 34(4). Whereas Section 33 contemplates correction of an

award for computational, typographical or clerical errors or to give an

interpretation on a specific point which may or may not require an additional

ARP-116-2018-CONNECTED MATTERS.odt award to be made on the claims, Section 34(4) operates in a different area

where the challenge to the award is adjourned to enable the tribunal to

resume proceedings. Resumption of proceedings may be as a result of the

necessity to apply for an additional award or for interpretation on any part.

If the proceedings are to be resumed before the arbitral tribunal, it is

indicative of the need to hear both parties since a pure interpretation under

Section 33 would not require or justify resumption of arbitral proceedings.

To consider the second aspect of Section 34(4) the tribunal is given an

opportunity to eliminate grounds for setting aside the arbitral award.

Existence of such grounds is therefore presumed. An application under

Section 34(4) may be opposed by one party if it believes that there were no

ground for setting aside award or there were sufficient ground for setting

aside the award without going back to the tribunal.

50. The facts of the present case are peculiar inasmuch as the parties

agreed to go back to the tribunal under Section 33 since Minutes of the order

makes reference to Section 33 but the subject matter of the Minutes appears

to be an attempt to arrive at an amount payable under the award which

would require an interpretation of the amount payable. Clause 2 of the

Minutes records the helplessness of both the parties in arriving at a

consensus and identifying the amount payable under the award. Both parties

were thus ad-idem that they could not identify the amount payable. The

award was thus unexecutable for vagueness. The parties therefore appear to

have consented to approach the Facilitation Council under Section 33 for

ARP-116-2018-CONNECTED MATTERS.odt correction, interpretation and issuance of an additional award. Clause 3 of

the consent minutes records this. It also records that parties would submit in

writing all their queries and documentary evidence in the form of affidavits

as directed by the Council within eight weeks. Thereafter Council would

correct, interpret and issue an additional award by calculating the amount

payable and thereby draw up a decree. It was also agreed between the parties

that the Council would convey the correction, interpretation and issue

additional award to the High Court directly along with interest payable under

the award and it for this reason that the parties agreed to adjourn the matter

and sought leave of the Court with liberty to apply. Parties agreed that all

contentions of the parties are kept open meaning the challenge in the petition

was unaffected and this agreement was without prejudice to the rights and

contentions of both parties. The parties however sought an adjournment in

order to enable the tribunal to decide.

51. Thus once having sought an adjournment and the Court having passed

an order in terms of the minutes as can be seen from the operative portion of

the Court's order it will constitute an application under Section 34(4) read

with Section 33. The Court has therefore adjourned the matter after

observing that the parties have agreed that grounds may exist for setting aside

the award since they were unable to arrive at consensus for interpreting the

amount payable and that being the primary mover had agreed with leave of

the Court to approach the Council under Section 33. The application for

adjournment of proceedings was granted. It could have been so granted only

ARP-116-2018-CONNECTED MATTERS.odt under Section 34(4). The arbitral tribunal therefore had opportunity to

resume arbitral proceedings rather than merely eliminate grounds for setting

aside since paragraph 3 of the consent minutes provide that the parties had

agreed to submit in writing all queries and documentary evidence in the form

of affidavits. This would entail in my view a resumption of arbitral

proceeding since parties submissions of documentary evidence probably

would have involved a contest on the material sought to be placed before the

Facilitation Council which would have required resumption of arbitral

proceeding and after hearing the parties. Here the Council erred seriously in

not hearing the parties before issuing the Additional Award.

52. Thus in my view, although the language used in the consent minutes

signed by the parties refers to approaching the Council under Section 33.,

the power contemplated under Section 33 was restricted to correction,

interpretation and issuance of an additional award. However, in view of the

parties having agreed to submit in writing queries / documentary evidence in

support of their respective cases or "as directed by the Micro and Small

Enterprises Facilitation Council within 8 weeks" it implies a hearing before

the Facilitation Council to seek appropriate directions. Thus this is an

application under Section 34(4) which seeks to provide an opportunity to the

Council to resume arbitral proceedings, eliminate grounds of challenge as

also carry out correction in the award, interpret any specific portion thereof

and with the possibility of issuing an additional award. It is therefore not an

ARP-116-2018-CONNECTED MATTERS.odt application under Section 33 per se but one under Section 34(4) with a

consensual request to the tribunal to invoke its power under Section 33 and

after hearing parties.

53. Having come to the conclusion that the order dated 7 th December,

2018 was one under Section 34(4) let us now consider the merits of the

challenge. The challenge as originally filed takes up various grounds. Firstly

that there was no application of mind. The order initiating arbitration was

without proper adjudication, no consent was given to appointment of the

Council. Under Section 11(2)of the Arbitration Act consent of the petitioner

was required and that the number of arbitrators could not have been an even

number, even considering Section 10 of the Arbitration Act. In the instant

case there were four arbitrators forming part of the Council. Later, on

remand the order was passed by five arbitrators which is in violation of

Section 10 and therefore the award is assailed on that ground as well. Apart

from the other ground of not framing issues, not giving any reasons, it is

submitted that the impugned award is vague. It observes that the principal

amount had already been paid and interest was being demanded at 41.1%

and stated to be effectively awarded at 27%.

54. By way of an amendment carried out on 5 th October, 2020 paragraph

13(a) to 13(c) were added in the petition seeking to challenge the additional

award dated 25th April, 2019 as well amongst other grounds. The petitioner

pleaded additional grounds q(i) and q(ii). These amendments are sought to be

ARP-116-2018-CONNECTED MATTERS.odt challenged as having been made beyond time since the additional award was

dated 25th April, 2019. Thus the amendment was carried out beyond the time

available for challenging the Award under Section 34(4). On this aspect of

the matter I am unable to agree with Mr. Quraishy that the petition is barred

by law of limitation in view of the fact that the amendment was carried out

beyond time and in effect Mr. Quraishy's contention that the original petition

was rendered infructuous upon passing of the consent order on 7 th December,

2018 cannot be accepted. When the petition was adjourned, the challenge

was very much subsisting and it is during the subsistence of this challenge

that the consensual request was made which could inter alia eliminated

grounds for challenge. The original award and the additional award had not

merged. A merger would entail that the original award would stand with

correction and interpretation under Section 33. However in the case at hand

the tribunal has thought it fit to also issue an additional award but no hearing

has been granted. A perusal of the order dated 7 th December, 2018 reads as

follows

"The Learned Advocates appearing for the parties have tendered

Minutes dated 7th December, 2018. They submit that the Minutes

be taken on record and an order be passed in terms of the Minutes.

The Minutes are taken on record and marked 'X' for identification.

The Minutes are signed by the Advocates for the parties. Order in

terms of Minutes marked 'X'. Stand over to 26th April, 2019.

Liberty to apply."

ARP-116-2018-CONNECTED MATTERS.odt All petitions were adjourned. The adjournment is clearly as contemplated

under Section 34(4). It is thereafter that an additional award has been passed

that too beyond time. In the additional award certain amounts have been

computed. I will shortly examine the original award and the additional

award when dealing with the challenge to the awards per se.

55. One of the contentions of the petitioners and as canvassed by Mr.

Sakhare before the order dated 7th December, 2018 came to be passed the

petitioners had filed affidavit of Narayan Ramanth Chakor, Additional

Executive Engineer (C), M.S.Elect.Trans.Co. Ltd. in which the deponent stated

that the calculation submitted by the respondent were erroneous and that at

best the interest calculation would reveal that total amount due would be

Rs.4,31,080/- is explained in Exhibit A to the first petition. Likewise in other

petitioners also affidavits have been filed and the amounts computed on

behalf of the petitioners. Thus even according to the petitioner if any interest

was payable the computation was incorrect. It is after this affidavit was filed

that the parties agreed to go back to the tribunal in terms of the minutes and

the order passed thereon. Mr. Sakhare has stressed his submission that the

award is bad in law since the Council did not communicate its decision

within 12 weeks and there was no occasion to address the Facilitation Council

before they took their decision on remand. I have already held that the

petition is not barred by the limitation. I am of the view that the interim

application is also not barred by limitation since the petition was simply

adjourned under Section 34(4). I am in agreement with the submission of

ARP-116-2018-CONNECTED MATTERS.odt Mr. Sakhare that there was no novation of the original award so to speak. The

adjournment of the petitions permitted the parties to go back to the Council

and the petitioner had filed the interim application by way of abundant

caution even before the Council could communicate its decision and upon

failure of the Council to submit the communication within the 12 weeks

period specified in the order dated 7 th December, 2018. If this was done in

time parties would have filed their objection.

56. The decision in Kinnari Mullick (supra) applies squarely to the facts at

hand inasmuch as the Court could only set aside the Award or adjourn the

matter when the petition was first urged and in view of the consensual

approach of the party the Court adjourned the matter in the first instance.

Having adjourned the matter the Facilitation Council has proceeded to

publish an additional award which according to it complies with the

direction of the High Court. The question is whether the petition under

Section 34 today survives as against both the original award and the

additional award and in my view the answer must be in the affirmative. The

facts in Kinnari Mullick (supra) reveal that the Award had already been set

aside and the Court had suo moto sent the parties to the tribunal. This was

found to be unsustainable inasmuch as the Supreme Court found that the

limited discretion available to the Court under Section 34(4) would have

been exercised only upon a written application made by a party to the

arbitral proceeding and the court could not exercise this power suo moto.

Moreover this request had to be made by the parties in writing and before

ARP-116-2018-CONNECTED MATTERS.odt the Award was formally set aside. It is only then that a request could be

made to the arbitral tribunal and the Court also observed that if the party to

the proceeding does not request the Court to defer the proceeding pending

before it, then it is not open to such a party to move an application under

Section 34(4) since upon setting aside of the Award the main proceeding

under Section 34 would have been disposed and the Court would become

functus officio. Thus the limited jurisdiction of the Court under Section 34(4)

was to be invoked and to be exercised by the Court before an Award was set

aside. That is precisely what has happened in the instant case inasmuch as

pending the decision on the 34 petition the parties sought an adjournment to

go back to the Council for obtaining correction, interpretation or additional

award so as to eliminate the ground of challenge and if thought fit to resume

proceedings before the tribunal.

57. As far as the amendment is concerned in Hindustan Construction

Company Ltd. (supra) the Supreme Court was considering amendment for

incorporation of additional grounds in an application under Section 34 or a

memo of appeal under Section 37. When the application was filed after

expiring of limitation period under Section 34(3) the Court observed that it

would not denude the Court of power to grant leave to amend if required in

the interest of justice. However, if addition of new grounds is sought without

any foundation in the application for setting aside, the Award would be

rightly rejected by the Court. More so when an amendment application

ARP-116-2018-CONNECTED MATTERS.odt under Section 34 had not been sought before Court of first instance. The

Court held that amendments and additions of grounds by way of amendment

is tantamount to filing a fresh application. In all situations, amendments

would normally not be allowed, however the words "the Court finds that

included in Section 34(2)(b) would enable a court to permit an amendment in

peculiar circumstances of the case and if so warranted in the interest of

justice".

58. I am of the view that in the present case the amendment was certainly

required in view of the tribunal having passed a subsequent award during

the pendency of the present petitions and for that reason also I hold that the

amendment is not barred by the law of limitation. Thus in effect there is no

absolute bar against amendment being allowed provided the party applying

had laid the foundation in the original petition under Section 34. Absent

such foundation no amendment to add new grounds or material could be

permitted. In the instant case the restriction to amendment contemplated

in Hindustan Construction Company Ltd. (supra) cannot apply since the

petitions were kept pending only to enable the parties to obtain the necessary

interpretation, corrections and if necessary an additional award. If the

intention of the Court was to permit a subsequent and renewed challenge

upon the corrections being made by the Facilitation Council or upon

interpretation of the Award by it or the passing of additional award the

present petitions need not have been kept pending but would have been

disposed. For this reason also the direction to the Facilitation Council is not

ARP-116-2018-CONNECTED MATTERS.odt one purely under Section 33 since the petitions would not have been kept

pending nor would they have been adjourned.

59. On the aspect of merger I do not believe that there is any doubt created

by the mixed bag remand to the arbitral tribunal inasmuch as provision of

Section 33 and 34 are both clear in their meaning. They are capable of

harmonious construction without reference to other provisions and there is

certainly no occasion to accept the respondents contention that there has been

a merger as a result of the additional award. The Awards are separate and

distinct and operate independently. The first seeks to fix liability and the

additional award seeks to quantify it. It is only on account of the

interpretation and correction that an additional award was found necessary,

more so since effectively the tribunal had revisited the disputes and the

reliefs and in an attempt to make an intelligible award it proceeded to issue

the additional award. Thus the legislative intent of Sections 33 and 34 are

both clear and there is no conflict. The unique nature of the order passed by

this court on 7th December, 2018 contemplated a combination of solutions

offered by Section 33 for correction, interpretation and issuance of additional

award as well as an opportunity to the tribunal to resume the arbitral

proceeding and in that manner remove any scope of challenge.

60. Let us now examine the Awards themselves to see whether they are

susceptible to a challenge as contemplated under Section 34. The first Award

dated 23rd May, 2018 is to be found at Exhibit "F" to the petition. The Award

ARP-116-2018-CONNECTED MATTERS.odt was forwarded on 23rd May, 2018. The findings and the operative portion

have already been reproduced elsewhere in this judgment. The finding

reveals that the respondent-claimant had received the principal amounts

after filing of the applications with the Council. The process of conciliation

had failed and therefore the Council had decided the matter on merits. This is

recorded as a finding of the Council under the heading "Findings and

reasoning". It does not take much effort to observe that the award is bereft of

any reasons. The order allows the petition "in terms of prayer". However

when one peruses the copy of the petition filed by the respondent before the

Council there are no specific prayers. The petition proceeds on the basis of

the work orders in question. It contains a synopsis. The prayer is said to be

part of item no. 17 in Annexure 3. However, all that it refers to is an

unspecified and attached page number. Going by the synopsis attached to

Annexure 3 the following appears in column 14.

       Amount Yet to receive         2,53,681.00
       (In) Rs.
       Interest @ 41.1 %             4,04,640.85
       Amount of Principal and 6,58,321.85
       interest



This in effect appears to be the prayer which has been allowed. The awards

are bereft of any reasons whatsoever for granting this prayer. When the

award is read in its entirety it sets out brief details of the work, case of the

petitioner, the case of the respondent and proceeds to observe that the

Council had taken into consideration the record, documentary evidence

ARP-116-2018-CONNECTED MATTERS.odt submitted by the claimant and had given stage wise notices to the petitioner

herein. It conducted hearings for conciliation and arbitration However

while allowing the reference in terms of the prayer no reasons are

forthcoming. There is no finding as to how if at all the computation of

interest is correct. The item no. 2 of the operative order reads as follows :

2. The Respondent is required to pay to the Petitioner a

principal amount of "Nil" along with interest as per the

Section 16A of the MSMED Act, 2006 on each and every due

amount of the invoice when become payable after deduction

of 30 days, till the realization of the amount to the Petitioner.

When one reads this portion it is clear that the Council expects the petitioner

herein to pay the principal amount which is described as "Nil" along with

interest under Section 16A on the amount of each and every invoice when

they become payable after deduction of 30 days. What it implies is that there

would be credit period of 30 days after which the bill would have become

payable forthwith. The last words of clause 2 of the operation portion reads

as follows "till the realization of the amount to the petitioner". This makes

little sense, if at all, inasmuch as the principal amount having been paid in its

entirety the amount falling due towards interest would only be from the due

date, after giving credit for 30 days till payment of the principal sum. There

was no question of including the word "till the realisation of the amount to

the petitioner" since the amount would have been crystallized as on date of

payment of the principal amount. It is not intended by this order that the

ARP-116-2018-CONNECTED MATTERS.odt petitioner would be liable to pay interest on interest. That is certainly not

evident from the award nor is it the case of the respondent. In clause 3 the

Council orders as follows :

"3. The Principal and interest amount are to be paid by the Respondent to the Petitioner within a period of one month from the date of receipt of this Award.. "

Once again reference to principal in clause 3 is devoid of any meaning since

principal amount adjudged as "Nil" having been paid before the passing of the

Award.

61. On this basis I am of the view that the Award is not intelligible and

obviously incapable of execution for being vague and expecting an

unspecified amount to be paid. The award is certainly not executable. This

was obviously the reason for the order dated 7 th December, 2018 came to be

passed. Let us therefore examine the order passed on remand on 25 th April,

2019. This is to be found at Exhibit "H" to the petition and described in the

reference column the order of this Court dated 7 th December, 2018. It also

contemplates all these petitions in serial order along with Petition no. 38 of

2017 which was before the Council. It is therefore evident that it is the very

same petition in which first award was passed that was subject matter of

consideration. It would not be difficult to see that what is contemplated here

is the resumption of arbitral proceeding under Petition 38 of 2017. The

Original Award reads as follows :

ARP-116-2018-CONNECTED MATTERS.odt ORDER

1. The reference Petition No. 38/2017 is allowed in terms of

prayer.

2. The Respondent is required to pay to the Petitioner a

principal amount of "Nil" along with interest as per the Section 16A

of the MSMED Act, 2006 on each and every due amount of the

invoice when become payable after deduction of 30 days, till the

realization of the amount to the Petitioner.

3. The Principal and interest amount are to be paid by the

Respondent to the Petitioner within a period of one month from the

date of receipt of this Award.

4. No Order as to costs.

5. The case is disposed off and closed.

6. This order is issued on this 23 day of May, 2018.

Place : Konkan

Date :     05. 2018

    sd/-                                                              sd/

(G.V. Bellale)                                                      (S.G.Rajput)
Member Secretary                                            Ex-Officio Chairperson
Deputy Director of Industries                               Joint Director of Industries
                                                                   Konkan Region
                                                         Directorate of Industries holding
                                                             the post of Additional
                                                          Development Commissioner
                                                                     (Industries)

   sd/-                                                              sd/-
(Umesh Tayade)                                                  (K. R. Gopi)
Member, MSEFC &                                                Member MSEFC &
Chairman, AAMA                                                  Chairman, SSEA



The Council has then proceeded to make additional awards by calculating

the interest amount payable in addition to the award issued by the Council

ARP-116-2018-CONNECTED MATTERS.odt on 23rd May, 2018. The additional award reads is as follows :

"Additional award as per the order dated 07.12.2018 by the Hon'ble High Court, Bombay ORDER For the reference Petition No. 38/2017 as per directives given by the Hon'ble

High Court, Bombay order dated 07.12.2018, and as per the request of

Petitioner and Respondent under Reference No. 3 & 4, the additional award

by calculating the interest amount payable In addition to the award issued by

the Council on 23.05.2018 is as follows. Other terms and conditions of the

award issued by the Council remains same."

The Additional award is followed by a table of interest computation to which I

will deal with shortly. The last sentence of the Additional Award makes it

evident that the original award continues to hold fort and the present

additional award is exactly what it says "in addition to the award issued by

the Council on 23.05.2018" When we peruse this additional award what

follows is tabulated interest computation in Petition no. 38 of 2017. It sets out

nine different bill nos, bill dates, their due dates the 30 th date from the bill

date and mentions , several particulars of amounts due, amounts received,

date of payment, three times RBI bank rate as on date of bill / RBI rates are

mentioned against each invoices without any cross reference to any

documents, delay in number of months, interest on amounts received till date

of payment and interest upto two different sets of dates (30.4.19 and

31.5.2019) are provided. In particular and as pointed out by the petitioners

no opportunity appears to have been given to the petitioner to show cause

ARP-116-2018-CONNECTED MATTERS.odt against this computation. The rate of interest applied does not seem to be

cross referenced with the base rate from which the rate is derived and

entered in this column which I have notionally numbered as column no. 8 for

this judgment. The 11 columns are briefly described below.

S. Bill Bill Due Amount Amount Date of 3 times Delay in Interest on Interest upto No. No Date Date 30 (Rs) Recd. Payme of RBI months received days nt Bank amount from the Rate as till date of bill date on date receipt of of payment bill/100 4/30/2019 5/31/2019

62. Thus, I find that in the Additional Award there is no co-relation with

the first. The first award simple states that the prayer is allowed, the prayer

includes interest computation at 41.1%. The additional award fails to specify

the base rate applied and in that respect, is once again bereft of reasoning.

There is no evidence of any corrections having been made or any

interpretation provided. The procedure contemplated under Section 33 does

not appear to have been followed. The consent minutes provided for parties

to submit documentary evidence and it was in my view necessary for the

Council to grant a hearing to the parties. The Additional Award is passed

without granting any such hearing. It is in this behalf that it is relevant to

note that the petitioners representative i.e. their Advocate Mr. Mukund

Manikrao Kadam has filed an affidavit dated 29 th January, 2020 deposing to

the fact that no proper notice was given. The affidavit of Mr. Mukund

Manikrao Kadam Advocate for the petitioners is on record of this

petition. The deposition firstly proceeds to find fault with the constitution of

ARP-116-2018-CONNECTED MATTERS.odt the Council. The petitioner was unaware of the exact composition of the

Council till they received the Award dated 23 rd May, 2018 which was signed

by four arbitrators. This was in violation of Section 10. It was further stated

that several applications had been filed by the petitioners about the

constitution of the tribunal but these were not decided. The impugned order

dated 25th April, 2019 also finds mention in the affidavit. This is the

additional award which the deponent states was passed once again without

following any procedure. A request was made to follow procedures under

the Arbitration Act but this fell on deaf ears. This however pertains to the

earlier award and to my mind loses significance in view of the remand

order.

63. The affidavit further states that no issues were framed and no findings

were rendered on the issues. More particularly and critically the affidavit

states that the tribunal did not provide any opportunity to the parties to

present evidence. It appears that the tribunal did not hear parties at all on

these aspects. In paragraph 11 it is stated by the deponent that during the

hearing of the matter before the Council there were two or sometime three

arbitrators i.e. the Chairman and one or two members. The number of

arbitrators were never made known to the parties. It is only upon the award

being issued that the petitioners realised that there were four members in the

Council. The affidavit in my opinion does indicate that there was no proper

hearing or consideration of the aspects on which corrections were sought.

ARP-116-2018-CONNECTED MATTERS.odt

64. I have not heard any submission on behalf of the respondent either

from Mr. Quraishy to the effect that hearings took place and both parties

attended before the Council to make their submissions pursuant to the

remand. In these circumstances I am of the view that the petitioner would be

entitled to rely upon decision of the Supreme court in M. K. Global Financial

Services Limited (supra) in which the Supreme Court found that in relation to

matters not found in the record in paragraph no 21 the Supreme Court

clarified the legal position by stating that an application for setting aside of an

Arbitral Award will not require anything beyond the record that was before

the arbitrator. However, if there are matters not contained in such record

and are relevant for the purposes of determination of issues arising under

Section 34 they may be bought to the notice of the Court by way of affidavits

by both parties. In that case it is observed that cross examination of persons

swearing affidavit should not be allowed unless absolutely necessary as the

truth will emerge on reading affidavits filed by both parties.

65. In the present case the affidavit of Mr. Kadam has not been

controverted nor have I heard the respondents to make any submissions in

that behalf and indeed none are contained in the written submission as well. I

am therefore inclined to and will be justified in holding that the contents to

the extent that no hearing was granted despite a request to follow basic

procedure appear to be correct. The Council did not afford a complete

opportunity to the parties despite the order of remand. For that reason I am of

the view that the award being bereft of any reasons and being passed without

ARP-116-2018-CONNECTED MATTERS.odt an opportunity to the petitioner to show cause against the computation of

interest would fail the test under Section 34 as lacking a judicial approach

and amounting to an award which is contrary to the fundamental policy of

Indian Law. The Award would therefore be liable to be set aside under

Section 34(2)(b)(ii).

66. This is an aspect which has been considered in great detail by the

Supreme Court in the decision of Associate Builders (supra). The Council has

proceeded to pass the additional Award without ascertaining the views of the

petitioners, no opportunity has been given to the petitioners to deal with the

documents, if any, filed on record by the claimant / respondent. The Award

to that extent is clearly without reasons. It is a non-speaking award. It does

not disclose the manner in which the Council came to its decision in

computing the amount of interest. These are aspects which would have to be

established before the Council in respect of each and every bill. Not having

given an opportunity to the petitioner to show cause against such

computation and having disregarded the computation provided by the

petitioners in this petition and reference being had to the affidavit filed on

behalf of the petitioners, I am of the view that the award suffers from a patent

illegality on the face of the award. For these reasons the Award is liable to be

set aside.

67. The Supreme Court in its decision of Ssangyong Engineering And

Construction Co. Ltd. vs National Highways Authority Of India 10 has 10 2019 SCC OnLine SC 677

ARP-116-2018-CONNECTED MATTERS.odt observed and reiterated its observation in paragraph 42 of Associate Builders

(supra) that although a mere contravention of the substantive law of India is

itself not a ground available for setting aside an arbitral award. If an

arbitrator gives no reasons he contravenes Section 31(3) of the Arbitration

Act and that would amount to a patent illegality. This is an aspect which has

been dealt with in some detail in the decision in Associate Builders (supra). In

this behalf I may observe that in paragraph 41 of Ssangyong Engineering

(supra) the Supreme Court had observed that a finding based on documents

taken behind the back of parties would also qualify as decision based on no

evidence as decision is not based on evidence lead by the parties and will

therefore have to be characterised as perverse.

68. In the instant case the Council does not appear to have permitted the

petitioners an opportunity to deal with documentation relied upon by the

respondent / claimant and that in my view would be hit by the Supreme

Court's findings that this approach of the Facilitation Council would be

perverse. Moreover under Section 34(2)(a)(iii) the petitioner would have

been found to be unable to present its case for want of a proper opportunity

to deal with documentary evidence on the basis of which the interest has been

computed. It is not necessary to delve into the details since on the face of it it

appears that no such opportunity was granted and it is not the case of the

respondent that any such opportunity was granted.

ARP-116-2018-CONNECTED MATTERS.odt

69. One other contention raised on behalf of the petitioner is that the

MSME Act would not apply and the provisions would not entail liability since

the contract in question was a works contract and not one for supply of

materials or services to be rendered. A works contract has already been held

to be falling outside the scope of a reference under the MSME Act. This has

been so held not only by this Court in Sterling And Wilson Private Ltd. vs

Union Of India And 3 Ors11 . but this view has been taken also by the

Allahabad High Court in Rahul Singh vs. Union of India12 on which reliance

was placed by Mr Quraishy. This was also the view of a Division Bench of

the Delhi High Court in the case of Shree Gee Enterprises vs Union of India

and Anr.13 that would entail the Council not having the jurisdiction to

entertain the claim. Mr. Quraishy had also relied upon decision of Ved

Prakash Mittal & Sons vs. Union of India14. However I find that Ved Prakash

Mittal (supra) will not be of any assistance to him since on the aspect of

limitation what it holds is that disposal of an application under Section 33

and that limitation to challenge the award would have to be computed from

the date of such disposal and disposal would mean either by allowing the

application or rejecting it. This contention would have been relevant but for

my holding that the additional award did not give rise to a fresh cause of

action to challenge the award that the pending petition was competent

11 AIR 2017 Bom 242

12Writ Petition C no. 2316 of 2016

13(2015) SCC online Delhi 13169 14 AIR 1984 Delhi 325

ARP-116-2018-CONNECTED MATTERS.odt enough for that purpose and therefore the amendment to the petition justifies

to incorporate the challenge. The decision of the Rajasthan High Court in the

case of Swastik Gases (P) Ltd. v. Indian Oil Corpn. Ltd. 15 would once again

deal with the provisions of Section 16 and the date from which interest was

payable to a supplier in the event of failure of the buyer to pay the money

due for the supplies made while the provisions of the act are not in dispute.

This decision will not come to the assistance of Mr. Quraishy since I have

already held that the Council was duty bound to provide an opportunity to

show cause against the computation of interest and given the unreasoned

award, there is no occasion for the petitioner or even this Court to appreciate

the basis of the additional award.

70. The requirement of a reasoned award has been highlighted by the

Supreme Court in Dyna Technologies Private Limited vs. Crompton Greaves

Limited16 The Supreme Court has in paragraph 36 of that decision observed

that the mandate of Section 31(3) of the Arbitration Act would require

intelligible and adequate reasons which can, in appropriate cases, even be

implied by Courts on a fair reading of the Awards and documents referred

to thereunder. That no elaborate judgment is required to be passed by the

arbitrators having regard to speedy resolution of a dispute.

71. The Supreme Court further observed that the requirement of a

reasoned award must satisfy three characteristics. They must be adequate,

15(2013) 9 SCC 32

162019 SCC online 1656.

ARP-116-2018-CONNECTED MATTERS.odt intelligible and proper. The reasoning should not reveal a flaw in the

decision making process and that would make the award unintelligible. In

the present case I am clearly of the view that the Award is been rendered

unintelligible by failure to give reasons for the basis of the computation of

interest in the additional award. No reference being had to the document

evidencing the base rates of interest and documents on which the

computation is based and an opportunity to the petitioners to deal with the

contentions. The decision making process is also rendered vulnerable in the

facts at hand. Thus the award is liable to be set aside since these defects have

not been cured despite an opportunity being granted to the Facilitation

Council by the order dated 7th December, 2018.

72. Summarizing I find that the order dated 7 th December, 2018 was one

under Section 34(4) of the Arbitration Act. Hence the challenge to the

Additional Award was within the scope of these petitions, the amendments

included. As regards the change in the number of members of the Facilitation

Council, the total number having undergone a change cannot in itself be

enough to render the Awards invalid if the reconstituted council had heard

the parties since the Council consisted of two new members. The Additional

Awards have been passed by the reconstituted Council and the new

members would have had opportunity of assessing the merits on both sides

and evaluating the documentary evidence and material that the parties could

have placed before the Council. This they have failed to do. Failure to do so

will attract the ills of lacking in a judicial approach. The Awards are thus also

ARP-116-2018-CONNECTED MATTERS.odt rendered bad for want of a judicial approach in deciding the matter even

after the limited scope of the remand.

73. The failure to adhere to time schedules is one aspect which has been

urged by the petitioner. However, I am of the view that non submission of its

interpretation within the 12 weeks specified by the High Court is something

that the High Court would have considered had there been a request for

condonation of delay. However, in the present set of facts there is nothing

on record to suggest that the Council in fact sought an extension of time.

However, in view of the fact that the petitioners have then moved for an

amendment and a challenge to the Additional Award, I am of the view there is

no occasion to decide this issue in the current set of facts. Hence that aspect

is left open for consideration in an appropriate case. That having been said I

am of the firm view that the petitions are not barred by the law of limitation

to the extent it contains a challenge to the Additional Awards. The

Facilitation Council has in my view failed to eliminate grounds for challenge

of the Awards. Moreover, the Council has also not offered its interpretation

on the original Award. Thirdly the Council has not passed a decree in the

exact amount payable merely by publishing the Additional Award which does

not cross reference the relevant bills would not be compliant with this order

passed by this Court. Being a Works Contract this and other Courts have

taken a view that a claim under a works contract would not fall within the

scope of the MSME Council. This is evident from the fact that the respondent

ARP-116-2018-CONNECTED MATTERS.odt was to send in running bills as the work progressed. It is not merely question

of supply or rendering services but an indivisible assignment that was

entrusted to the respondent. Apart from Sterling And Wilson Private Ltd.

(supra) this Court has also taken a view in the case of M/s. P. L. Adke vs.

in the aforesaid circumstances

all Awards are liable to be set aside.

74. For all the aforesaid reasons I am of the view that the petition must

succeed and in view thereof I pass the following order in all these petitions.

(i) The impugned awards dated 23 rd May, 2018 and the

Additional Awards dated 25th April, 2019 passed by the Micro and

Small Enterprises Facilitation Council are hereby set aside.

(ii) Parties are left to seek their independent remedies if

permissible in law.

(iii) Arbitration Petitions are disposed in the above terms. In view

of the disposal of the Arbitration Petitions all pending Applications

are disposed as infructuous.

           (iv)        No orders as to costs.



                                                                               (A. K. MENON, J.)


           17    ARA(ST)-30508-19-ARA-7-2019


           ARP-116-2018-CONNECTED MATTERS.odt



rrpillai
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter