Citation : 2021 Latest Caselaw 5626 Bom
Judgement Date : 25 March, 2021
2.ial.3041.21..doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
INTERIM APPLICATION(L)NO. 3041 OF 2021
IN
COMMERCIAL ARBITRATION PETITION (L)NO. 8430 OF
2020
WITH
COMMERCIAL ARBITRATION PETITION (L)NO. 8430 OF
2020
Sulzer Pumps India Pvt Ltd ..Applicant
IN THE MATTER BETWEEN
Shriram EPC Ltd ..Petitioner
Vs.
Sulzer Pumps India Pvt Ltd ..Respondent
Mr.Kevic Setalvad, Senior Counsel a/w Ms.Rajalakshmy
Mohandas, Ms. Pooja Shinde, Ms. Rajul Jain i/b Rajalakshmy
Associates, for the Petitioner in CARBPL. 8430/20 and for the
Applicant in IAL 8430 of 2020 for the Respondent in IAL. 3041 of
2021.
Mr.Cyrus Bharucha a/w Mr. Hormuz Mehta, Mr.Ahsan Allana i/b
J. Sagar Associates, for the Applicant in IAL. 3041 of 21 and for
the Respondent in IAL. 8430 of 2020 and for the Respondent in
CARBPL. 8430 of 20.
CORAM :- B.P.COLABAWALLA, J.
DATE :- MARCH 25, 2021.
Aswale 1/22
2.ial.3041.21..doc
P. C.:
1. The above Interim Application is filed under Section 34
(4) of the Arbitration and Conciliation Act, 1996 (for short "the
Arbitration Act") seeking to adjourn the above Section 34
Petition in order to permit the Arbitral Tribunal to resume the
arbitral proceedings or take such action as in the opinion of the
Tribunal is necessary, so as to eliminate the ground of challenge in
relation to the Awards dated 14th March, 2020 and 18th March,
2020 insofar as they do not constitute the majority consensus
Award.
2. Mr. Bharucha, the learned counsel appearing on behalf
of the Applicant (the Respondent in the Petition) submitted that
pursuant to arbitration proceedings that commenced between the
parties in 2014, an Award of the Presiding Arbitrator (the Hon'ble
Mr. Justice S. N. Variava) came to be passed on 18th March, 2020
in favour of the Applicant. Along with the Presiding Arbitrator's
Award, the concurring Award passed by the Hon'ble Mr. Justice
A.V. Savant dated 14th March, 2020 was also in favour of the
Applicant. The Awards of the Presiding Arbitrator as well as that
Aswale 2/22
2.ial.3041.21..doc
of the Hon'ble Mr. Justice A. V. Savant, for the sake of
convenience, be referred to as the "majority Award". An
undated Dissenting Award was also passed by the Petitioner's
nominated Arbitrator the Hon'ble Mr. Justice J. D. Kapoor (the
Dissenting Award). These Awards have been challenged in the
present Petition on various grounds.
3. Mr. Bharucha submitted that one of the grounds of
challenge is that the Arbitral Tribunal has passed three separate
Awards and there is no majority consensus Award. According to
the Petitioner, these separate Awards ought to be set aside in light
of the above. Mr. Bharucha submitted that according to the
Petitioner, (i) the Award passed by the Presiding Arbitrator dated
18th March, 2020 does not refer to the Award dated 14th March,
2020 passed by the Hon'ble Mr. Justice A. V. Savant; (ii) it does
not specify that the same is passed on a majority basis with the
concurrence of the Hon'ble Mr. Justice A. V. Savant; and (iii) is
signed by the Presiding Arbitrator alone and does not bear the
signature of the Hon'ble Mr. Justice A. V. Savant. Similarly,
according to the Petitioner, the Award passed by the Hon'ble Mr.
Justice A. V. Savant dated 14th March, 2020 (i) refers to an
Aswale 3/22
2.ial.3041.21..doc
opinion prepared by the Presiding Arbitrator, and therefore,
cannot be linked or connected with the Award passed by the
Presiding Arbitrator on 18th March, 2020 and which was in any
event after the concurring Award (dated 14th March, 2020), and
therefore, the Hon'ble Mr. Justice A. V. Savant could not have
concurred with an Award passed by the Presiding Officer
subsequently; and (iii) the Award passed by the Hon'ble Mr.
Justice A. V. Savant is an independent document and does not
form the part of the Award passed by the Presiding Officer.
4. Mr Bharucha submitted that submitted that in view of
these technical objections taken by the Petitioner, the Applicant
addressed a letter to the Tribunal as well as the Petitioner's
advocate dated 7th January, 2021 wherein the Applicant inter alia
requested a response to the following queries:-
(a) Whether the Hon'ble Mr. Justice Savant concurs with the Award dated 18th March 2020?
(b) Whether the Award dated 14th March 2020 issued by the Hon'ble Mr. Justice Savant ought to be read with/in addition to the Award dated 18th March 2020?
Aswale 4/22
2.ial.3041.21..doc
5. Mr. Bharucha brought to my attention that the
Petitioner objected to the aforesaid clarification sought by the
Applicant vide its letter dated 9th January, 2021. Thereafter, the
Presiding Arbitrator (the Hon'ble Mr. Justice S. N. Variava) by his
letter dated 11th January, 2021 inter alia clarified that:-
(a) He had not prepared any opinion in the matter. He had prepared the draft Award.
(b) The Presiding Arbitrator forwarded the draft Award to both his Co-Arbitrators.
(c) The Hon'ble Mr. Justice J. D. Kapoor issued an undated dissenting Award by his email dated March 11, 2020.
(d) the Hon'ble Mr. Justice A. V. Savant issued a "concurring opinion" dated March 14, 2020 which referred to the draft Award as an "opinion" as it has not been signed and dated.
(e) On receipt of the dissenting Award and the concurring opinion/award the draft Award was corrected, signed and issued with the date of March 18, 2020.
6. Similarly, the Hon'ble Mr. Justice A. V. Savant, by his
letter dated 13th January, 2021, clarified that:-
(a) He had received the draft Award from the Presiding Arbitrator.
Aswale 5/22
2.ial.3041.21..doc
(b) He had the benefit of perusing the same before issuing
his concurring award/opinion dated March 14, 2020.
(c) The concurring award/opinion was not an independent document and was based on the reasoning and conclusions recorded in the Award of the Presiding Arbitrator.
(d) In any event he completely agrees and entirely concurs with the Award dated 18th March 2020 of the Presiding Arbitrator.
7. Mr. Bharucha, therefore, submitted that the above
clearly establishes that though the concurring opinion/Award
dated 14th March, 2020 passed by the Hon'ble Mr. Justice A. V.
Savant was based on the draft Award sent to him by the Presiding
Arbitrator, he in any event completely concurs with the Award of
the Presiding Arbitrator dated on 18th March, 2020.
8. Mr. Bharucha submitted that though this would be
enough to overrule the objection raised by the Petitioner on this
technical aspect, since the Petitioner has raised arguments to the
effect that the Tribunal has become functus officio and hence no
clarifications could have been sought from the Tribunal, the
present Interim Application is filed to obviate such an argument.
Aswale 6/22
2.ial.3041.21..doc
It is in these circumstances that Mr. Bharcuha submitted that the
said objection/challenge raised by the Petitioner is technical in
nature and is such as can be eliminated by making a reference to
the Arbitral Tribunal in accordance with Section 34(4) of the
Arbitration Act.
9. On the scope of the provisions of Section 34 (4), Mr.
Bharcucha relied upon the following judgments:-
(i) Dyna Technologies Pvt Ltd v/s Crompton Greaves Ltd [(2019) 20 SCC 1];
(ii) Kinnari Mullick and Another v/s Ghanshyam Das Damani [(2018) 11 SCC 328].
10. On the other hand, Mr. Setalvad, the learned Senior
Counsel appearing on behalf of the Petitioner, submitted that
Section 34(4) contemplates an opportunity being given to an
Arbitral Tribunal to eliminate the grounds for setting aside the
Arbitral Award. This necessarily means that there must be a valid
Award in existence. It is only the grounds for setting aside the
Arbitral Award which may be eliminated, subject to there being a
valid Award in existence. Mr. Setalvad submitted that Section
34(4) does not contemplate the rectification of the record so as to
Aswale 7/22
2.ial.3041.21..doc
validate an Award, which is otherwise invalid in law. He
submitted that in the present case there is no Award as
contemplated in law. There are three separate Awards i.e. (i) the
Hon'ble Mr. Justice A. V. Savant's Award dated 14th March, 2020
(which purports to be the "Concurring Opinion"); (ii) the Presiding
Arbitrator's Award dated 18th March, 2020; and (iii) the Hon'ble
Mr. Justice Kapoor's Dissenting Award which is undated. Notably,
the Presiding Arbitrator (the Hon'ble Mr. Justice S. N. Variava)
has, in his communication dated 11th January, 2021 stated that
"after I received the Dissenting Award and Concurring
Award/Opinion, I corrected the draft, signed it and made it into an
Award on 18th March, 2020." Mr. Setalvad submitted that
indisputably, there was no joint deliberation between the
Arbitrators with regard to the corrections effected. Further the
nature of the corrections are also not known. He therefore
submitted that in these facts following position emerges:-
a. There is no "Award" as contemplated by law. What the Arbitration Act contemplates - Section 31 (5) - is that "the arbitral award" is made, signed and delivered to each party;
b. Section 31 (1) contemplates that "an Arbitral Award"
Aswale 8/22
2.ial.3041.21..doc
shall be signed by the members of the arbitral tribunal. Section 31(2) sets out that for the purposes of sub- section (1), in arbitral proceedings with more than one arbitrator, the signatures of the majority of the members of the arbitral tribunal shall be sufficient so long as the reason for any omitted signature is stated;
c. The Supreme Court in State of Maharashtra v. Ark Builders (2011) 4 SCC 616 after considering the provisions of Section 31 (5) and Section 31(1) held that - "what Section 31(5) contemplates is not merely the delivery of any kind of a copy of the award but a copy of the award that is duly signed by the member of the arbitral tribunal." [emphasis supplied]. The Supreme Court in Union of India v. Tecco Trichy Engineers & Contractors (2005) 4 SCC 239 held that - "6. Form and contents of the arbitral award are provided by Section 31 of the Act. The arbitral award drawn up in the manner prescribed by Section 31 of the Act has to be signed and dated." Further - "8. The delivery of an arbitral award under sub-section (5) of Section 31 is not a matter of mere formality. It is a matter of substance." In the present case there is no single Award, as is mandated by law. The Award dated 18th March 2020 has not been signed by all three arbitrators and therefore is not "duly signed" as required by the Supreme Court. There is also no single date.
Aswale 9/22
2.ial.3041.21..doc
d. The Bombay High Court in MSEDC v. Deltron
Electronics 2017 (2) MhLJ 605 has held that "That still does not dispense with the requirement of participation of all Arbitrators in the reference and in the deliberations of making of the award." It is further held that the absence of a signature of an arbitrator "goes to the root of the award and undermines its validity." In the present case, the "Award" dated 18th March 2020 was not deliberated upon by all three arbitrators. The corrections carried out by the Presiding Arbitrator were not shown to the other two arbitrators. The same were not perused or deliberated upon. The said 'Award' dated 18th March 2020 was not signed by two of the arbitrators (i.e. Justice Savant and Justice Kapoor). The said defects in the Award undermine its very validity and are not curable;
e. The elimination of grounds as contemplated by Section 34(4) can only be with regard to the merits of the case. An invalid award cannot be validated by resorting to Section 34(4) - see AIR 1962 SC 551 Rikhabdass v. Ballabhdas and 1998 1 Mah LJ 700 Ashok Tubes v.
Steel Industries; and
f. The Lahore High Court has held that an award signed on different dates by two arbitrators renders the
Aswale 10/22
2.ial.3041.21..doc
award invalid in law - see AIR 1914 Lah 436 (DB) Bhagwan Das v. Shiv Dial.
11. Mr. Setalvad therefore submitted that there was no
merit in the above Application filed under Section 34 (4) of the
Arbitration Act and the same ought to be dismissed.
12. In the alternative, Mr. Setalvad submitted that if I am
inclined to allow the Application under Section 34 (4) of the
Arbitration Act, then the bank guarantee of Rs.3.5 crores given by
the Petitioner at the stage of the Section 9 petition (and which
petition was filed post the passing of the Awards), should be
returned to the Petitioner. If an order under Section 34 (4) is
passed at the request of the Applicant, it plainly demonstrates
that there are errors on the face of the Award. In the present
case, the validity of the Award itself is in doubt. In such
circumstances, a pre-deposit order which has been passed in the
section 9 petition ought not to be permitted to stand and hence I
ought to direct the return of the bank guarantee of Rs. 3.5 Crores
furnished by the Petitioner to this Court. The last submission
made by Mr. Setalvad and which was also in the alternative was
Aswale 11/22
2.ial.3041.21..doc
that, if I am inclined to entertain the present Application, then the
Arbitral Tribunal also ought to consider all the submissions made
by the Applicant in connection with mitigation of damages.
13. I have heard the learned counsel for the parties at
length and have perused the papers and proceedings in the
Interim Application. The challenge in the above section 34
Petition is to quash and set aside the Award dated 18th March,
2020, Award dated 14th March, 2020 and the Dissenting Award.
One of the grounds of challenge to the aforesaid Awards is that
there are three separate Awards i.e. (i) the Hon'ble Mr. Justice
Savant's Award dated 14th March, 2020 (which purports to be the
"Concurring Award"); (ii) The presiding Arbitrator's Award dated
18th March, 2020 (the Hon'ble Mr. Justice Variava's Award); and
(iii) the Hon'ble Mr. Justice Kapoor's Award which is undated and
which is the Dissenting Award. The argument canvassed before
me is that the Hon'ble Mr. Justice Savant's Award is dated 14th
March, 2020 and which is the concurring opinion with the
Presiding Arbitrator's Award. On the other hand, the Presiding
Arbitrator's Award (the Hon'ble Mr. Justice S. N. Variava) is
dated 18th March, 2020. The argument canvassed is that the
Hon'ble Mr. Justice A. V. Savant could not have given a
Aswale 12/22
2.ial.3041.21..doc
concurring opinion on 14th March, 2020 when the Presiding
Arbitrator's Award (Justice Variava's Award) itself, and with
which he concurred with, is dated 18th March, 2020. He
submitted that this is fatal and cannot be cured under Section
34(4) of the Arbitration Act. The entire argument before me
proceeded on this basis.
14. I am unable to agree with the submissions of Mr.
Setalvad as I find that the objection taken is a hyper technical one,
to say the least. Though it may be true that the Hon'ble Mr.
Justice A. V. Savant could not have given a concurring opinion on
14th March, 2020 to the Award passed by the Presiding Arbitrator
on 18th March, 2020, the facts of this case would clearly show that
when this objection was raised, the Hon'ble Mr. Justice A. V.
Savant clearly opined that it is incorrect to assume that his
concurring opinion/Award could not have referred to the
opinion/Award passed by the Presiding Arbitrator. He has clearly
stated that the Presiding Arbitrator forwarded a draft of his
Award in the first week of March, 2020. Having perused the
same, he prepared his concurring opinion and signed the same on
14th March, 2020 and sent the hard copy to the learned Presiding
Aswale 13/22
2.ial.3041.21..doc
Arbitrator. He therefore clarified that it is in this factual
background that one has to read the opening two paragraphs of
his concurring opinion and which has been quoted in paragraph 5
(I) (a) of the above Arbitration Petition. The Hon'ble Mr. Justice
A. V. Savant thereafter has categorically stated that he fully
concurs with the Presiding Arbitrator's Award dated 18th March,
2020 and his concurring opinion ought to be read with/in addition
to the Award dated 18th March, 2020. In effect, what has been
stated by the Hon'ble Mr. Justice A. V. Savant is that he has had
the opportunity to see the signed Award of the Presiding
Arbitrator dated 18th March, 2020 and he fully concurs with the
same. In fact, on the basis of this correspondence itself, I would
have been justified in rejecting the aforesaid objection taken by
the Petitioner in the above Petition. However, as mentioned
earlier, in order to obviate any argument by the Petitioner that no
such clarifications could have been given by the Tribunal after
passing of the Award as it had become functus officio, is why the
present application is filed under Section 34 (4) of the Arbitration
Act.
15. Section 34 deals with an application for setting aside
the Arbitral Award. The grounds on which the Arbitral Award can
Aswale 14/22
2.ial.3041.21..doc
be set aside are also set out in the said Section. Sub-section 4 of
Section 34 stipulates that on receipt of an application under sub-
section (1) (i.e. to challenge an Arbitral Award), the Court may,
where it is appropriate and it is so requested by a party, adjourn
the proceedings for a period of time determined by it in order to
give the Arbitral Tribunal an opportunity to resume the arbitral
proceedings or to take such other action as in the opinion of the
Arbitral Tribunal will eliminate the grounds for setting aside the
Arbitral Award.
16. I am cognizant of the fact that Arbitral Awards should
not be interfered with in a casual and cavalier manner, unless the
Court comes to a conclusion that the perversity of the Award goes
to the root of the matter without there being a possibility of an
alternative interpretation which may sustain the Arbitral Award.
Undoubtedly, Section 34 is different in its approach and cannot be
equated with a normal appellate jurisdiction. The mandate under
Section 34 is to respect the finality of the Arbitral Award and the
party autonomy to get their dispute adjudicated by an alternative
forum as provided under the law. If the Courts were to interfere
with Arbitral Awards in the usual course on factual aspects, then,
the commercial wisdom behind opting for alternate dispute
Aswale 15/22
2.ial.3041.21..doc
resolution would stand frustrated.
17. I am stating this not merely as my opinion but the
same has been clearly stated by the Supreme Court in Dyna
Technologies Pvt Ltd (supra). Paragraphs 24 and 25 of this
decision read thus:-
"24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act."
18. In the very same decision, the Supreme Court has also
held that the legislative intent of enacting Section 34 (4) of the
Arbitration Act was to make the Award enforceable, after giving
Aswale 16/22
2.ial.3041.21..doc
an opportunity to the Tribunal to undo the curable defects. This
provision cannot be brushed aside. In fact, the Supreme Court has
opined that even in the case of an unreasoned Award the power
under Section 34(4) of the Arbitration Act can be exercised to
cure such a defect. The Supreme Court has clearly laid down that
the power vested under Section 34(4) of the Arbitration Act to
cure defects can be utilized in cases where the Arbitral Award
does not provide any reasoning or if the Award has some gap in
the reasoning or otherwise and that can be cured so as to avoid a
challenge based on the aforesaid curable defects under Section 34
of the Arbitration Act. The relevant portion reads thus:-
"36. At this juncture it must be noted that the legislative intention of providing Section 34(4) in the Arbitration Act was to make the award enforceable, after giving an opportunity to the Tribunal to undo the curable defects. This provision cannot be brushed aside and the High Court could not have proceeded further to determine the issue on merits.
37. In case of absence of reasoning the utility has been provided under Section 34(4) of the Arbitration Act to cure such defects. When there is complete perversity in the reasoning then only it can be challenged under the provisions of Section 34 of the Arbitration Act. The power vested under Section 34(4) of the Arbitration Act to cure defects can be utilised in cases where the arbitral award does not provide any reasoning or if the award has some gap in the reasoning or otherwise and that can be cured so as to avoid a challenge based on the aforesaid curable defects under Section 34 of the Arbitration Act. However, in this case such remand to the Tribunal would not be beneficial as this case has taken more than 25 years for its adjudication. It is in this state of affairs that we lament that the purpose of arbitration as an effective and expeditious forum itself stands effaced."
Aswale 17/22
2.ial.3041.21..doc
19. In the present case, I find that the objection taken is
purely of a technical nature. The Petitioner wants to take
advantage of the fact that the concurring opinion of the Hon'ble
Mr. Justice A. V. Savant was based on a draft Award of the
Presiding Arbitrator (the Hon'ble Mr. Justice S. N. Variava) and
not on the basis of his final Award. This defect can certainly be
cured under Section 34 (4) of the Arbitration Act by giving an
opportunity to the Arbitral Tribunal to resume the arbitral
proceedings or take such other action as in its opinion will
eliminate the aforesaid ground of challenge. I am unimpressed
with the argument of Mr. Setalvad that to eliminate a ground for
setting aside the Arbitral Award would necessarily mean that
there must be valid Award in existence. I fail to understand this
argument. Any Petitioner who approaches the Court under
Section 34 of the Arbitration Act, seeks to set aside Award on the
ground that it is invalid. No party approaches the Court under
Section 34 to challenge a valid Award. That would be
preposterous. Every Petition under Section 34 proceeds on the
basis that the Award is invalid for the reasons set out in the
Petition and hence be set aside. I, therefore, fail to understand as
to how Mr. Setalvad contends that the power under Section 34(4)
Aswale 18/22
2.ial.3041.21..doc
can only be exercised when there is a valid Award in existence. If
the Award is valid, there is no question of challenging the same
under Section 34 of the Arbitration Act. In fact, from the Petition
it can be seen that there are several grounds on which the
impugned Awards are challenged. This being the case, I do not
think that this Court would be precluded from exercising its
jurisdiction under Section 34(4) of the Arbitration Act.
20. There is yet another reason why I am inclined to
exercise my jurisdiction under Section 34 (4) of the Arbitration
Act. It is not in dispute that the arbitration proceedings
commenced in the year 2014. Both parties led their respective
evidence and were thereafter heard by the Arbitral Tribunal
which culminated into the impugned Awards. If I was to set aside
the Awards on the hyper technical ground that they are not signed
on the same date, it would not only be highly unjust but would run
counter to the very object of the Arbitration and Conciliation Act,
1996 and the Commercial Courts Act, 2015 which is to dispose of
commercial disputes as expeditiously as possible.
21. This now only leaves me to deal with the alternate
arguments canvassed by Mr. Setalvad. Mr. Setalvad argued that if
Aswale 19/22
2.ial.3041.21..doc
I am inclined to exercise my jurisdiction under Section 34(4), the
bank guarantee given by the Petitioner of Rs.3.5 Crores be
returned. This argument proceeds on the basis that the Court is
therefore satisfied that there is a defect in the Awards which is
required to be cured and without which the Awards would be set
aside. I am afraid, I am unable to entertain this argument at this
stage. By order dated 23rd July, 2020 passed in a Section 9
Petition filed by the Applicant herein (the Respondent in the
Section 34 Petition), the Petitioner was required to deposit or
furnish a bank guarantee in the sum of Rs. 3.5 Crores. The
Petitioner has in fact furnished a bank guarantee for the said
amount. Whilst passing its order, the Court made it clear that
when this Court hears any application for stay preferred by the
Petitioner herein, it will be open to the Petitioner to argue that the
bank guarantee furnished should be returned or the bank
guarantee furnished be allowed to be adjusted or reckoned in any
conditional order that this Court may pass in that regard. Today, I
am not considering any application for stay of the impugned
Award. This will be decided as and when the application for stay
of the impugned Award is heard by this Court. This being the
position, I do not think that at this stage any such order can be
Aswale 20/22
2.ial.3041.21..doc
passed and that too in an Application filed by the Applicant herein
under Section 34 (4) of the Arbitration Act.
22. As far as the other alternative submission regarding
the fact that the Arbitral Tribunal ought to consider all the
submissions made by the Applicant in connection with mitigation
of damages is concerned, I fail to understand how such a request is
made by a party who is challenging the Award. One of the
grounds taken by the Petitioner is that the Tribunal failed to
consider all the submissions in connection with mitigation to
damages. If it is correct in its submission it would succeed so long
as it able to satisfy the Court that it falls within the parameters of
Section 34. I, therefore, do not think that even this alternative
argument can be granted by this Court.
23. In view of the foregoing discussion, the Interim
Application is allowed and the Arbitral Tribunal is directed to
resume the arbitral proceedings or take such other action as in the
opinion of the Tribunal is necessary to eliminate the ground of
challenge in relation to the two Awards dated 14th March, 2020
and 18th March, 2020 insofar as they do not constitute the
majority consensus Award.
Aswale 21/22
2.ial.3041.21..doc
24. The Tribunal is requested to carry out this exercise
within a period of four weeks from today.
25. Place the above Arbitration Petition along with the
Application for stay on 5th May, 2021.
26. The above Interim Application is accordingly disposed
of. However, there shall be no order as to costs.
27. At this stage, the learned counsel appearing on behalf
of the Petitioner (the Respondent in the Interim Application) has
prayed for stay of this order. Considering what I have already
held in the order, I do not think any stay is warranted. The
application for stay is therefore rejected.
28. This order will be digitally signed by the Private
Secretary/Personal Assistant of this Court. All concerned will act
on production by fax or email of a digitally signed copy of this
order.
(B. P. COLABAWALLA, J.)
Aswale 22/22
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!