Citation : 2021 Latest Caselaw 4356 Bom
Judgement Date : 10 March, 2021
1 1033-wp 2128-2021+.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 2128 OF 2021
M/s ISC Projects-BNA-Infra (JV),
Joint Venture through its Director -
Special Power of Attorney
Ashwin Suresh Agrawal .. Petitioner
Versus
The Union of India and others .. Respondents
Mr. R. S. Deshmukh, Senior Advocate i/by Mr. Nirmal Rajendra
Dayama and Devang Deshmukh, Advocate for the Petitioner.
Mr. A. G. Talhar, A.S.G. for Respondent No. 1.
Mr. S. B. Deshpande, Advocate for Respondent Nos. 2 and 3.
WITH
WRIT PETITION NO. 2294 OF 2021
M/s B N Agrawal,
through its partner -Special
Power of Attorney
Ashwin Suresh Agrawal .. Petitioner
Versus
The Union of India and others .. Respondents
Mr. R. S. Deshmukh, Senior Advocate i/by Mr. Nirmal Rajendra
Dayama and Devang Deshmukh, Advocate for the Petitioner.
Mr. A. G. Talhar, A.S.G. for Respondent No. 1.
Mr. S. B. Deshpande, Advocate for Respondent Nos. 2 and 3.
CORAM : S. V. GANGAPURWALA &
SHRIKANT D. KULKARNI, JJ.
DATED : 10th March, 2021.
1 of 6
2 1033-wp 2128-2021+.odt
PER COURT:-
. The petitioners are assailing the recovery notices issued to them
by the respondent No. 3.
2. Pursuant to the tender notice the petitioners filled in the tender.
The petitioners were awarded the work for construction of 165 Nos
Minor bridges and Earthwork in embankment and cutting between
Chalisgaon - Jalgaon (93 Kms.) in Writ Petition No. 2128 of 2021. The
work of construction of one important and 21 Major bridges in
Manmad - Jalgaon section in connection with Manmad - Jalgaon 3 rd
line (160 Kms.) in Writ Petition No. 2294 of 2021 was awarded. The
said work was awarded in March 2019. During the continuance of the
work the impugned recovery notices are issued.
3. Mr. Deshpande, learned counsel for respondent Nos. 2 and 3
raises a preliminary objection that the parties under the terms of the
contract have agreed to refer the dispute to the arbitration.
4. Mr. Deshmukh, learned senior counsel for the petitioners
strenuously contends that excepted matters as provided in the clause of
arbitration cannot be referred to arbitration. The learned senior counsel
refers to clauses 57.2 and 57.3 (15) of the terms of the tender.
According to the learned senior counsel, the present dispute would be
2 of 6
3 1033-wp 2128-2021+.odt
within the realm of excepted matters as provided under clause of
tender and cannot be referred to arbitration.
5. The learned senior counsel further contends that availability of a
remedy before the arbitrator or before any other Court would not affect
the powers of this Court under Article 226 of the Constitution of India
and even in matters involving contractual disputes, this Court can
entertain the writ petition. The learned senior counsel relies on the
judgment of the Apex Court in case of Union of India & Ors. Vs. Tantia
Construction Pvt. Ltd. Reported in 2011 (5) SCC 697.
6. The learned senior counsel further lays emphasis that the
impugned recovery notices are issued in violation of principles of
natural justice. Prior to issuance of the recovery notices no show cause
notices were issued, nor say of the petitioners was called. The
petitioners could have explained the payments made to it and that the
payments are not illegal or excess payments. Referring to the affidavit
in reply filed by the respondents, the learned senior counsel submits
that the respondents are also not fully convinced of the alleged over
payments or excess payments. They do not have any record to verify
the same, still the recovery notices are issued against the petitioners.
The same suffers from non application of mind.
3 of 6
4 1033-wp 2128-2021+.odt
7. The learned senior counsel further submits that the officer who
has issued the recovery notices, on the same day has also issued
another communication to the effect that the matter of wrongful
payment / over payment / bogus payment done previously is under
investigation by the vigilance department. The said letter is of even
date. The impugned recovery notice is issued before completion of
investigation. The same would not satisfy the test of the reasonableness
and also no conclusive finding could have been arrived at about excess
payment made to the petitioners. In the light of that, the learned senior
counsel emphasizes to entertain the writ petitions under Article 226 of
the Constitution of India.
8. The learned senior counsel further submits that the recovery
claimed is of Rs. 04 Crore and odd amount in each matter and the
security deposit of the petitioners is more than Rs. 08 Crore in each
matter. The amount claimed by the respondents even if found to be
genuine could be recovered from the security deposit of the petitioners.
9. Though the learned senior counsel for the petitioners and the
learned counsel for the respondents canvassed their submissions on
merits, it would appear that clause of arbitration exists between the
parties. The respondents have not determined the contract as per the
terms of settlement of disputes. Excepted matters are detailed under
4 of 6
5 1033-wp 2128-2021+.odt
clause 57.3. The clause relied by the learned senior counsel for the
petitioners would not inure to the benefit of the petitioners in as much
as clause 57.3. (15) would apply only if the contract is determined
owing to the default of contractor. In the present matters the contract
between the parties still subsist. The contract is not determined. None
of the other matters as detailed under clause 57.3 can be invoked to
bring it within the purview of the excepted matters.
10. As contended by the learned counsel for the respondents, the
present matter is arbitrable and can be dealt with by the arbitrator to
be appointed in terms of the agreement between the parties.
11. In the case of Union of India & Ors. (supra) the matter before the
Apex Court was for payment of the work already completed by the
company. In the said matter it does not appear that there was dispute
with regard to the work done and the rate agreed upon. In the present
matters the dispute between the parties revolve around the alleged
excess payment or otherwise. The same would certainly require the
evidence and detailed investigation of disputed facts.
12. As the dispute between the parties is arbitrable and the matter
can be dealt with by the arbitrator as per the terms and conditions
agreed between the parties, we are not inclined to invoke our writ
5 of 6
6 1033-wp 2128-2021+.odt
jurisdiction under Article 226 of the Constitution of India.
13. The parties may take up the process for arbitration and for
further reliefs as the petitioners may claim under the provisions of the
Arbitration and Conciliation Act. In that event, all contentions of the
parties are kept open.
14. Writ petitions, as such, are disposed of with aforesaid
observations. No costs.
( SHRIKANT D. KULKARNI ) ( S. V. GANGAPURWALA )
JUDGE JUDGE
P.S.B.
6 of 6
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!