Citation : 2021 Latest Caselaw 7984 Bom
Judgement Date : 17 June, 2021
4.wp.6096.19.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CRIMINAL APPELLATE JURISDICTION
CRIMINAL WRIT PETITION NO. 6096 OF 2019
Kishor V. Patil & Ors. ... Petitioners
Versus
The State of Maharashtra & Ors. ... Respondents
.........
Mr. Sugandh B. Deshmukh for the Petitioners.
Mr. Amit A. Gharte for Respondent No.8.
Mr. J.P. Yagnik, A.P.P. for the Respondent-State.
.........
CORAM : K.K. TATED &
R.I. CHAGLA, JJ.
DATE : 17th JUNE, 2021.
(V.C.)
P.C. :-
1 Heard learned Counsel for the parties.
2 By this Criminal writ Petition under Article 226 of the
Constitution of India, the Petitioners are seeking directions against
Respondent-Police Authority to register the F.I.R. against Respondent
Nos.8 and 9 on the basis of their complaints dated 26.09.2017 and
07.05.2019.
Waghmare 1 / 15
4.wp.6096.19.doc
3 The learned Counsel Mr. Sugandh B. Deshmukh appearing
on behalf of the Petitioners submits that the Petitioners are purchasers
of flat in a project floated by Respondent Nos.8 and 9 on Survey
No.210/1/1 Viman Nagar, Pune. The learned Counsel for the
Petitioners submits that the Petitioners purchased the flats by
registered agreements. Some of the agreements are placed on record
in the present Petition from pages 26 to 667. The learned Counsel for
the Petitioners submits that as Respondent Nos.8 and 9 failed and
neglected to handover the possession of the respective flats to the
purchasers, they filed the police complaint against Respondent Nos.8
and 9 for taking action under Section 406, 409, 420 and 120B r/w
Section 34 of Indian Penal Code, 1860. He submits that the police
authority failed and neglected to take action. Hence, the present Writ
Petition.
4 The learned Counsel for the Petitioners submits that bare
reading of the complaint dated 07.05.2019 clearly shows that
Respondent Nos.8 and 9 misappropriated the amount of more than
Rs.90 crores. Not only that Respondent Nos.8 and 9 in connivance
with Pune Municipal Corporation handed over portion of land from
the said plot for construction of road to Corporation. He further
Waghmare 2 / 15
4.wp.6096.19.doc
submits that even Respondent Nos.8 and 9 agreed, as per terms and
conditions of the agreement, that if there is delay in handing over
possession of flats, in that case they will pay the monthly
compensation, which they failed and neglected to do so. Not only that
Respondent Nos.8 and 9 raised funds from several banks for the said
project and utilized the said in some other projects. In this way
Respondent Nos.8 and 9 committed criminal breach of trust and
therefore they filed the complaint with the police authority.
5 The learned Counsel for the Petitioners submits that if the
case of criminal breach of trust is made out, then the police authority
are duty bound to register the offence. He further submits that even
bare disclosure of criminal offence, then also Police Authority shall
register the offence i.e. F.I.R. In support on this contention, the learned
Counsel for the Petitioners relies on the judgment of Apex Court in the
matter of Lalita Kumari vs. Government of Uttar Pradesh and others 1
Para 119 of the said judgment reads thus :
"119. Therefore, in view of various counterclaims regarding registration or non-registration, what is necessary is only that the information given to the police must disclose the commission of a cognizable offence. In
1 2014 SCC page 1
Waghmare 3 / 15
4.wp.6096.19.doc
such a situation, registration of an FIR is mandatory. However, if no cognizable offence is made out in the information given, then the FIR need not be registered immediately and perhaps the police can conduct a sort of preliminary verification or inquiry for the limited purpose of ascertaining as to whether a cognizable offence has been committed. But, if the information given clearly mentions the commission of a cognizable offence, there is no other option but to register an FIR forthwith. Other considerations are not relevant at the stage of registration of FIR, such as, whether the information is falsely given, whether the information is genuine, whether the information is credible etc. These are the issues that have to be verified during the investigation of the FIR. At the stage of registration of FIR, what is to be seen is merely whether the information given ex facie discloses the commission of a cognizable offence. If, after investigation, the information given is found to be false, there is always an option to prosecute the complainant for filing a false FIR."
6 On the basis of these facts, the learned Counsel for the
Petitioners submits that in the interest of justice this Hon'ble Court be
pleased to direct the Police Authority to investigate and register the
F.I.R. against Respondent Nos.8 and 9.
7 On the other hand the learned Counsel Mr. Amit A. Gharte
Waghmare 4 / 15
4.wp.6096.19.doc
appearing on behalf of Respondent No.8 vehemently opposed the
present Writ Petition. He submits that the Writ Petition as it is filed by
the Petitioners, is not maintainable. He submits that as per the Code
of Criminal Procedure, for failure to take cognizance of the complaint
and/or non registration of F.IR. then alternative remedy is available.
He submits that as per Section 154(3) of Criminal Procedure Code,
complainant can make application to the Superintendent of Police
and/or filed complaint under Section 156(3) of the Cr.P.C. In support
of this contention, he relies on the judgment of Apex Court in the
matter of Sakiri Vasu vs. State of Uttar Pradesh and others 2. Para 11
of the said judgment reads thus :
11. In this connection we would like to state that if a person has a grievance that the police station is not registering his FIR under Section 154 Cr.P.C., then he can approach the Superintendent of Police under Section 154(3) Cr.P.C. by an application in writing. Even if that does not yield any satisfactory result in the sense that either the FIR is still not registered, or that even after registering it no proper investigation is held, it is open to the aggrieved person to file an application under Section 156 (3) Cr.P.C. before the learned Magistrate concerned. If such an application under Section 156 (3) is filed before the Magistrate, the Magistrate can direct the FIR to be registered and also can direct a proper investigation to be 2 2008 AIR SCW 309
Waghmare 5 / 15
4.wp.6096.19.doc
made, in a case where, according to the aggrieved person, no proper investigation was made. The Magistrate can also under the same provision monitor the investigation to ensure a proper investigation.
8 The learned Counsel for Respondent No.8 submits that as an
efficacious alternate remedy is available to the Petitioners, there is no
question to entertain the present Writ Petition. Same is required to be
dismissed with costs.
9 The learned Counsel for Respondent No.8 submits that in
respect of the flats purchased by Petitioner Nos.1-Mr. Kishor V. Patil, 3-
Mr. Balbhim D. More, 4-Mr. Rameshchandra Manilal Dhodia, 5-Mr.
Satya Swarup Udgata, 7-Mr. Swapnil Naik and 13-Mr. Kishor Dighe,
they have already obtained occupation certificate last year. He
submits that unless and until these Petitioners pay balance amount,
there is no question of handing over possession to them. He further
submits that he received instructions from his client that Petitioner
Nos.6, 10 and 11 do not want to prosecute the Petition. This fact is
not disputed by the learned Advocate for the Petitioners across the bar.
The learned Counsel for Respondent No.8 submits that construction in
the remaining Petitioners' five flats, is carried out upto 95%. He
Waghmare 6 / 15
4.wp.6096.19.doc
submits that because of lock-down since last year it remained on their
part to complete the work. He submits that the work of remaining five
flats shall be completed immediately.
10 The learned Counsel for Respondent No.8 submits that
before completion of construction of flats and obtaining NOC, they
handed over possession of flats to the Petitioners, for carrying out their
interior work. He submits that at the time of doing interior work,
most of the Petitioners carried out unauthorised construction in those
flats. Hence, the Corporation issued notice dated 27.01.2020 to
Respondent No.8 for removing unauthorised work. He submits that
unless and until the said unauthorised work is removed, there is no
question getting occupation certificate from the Corporation.
11 The learned Counsel for the Petitioners submits that as per
Clause 14 of the agreement between the parties, if there is a delay in
handing over possession of flats, in that case purchaser can demand
refund of the entire amount with interest.
Clause 14 of the said agreement reads thus :
"14. It is agreed between the parties hereto that if the Promoter/s fail to give possession of the said Unit in accordance with the terms of this Agreement on the
Waghmare 7 / 15
4.wp.6096.19.doc
date mentioned in Clause 5(b) hereinabove, or if, the Promoter/s and/or its Agents for reasons beyond their control, are unable to give possession of the said Unit by the said date and after a period of three months if those reasons still exist, then in such case, the Promoter/s shall, without prejudice to their rights reserved hereunder and on demand therefor made by the Purchaser/s, be liable to refund the amounts already received by them in respect of the said Unit from the Purchaser/s with simple interest thereon at the rate of 9% per annum from the date it received the same till the date the amounts and interest thereon is refunded to the Purchaser/s and the said amount and interest shall be charged on the said Unit to the extent of amounts due, but subject to any prior encumbrance. Provided however, that the Promoter/s shall be entitled to a reasonable extension of time for giving delivery of the Unit by the aforesaid date, if the completion of the said Building in which the Unit is to be housed is delayed on account of :
i) War, Civil Commotion or Act of God.
ii) Any notice, order, rule, notification of Government and/or Municipal or other public or competent authority which prevents the Promoter/s from carrying out with the work of development and construction on the said land.
Waghmare 8 / 15
4.wp.6096.19.doc
iii) Any delay on the part of the Municipal
Corporation of Pune or any other Public Body or Authority, including the M.S.E.D.C.L. in issuing or granting necessary Certificates / Noc's / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Complex under construction by the Promoter/s on the said Land.
iv) Force-majeure Causes or other reasons beyond the control of the Promoter/s.
v) Any additional work in the said Unit undertaken by the Promoter/s at the instance of the Purchaser/s.
vi) Any delay or default by the Purchaser in making payments as per terms and conditions of this Agreement (without prejudice to the right of the Promoter/s to terminate this agreement under Clause 15 mentioned herein below).
The Purchaser/s shall take possession of the said Unit within seven days of the Promoter/s intimating to the Purchaser/s that the said Unit is ready for use and occupation and, in that behalf, comply with all necessary legal formalities. The Purchaser/s shall not without the prior written consent of the Promoter/s or
Waghmare 9 / 15
4.wp.6096.19.doc
the ultimate body to be formed, as the case may be, to carry out any alternations of whatsoever nature in the said Unit or make any alterations in any of the fittings, pipes, water supply connections as this may result in seepage of water. The Purchaser/s shall also not chisel or cause damage to the columns, beams, walls, slabs, R.C.C. members and other structural members or damage the water proofing of the flooring of the said Unit. If any of such works are carried out without the written consent of the Promoter/s, the liability of the Promoter/s under the Ownership Flats Act, 1963 to rectify defects automatically shall become void and Purchaser/s shall be liable to pay all costs and damages towards restoration, repairs etc. arising from such unauthorized works. It is also mutually agreed that the said statutory liability period will start from the date of the Promoter/s obtaining Completion Certificate of the said Unit from the Municipal Corporation of Pune and shall extend for a period of three years. The Purchaser/s shall take possession of the said Unit after inspecting the same and satisfying itself / herself / themselves that the same has been constructed in accordance with the Building Plans in respect thereof and that the same has been provided with the Amenities agreed upon and that the quality of the workmanship and material used is of the requisite quality. Subject to what is stated above, save
Waghmare 10 / 15
4.wp.6096.19.doc
and except any latent defects which become visible during the said defect liability period, the Promoter/s shall not be obliged to entertain any complaint or claim made by the Purchaser/s in respect of the said Unit after possession thereof has been handed over to the Purchaser/s."
12 The learned Counsel for Respondent No.8 submits that even
if there is a delay in handing over possession of the constructed flat,
the purchasers can demand compensation for delay as per The Real
Estate (Regulation and Development) Act, 2016. He submits that one
of the purchasers Mr. Vivek Rameshchandra Dhodia with Mr.
Rameshchandra Manilal Dhodia filed complaint before the
Maharashtra Real Estate Regulatory Authority, Pune. The Maharashtra
Real Estate Regulatory Authority, Pune, after hearing both the sides
passed final order dated 25.05.2018 directing Respondent Nos.8 and 9
to pay simple interest @10.05% p.a. to the complainants on the
amount of Rs.1,75,32,000/- since 01.01.2017. The operative part of
the said order is thus :
"ORDER
1. The Respondents are directed to pay simple interest @10.05% p.a. to the complainants on the amount of Rs.1,75,32,000/- since 01.01.2017.
Waghmare 11 / 15
4.wp.6096.19.doc
2. The Respondent shall pay the interest due and payable to the Complainants within 30 days from the date of this order and shall be continued to pay for every month's delay till handing over possession of the respective flats to each of them.
3. In addition to this, the Respondents are also directed to pay the amount of Rs.10,000/- to the Complainants towards the cost of this litigation."
13 The learned Counsel for Respondent No.8 submits that it is
crystal clear from the order dated 25.05.2018 passed by the
Maharashtra Real Estate Regulatory Authority, Pune, if there is delay
in handing over possession on the part of developer, they have to pay
compensation including interest to the purchaser on facts of each
case.. Hence, there is no question of filing any complaint.
14 The learned Counsel for Respondent No.8 further submits
that the present project is already registered with RERA. He submits
that if any offence is committed, then cognisance of offence can only
be taken in compliance with Section 80 of the Real Estate (Regulation
and Development) Act, 2016. Section 80 reads thus :
Waghmare 12 / 15
4.wp.6096.19.doc
"80. Cognizance of offences
(1) No court shall take cognizance of any offence punishable under this Act or the rules or regulations made thereunder save on a complaint in writing made by the Authority or by any officer of the Authority duly authorised by it for this purpose.
(2) No court inferior to that of a Metropolitan Magistrate or a Judicial Magistrate of the first class shall try any offence punishable under this Act."
15 On the basis of these facts, the learned Counsel for the
Respondent No.8 submits that there is no substance in the present
Petition and same is required to be dismissed with costs.
16 We heard both the sides at length. It is to be noted that in
the present proceeding the Petitioners purchased flat from Respondent
Nos.8 and 9 in their project at Pune. As per agreement there is delay
on the part of Respondent Nos.8 and 9 in handing over possession.
Therefore, the Petitioners made a complaint to the Police Authority for
taking cognizance under Sections 406, 418 and 420 of Indian Penal
Code. Bare reading of the said complaint dated 07.05.2019 clearly
shows that, grievances made by the Petitioners are of civil nature only.
Their main grievance is that, Respondent Nos.8 and 9 in connivance
Waghmare 13 / 15
4.wp.6096.19.doc
with the Corporation handed over plot of land from the said project
for construction of road. We find, there is no question of any
connivance between the Corporation and Respondent/Developer.
Corporation can take any land for construction of road after following
due process of law. Same is not challenged by the Petitioners. Not
only that, nothing is placed on record by the Petitioners in this
complaint, how there is connivance between Respondent Nos.8 and 9
with Corporation. Further in respect of delayed possession, some of
the purchasers filed complaint before the RERA.
17 Considering these facts, prima facie we do not find any case,
that Petitioners have made out for criminal action against Respondent
Nos.8 and 9. Apart from that, if the Police Authority failed to register
the F.I.R. then alternative remedy is available to the Petitioners under
Section 154(3) to approach the Superintendent of Police or file
application before the Magistrate under Section 156(3) of Cr.P.C.
18 The Apex Court in the matter of Lalita Kumari vs.
Government of Uttar Pradesh, specifically held in para 119 that unless
and until information given to the police discloses commission of a
cognizable offence, there is no question of registering F.I.R.
Considering these facts and the decision of the Apex Court in Sakiri
Waghmare 14 / 15
4.wp.6096.19.doc
Vasu (supra) and Lalita Kumari (supra), we do not find any reason to
entertain the present Writ Petition.
19 In view of above mentioned facts, Criminal Writ Petition
required to be dismissed. Hence, the following order is passed :
i) Criminal Writ Petition stands dismissed.
ii) No order as to costs.
( R.I. CHAGLA, J. ) ( K.K. TATED, J. )
Waghmare 15 / 15
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!