Citation : 2021 Latest Caselaw 226 Bom
Judgement Date : 6 January, 2021
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
INTERIM APPLICATION (L) NO.3557 OF 2020
ALONG WITH
INTERIM APPLICATION (L) NO.3559 OF 2020
ALONG WITH
CHAMBER SUMMONS (L) NO.824 OF 2019
IN
COMMERCIAL EXECUTION APPLICATION (L)NO.1268 OF 2019
Kash Foods Pvt.Ltd. & Ors. .. Applicants/Claimants
Vs.
Omkar Realtors & Developers Pvt.Ltd. .. Respondent
Mr. Haresh Jagtiani, Sr. Advocate, a/w Mr. Sharan Jagtiani, Sr.
Advocate, a/w Ms. Bhumika Chulani & Ms. Bhavi Vora i/b.
Siddhesh Bhole for the applicant.
Mr. Mayur Khandeparkar a/w Jamshed a/w H. Diamondwala
i/b. Diamondwala & Co. for the respondent.
CORAM : A. K. MENON, J.
DATED : 6TH JANUARY, 2021.
P.C. :
1. The applicants are proceeding in execution of consent
award passed by a sole arbitrator. The applicants are the
claimants in arbitration. Three separate applications seek
Chsl-824-19 wadhwa the diverse reliefs against the sole respondent. In the
Chamber Summons of several reliefs, the applicants have
now restricted their claim to prayer clauses j (i) & (ii) and
prayer clause k(ii) restricted to unsold units in Tower C.
2. In application no.3557 of 2020, the applicant seeks a
temporary injunction restraining the respondent, its
servants and agents from alienating, creating third party
rights or transferring development rights granted to
respondent under a development agreement dated 13 th
April, 2013 without prior approval of the applicants. The
applicants also seek an order directing the respondent to
disclose (a) Minutes of Meetings held on 30 th August,
2020 between respondent and its lead investors and third
parties in relation to the project known as Omkar 1973
at Worli; (b) details and information about any
transaction entered into by the respondent and any third
party in relation to transfer of its development rights in
the project and (c) details and information entered into
between the respondent and third parties in relation to the
said project.
Chsl-824-19 wadhwa
3. In the third proceeding, Interim application no.3559 of
2019, the applicants seek an order directing the
respondent to pay a sum of Rs.71,09,820/- p.m. to the
applicants under clause 21 of the consent terms between
the parties till the applicants are handed over the agreed
and allocated constructed premises described as "Modified
Owners' Allocation."
4. According to the applicants, based on the respondent's
calculation in accordance with clause 21, monthly rent of
Rs.71,09,820/- is payable to the applicants. As of August
2020, the total outstanding is Rs.12,53,37,885/-. The
respondent is liable to pay the monthly sums under the
Award until the entire Modified Owners' Allocation is
handed over, monthly rent would have to be paid. Some
demand drafts were handed over in part payment of rent
but these were not encashed since the rent was not
tendered in full.
5. Pursuant to breaches of the development agreements, the
claimant/applicants had filed a petition under Section 9 of
Chsl-824-19 wadhwa the Arbitration and Conciliation Act which the Court
converted to one under Section 17 before the Arbitrator.
That application came to be allowed and the respondent
was restrained from parting with possession of any units
till handing over of the Owners' Allocation. The parties
thereafter entered into negotiations and consent terms
were arrived at thereby the restraint under Section 17 was
relaxed, partially vacated on the promise of timely
completion of Owners' Allocation and payment of certain
monetary consideration. Monetary consideration in a
substantial sum has been paid but the rent promised is
still outstanding.
6. On behalf of the applicants, Mr. Jagtiani submitted that
the applicant nos.1, 2 & 3 are owners of the land upon
which the project is being constructed and had entered
into a Development Agreement with the respondent. The
project contemplates construction of three towers A, B &
C. The applicant no.4 though not a party to the
development agreement, is a beneficiary under the
consent terms dated 3rd October, 2018 which led to the
Chsl-824-19 wadhwa passing of a consent award. The non-monetary
obligations of the respondent was to provide the
applicants all 5 flats on the 69 th floor of Tower A, one flat
on the 30th floor of Tower A, two duplex flats on 66 th and
67th floor of Tower B and flats no.4801, 4802, 4901 and
4902 in Tower B. These were required to be completed
and handed over in a time bound fashion. Mr. Jagtiani
submitted that the respondent had committed breach of
all the undertakings to hand over flats in question. He
relied upon a list of breaches. According to him the
respondents had committed breach of the Clauses 10(ii),
11(ii), 12, 13(ii) (iv) 14(i)(iv) and 21 of the consent
Award.
7. The respondent was required to get plans amended by
15th November, 2018 and register supplemental
agreements in relation to floor nos.66th and 67th which it
failed to do and thus defaulted in constructing /handing
over duplex flat on floor nos.66th and 67th along with
nine car parking spaces.
(ii) It breached clause 12 which required completion of
interior work and providing flat nos.B-4801, 4802, 4901,
Chsl-824-19 wadhwa 4902. These works were required to be completed by 31 st
January, 2019.
(iii) 5 flats which were permitted to be used by the
respondent had not been handed over back to the
applicant,
(iv) The lift installed was not upto floor 69.
(v) In respect of 5 flats on floor 69 th and the additional
flat on floor 30th of Tower A, agreements were to be
registered but agreements for only flat no.A-6901 and A-
3001 have been registered on 15 th July, 2019. The
registration in respect of other flats is pending because the
respondent now expects the applicant to pay stamp duty
and registration charges.
(vi) The respondent has defaulted on payment of rent and
in paying sum of Rs.20 crores against the adjustable
deposit.
8. In the Chamber Summons, the applicants have pressed for
relief in terms of prayer clause j(i) and j(ii) and prayer
clause k(ii). Mr. Jagtiani submitted that the respondent
was also bound to disclose (a) a list of unsold flats on the
Chsl-824-19 wadhwa part of the respondents allocation in Tower A, B & C; (b) a
list of assets held by the respondent over which the
respondent had power of disposal; (c) the stage of
approvals of duplex flats from SRA and MCGM supported
by copies of the plans and documents; (d) confirmation
that the respondent had not handed over possession of
flats on the 67th, 68th and 69th floor of Tower A excluding
flat nos.6701 and 6802 in Tower A of its purchasers.
9. Mr. Jagtiani submitted that under Order 21 Rule 32 a
decree for specific performance can be enforced by the
attachment of the property or with leave of the Court by
detaining Directors and Principal Officers of the
respondent in civil prison. According to him, it was
necessary to pass appropriate orders to enforce the decree
by directing detention as aforesaid. Under sub-rule (2) he
submitted that decree should be enforced by the
attachment of the property of the respondent in
complying with the award and would justify orders for
attachment and sale of property. He submitted that there
is willful default on the part of the respondent. Despite
giving undertakings each one has been violated. He,
Chsl-824-19 wadhwa however, admitted that a sum of Rs.230 crores has been
paid by the respondent as a pre-condition of the consent
terms but thereafter all other undertakings have been
breached willfully. He submitted that the respondent was
bound to obtain approval of plans by the SRA in respect of
duplex flats on the 66th and 67th floors of Tower A by 15 th
November, 2018 but had filed an application only after
December 2018.
10. It is contended that the respondent had benefited
immensely after being relieved of the injunction and
being permitted to handover possession of its allocation to
third parties and able to generate cash flows. He
therefore seeks attachment of unsold units of Tower C. He
referred to breach of clause 29 of the consent terms
relating to the insolvency proceedings and that an
attachment under Order 21 Rule 32(i) must extend to the
respondent's properties including unsold units. Despite
an order of this Court dated 27 th February 2020 directing
disclosure of unsold units he submitted that the disclosure
was selective and the respondent had not provided list of
unsold units but only stated that 6,70,000 sq. ft. had been
Chsl-824-19 wadhwa encumbered.
11. In relation to interim application no.3557 of 2020
in which the applicants seek an injunction restraining
transfer of development rights, Mr. Jagtiani submits that
in August 2020, the applicants came to learn that the
respondent had meetings with some investors thereby
leading the applicant to believe that the respondent was in
process of transferring development rights to a third party
without consent of the applicants. That such action is
breach of the development agreement. Mr. Jagtiani
submits that the applicants learnt of an order dated 7 th
August, 2020 passed in proceedings initiated against the
respondent by Shapoorji Pallonji Investment Advisors Pvt.
Ltd. It recorded that a board meeting of two lenders viz.
Piramal and Yes Bank was scheduled to be held on 30 th
August, 2020. In another proceedings in Commercial Suit
No.78 of 2016 also the Advocate contend that they were
awaiting lenders response to restructuring proposal that
the respondent cannot part with development rights
without the applicants prior approval and all the
Chsl-824-19 wadhwa aforesaid meetings indicated the intention of respondent
to part with development rights.
12. In Interim Application No.3559 of 2020 in which
the applicants seek recovery of rent pursuant to clause 21
of the consent terms. Mr. Jagtiani submitted that the
default in payment of rent is admitted and in the affidavit
of the respondent, it has undertaken to pay 4% rent as per
clause 21 of the consent terms. In a subsequent additional
affidavit dated 8th September, 2020 the respondent has
undertaken to pay the rent, but they are in default of
payment of Rs.12,53,37,885/- upto August 2020 and
further amounts of Rs.71,09,820/- p.m. till the Modified
Owners' Allocation is handed over. He submitted that the
applicants would give credit sum of Rs.50 lakhs to the
respondents since the applicants have encashed the
demand drafts amounting to Rs.50 lakhs sent to them on
28th August, 2019. As a matter of protest, some demand
drafts of Rs.24,81,285/- had not been deposited since rent
payable upto December 2019 was not being paid in full
and as of 31st October, 2020 Mr. Jagtiani contended that a
Chsl-824-19 wadhwa total sum of Rs.13,45,57525/- was overdue.
13. According to Mr. Jagtiani, vide clause 28 of the
consent terms, the respondent had agreed that all
obligations to the extent that they had not been modified
under the consent terms would continue to bind the
respondent and in such circumstances, the development
rights cannot be dealt with. The respondent was therefore
bound not to create third party rights. According to the
respondent however clause 19 and 28 of the consent
terms, the requirements under clause 26 of the
development agreement is no longer binding and
therefore the respondent does not require clearance from
the applicants for development of Tower C which
according to the respondent can be dealt with and
without reference to the applicants, the respondent's
contention being that certain bank guarantees had been
provided against which the applicants agreed to give up
securities for the top most three floors of Tower C.
According to Mr. Jagtiani the clause is not omnibus clause
allowing the respondent to transfer the development
Chsl-824-19 wadhwa rights of the project itself but only permits the respondent
to construct and deal with by way of sale, flats in Tower C.
He therefore submitted that transfer of all development
rights is not permissible without the prior approval of the
applicant.
14. As far as the Reserved Area B is concerned, Mr.
Jagtiani submitted that the respondent's contentions are
misleading that the monetary value of Reserved Area
consisting of six flats in Tower B can be equated only with
part of the Modified Owners' Allocation i.e. 5 flats on the
69th floor of tower A. He submitted that Reserved Area B is
insufficient. Secondly, the respondent's contention that it
has not been able to construct the apartments since
permissions are awaited is unacceptable because they
applied for approval only in December 2018 by which
time they should have obtained approvals as evident from
the additional affidavit of Kamal Gupta. The respondent
was not therefore diligently pursuing the permissions and
had not followed up with the authorities to obtain
approvals.
Chsl-824-19 wadhwa
15. As far as the interior work of flats for B-4801,
4802, 4901 and 4902 is concerned, the respondent has
contended that certain material had to be ordered from
abroad. To this, Mr. Jagtiani submitted that the
respondent was to complete interior work by 31 st January,
2019 yet none of the interiors were completed and the
reasons given were unacceptable. It is difficult to believe
that material imports were delayed by more than a year.
He also submitted that the other reason for non-payment
of rent is due to the pandemic which is once again not
believable.
16. On behalf of the respondent, Mr. Khandeparkar
contended that the applicants were the original owners of
a non-slum plot. Respondent as a developer is also a co-
owner in implementation of the project Omkar 1973 on
an adjoining plot. Joint Development was proposed of
several other plots. The SRA scheme were sought to be
combined by amalgamation and was intended to be
developed as a single plot. The applicants plot being land
locked could not be developed independently and hence
Chsl-824-19 wadhwa the applicants entered into the development agreement
dated 13th April, 2013. Disputes thereafter arose which
were resolved vide the consent terms. He submitted that
Rs.230 crores had already been paid over pursuant to
which the applicant consented with 27% share in the
applicants plot. This payment was made in October 2018
thus the respondent claims to be co-owner with the
applicant in relation to the applicants plot. He submitted
that the claim of Rs.20 crores under clause 10(ii) of the
consent terms has already been paid by adjustment as
already set out in its affidavit dated 25 th July, 2019 in the
Chamber Summons. This need not detain us since Mr.
Jagtiani has restricted his reliefs in the Chamber Summons
to prayer clause (j) (i) and (ii) and K(ii).
17. Mr. Khandeparkar submitted that in Tower A and
he has already disclosed that 64 flats are unsold and are
encumbered and in Tower C, 6,70,000 sq. ft. of unsold
area has been mortgaged. He admitted to liquidity
problems but reiterated that in the process of
restructuring the respondent will honour its obligations to
Chsl-824-19 wadhwa the applicant in respect of the 5 flats 6901 to 6905
applicants had taken possession and permitted the
respondent to use the units to complete the construction
of the higher floors and to complete the amenities cost of
which is about Rs.4 crores. He submitted that occupation
certificates for the said flats have been already obtained.
In respect of duplex flats on floor 66 th and 67th in Tower
approval of the modified floor plan layout is to be
obtained from SRA. Regularization has been sought but
the issues are still not resolved on account of lack of
clarity in implementing DCPR-2034. The respondent is
ready to execute agreements upon approvals being
granted.
18. As far as flat nos.B-4801, 4802, 4901 and 4902 are
concerned, Occupation Certificates have been already
handed over along with possession to the applicants and
the relevant agreements have been executed and
registered. He submitted that in respect of flat nos. 6901
to 6905 and 3001 the respondent is ready and willing to
share draft agreements and later enter into supplemental
agreements, copies of which have been shared.
Chsl-824-19 wadhwa
19. According to Mr. Khandeparkar the respondent has
complied with 93% of all obligations under the consent
terms and is making efforts to willfully comply with the
rest. Rent of Rs.13 crores is admittedly outstanding and
the cost of interior work to be carried out in flats 6901 to
6905 is about 4 crores whereas the applicant is secured to
the extent of Rs.129.29 crores. The liquidity issues
prevent them from undertaking interior work and the
respondent has suggested that the Reserved Area can be
sold and funds from those sales could be used for funding
the interior work in terms of the consent terms. The
monetary claim being entirely secured with a minimum
value of Rs.129.29 crores of 6 flats constituting the
Reserved Area and therefore no relief should be granted in
the Chamber Summons.
20. As far as the interim application no.3557 of 2020 is
concerned, Mr. Khandeparkar submitted that two floors
remained to be constructed in Tower A. Tower B has been
partly completed upto 69th floor. Occupation Certificates
Chsl-824-19 wadhwa are awaited only for floors 61 to 69. As far as tower C is
concerned, it is partly constructed upto the slab of 48 th
floor. According to him, the applicants have no right over
Tower C and no consent is required. Applicant no.3 is
said to have already sold 27% share to the respondent and
cannot seek such injunctions. The consent terms he
submitted provides in clause 28 that in any event of any
conflict between the development agreement and the
consent terms, the consent terms would prevail. This
Court as an Executing Court cannot go behind the decree
and grant relief contrary to the decree. The attempt of the
applicants is to seek injunction to pressurize the
respondent. Mr. Khandeparkar submitted that there has
been in-principle agreement for restructuring the debts of
the respondent and the respondent is awaiting the final
term sheet from the lenders.
21. In Interim Application no.3559 of 2020 the prayer
merely seeks a direction to pay the amount. No such relief
can be granted in execution proceedings since the
respondent has already admitted liability. The award is
being executed and no further orders are required to be
Chsl-824-19 wadhwa passed. According to Mr. Khandeparkar the applicants
are completely secured by clause 23(a) read with
Annexure VI of the consent terms and six flats having
market value of Rs.129 crores have been reserved for the
benefit of the applicants. A proposal made to the
respondent to sell these flats to recover monies has been
declined. It is further contended that the Execution
Application having been filed for recovery of only an
amount of Rs.77,56,984/- which Rs.74,81,285/- was
already been paid over. He therefore submitted that the
contents of the applicants cannot be accepted.
22. In conclusion, Mr. Khandeparkar submits that these
obligations under the consent terms clause 11(ii), 13(i),
13(ii) and 13(iv) are being complied, SRA approvals are
awaited on amended plans, interior works are yet to be
completed for reasons already set out and the
supplemental agreement remained to be signed. As far as
clause 12 of the consent terms is concerned, all
occupation certificates for flat B-4801, 4802, 4901 and
4902 along with 18 car parking spaces, possession have
been handed over but interior works remain to be
Chsl-824-19 wadhwa completed. Amenities and finishing work in flat nos.A-
6901 to 6905 were pending. Supplemental agreements
have to be registered in respect of one flat 6901. Interior
work of all 5 flats is yet to be completed and agreements
for four flats have been delivered for signature and
registration is to be completed. With reference to clause
14(ii) of the consent terms, flat no.A-3001 has already
been handed over within time and the supplemental
agreement is to be registered. As far as requirement of
obtaining NOC from mortgagees is concerned, for flats A-
3001, A-6901, B-4801, B-4802, B-4903 and 4902
NOCs have been furnished, NOCs for flats A-6902, 6903
and 6904 are in the process of being obtained. Clause 18
of the consent terms has been complied with. Clause 21
remains to be complied. As far as clause 23(a) is
concerned, flat nos.B-3702, 1801, 1703, 1803, 2203 and
2303 are reserved for the applicants and will be
maintained so till possession of all flats are completed.
Since the flats are already reserved, the obligations under
clause 23 have been complied. Mr. Khandeparkar
submitted that any transaction dealing with immovable
Chsl-824-19 wadhwa property would have the effect of extinguish title
possession or the right to possess, such property to deal
with which would have to dealings with to business and
the expression "deal with" would mean the right to enter
into any kind of transaction. He therefore submitted that
the respondent was entitled to sell, dispose of flats without
reference to the applicants.
23. Mr. Jagtiani submitted in rejoinder that the
opposition during submissions to payment of rent despite
a clear undertaking to pay the rent is obviously an
afterthought. He submitted that the Reserved Area B is not
sufficient to meet the liability under the consent terms.
The respondent had calculated the amount of rent payable
and was bound to honor the same. The obligation to pay
rent was independent and unconditional and was binding
till handover of the modified Owners' Allocation under
the consent terms. Reserved Area B was only to be held as
security till possession of the entire Owners Allocation is
handed over. He made reference to clause 22 of the
development agreement in support of his contentions and
Chsl-824-19 wadhwa submitted that there is no question of sale of that area. The
Reserved Area what to be retained till possession of the
flats to be provided to the applicants are handed over.
Therefore the Reserved Area cannot be sold. He submitted
that in relation to duplex 466 and 467 of tower B the
respondent had contended that Occupation Certificate
had been received upto 60th floors. Part Occupation
Certificate was obtained only upto 60 floors. According to
Mr. Jagtiani the obligation to procure approvals of plans
for construction of duplex on floor 66 and 67 had not
been complied with. As regards the contention that the
Reserved Area B covers the amount sought to be recovered
under execution, it is contended that a total of 50,396 sq.
ft. across 12 units was to be handed over of which 47760
sq.ft. still remains to be delivered. Although possession
letters for four flats two each on 4801, 4802, 4901 and
4902 possession had not been handed over because
interior work was not completed. There is admitted
default in delivering possession an area of 47.750 sq.ft.
owners reserved area is admeasuring 23.389 sq. fts all of
which are on lower floors. Mr. Jagtiani denied that the
Chsl-824-19 wadhwa value of the Reserved Area is 129.29 crores and denied
that the value of the applicants entitlement is above 275
crores and therefore the Reserved Area is not adequate
security. Moreover, the Reserved Area has to be
maintained since no Occupation Certificate has been
issued for the duplex flat and the other units are not ready
for possession since interior work remains to be carried
out. In view of continuing of a breach of the decree which
is for first specific performance, the reliefs for injunction
are liable to be allowed.
24. I have heard learned counsel at length. In reply to
the Chamber Summons, an affidavit dated 25 th July, 2019
of one Paras Pathak and an additional affidavits of
Bhanupratap Singh and one Kamal K. Gupta dated 19 th
September, 2020 on behalf of the respondent are on
record.
25. In the affidavit of Paras Pathak dated 25 th July 2020,
the deponent has denied the applicants contentions and
reiterates that the consent terms have been acted upon.
Non-monetary elements setting out the stages of
Chsl-824-19 wadhwa completion of work with reference to the approvals by
MCGM and SRA have been complied with and that
Occupation Certificates have been obtained in respect of
flats mentioned therein. Completion of pending interior
work and other obligations is underway. In the
meantime, respondent is willing to pay additional rent at
4% p.a. till the date of handing over the flats. The
respondent has not denied liability to pay rent at any time
and are willing to pay rent. A flat-wise breakup was also
provided.
26. It is contended that the application is a pressure
tactic and that the consent terms upon bank guarantees
being provided, the claimants were to relinquish their
rights in the top three floors of Tower C and the
respondent was giving their absolute discretion. The bank
guarantees are reportedly handed over and therefore the
applicants cannot claim any relief as against Tower C.
The deponent admits that respondent has been facing a
liquidity crunch due to poor performance of the realty
sector, however, they have held various discussions with
their lenders in order to restructure their outstanding
Chsl-824-19 wadhwa loans and once the restructuring of debts is finalized, the
respondent will be able to honour its commitment to the
claimant. As of 19th September, 2020, the respondent has
not relinquished control over the project to any third
party and the respondent is awaiting the final term sheets
and offer letter from the lenders. As regards Towers A &
B are concerned, Occupation Certificates upto the 69 th
and 60th floor were obtained and therefore the question of
relinquishing the control of the said project to a third
party does not arise.
27. According to the respondent, the applicants are
adequately protected and the balance of convenience
favours them. According to the deponent, consent terms
provide for retention of an area described as 'Reserved
Area B' as security and temporary injunctions cannot be
sought in execution proceedings. The premises mentioned
in Reserved Area B adequately covers the amount sought
to be recovered and if any restraint order is passed, it will
cause great prejudice to the respondent. It is further
stated that unsold inventory in Tower A, B & C has been
mortgaged to various lenders and therefore third party
Chsl-824-19 wadhwa rights have already been created. It is also stated that the
disclosures sought are confidential and are not required to
be provided.
28. The respondent admits that by reason of default,
rent is payable under the consent Award and reaffirms
that the respondent is making all efforts to restructure
their loans and make payments. The respondent has
offered to sell flats acquired in the reserved area and
recover the amounts due to the applicants but the
applicants have refused to agree. In the additional
affidavit all particulars have been disclosed by the
respondent as directed by the Court and therefore, the
applicants are sufficiently protected. The balance of
convenience is not in favour of the applicants. Substantial
compliance with the consent terms and the Reserved Area
B under the consent terms offers sufficient security.
29. In a rejoinder affidavit filed by applicant no.2 dated
2nd August, 2019 it is contended that the respondent has
violated consent terms since they have admitted that
compliance with non-monetary obligations is delayed.
Chsl-824-19 wadhwa The contentions of the respondent are denied. The
obligation under Clause 21 is reiterated in paragraph 2 of
the application and it is reiterated that the applicants are
entitled to default rent as per clause 21 of the consent
terms.
30. An additional affidavit has been filed on behalf of
the applicants vide dated 29 th January, 2020 disclosing
that several proceedings have been filed against the
respondent in NCLT Mumbai. These have not been
disclosed in prior proceedings in Arbitration despite
clause 21 of the award providing that the respondent and
its Director would inform the applicants in writing about
the pendency of liquidation or winding up proceedings
under the Insolvency and Bankruptcy Code. In the
additional affidavit of one Bhanupratap Singh dated 26 th
February, 2020 the deponent has disclosed proceedings
before the NCLT. It is in this background that the
aforesaid applications have to be considered.
31. Out of three applications that have been urged, I
am of the view that there is no merit in interim
Chsl-824-19 wadhwa application no.3559 of 2020. Clause 21 of the consent
terms reads as follows;
"Clause 21 - In the event the construction of the Owners' Allocation (as set out in Annexure-II hereto) is not completed or Occupation Certificate(s) in respect thereof from SRA/MCGM is not received within the Completion Period mentioned herein in that event the respondent shall pay to the respective claimants and the respective claimants shall be entitled to receive from the respondent, a further sum equivalent to ongoing market rental of the flats in question, from the scheduled date of completion thereof mentioned herein till the actual date of completion and handover to respective claimant with Occupation Certificate, water, electricity along with amenities as stipulated herein whereby the claimants in turn are able to fulfill their obligations towards purchasers of premises from them, subject to and without prejudice to the other rights and remedies which may be available to the claimants. The ongoing market rental shall be computed at 4% p.a. of Ready Reckoner value of flats as per ASR and which shall be payable every month."
32. The respondent has not and indeed cannot dispute
their obligation to make payments since it is not the case
of the respondents that the construction of the Owners'
Allocation has been completed or that Occupation
Chsl-824-19 wadhwa Certificate has been obtained from SRA/MCGM within the
completion period. The respondent is in my view, bound
to comply with the Award and make payments of the
amounts computed in terms of clause 21. The obligations
of the respondent under clause 21 remained to be
complied with as evident from the affidavit of Paras
Pathak dated 25th July, 2019 filed in reply to the Chamber
Summons. The question is when compliance will be
complete. In the event of non-compliance, the overdue
amounts claimed under clause 21 may attract interest. In
that view of the matter, no further relief is called for and
in view of the order that I propose to pass in the Chamber
Summons and the obligation to pay rent being admitted,
there is no warrant to grant any reliefs in Interim
Application no.3559 of 2020.
33. As far as the Interim Application no.3557 of 2020
is concerned, the restraint that is sought would be
premature inasmuch as to grant an injunction restraining
the respondent from entering into any agreement to
alienate, transfer or to create third party rights and
Chsl-824-19 wadhwa development rights, being the main relief, I find that the
applicants are also seeking certain disclosures from the
respondent in relation to the negotiations the respondent
is said to be engaged in with some investors.
34. Clause 26 of the development agreement does
contain a bar against assignment and transfer. It is not in
dispute that the Chamber Summons has come up for
hearing on several occasions and orders have been passed
therein as to the deposit of rentals. The applicants have
since brought to the attention of the Court that in separate
proceedings pending in this Court, the respondent has
admitted to being in negotiations on a restructuring
proposal. It appears that thereafter applicants' Advocates
have sought disclosures in respect to the unsold units in
Towers A, B and C. Under clause 28 of the consent award,
parties agreed that except for changes in amendment in
the consent terms, all other terms and conditions of the
development agreement would prevail, except in the event
of some repugnancy between the development agreement
and the consent terms, the consent terms have to prevail.
Chsl-824-19 wadhwa The intention of the parties is therefore clear viz. the
development agreement continues to govern the
relationship between the parties except as modified by the
consent terms and to the extent of such modification if
there is any repugnancy, the provisions of the consent
award would prevail. The respondent has not disputed
this aspect except that in regard to Tower C the
respondent is said to have full liberty to deal with Tower
by virtue of clause 19 of the consent terms. Clause 19
does not render provisions of clause 26 of the
development agreement nugatory.
35. I am of the view that there is no warrant for
directing the respondent to make the disclosure sought in
Interim Application no.3557 of 2020. However, the
respondent is obliged to comply with its obligation under
the consent award. However, that having been said, I am
of the view that it is not for the executing court to
consider grant of reliefs in terms of injunction sought
since that is an aspect which pertains to the parties
obligation under the development agreement which even
Chsl-824-19 wadhwa according to the applicants are not modified by the
consent award and remained unaffected and is by any
repugnancy contemplated under clause 28 of the consent
award. The relief sought may be available to the
applicants in appropriate proceedings but not in
execution of the consent award. Interim Application
no.3557 of 2020 must fail. That leaves us with the reliefs
sought in the Chamber Summons.
36. The amounts payable towards rent remain to be
paid and the applicants are admittedly entitled to receive
the same. The respondent's plea of being faced with the
liquidity crunch does not absolve the respondent of the
obligation to comply with the award and in execution
proceedings the decree holder is entitled to apply for
attachment. Under Rule 42 of Order XXI where the
decree is for rent, property of the judgment debtor may be
attached even before the amount due from judgment
debtor is ascertained. In the instant case, the respondent
claims to have furnished certain details along with
additional affidavit of September 2020 furnishing details
of 64 flats. The respondent admittedly has liquidity issues
Chsl-824-19 wadhwa but that alone will not prevent from steps being taken in
execution. In my view, considering the admitted liability
which is only escalating, the plaintiffs will be entitled to
further disclosures. The vague disclosure to the effect that
6.7 lakhs sq.fts remained unsold and have also been
mortgaged is of no consequence. In my view, the
respondent is liable to be ordered to disclose in all
particulars the flats/units unsold along with particulars of
the mortgage. The rights of the mortgagee is only to the
extent of the mortgaged debt and the security created any
amounts and overflow would be liable for attachment and
in the face of the admitted liquidity crunch, a disclosure is
thus warranted.
37. In view of the contention that the unsold premises
are said to be mortgaged and the possibility after
foreclosure of no overflow being available, it will be
necessary to secure the applicants entitlement. The
contention that 93% obligations under the consent terms
have been complied is of no avail. The security of
Reserved Area said to be valued at a sum of Rs.129.29
crores by the respondent is not acceptable to the applicant
Chsl-824-19 wadhwa and indeed as on date, there is no value agreed between
the parties so as to ascertain whether the Reserved Area is
sufficient security to meet all liabilities of the respondent
including the non-monetary obligation. In that view of
the matter, further disclosure would be justified and till
such disclosure is completed, in my view, it will be
appropriate that the respondent be restrained from
alienating, dealing with, selling, transfer of further
encumbering or parting with possession of any of the
unsold units forming part of the respondents allocation in
Tower C as sought by the applicants.
38. As far as the other aspects pertaining to the
approval of plans in respect of the duplex flats on the 66 th
and 67th floor, it is not in dispute that the respondent is
behind schedule. That amended plans have been
submitted for approval and approvals are awaited,
interior work is also not completed. The respondent has
sought further time. In my view, reasonable time will be
required since grant of approvals will not entirely be in
the hands of the respondent. No doubt, there are
Chsl-824-19 wadhwa allegations that there have been delays in seeking
approvals but that alone would not entitled to justify any
further order in execution at this stage. Likewise,
obligations under clause 12 of the consent award 14(i),
14(iii), 14(iv) of the consent award are said to be awaiting
compliance. These are the non-monetary aspects in
respect of which no further reliefs are sought at this stage.
39. The respondent has contended that possession of flat
A-3001 has already been handed over and the agreement
in respect thereof has been registered and hence no
occasion to seek any relief in this respect. The respondent
has also stated that No Objection Certificates (NOCs) in
respect of flat nos.A-6902, A-6903 and 6904 are awaited.
This is also an aspect that requires some time. Although
the breach is alleged of clause 18 of the consent terms, it
is the contention of the respondent that possession of the 5
flats on the 69th floor and one flat on 30th floor has already
been handed over to applicant no.4 and hence that
obligation has been complied. The respondent has also
confirmed that the Reserved Area B will be maintained till
possession of all flats complete in all respect has handed
Chsl-824-19 wadhwa over. The Reserved Area is intended to be security for
completion of all obligations and not merely for the rent
in relation to the payment of rent. The respondent has
already undertaken to pay rent as aforesaid and in
affidavit in reply to the Chamber Summons admitted that
they are willing to pay the additional rent at 4% p.a. upto
the date of handing over the possession.
40. The respondent has also sought from the claimant
flat-wise breakup / bifurcation of the amount claimed
towards rent. In the additional affidavit of 8 th September,
2020 the respondent has admitted that it has disclosed
details of outstanding rent payable and has reiterated its
resolve to make payment. The contention that the
Reserved Area provides sufficient security is not an
answer. The respondents suggestion that the Reserved
Area be sold and the monies be applied towards carrying
out internal works is also not acceptable. Therefore to
suggest that the Reserved Area is security to meet all the
pending obligations is not correct, for the parties have
agreed to and/or are bound by Clauses 22 and 23 of the
consent award which sets out the reason for providing the
Chsl-824-19 wadhwa Reserved Area viz. to ensure the respondents handing over
to the claimants the flats complete in all respects with
amenities specified in the annexures free from all
encumbrances not limited to allotment, sale of mortgage.
The contention that the Reserved Area secures the amount
of overdue rent and cost of interior works cannot be
accepted. There is substance in the applicants contentions
that, prima facie, a total of 47,760 sq. fts is yet to be
handed over complete in all respects since some of the
initial work is yet to be completed apparently for want of
funds. The Reserved Area is said to be only 22,389 sq. fts
and hence will clearly not cover the flats remaining to be
handed over completed in all respects as contemplated in
the Award. In my view, the applicants have made out a
case for further reliefs of disclosure prayed for in
Chamber Summons and for a temporary restraint. Upon
disclosures being made the applicants are at liberty to
proceed further to seek attachment in execution.
41. In view of the above I pass the following order;
(i) Chamber Summons is made absolute in terms of prayer
Chsl-824-19 wadhwa clauses j(i) and J(ii). Chamber Summons is also made
absolute in terms of prayer clause k(ii) restricted to
unsold units/flats in Tower C.
(ii) Interim Application nos.3557 of 2020 and 3559 of
2020 are dismissed.
(iii) No orders as to costs.
(A.K. MENON, J.)
Digitally signed by Sandhya Sandhya Wadhwa Wadhwa Date:
2021.01.12 10:21:52 +0530
Chsl-824-19 wadhwa
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!