Citation : 2021 Latest Caselaw 2187 Bom
Judgement Date : 3 February, 2021
12 WPST 29777-19.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION (ST.) NO. 29777/2019
M/s. Madhoor Buildwell Pvt. Ltd. .. Petitioner
vs.
The Tahasildar, Shahapur & Ors. .. Respondents
.....
Mr. R. D. Soni i/b Ram & Co. for the petitioner.
Mr. C. D. Mali, AGP for the State.
.....
CORAM: K.K.TATED, &
RIYAZ I. CHAGLA, JJ.
DATED : FEBRUARY 03, 2021 P.C.
. Heard.
2. By this Petition, under Article 226 of the Constitution of India, the Petitioner is challenging the demand notice dated 16/09/2016 and order dated 04/03/2017 passed by Respondent No. 1 calling upon the Petitioners to deposit a sum of Rs. 2,27,13, 659/- (Rupees Two Crore Twenty Seven Lac Thirteen Thousand Six Hundred and Fifty Nine only) by way of royalty and penalty under Section 48(7) of the Maharashtra Land Revenue Code, 1966.
3. It is the case of the Petitioners that Respondent No.2 floated online Tender No. 1862 for construction of Ellavya Model Residential School Campus at Village Shendegaon, Talula Shahapur, Dist-Thane. The Petitioners were successful bidder in that tender. Respondent No.2 awarded
Laxmi 1/4
12 WPST 29777-19.odt
the said contract in favour of the Petitioners. Hence, the Petitioners after obtaining the permission to start construction activities.
4. The learned counsel for the Petitioners submit that while carrying out construction activity the excavated earth soil has been used by them in the said land itself. Inspite of that the Respondent-Tahasildar issued notice dated 16/09/2016 calling upon the Petitioners why they should not impose the royalty plus penalty of Rs. 2,27,13, 659/- (Rupees Two Crore Twenty Seven Lac Thirteen Thousand Six Hundred and Fifty Nine only) on them.
5. The learned counsel for the Petitioners submit that, in the present proceedings, the concerned offcer has called the report from the Executive Engineer in respect of the Petitioner's excavation of the earth. He submits that the Executive Engineer submitted the report dated 21/05/2019 in which it is specifcally stated in paragraph 6 that there is no misuse of the said excavation minerals from the said land and the same is used by the Petitioners for the same project in the same land itself. He submits that, these facts are not considered by the concerned Tahasildar while passing the impugned order dated 04/03/2017.
6. The learned counsel for the Petitioners submit that, similar issue was there before the Apex Court in the matter of Promoters and Builders Association of Pune Vs. State of Maharashtra and Others reported in (2015) 12(SCC) 736. It is held in that matter, if the mineral are used for the same
Laxmi 2/4
12 WPST 29777-19.odt
project in the same land then there is no question of payment of any royalty and/or penalty under Section 48(7) of the Maharashtra Land Revenue Code, 1966. He relies on paragraph 15 of the said Judgment which reads thus:
"15 As use can only follow extraction or excavation it is the purpose of the excavation that has to be seen. The liability under Section 48(7) for excavation of ordinary earth would, therefore, truly depend on a determination of the use/purpose for which the excavated earth had been put to. An excavation undertalen to lay the foundation of a building would not, ordinarily, carry the intention to use the excavated earth for the purpose of flling up or levelling. A blanlet determination of liability merely because ordinary earth was dug up, therefore, would not be justifedd what would be required is a more precise determination of the end use of the excavated earthd a fnding on the correctness of the stand of the builders that the extracted earth was not used commercially but was redeployed in the building operations. If the determination was to return a fnding in favour of the claim made by the builders, obviously, the Notifcation dated 3-2-2000 would have no applicationd the excavated earth would not a specie of minor mineral under Section 3(e) of the 1957 Act read with the Notifcation dated 3-2-2000."
On the basis of those submissions, the learned counsel for the petitioners submits that, the impugned order passed by the Authority is required to be set aside. He submits that, pending the hearing and fnal disposal of the present petition, the Respondent may be restrained from taling any
Laxmi 3/4
12 WPST 29777-19.odt
coercive action against the Petitioners for recovery of the said amount i.e. Rs. 2,27,13, 659/- (Rupees Two Crore Twenty Seven Lac Thirteen Thousand Six Hundred and Fifty Nine only).
7. The learned AGP for the State submits that, he requires some time to fle an affdavit in reply.
8. Considering the submissions made by the learned counsel for the Petitioners and the Judgment of the Apex Court in the matter of Promoters and Builders Association of Pune Vs. State of Maharashtra and Others (supra), we are satisfed that the Petitioners have made out a case for ad- interim relief. Hence, the following order:
a. The Respondent -State to fle an affdavit in reply on or before 26/02/2021, with copy to other side.
b. Rejoinder, if any, to be fled on or before 12/03/2021, with copy to other side.
c. The Respondents are restrained from taling any coercive action against the Petitioners for recovery of an amount of Rs.2,27,13, 659/- (Rupees Two Crore Twenty Seven Lac Thirteen Thousand Six Hundred and Fifty Nine only) as per order dated 04/03/2017 passed by the Tahasildar.
d. Matter to appear on board on 31/03/021.
( RIYAZ I. CHAGLA, J.) (K.K.TATED, J.) Laxmi 4/4
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!