Citation : 2021 Latest Caselaw 11528 Bom
Judgement Date : 23 August, 2021
caf1605.21.odt
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR.
CIVIL APPLICATION (F) NO. 1605 OF 2021
IN
FIRST APPEAL (FA) ST. NO. 2666 OF 2021.
The Executive Engineer,
Lower Veena Project, Division No.2,
Nagpur. ...APPLICANT.
Versus
Santosh S/o Bala Derkar,
Since deceased, throuh his LRs
1.Smt. Kasubai Wd/o Santoshrao Derkar,
Aged about : 69 years, Occ :Household.
2.Smt. Jijabai w/o Kawdooji Gaurkar,
Aged about : 49 years, Occ :Household.
3.Shri Punjabrao S/o Santoshrao Derkar,
Aged about : 44 years, Occ :Agriculturist.
4.Shri Ajabrao S/o Santoshrao Derkar,
Aged about : 42 years, Occ :Agriculturist.
5. Shri Rajendra S/o Santoshrao Derkar,
Aged about : 34 years, Occ :Agriculturist.
6.Shri Sudhakar S/o Santoshrao Derkar,
Aged about : 36 years, Occ :Agriculturist.
Respondent nos. 1 to 6 R/o Kanhalgaon (Satgaon)
Tahsil and Dist. Nagpur.
7. The State of Maharashtra,
Through : Department Of Irrigation,
Mantralaya, Mumbai.
Through its Secretary.
::: Uploaded on - 27/08/2021 ::: Downloaded on - 08/10/2021 19:56:00 :::
caf1605.21.odt
2
8. The Special Land Acquisition Officer,
Pench Project, Office of the Collector,
Nagpur, Civil Line, Dit. Nagpur. ...RESPONDENTS.
----------------------------------------------------------------------------------------------
Shri Tariq Mohammad Zaheer, Advocate for the applicants.
------------------------------------------------------------------------------------------------------------
CORAM : PUSHPA V. GANEDIWALA, J.
DATED : 23/08/2021.
ORDER:
Heard.
2. The facts relevant may be stated as under:-
i. The State of Maharashtra issued a notification under Section 4 of the Land Acquisition Act, 1894 (hereinafter referred to as "the Act") on 21/02/1994 for acquiring land of the respondents situated at Village Kanhalgaon, Tahsil and Dist Nagpur bearing Survey No. 49/3 (New S.No.76), ad measuring 0.23 H.R. and 0.75 H.R. land total 1.28 H.R. for construction of Nimn Veena Project.
ii. The Special Land Acquisition Officer declared the award under Section 11 of the Act on 13/12/1996.
iii. The Special Land Acquisition Officer awarded compensation of @ of Rs.35,420/- P.H. for 0.23 H.R., @ Rs. 53,235/- P.H. for 0.30 H.R. and @ Rs. 70,980/- for 0.75 H.R. to the claimants for
caf1605.21.odt
acquisition of their lands.
iv. The claimants being dissatisfied with the compensation awarded to them, preferred a reference under Section 18 of the Act. That the said reference came to be decided by the learned Ad-hoc District Judge-2, Nagpur on 22/07/2016, thereby awarded Rs.2,00,000/- per hectare towards enhanced compensation. This Judgment and Award is impugned in this appeal.
3. The delay of 1568 days is sought to be condoned. The reasons for delay as stated in the application are that the impugned judgment came to be passed on 22/07/2016 and the appellant came to the knowledge of the judgment on 07.09.2020 from the Land Acquisition Officer when the appellant received application dated 24.09.2020 from the claimants, claiming enhanced compensation on the basis of judgment dated 22.07.2016. It is further stated that thereafter the department has sought legal opinion in the matter on 29.09.2020. It was opined and advised to file appeal before this Court. Thereafter the matter was handed over to the counsel, who further demanded Court fees and certified copy of the judgment and reasons for the delay, which are required for filing appeal. The appellant applied for the certified copy. The certified copy of the judgment received on 16.10.2020. Thereafter the appellant supplied certified copy of the judgment to the panel counsel in the month of January 2021. It is further submitted that thereafter the appeal came to be filed on 4.2.2021.
caf1605.21.odt
4. The learned counsel for the applicant urged that the delay was caused mainly on account of procedural requirements for preferring the appeal. The delay is unintentional and was caused due to unavoidable circumstances and thus, he prayed for condoning the delay.
5. I have perused the record and considered the submission of the learned counsel for the applicant. At the outset, it took almost 4 years to communicate the judgment by the Land Acquisition Officer to the Department. The V.I.D.C., being a statutory Corporation have its own full-fledged legal department dealing with thousands of Land Acquisition Cases. The land of poor farmers has been compulsorily acquired on the pretext of public purpose for meagre amount of compensation to the farmers. The poor farmers had to approach the Court and got the same enhanced in the impugned judgment and award. As per law, once the period of limitation expires, a valuable right accrues in favour of the decree holder. In the instant case, after passing of the judgment and award, the right has already been accrued in favour of the respondents, whose land has been compulsorily acquired. In a welfare State like India having robust digital and information technology sector, it took almost 4 years to communicate the passing of the judgment to the Corporation by the LAO which indicate the casual, callous and lackadaisical approach of the officers concerned at every level, which cannot be taken lightly, at the cost of the right accrued to the land loser.
caf1605.21.odt
6. A Division Bench of this Court in Civil Application (F) No.3497 of 2019 in First Appeal (St).No.29903 of 2018 ( Vidarbha Irrigation Development Corporation Vs. Ashok Balkrushna Joshi and others), of which I was one of the members, refused to condone delay 1009 days for want of sufficient explanation for the delay by the VIDC.
7. In The State of Maharashtra (through the Special Land Acquisition Officer Irrigation No.1, Nashik) Vs. Kashinath Shivram Tidke, Civil Application Nos. 2109 and 2110 of 1999 In First Appeal (ST.) No. 6868 of 1998 In L. A. R. No. 39 of 1988 and other connected matters, in the similar facts and circumstances as in the present case, the learned Single Judge of this Court, after referring various judgments of the Hon'ble Supreme Court and this Court refused to condone the delay of 860 days in preferring an appeal by the State against the Land Acquisition Award of the reference Court for want of explanation for causing inordinate delay of two years for sending the certified copy of the award to the office of the Government Pleader.
8. The Hon'ble Apex Court in the case of K. Subbarayudu & Ors. Vs. Special Deputy Collector (Land Acquisition), reported in (2017) 12 SCC 840, in order to do substantial justice, condoned the delay of 3671 days wherein the applicant/appellant was the farmer and it was found that there was sufficient cause for delay, and to bring this farmer at par with the similarly situated farmers who had already received enhanced compensation in the same notification.
9. The Hon'ble Apex Court in the case of Postmaster General & Ors. Vs. Living Media India Limited & Anr., reported in
caf1605.21.odt
(2012) 3 SCC 563 while declining to condone delay of 427 days in preferring Special Leave Petition has observed thus:
"........ In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/year due to considerable degree of procedural red-tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government deparments. The law shelters everyone under the same light and should not be swirled for the benefit of a few...."
10. The Hon'ble Apex Court in the case of the Registrar of Companies Vs. Rajshree Sugar and Chemicals Limited & Ors., reported in (2000) 6 SCC 133 held that though some latitude has to be shown to the Government in deciding the question of delay, that does not give license to the officers of the Government to shirk their responsibility to act with reasonable expedition.
11. The Division Bench of this Court in the case of State of
caf1605.21.odt
Maharashtra & Ors. Vs. Vithu Kalya Govari & Ors., 2008 (6) Mh.L.J. 239, while refusing to condone inordinate delay of more than two years in preferring the appeal against the judgment and award of the reference Court, in concluding paragraph 12 has observed as under:
"12. Before these files are consigned to record room, the Courts cannot help but notice that most of the appeals filed on behalf of the State are barred by time and the delay normally is inordinate. They suffer from defect of inordinate delay. Normally, it is expected of the State, in the modern times and with modern amenities and infrastructure, to govern its affairs to the much expected standards. It hardly stands to reason that most of the appeals filed by the State, particularly in land acquisition matters, should be barred by time. They are filed after much delay and normally after considerable delay which remains unexplained and is ex facie unjustified. Filing of appeal within limitation is an exception but filing appeals barred by time is the rule. Filing appeal in a mechanical manner beyond the period of limitation has become a rule. This needs to be checked by the concerned authorities at the earliest. Unreasonable delay on the part of the concerned authority in completion of execution proceedings, disbursement of compensation, determination of compensation and then in filing legal proceedings include the appeals invites twin
caf1605.21.odt
disadvantages that are opposed to public policy and even good governance. Firstly, even in good cases because of inordinate and unexplained delay, the Court may decline to entertain the appeals. Secondly, the liability of statutory interest increases every passing day which burdens the public exchequer. Both these adverse rigors could be avoided by timely and co-ordinate actions. The authorities are required to have a more practical and pragmatic approach to provide solution to this problem. The inordinate delays occurring from inaction or non-co-operation of the departments, as is demonstrated by the facts of the present cases, needs to be corrected and it will be desirable to fix the responsibility of the erring officer/official. The concept of public accountability for default of performance of statutory and public duties relatable to the powers vested in the authorities under the Act or other administrative authorities, is squarely applicable....."
12. The Hon'ble Apex Court in the case of Pundlik Jalam Patil (D) by Lrs. Vs. Exe. Eng. Jalgaon Medium Project & Anr., reported in 2008 (6) ALL MR 954 has observed thus:
"23. ...... Pursuing stale claims and multiplicity of proceedings in no manner sub-serves public interest. Prompt and timely payment of compensation to the land losers facilitating
caf1605.21.odt
their rehabilitation/resettlement is equally an integral part of public policy. Public interest demands that the State or the beneficiary of acquisition, as the case may be, should not be allowed to indulge in any act to unsettle the settled legal rights accrued in law by resorting to avoidable litigation unless the claimants are guilty of deriving benefit which otherwise not entitled in law in any fraudulent manner. One should not forget the basic fact that what is acquired is not the land but the livelihood of the land losers. These public interest parameters ought to be kept in mind by the courts while exercising the discretion dealing with the application filed under Section 5 of the Limitation Act. Dragging the land losers to courts of law years after the termination of legal proceedings would not serve any public interest. Settled rights cannot be lightly interfered with by condoning inordinate delay without there being any proper explanation of such delay on the ground of involvement of public revenue. It serves no public interest.
24. It is true when the State and its instrumentalities are the applicants seeking condonation of delay they may be entitled to certain amount of latitude but the law of limitation is same for citizen and for Governmental authorities. Limitation Act does not provide for a different period to the
caf1605.21.odt
government in filing appeals or applications as such..........."
13. It is well settled that "sufficient cause" is required to be shown for condoning the delay. In the instant case, I am not satisfied with the explanation given, i.e. after four years the LAO communicated about the passing of the judgment, that is too in the era of digitization and computer technology. Moreover, this explanation shows that the legal Department of VIDC is negligent in keeping the track of the matters.
14. I am conscious about the settled position of law that justice oriented and liberal approach of the Court is required in deciding the delay application. I am of the view that in the instant case, the substantial justice would be done by rejecting the application which has been filed after 1568 days of the passing of the judgment, without any proper explanation for the delay. No public interest is going to be served in pursuing the stale claims against the land loser and that too in the era of the Land Acquisition Act of 2013 (i.e. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.)
15. In the circumstances, the application deserves to be dismissed and the same is accordingly dismissed. Consequently, the appeal is rejected.
JUDGE Ambulkar
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!