Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gmr Airports Ltd. Through ... vs Mihan India Ltd. Thr. Chairman And ...
2021 Latest Caselaw 11207 Bom

Citation : 2021 Latest Caselaw 11207 Bom
Judgement Date : 18 August, 2021

Bombay High Court
Gmr Airports Ltd. Through ... vs Mihan India Ltd. Thr. Chairman And ... on 18 August, 2021
Bench: S.B. Shukre, Anil S. Kilor
                                1                  wp1723.20.odt




          IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
                    NAGPUR BENCH, NAGPUR


                      WRIT PETITION NO. 1723 OF 2020


1.GMR Airports Ltd.
  A Company incorporated under the
  Companies Act, 1956, having its
  Registered Office at 25/1, Skip
  House, Museum Road, Bangalore-
  560025, through Authorised
  Representative T.V. Ganesan,
  Aged about 54 years, r/o. 366D,
  Mayur Vihar Phase II, Delhi 110091.

2.GMR Nagpur International Airport Ltd.
  A Company incorporated under the
  Companies Act, 1956, having its
  Registered Office at 1st Floor, Terminal
  Building, Dr.Babasaheb Ambedkar
  International Airport, Nagpur-440005,
  Maharashtra through Authorised
  Representative T.V. Ganesan,
  Aged about 54 years, r/o. 366D,
  Mayur Vihar Phase II,
  Delhi 110091.                              ......     PETITIONERS.


      // VERSUS //


1.MIHAN India Ltd.,
  through Chairman and Managing
  Director, having its Registered Office
  at 1st Floor, Old Terminal Building,
  Dr.Babasaheb Ambedkar International
  Airport, Nagpur-440005, Maharashtra.




 ::: Uploaded on - 19/08/2021                ::: Downloaded on - 19/08/2021 15:11:47 :::
                                 2                         wp1723.20.odt

2.Government of Maharashtra,
  Through its Secretary,
  Administration Reforms and Special
  Projects, General Administration
  Department, Mantralaya, Madam Cama
  Road, Hutatma Rajguru Square,
  Nariman Point, Mumbai 400032.      ........           RESPONDENTS

-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=
Mr.A.M.Singhvi, Senior Advocate assisted by Mr.C.B.Dharmadhikari,
Advocate for petitioners.
Mr.M.G.Bhangde, Senior Advocate with Mr.R.M.Bhangde, Advocate
for respondent no.1.
Ms N.P.Mehta, A.G.P. for respondent no.2/State.
-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=

                       ********
Date of reserving the Judgment                     : 12.7.2021.
Date of pronouncement of the Judgment              : 18.8.2021.
                       ********

                                         CORAM : SUNIL B. SHUKRE &
                                                 ANIL S. KILOR, JJ.

ORAL JUDGMENT (Per Sunil B. Shukre, J) :

1. Rule. Rule made returnable forthwith. Heard finally with

the consent of learned Counsel for the respective parties.

Introduction

2. Petitioner no.1, a public limited Company. It claims to be

an Airport developer and operator across the globe. Petitioner no.2 is

3 wp1723.20.odt

a wholly owned subsidiary company of petitioner no.1 and it is a

Special Purpose Vehicle (for short "SPV ") incorporated by petitioner

no.1 for the purpose of implementation of the project for up-

gradation, modernization, operation and management of

Dr.Babasaheb Ambedkar International Airport, Nagpur (for short

"Nagpur Airport"), for which bids were invited from qualified bidders

through a tender floated by respondent no.1.

3. Petitioner no.1 submitted its bid for the said project on

28.9.2018 and on completion of bid evaluation process by respondent

no.1, petitioner no.1's bid was adjudged to be the highest in terms of

the bidding documents. There were some negotiations between

petitioner no.1 and respondent no.1 regarding possibility of petitioner

no.1 increasing it's offer of revenue share, which petitioner no.1 did

in-fact. Petitioner no.1 raised it's offer of revenue share from 5.76 %

to 14.49 %. Petitioner no.1 in doing so stated that although any

upward revision in the offer may adversely impact the financial

position considered by petitioner no.1, it agreed to increase it's offer,

in view of request made by the Project Monitoring and

Implementation Committee (for short "PMIC"), importance of the

project and larger interest of the people of Maharashtra and Nagpur.

4 wp1723.20.odt

4. It is the case of the petitioners that, in response to the

revised offer given by petitioner no.1, respondent no.1 issued a letter

of acceptance dated 7.3.2019, which petitioner no.1 says was a Letter

of Award accepting the revised bid of the petitioner no.1 subject to

further approval of GOI for (a) alienation of land owned by Airport

Authority of India (for short "AAI") in favour of petitioner no.1 and

(b) formation of SPV for the project. The petitioners further submit

that petitioner no.1 was also called upon to return duplicate copy of

the letter dated 7.3.2019 duly signed by it, to respondent no.1 within

seven days thereby indicating its acceptance by petitioner no.1. The

petitioners further submit that by letter of petitioner no.1 dated

12.3.2019, petitioner no.1 informed respondent no.1 its acceptance of

the letter dated 7.3.2019 and returned a duly signed duplicate copy

of the letter dated 7.3.2019 along with it.

5. Petitioners submit that petitioner no.1 took various steps

for implementation of the project as required under the letter dated

7.3.2019 and respondent no.1 also acted in the direction of

implementation of the project. Petitioners submit that letter of

acceptance dated 7.3.2019 is a Letter of Award and it's acceptance by

petitioner no.1 has resulted into a concluded contract between the

5 wp1723.20.odt

parties. Petitioners submit that execution of Concession Agreement

was the next step, as per letter dated 7.3.2019, towards

implementation of the project. But, respondent no.1 delayed

execution of the Concession Agreement compelling the petitioners to

file a petition being Writ Petition No.1343 of 2020 seeking directions

to respondent no.1 to complete its formal obligation of executing

Concession Agreement for the project. The petitioners submit that

notice was issued by this Court in the said Writ Petition vide its order

dated 11.3.2020 and according to the petitioners, copy of the notice

was served by them upon respondent no.1 on 11.3.2020 itself. The

petitioners submit that the notice that was issued in the Writ Petition

was for final disposal of the petition at the admission stage and

considering urgency of the matter, this Court had listed the petition

for final disposal on 18.3.2020. Meanwhile, as submitted by the

petitioners, respondent no.1 was also served with notice of Writ

Petition through Court bailiff on 16.3.2020 and when this case was

sub-judice, the petitioner no.1 received a letter dated 19.3.2020

informing it that pursuant to the directives received from the

Government of Maharashtra vide communication dated 16.3.2020

and in accordance with clause 2.16 of RFP, respondent no.1 annulled

the bidding process without award of contract. Being aggrieved by it,

6 wp1723.20.odt

the petitioners are before this Court through this petition.

6. According to respondent no.1, this is not a case of any

concluded contract and no right whatsoever was vested in the

petitioners by issuance of letter dated 7.3.2019. Respondent no.1

submits that, by this letter, it only communicated its acceptance of the

revised bid for 14.49 % share in the gross revenue for the purpose of

further consideration of the revised offer submitted by the petitioner

no.1. It is further submitted by respondent no.1 that such acceptance

of bid was subject to approval of Government of India regarding

alienation of land owned by AAI in favour of petitioner no.1 and

formation of SPV between the petitioner no.1 and the answering

respondent. Respondent no.1 asserts that the letter dated 7.3.2019 is

only a bid acceptance communication and not a Letter of Award and

places its reliance upon clause 3.3.6 of the Request for Proposal.

7. The respondent no.1 further submits that copy of letter

dated 7.3.2019 was sent by it to the AAI for processing of approvals

stated therein. Ministry of Civil Aviation (for short "MoCA"),

Government of India (for short "GoI") vide its communication dated

20.8.2019, raised certain queries regarding present tender process

7 wp1723.20.odt

following which a meeting was convened under the Chairmanship of

Secretary, MoCA, GoI at New Delhi on 30.8.2019. Respondent no.1

further submits that, in this meeting the Secretary, MOCA, GOI,

expressed dissatisfaction on the revenue share offered by petitioner

no.1 and questioned financial viability of the project considering the

present revenue being generated by the Nagpur Airport and thus, the

MoCA sought a detailed justification in the matter.

8. Respondent no.1 further submits that the observations of

MoCA were considered by the PMIC in its meeting held on

14.10.2019 and finding them to be correct, the PMIC decided to

cancel the tender process and re-tender the project. Respondent no.1

also submits that the MoCA, Government of India is a necessary party.

Respondent no.1 submits that the decision of the PMIC was

communicated to it by letter dated 16.3.2020. Respondent no.1 also

submits that even the audit report raised concerns about the financial

viability of the bid submitted by the petitioner. Respondent no.1

further submits that the bank guarantee which was issued by

petitioner no.1 towards the bid security was valid only till 30.4.2020

and the bank guarantee was not renewed thereafter by petitioner

no.1 thereby indicating that petitioner no.1 also accepted the decision

8 wp1723.20.odt

to annul the tender process taken by respondent no.1 on the directive

of respondent no.2 and communicated to petitioner no.1 on

19.3.2020.

9. Respondent no.1 further submits that it has earned gross

profit of 49 Crores during the financial year 2018-19 and has

estimated gross profit of Rs.64 Crores (unaudited) during the

financial year 2019-20 and in its opinion, the offer of respondent no.1

at 14.49 % of gross revenue share is extremely low and financially

unviable, which would cause great loss to the public exchequer.

Respondent no.1 states that any up-gradation and modernization of

Airport should lead to increase in revenue for the Government from

the project or in other words the project should be financially viable

and that being not the case here, it has annulled the tender process

well within its rights and well in terms of the bidding documents and

that now it has opted for the fresh tender process in public interest,

wherein the financial model will be different from that of the present

tender process. It, thus, prays for dismissal of the petition.

10. Respondent no.2 submits that the facts and circumstances

leading to the impugned decision have already been pointed out by

9 wp1723.20.odt

the respondent no.1 and in view of them, respondent no.2 as well as

the AAI, one of the stake holders in respondent no.1, which only

implements on behalf of the State of Maharashtra a comprehensive

project for development of Nagpur Airport to world class standards

which goes by the acronym 'the MIHAN project', using the resources

of respondent no.2 and the AAI, do not wish to go ahead with the

present tender as their own financial bid received in the tender

process is extremely low. It further submits that the respondents and

the AAI have, therefore, decided to call for fresh tenders, possibly

with a different financial model which will generate better revenue

for the public exchequer.

Rival Submissions

11. Mr.A.M.Singhvi, learned Senior Advocate submits that the

letter of acceptance dated 7.3.2019 is actually a Letter of Award, if

one goes by it's tenor and terms and conditions of the RFP. He

further submits that the Letter of Award has been accepted by

petitioner in accordance with what is mentioned therein and the

bidding documents and therefore, what is now there between the

parties is a concluded contract which must lead to execution of

10 wp1723.20.odt

Concession Agreement(for short "CA"). Learned Senior Advocate

further submits that the conditions mentioned in the Letter of Award

dated 7.3.2019 are the post bid conditions as they are neither stated

in the bidding documents nor are contemplated under the bidding

documents. He submits that these conditions are for respondent no.1

to fulfill. In any case, he further submits, they are only a formality as

the transfer of the Airport and its assets together with the land to

respondent no.1 has already taken place with the approval of GoI. He

further submits that the directive of respondent no.2 as mentioned in

the impugned letter, is misplaced as respondent no.2 has no role to

play in the matter. He further submits that the impugned

communication does not show that there is any decision as such by

respondent no.1 as the decision is taken by respondent no.2, which

has no role to play in the bidding process.

12. Mr.Singhvi, learned Senior Advocate further submits that

invocation of clause 2.16 for annulment of bidding process by

respondent no.1 is wrong as it could be resorted to only when

bidding process is on and not after it is over. He submits that with

the issuance of Letter of Award dated 7.3.2013 by respondent no.1,

and its acceptance by the petitioner no.1, marked completion of

11 wp1723.20.odt

bidding process. He further submits that as there was a concluded

contract between the parties, what had remained to be done was only

a ministerial act of execution of CA. He further submits that

respondent no.2, by issuing a directive to the respondent no.1 in

annulling the bidding process, has gone against the decision of Union

Cabinet to subsequently transfer the Airport for further

"development". He further submits that subsequent conduct of parties

would show that letter dated 7.3.2019 was a Letter of Award infact

and in law. He further submits that now contractual obligations have

come into play, which could not be nullified by the acts of the parties

with just exceptions arising from compelling circumstances such as

threat to security or sovereignty of India or statutory provisions newly

made, which circumstances are admittedly absent here. He also

submits that principle of promissory estoppel would prevent the

respondent no.1 from back-tracking on it's promise.

13. Learned Senior Advocate for petitioners submits that the

justification now being given, which is based on so called audit report

and which harps on the string of financial viability, is factually

incorrect and misleading. He submits that this justification was not

part of impugned communication. He submits that as vested rights

12 wp1723.20.odt

had been created in favour of petitioners, respondent no.1 should

have atleast called for response of petitioner no.1 regarding it's so-

called concerns over the profitability issue, but it did not, which was

against the principles of good governance and transparency.

14. Thus, Mr.Singhvi, learned Senior Advocate submits that

the whole action on the part of respondent in cancelling the

annulment process through the impugned communication is

arbitrary, unreasonable and violative of principles of natural justice

and it smacks of legal malice deserving it to be quashed and set aside

while issuing consequential directions.

15. Mr.M.G.Bhangde, learned Senior Advocate appearing for

respondent no.1 disagrees. He asserts that there was never any

concluded contract which came into being. He submits that the letter

dated 7.3.2019 is not a Letter of Award but only a letter which

indicated that bid was accepted subject to conditions, namely

approval of GoI for alienation of land to the petitioners no.1 and for

formation of SPV. He submits, by relying upon the bidding

documents, that the bidding process had not been completed and it

would have been completed only upon execution of the Concession

13 wp1723.20.odt

Agreement and, therefore, there is nothing wrong in cancellation of

bidding process.

16. Mr.Bhangde, learned Senior Advocate for respondent no.1

further submits that circumstances of the case showed that efforts

were made by respondent no.1 to seek necessary approval from the

Government of India, but since certain queries were raised and some

observations were made by the Secretary, MoCA, the PMIC held a

meeting and on financial analysis, found that those observations were

right and therefore, it decided to cancel the bidding process and re-

tender the project and rightly so. He further submits that in the

whole process, the Transaction Advisor was consulted, the Audit

report was also considered and it was found that the revenue share

offered by petitioner no.1 was inadequate and any acceptance of it

would have led to loss to public exchequer and so the impugned

decision was taken. He submits that such a decision taken by

respondent no.1 was in the public interest inasmuch as there was

unanimity amongst members of PMIC about it. He further submits

that when the Nagpur Airport was earning good profit, existing model

of revenue share, in which the revenue share offered by petitioner

no.1 was not to the satisfaction of the Authorities, could not have

14 wp1723.20.odt

been a profit making proposition.

17. Learned Senior Advocate for respondent no.1 further

submits that pre-requisites of a concluded contract is that it's

acceptance must be absolute and not conditional in accordance with

Section 7 of the Indian Contract Act and in the present case, letter

dated 7.3.2019 only informs to the petitioner no.1 decision of

respondent no.1 regarding acceptance of the bid in a conditional

manner and subject to the approvals regarding land transfer and

formation of SPV from the Government of India. He, therefore,

submits that the letter of acceptance dated 7.3.2019 is not a Letter of

Award, that it is subject to afore-said two conditions and further

conditions like execution of Concession Agreement and furnishing of

performance security within the time prescribed in the Concession

Agreement. He submits all these conditions were never fulfilled, no

Concession Agreement was executed within the stipulated time of

sixty days of the receipt of letter dated 7.3.2019 and there was no

furnishing of the performance security within the prescribed time and

as such, no vested rights are created in petitioner no.1. He submits

that there is neither any promise given nor any position altering as a

result of any promise, and so principle of promissory estoppel has no

15 wp1723.20.odt

application here.

18. Mr.Bhangde, learned Senior Advocate further submits that

this case involves disputed questions of facts and also enforcement of

contractual obligations, if any. He further submits that there is also

no involvement of any public law element and there is no question of

legal malice. He maintains that appropriate remedy for the

petitioners would be to approach the Civil Court. He further submits

that the petitioner has accepted the conditions of the letter of

acceptance dated 7.3.2019, and so now cannot say that approvals of

GoI are not necessary, and if it says so, it would mean that petitioner

no.1 desires to accept only a part of it and wishes against rest of its

parts, which is not permissible in law, as acceptance must be absolute

and unqualified. Mr.Bhangde, learned Senior Advocate further

submits that there has been a long gap of about five years from the

initiation of the bidding process and now the situation has

substantially changed warranting annulment of the bidding process.

19. Mr.Bhangde, learned Senior Advocate further submits that

Bank guarantee towards bid security has not been extended after

30.4.2020 which itself shows that petitioners have accepted the

16 wp1723.20.odt

impugned decision. He further submits that subsequent conduct of

the parties is not relevant, there being no Letter of Award issued. He

submits that SPV that is petitioner no.2, was not constituted in

accordance with bidding documents. He submits that there is no

arbitrariness and unreasonableness. On all these grounds, the

learned Senior Advocate urges that the petition be dismissed.

20. Ms Nivedita Mehta, learned A.G.P. supports the decision of

annulment of the bidding process as reflected in the impugned letter

dated 19.3.2020 and adopts the argument of Mr.M.G.Bhangde,

learned Senior Advocate.

Historical Facts

21. For effectively dealing with rival submissions, it would be

necessary to consider the historical facts from which has evolved the

present bidding process for development of the Airport at Nagpur.

These facts, about which there is no dispute, are summarised thus :

a) Nagpur Airport was established in the year

1917-18 and saw its being managed since then by different

17 wp1723.20.odt

Authorities at different times starting with Royal Military

Force, then Indian Air Force and National Airport

Authority and finally AAI till the year 2009. Respondent

no.2 took the initiative to develop a "Multi Modal

International Passenger and Cargo Hub Airport" at Nagpur

("MIHAN Project") in co-ordination with MoCA, AAI and

Ministry of Defence and appointed Maharashtra Airport

Development Company (for short "MADC") as a nodal

agency for taking further steps to implement the MIHAN

project. Accordingly, a Memorandum of Understanding

(for short 'MoU'), dated 18.12.2006 was entered into

between the MoCA and AAI of one part and GoM

(respondent no.2) and MADC of the other part. By this

MoU, it was agreed between the parties that a Joint

Venture Company (for short "JVC") consisting of MADC

and AAI would be incorporated. It was agreed that MADC

would have 51% shareholding and AAI would have 49%

shareholding. The purpose of establishing a JVC was to

develop and run the Nagpur Airport. It was agreed that

Nagpur Airport would be transferred to the said JVC. It

was agreed between the parties that MoCA and AAI would

18 wp1723.20.odt

take all necessary steps for expediting the transfer of

Airport to the JVC to be formed including transfer of land

and other assets. The relevant clauses of said MoU are re-

produced as below :

"8. The JVC should be formed expeditiously and best efforts should be made to transfer the Airport to be the JVC within 3 months from the date of the signing of the MoU at an annual lease rent of Rs.1/- for a period of 30 years. This period can be extended on mutually agreed terms and conditions."

"14.MoCA/AAI shall take necessary steps to transfer the Nagpur Airport along with all its land and other assets to the JVC within a period of 180 days from the date of signing of this MOU."

b) Subsequently, the Union Cabinet gave its "in-

principle" approval for transfer of the Nagpur Airport to

the proposed JVC on 17.1.2008. It also permitted the

proposed JVC to involve a strategic partner on build,

operate and transfer basis for development of Nagpur

Airport to world-class standards. The Union Cabinet, in

the said approval, noted the fact that transfer of Nagpur

19 wp1723.20.odt

Airport would bring about much needed development in

the Vidarbha region, which had been a long and cherished

demand of the people of the region.

              c)               In pursuance of the said MoU, a Joint Venture

              Agreement ("JVA" for short) dated 22.2.2009,                       was

executed between the MADC and AAI. Clause 3.1 of the

JVA noted the fact that GoI had accepted approval of

transfer of Nagpur Airport to the JVC, proposed to be

formed for its development as MIHAN. The JVA led to

formation of the JVC, the MIL, the respondent no.1.

Respondent no.1, MIL was thus established with the

primary object of maintaining, operating and developing

Nagpur Airport as a part of MIHAN project. Respondent

no.1 took over the Nagpur Airport for its operation,

maintenance and further developments w.e.f. 7.8.2009.

d) Under the JVA, MADC and AAI agreed that

development of Nagpur Airport shall be undertaken after

the transfer of assets to the MIL. It was agreed, amongst

others, that AAI would contribute its existing land and

20 wp1723.20.odt

MADC would bring in additional land. It was further

agreed that the first JVC would enter into a Concession

Agreement with the developer who would be selected

through competitive bidding for highest revenue share as

per standard methodology for development of Airports,

using the standard bidding documents and procedures,

including the Request for Qualification ( for short "RFQ")

and Request for Proposal (for short "RFP") and

Concession Agreement already approved by the

Government of India. Relevant extract of clause (G) is

reproduced as below :

"G. Further development of the Nagpur airport will be undertaken by the JVC after transfer of the assets (as defined in the Annexures to this JVA) to the JVC comprising MADC having 51% equity and AAI having 49% equity. Both the partners will bring in their respective assets to the JVC, with AAI contributing the existing land, building and structure and MADC bringing in additional land for development of the airport irrespective of the non-cash assets brought in by the JV Partners, the equity structure of the JVC will continue to be 49:51 of the Partners to the JVC. The first JVC will enter into a Concession Agreement with Developers who will be

21 wp1723.20.odt

selected through competitive bidding for highest revenue share as per standard methodology for development of airports, using the standard bidding documents and procedures, including RFQ, RFP and Concession Agreements, already approved by the Government of India. "

It was, thus, agreed that after transfer of assets to

respondent no.1, respondent no.1 would undertake further

development of Nagpur Airport, which would be done by it by

entering into a Concession Agreement (CA) with Developers, who will

be selected through competitive bidding for highest revenue share as

per standard methodology for development of Airports, using the

standard documents including RFQ, RFP and CA, already approved by

GoI.

Backdrop Facts of the Dispute

22. The above referred facts and circumstances indicate the

history of evolution of Airport at Nagpur to it's present stage and

aspirations of the Government and people of Maharashtra to develop

the Airport to world class standard. There are still a few more facts

22 wp1723.20.odt

which are relevant, undisputed and helpful in our endeavour to

resolve the dispute. We have chosen to call them backdrop facts of

the dispute. They are recapitulated in the ensuing sub-paragraphs.

a) In pursuance of the MoU and JVA, AAI handed over its

assets pertaining to Nagpur Airport to MIL on 6.8.2009 and these

assets included the land belonging to AAI. Completion of handing

over of the assets was recorded in handing over agreement entitled

"Handing over of AAI's assets of Dr.Babasaheb Ambedkar

International Airport, Nagpur to MIHAN India, Joint Venture

Company" executed between the AAI and MIL on 6.8.2009. This

document recorded the fact of handing over of Nagpur Airport to MIL

for the purpose of its operation and management w.e.f. 7.8.2009.

b) In order to achieve the object of maintenance and

development of Nagpur Airport and as contemplated by MoU, JVA

and also the in-principle approval given by Union Cabinet and steps

taken for handing over of assets of Nagpur Airport to respondent

no.1, respondent no.1 decided to invite International competitive bids

for receipt of the highest revenue share in the award to be made of

the project for up-gradation, modernisation, operation and

23 wp1723.20.odt

management of Nagpur Airport through public private partnership on

Design, Build, Finance, Operate and Transfer ("DBFOT" for short)

basis which was to be given to the selected bidder. Accordingly,

respondent no.1 initiated an open competitive two stage bidding

process for the said project. The first part was of qualification stage

and the second was of bid stage. The first part had the object of

shortlisting the bidders while the second part had the object of

selecting the bidder for the project. So, applications for the project

were invited by issuance of RFQ, dated 12.5.2016, as amended from

time to time. Through the RFQ, respondent no.1 informed all

interested parties that AAI had transferred all the assets including

existing and additional land, buildings and structures at the Airport to

the Authority i.e. MIL, respondent no.1. This fact was noted in clause

1.1.1 (a)(4.) of the RFQ. Relevant portion of this clause is extracted

as below :

"1.1.1 (a) Brief particulars on Nagpur Airport :

1.........

2.........

3..........

4.MIHAN India Limited (the "Authority") a joint venture company formed by Maharashtra Airport Development

24 wp1723.20.odt

Authority (MADC) and Airport Authority of India (AAI), was formed in 2009. As per the joint venture agreement, AAI had transferred all assets including existing and additional land, buildings and structures to the Authority. The current terminal facility include the building over an area of 22,500 square metres and has a capacity to handle 400 arriving and 400 departing domestic passengers and 150 arriving and 150 departing international passengers during peak hours, two conveyor belts each in departure, the domestic arrival hall and in the international arrival hall, two aerobridges, eighteen parking bays and a car park to accommodate 600 vehicles. "

c) In response to RFQ, petitioner no.1 submitted its

application and was eventually shortlisted as a qualified bidder. A

qualified bidder, as per the structure of the bidding process, would

get the RFP, if it deposited stipulated amount. Petitioner no.1 on

being called upon by respondent no.1, deposited an amount of Rs.8

lacs (Rupees Eight Lacs only) towards procurement of the RFP

documents and same were issued to it. The RFP contained necessary

information, terms and conditions required to be followed by the

prospective bidders and various clauses governing the bidding

process. The RFP also included the bidding documents including

draft concession agreement, master plan and so on. It required the

25 wp1723.20.odt

prospective bidders to submit bid security of Rs.16.85 Crores along

with their respective bids. The bid security was refundable within 60

days of the last date of submission of the bid, except in the case of a

successive bidder, whose bid security would be retained till the

selected bidder had provided a performance security in terms of the

Concession Agreement. The RFP contained a schedule of bidding

process and it stated that the Authority i.e. respondent no.1 would

endeavour to adhere to it, though in the present case, it was not

followed in it's letter and spirit.

d) In the background of the above referred facts and

circumstances, the present bidding process for up-gradation,

development, operations, maintenance of Nagpur Airport (the

project) as envisaged in the JVA (clause G) was initiated on DBFOT

basis and the bids were invited with a view to selecting a Developer

through competitive bidding for highest revenue share as per

standard methodology for development of Airports using standard

bidding documents and procedure including RFQ, RFP and

Concession Agreement already approved by the GoI.



e)             The bidding process was thus initiated.        It went on





                                26                         wp1723.20.odt

substantially as per the terms of RFQ and RFP. At the qualification

stage, scrutiny of the bidders was made and after due evaluation, six

bidders were shortlisted for participation in the second stage of

bidding process. Details from these bidders were called for, but only

five of the shortlisted bidders submitted those details which included

the petitioner no.1. Security clearance of these five shortlisted

bidders was obtained from the Ministry of Home Affairs and

thereafter the Government of Maharashtra granted approval for

issuance of RFP to all the five Companies which were found to be

qualified bidders.

f) The Government of Maharashtra, on 11.12.2017,

constituted an eleven member Project Monitoring and

Implementation Committee (PMIC) under the Chairmanship of

Chief Secretary, Government of Maharashtra for the purpose of

finalising the RFP documents consisting of RFQ, Concession

Agreement (CA) and schedules thereto. The PMIC approved these

documents and thereafter, they were issued to all the five qualified

bidders for submitting their quotations regarding the percentage of

revenue shares they intended to offer to respondent no.1, with date

of 28.9.2018 being the revised final due date for submission of the

27 wp1723.20.odt

quotation bids, which was the last extended date for submission of

such bids.

g) On 28.9.2018, the respondent no.1 received two bids.

One bidder offered 3.08% share of gross revenue while the other

bidder, which was petitioner no.1, offered 5.76 % share of gross

revenue and thus, petitioner no.1 emerged to be the highest bidder.

However, this offer of petitioner no.1 was considered to be

financially low and therefore, the issue was discussed in the Board

meeting of respondent no.1 held on 14.2.2019 which ultimately

decided to approach the PMIC for the possibility of negotiations

with petitioner no.1. Petitioner no.1 was called to the meeting

convened by PMIC on 5.3.2019 for negotiations. The PMIC

requested the petitioner no.1 to revise the offer in line with the

assumptions presented by the PMIC during the course of meeting.

Petitioner no.1 accepted the request and revised the offer by

enhancing the revenue share percentage from 5.76 % to 14.49 %.

Petitioner no.1 communicated such upward revision of it's offer to

respondent no.1 vide it's letter dated 6.3.2019. It also noted the

fact that though the upward revision made in the offer would

impact adversely it's financial projections for the project, it

28 wp1723.20.odt

enhanced it's offer in view of request made by the PMIC, the

importance of the project and also larger interest of the people of

Maharashtra and Nagpur. Accordingly, it made a request to

petitioner no.1 to issue Letter of Award (LoA) at the earliest.

h) The revised offer of 14.49 % gross revenue share given

by petitioner no.1 was accepted by respondent no.1. The

acceptance was communicated to petitioner no.1 by respondent

no.1 (1st party) vide it's letter dated 7.3.2019. The acceptance

letter made it clear that respondent no.1 had right to revoke the

acceptance and forfeit and appropriate the bid security as per the

terms of RFP in the event the petitioner no.1 (2 nd party) failed to

accept and comply with it's obligations as specified in the RFP and

this letter and in case of such revocation of acceptance and

consequent encashment of bid security, the petitioner no.1 would

have no claim whatsoever against respondent no.1 save and except

as expressly provided under the law. By this letter of acceptance,

respondent no.1 informed the petitioner no.1 that, in the event of

duplicate copy of letter of acceptance duly signed by it was not

received by respondent no.1 within seven days, it may revoke the

acceptance and consequences noted earlier would follow.

29 wp1723.20.odt

Petitioner no.1 by it's letter dated 12.3.2019 sent it's acceptance

without prejudice and pursuant to the provisions of RFP and

Concession Agreement. It also sent along with it a duplicate copy of

the letter dated 7.3.2019 duly signed by the authorised signatory of

petitioner no.1.

i) In terms of RFP, every bidder was required to submit bid

security along with it's bid. The petitioner no.1 had also submitted

it's bid security by furnishing a bank guarantee of the requisite

amount in favour of respondent no.1. After issuance of letter of

acceptance dated 7.3.2019, further events took place such as

extension of bid security from time to time, at the request of

respondent no.1, exchange of drafts of Concession Agreement (CA)

to be executed by petitioner no.1 with some correspondence

regarding corrections of some errors suggested by petitioner no.1,

giving of no objection and concurrence by respondent no.1 to

petitioner no.1 for incorporation of Company, GMR Nagpur

International Airport Limited as SPV to execute the Concession

Agreement and implement the project, giving of No Objection by

respondent no.1 to petitioner no.1 for use of office space and

address by the SPV to be formed and formation of SPV i.e.

30 wp1723.20.odt

petitioner no.2 and it's intimation being given by petitioner no.1 to

respondent no.1. Apart from these events, there were also some

events which took place at the end of respondent nos. 1 and 2

together with Ministry of Civil Aviation and PMIC. But, the

petitioner no.1 was not aware of them as it was not kept informed

by the respondents. The CA was never executed and ultimately, the

whole exercise carried out by respondent no.1 for about five years

saw it's unexpected end, which was bitter for petitioner no.1, in

issuance of impugned communication annulling the bidding process

without award of contract.

j) Meanwhile, the petitioner no.1 kept on requesting

respondent no.1 to complete the formality of execution of

Concession Agreement and let it start the work of implementation

of the project. The petitioner no.1 informed the respondent no.1

that since it had complied with all it's obligations under the RFP and

the letter of acceptance dated 7.3.2019, it was necessary that the

Concession Agreement was executed. It sent a letter dated

25.2.2020 in this regard to the respondent no.1. But there being no

response given by the respondent no.l, the petitioners filed a Writ

Petition bearing Writ Petition No.1343 of 2020 seeking direction to

31 wp1723.20.odt

respondent no.1 to execute the concession agreement. Notice in

this petition was issued on 11.3.2020. Private service of notice was

permitted. The petitioners filed an affidavit of service on

17.3.2020. However, on 19.3.2020, the petitioner received a

communication from the respondent no.1 annulling the bidding

process without award of contract. The communication noted that

annulment of the bidding process was done in pursuance of the

directives dated 16.3.2020 received from the Government of

Maharashtra.

23. Being aggrieved by the abrupt end of the bidding

process, the petitioners have filed the present petition seeking

quashing of the letter dated 19.3.2020 annulling the bidding

process and issuing a direction to the respondents to comply with

the RFP conditions in their letter.

Questions To Be Answered

24. Now, let us come back to the present dispute as put

before us by the parties in the light of their rival submissions. These

rival submissions point out certain questions which we must

32 wp1723.20.odt

answer. These questions could be broadly formulated as under :

a) Whether the letter of acceptance dated 7.3.2019 is a Letter of Award ?

b) Whether the letter of acceptance dated 7.3.2019 is only a communication that the bid is accepted, it being conditional ?

c) Is there any concluded contract between the parties ?

d) Whether the action of respondent no.1 in annulling the bidding process by it's letter dated 19.3.2020 (impugned communication) is arbitrary, unreasonable and unfair ?

e) Whether the case involves disputed questions of fact and an issue of enforcement of contractual obligations simplicitor, a remedy for which would lie elsewhere ?

25. We now begin our quest to attempt answers to the

questions by organising them in two parts; first part would deal with

first three questions; and the second part with remaining two

questions.

                                 33                       wp1723.20.odt




                                Part I Questions



26. The letter dated 7.3.2019, which is at the centre of the

controversy here, addressed by respondent no.1 to petitioner no.1

makes a reference to certain relevant facts. It notes that pursuant to

the bid submission for the said project by petitioner no.1 on

28.9.2018 and completion of bid evaluation process, the bid

submitted by petitioner no.1 was observed to be the highest with the

revenue share quote of 5.76 % of the gross revenue which was,

following the discussions and negotiations held between the parties

on 5.3.2019, revised to revenue share quote of 14.49 %. It makes a

categorical statement that this revised Bid has been accepted by the

Competent Authority. It, however, puts a rider that such acceptance

is "subject to further approval of Government of India for (a)

alienation of land owned by the AAI in favour of the second party i.e.

petitioner no.1 and (b) formation of SPV for the Project ("Approval)"

and other terms and conditions mentioned in the letter. It further

mentions that in case approval is not received, this acceptance would

stand revoked without any legal or financial implications to either

parties. It further states that subject to written intimation of the

34 wp1723.20.odt

approval by the first party i.e. respondent no.1 to the second party i.e.

petitioner no.1, the latter shall complete various activities from the

date of such intimation including but not limited to the actions named

therein within the time period specified therein. The actions that

were supposed to be completed by petitioner no.1 were in respect of

execution of the Concession Agreement (CA) within sixty days of

receipt of written intimation of the approval from the respondent

no.1 and the petitioner no.1 furnishing a performance security within

the time prescribed in the CA. The letter of acceptance emphasises

that the first party or the respondent no.1 would have the right to

revoke this acceptance, forfeit and appropriate the bid security as per

the terms of RFP in the event the second party fails to accept and

comply with it's obligations as specified in the RFP and the letter

dated 7.3.2019. Lastly, it lays down that in the event the duplicate

copy of this letter of acceptance duly signed by the petitioner no.1 is

not received within 7 days, the respondent no.1 may revoke this

acceptance and the consequences stated in the letter would follow.

Now, the question is whether this letter of acceptance

dated 7.3.2019 is a Letter of Award, which it is, as argued by the

learned Senior Advocate for the petitioners or it is only a simple

35 wp1723.20.odt

communication made by the respondent no.1 to the petitioner that

the bid is accepted, which it is, as submitted by the learned Senior

Advocate for the respondent no.1 and also learned A.G.P. for

respondent no.2.

27. Learned Senior Advocate for the petitioners submits that

this letter of acceptance having been issued in terms of the RFP and

containing categorical statements regarding acceptance of revised bid

offered by the petitioner no.1 and calling upon the petitioner no.1 to

send a duly signed duplicate copy of letter within seven days towards

acceptance of what is stated in this letter is unmistakably a Letter of

Award (LoA) of contract of the project to the petitioner no.1. He

submits that with issuance of LoA, there is a concluded contract

which binds the parties. He places reliance upon the case of Har

Shankar and Others .vs. The Deputy Excise and Taxation

Commissioner and Others reported in (1975) 1 SCC 737.

28. Learned Senior Advocate for respondent no.1 would

submit that not only the conditions stated in the said letter but also

various clauses of the RFP would certainly show that by the said

letter, respondent no.1 has only communicated to the petitioner no.1

36 wp1723.20.odt

it's acceptance of bid subject to fulfillment of the conditions stated

therein and as those conditions were not fulfilled and even the part

that was required to be completed by the petitioner no.1 remained to

be fulfilled, the said letter could not be termed as the LoA. Learned

Senior Advocate for respondent no.1 further submits that this LoA

does not create any binding obligations so as to result into a

concluded contract between the parties, as the acceptance is not

conditional. He seeks support from Section 7 of the Indian Contract

Act, 1872. He points out that, in the said letter of acceptance, the

words "tendered work is awarded to you " are not mentioned and

therefore, it could not be regarded as LoA. He also submits that

having accepted the conditions of the said letter of acceptance, it was

necessary for the petitioner no.1 to have executed Concession

Agreement and furnished a performance security and same having

not done, no vested rights are created in petitioner no.1 and that it

cannot say that it would accept only some of the conditions of the

said letter and would reject the others. He places reliance upon the

cases of Rishi Kiran Logistics Private Limited vs. Board of Trustees of

Kandla Port Trust and Others reported in (2015) 13 SCC 233, Padia

Timber Company Private Limited .vs. Board of Trustees of

Visakhapatnam Port Trust, through its Secretary reported in (2021) 3

37 wp1723.20.odt

SCC 24 and PSA Mumbai Investments PTE. Limited vs. Board of

Trustees of the Jawaharlal Nehru Port Trust and another reported in

(2018) 10 SCC 525.

29. Parties here have not pointed out to us any prescribed

format for issuance of LoA. The RFP and other approved documents

do no include any such pre-determined form. Therefore, whether the

letter of acceptance dated 7.3.2019 is a Letter of Award or not would

have to be ascertained from its contents, clauses of RFP and intention

of the parties as gathered from the attending facts and circumstances.

Let us, therefore, consider the relevant clauses of the RFP, the

contents of the letter of acceptance and the relevant circumstances.

30. Clause 3.3.1 of the RFP makes it clear as to who would be

declared as the Selected Bidder. It reads as under :

"3.3 Selection of Bidder

3.3.1 : Subject to the provisions of Clause 2.16.1, the Bidder whose Bid is adjudged as responsive in terms of Clause 3.2.1 and who quotes the highest Revenue Share offered to the Authority shall ordinarily be declared as the selected Bidder (the "Selected Bidder"). In the event that the Authority

38 wp1723.20.odt

rejects or annuls all the Bids, it may, in its discretion, invite all eligible Bidders to submit fresh Bids hereunder. "

31. In this case, there is no dispute about the fact that

petitioner no.1's bid was found to be the highest and therefore, the

petitioner no.1 was declared as the highest bidder on 28.9.2018

based on the revenue share, highest among all, offered by the

petitioner no.1. Such declaration of the petitioner no.1 made it "the

Selected Bidder" in accordance with the above referred clause.

32. In the disclaimer statement of RFP, there is a clause to the

effect "the bidder shall not claim for selection or appointment as the

Selected Bidder or Concessionaire upon participation unless the

Authority intimates to any bidder about its selection as such and the

decision of the Authority in all cases would be final and binding on

Bidder as the case may be. " Here, the Authority is "respondent

no.1".

33. Thus, as per clause 3.3.1 r/w. said disclaimer part of the

RFP, the petitioner no.1 became the Selected Bidder or

Concessionaire. Clause 3.3.5 reveals what follows after appointment

39 wp1723.20.odt

of a bidder as the Selected Bidder. For the sake of convenience, it is

re-produced as below :

" 3.3.5. After selection, a Letter of Award (the "LOA") shall be issued, in duplicate, by the Authority to the Selected Bidder and the Selected Bidder shall, within 7 (seven) days of the receipt of the LOA, sign and return the duplicate copy of the LOA in acknowledgement thereof. After acknowledgement of the LOA as aforesaid by the Selected Bidder, the Selected Bidder will be required to submit the Performance Security within the time period prescribed in the LOA/Concession Agreement. In the event the duplicate copy of the LOA duly signed by the Selected Bidder is not received by the stipulated date or the Selected Bidder fails to provide the Performance Security within the stipulated date, the Authority may, unless it consents to extension of time for submission thereof, appropriate the Bid Security of such Bidder as Damages on account of the Selected Bidder to acknowledge the LOA or submission of Performance Security as the case may be, and the next eligible Bidder may be considered. "

34. It would be clear from the above referred clause that after

appointing a bidder as Selected Bidder what would follow is a "Letter

40 wp1723.20.odt

of Award (LOA)" to be issued in duplicate by the Authority i.e.

respondent no.1 to the selected bidder i.e. petitioner no.1. The

words "Letter of Award ("the LOA") shall be issued" are significant.

They do not leave any further choice to the Authority or respondent

no.1 to deviate from it's obligation to issue the Letter of Award in

duplicate. However, there is an exception to this course which is

otherwise mandated to be followed by respondent no.1 under clause

3.3.5. The exception is to be found in clause 2.6.3. This clause being

relevant is re-produced as below :

"2.6 Verification and Disqualification 2.6.1........

2.6.2.........

2.6.3. In case it is found during the evaluation or at any time before signing of the Concession Agreementor after its execution and during the period of subsistence thereof, including the Concession thereby granted by the Authority, that one or more of the pre-qualification conditions have not been met by the Bidder, or the Bidder has made material misrepresentation or has given any materially incorrect or false information, the Bidder shall be disqualified forthwith if not yet appointed as the Concessionaire either by issue of the LOA or entering into of the Concession Agreement, and if the Selected Bidder

41 wp1723.20.odt

has already been issued the LOA or has entered into the Concession Agreement, as the case may be, the same shall, notwithstanding anything to the contrary contained therein or in this RFP, be liable to be terminated, by a communication in writing by the Authority to the Selected Bidder or the Concessionaire, as the case may be, without the Authority being liable in any manner whatsoever to the Selected Bidder or Concessionaire. In such an event, the Authority shall be entitled to forfeit and appropriate the Bid Security or Performance Security, as the case may be, as Damages, without prejudice to any other right or remedy that may be available to the Authority under the Bidding Documents and/or the Concession Agreement, or otherwise."

35. A bare reading of the above referred clause would show

that the power which it confers upon the Authority or the respondent

no.1 is about disqualification of the bidder if not appointed as a

Concessionaire either by issuance of Letter of Award or by entering

into the Concession Agreement or termination of the Letter of Award

or Concession Agreement as the case may be, upon happening of the

contingencies stated therein. These contingencies are :

a) the bidder not meeting any of the pre-qualification conditions.

                                 42                     wp1723.20.odt



              b)     the bidder making material misrepresentations or

giving materially incorrect or false information.

If any of these contingencies are met, the Bidder shall be

disqualified forthwith if not yet appointed as a Concessionaire either

by issuance of LoA or entering into CA or the LoA or CA itself would

be liable to be terminated, in case the Selected Bidder has been

issued the LoA or has executed the CA.

36. In the present case, however, the contingencies mentioned

in clause 2.6.3 never arose and therefore, there was no occasion for

the respondent no.1 to have invoked it's power thereunder. That

being so, what was left for respondent no.1 to do was to proceed

further as per clause 3.3.5. It then became necessary for the

respondent no.1 to have issued LoA, in duplicate, in favour of

petitioner no.1 and thereby call upon the petitioner no.1 to sign and

return the duplicate copy of LoA in acknowledgement thereof, within

seven days of it's receipt, which in fact the respondent no.1 did.

37. Clause 3.3.6 lays down that after acknowledgement of the

LoA as required under clause 3.3.5 by the Selected Bidder, the

43 wp1723.20.odt

respondent no.1 shall cause the Concessionaire to execute the

Concession Agreement within the period prescribed in Clause 1.3,

which is sixty days of the LoA. For the sake of convenience, this

clause is re-produced thus :

"Clause 3.3.6. After acknowledgement of the LOA as aforesaid by the Selected Bidder, it shall cause the Concessionaire to execute the Concession Agreement within the period prescribed in Clause 1.3. The Selected Bidder shall not be entitled to seek any deviation, modification or amendment in the Concession Agreement."

38. It is seen from the letter dated 7.3.2019 that it not only

acknowledges the petitioner no.1 to be the Selected Bidder as

defined under clause 3.3.1, but also appoints the petitioner as

Concessionaire in terms of clause 2.6.3 which says that a Selected

Bidder would be a Concessionaire upon issuance of the LoA or

entering into of the Concession Agreement. It is further seen that

this letter of acceptance dated 7.3.2019 has all the attributes, barring

the GoI approval part, of a Letter of Award, which are detailed in

clauses 3.3.5 and 3.3.6. It requires that it's duplicate copy duly

44 wp1723.20.odt

signed by petitioner no.1 be returned to the respondent no.1 within

seven days in acknowledgement of it's acceptance by petitioner no.1

and any failure on the part of petitioner no.1, would lead to

respondent no.1 revoking the acceptance with the consequence of

forefeiture and encashment of bid security and the Selected bidder

having no claim as regards such forfeiture against the respondent

no.1 stated therein. It also directs the petitioner no.1 to execute the

Concession Agreement within sixty days of receipt of written

intimation of the approval from respondent no.1 and further directs

the petitioner no.1 to furnish the performance security within the

time prescribed in the CA. Here a deviation regarding the time

stipulated for execution of the CA is seen. As per clause 1.3, Item

No.11, CA is required to be executed within 60 days of the award of

LoA while, in this acceptance, period of 60 days is to be reckoned

from the date of written approval from respondent no.1. The

approval spoken about is of the GoI as regards alienation of land

owned by the AAI in favour of the petitioner no.1 and formation of

SPV for the project. This deviation about ascertainment of time of

sixty days would not be significant, if it is seen that putting of

condition of GoI approval itself was impermissible, and in any case

did not prevent the contractual relationship from coming into

45 wp1723.20.odt

existence, which we have found to be so in next paragraphs.

39. Now, if we consider the terms of the RFP, we would find

that in the entire RFP it has not been stated anywhere that

acceptance of bid and issuance of LoA would be subject to further

approval of Government of India as regards land alienation and SPV

formation. But, in the letter dated 7.3.2019, the acceptance though

given, has been made subject to such approval of GOI. This is a

departure from clause 3.3.5 of the RFP. This departure, would not, in

our opinion, be sufficient to say that the letter dated 7.3.2019 has not

been issued in terms of clause 3.3.5 as, except for the said deviation,

every parameter of the LoA prescribed in clause 3.3.5 read with

clause 3.3.6 of the RFP is seen to be met in it. The condition of GoI

approval, being not part of the RFQ or the RFP, is a post bid

condition, as rightly submitted by the learned Senior Advocate for

petitioners, and therefore, would not prevent the birth of a contract

from taking place on the petitioner no.1 signing a duplicate copy of

the said letter and returning it to respondent no.1 within stipulated

time in terms of clause 3.3.5 and what is stated in the said letter.

The petitioner no.1, there is no dispute, signed the duplicate copy of

the said letter acknowledging it's acceptance in toto and returned it

46 wp1723.20.odt

to petitioner no.1 within stipulated time of seven days. The

acceptance of letter dated 7.3.2019 here by the petitioner no.1 has

been absolute and unqualified, and it has turned the promise held

out by respondent no.1 in the letter dated 7.3.2019, the promise to

award the project with condition of GoI approval, into a binding

contract in terms of Section 7 of the Contract Act. It is the LoA which

would create binding obligations for respective parties and which

would conclude a contract. When acceptance of bid is communicated

without mention of Letter of Award and there is a dispute about what

it means, the Court is required to examine it's contents in the light of

the relevant clauses of the bidding documents and intention of the

parties discernible from their conduct and attending facts and

circumstances of the case. As said earlier, the letter dated 7.3.2019

fits into all the parameters and requirements of clause 3.3.5 read

with clause 3.3.6, except the post bid condition of GoI approval, not

part of the RFQ and RFP, which was really meant for, not the

petitioners, but the respondent no.1. A post bid condition like the

contract being subject to further approval of GoI regarding land

alienation and SPV formation, without saying anything about it's

rationale and permissibility, when accepted by the Selected Bidder

and Concessionaire as it is and without any qualification, would

47 wp1723.20.odt

result into a binding contract between the parties. Thereafter, the

burden to obtain approval from GoI would be on the party which has

put such a condition and in case approval is refused, at the most, it

would enable the party stipulating the condition to save itself from

the ignominy of paying damages. But, a post-bid condition like the

present one, would not stop the contract from coming alive. At the

most, it may affect the excutability and workability of a contract, and

that too, when the approval is expressly refused, and not otherwise.

40. As regards the approval of GoI mentioned in the letter

dated 7.3.2019, we must say, there is force in the argument of the

learned Senior Advocate for the petitioners that the approval of GoI

appears to be a formality considering the background facts discussed

earlier. We must say it here that petitioners have not said that

approval is not necessary. What they have said is that it is only a

formality. The MoU dated 18.12.2008 shows that it was agreed

between MoCU and AAI of one part and GoM and MADC of other

part to transfer Nagpur Airport to the JVC to be formed, which is now

Respondent no.1 and that parties would take all necessary steps to

transfer Nagpur Airport along with all it's land and other assets to the

JVC in 180 days of the date of the MoU. This was followed by Union

48 wp1723.20.odt

Cabinet giving it's approval for transfer of the Nagpur Airport to the

proposed JVC on 17.1.2008. This approval also permitted the

proposed JVC to involve a strategic partner on build, operate and

transfer basis for development of Nagpur Airport to world class

standards. The JVA dated 22.2.2009, by virtue of which respondent

no.1 was constituted, made it clear that further development of

Nagpur Airport would be undertaken by the respondent no.1 after all

the assets of the Airport were transferred to it and such development

of the Airport would be through a Developer with whom the

respondent no.1 would enter into a Concession Agreement and who

would be selected through competitive bidding for highest revenue

share as per standard methodology for development of Airports,

using the standard bidding documents and procedures, including

RFQ, RFP and CA, already approved by the GoI. On 6.8.2009, the

assets of the AAI pertaining to the Nagpur Airport were also handed

over. On this backdrop, it would be gee-whiz naivete to say that

seeking of approval regarding land alienation was a serious business

for respondent no.1 to do. Ordinarily, it would be a matter of course,

except for some extra-ordinary reasons interjecting between

respondent no.1 and the petitioners, which was never the case here

as there was no letter sent by respondent no.1 to GoI seeking latter's

49 wp1723.20.odt

formal approval and admittedly, there was no refusal of approval

whatsoever by the respondent no.1.

41. Coming back to the manner in which the bid process was

conducted, we find it worthy to note that respondent no.1 had

declared that the bidding process would be governed by the

approved documents including the RFQ and the RFP; that the bidders

had, believing in this declaration, submitted their bids and, therefore,

reasonable expectation of any bidder including the petitioner no.1

would be that these documents were treated by the party issuing the

documents with sanctity that they deserved. These documents laying

down a frame-work of rules of completion of bidding process

obligated not only the bidders but also the employer of the contract

who invited offers from the tenderers, to abide by the rules of the

game. The rules were framed by the employer and accepted by the

bidders and the sanctity of the rules and morality of law required the

parties, especially the State of which respondent no.1 is an

instrumentality, to adhere to the rules, and not deviate from them,

without any reason of extra-ordinary nature like some unforseen

event not within the power and control of parties overtaking the

bidding process. This is a principle of law which applies with greater

50 wp1723.20.odt

force to the State which is a willing party to a contract. Observations

of Hon'ble Apex Court, as they appear in paras 22 and 24 of it's

Judgment in Kumari Shrilekhavidyarthi vs. State of U.P., (1991) 1

SCC 212 would elucidate the point and they are extracted as below :

" The impact of every State action is also on public interest. It is really the nature of its personality as State which is significant and must characterize all its actions, in whatever field, and not the nature of function, contractual or otherwise which is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters."

Such obligation of the State flows from the very nature of it's

Constitutional power and it's duty to act fairly under Article 14.

After all, the Government is nevertheless the Government; and it's

every action has a public element in it and the legality and morality

of it's Constitutional power would not let it go astray from it's

Constitutional duty [see Kasturilal Lakshmi Reddy .vs. State of J & K

(1980) 4 SCC 1, (para 11) and M/s. Motilal Padampat Sugar Mills

51 wp1723.20.odt

Co. Ltd. vs. State of Uttar Pradesh and Others reported in (1979) 2

SCC 409, (para 24)]

42. Clause 3.3.5 of the RFP did not contain any condition

that the Letter of Award shall be issued subject to further approval of

the Government of India regarding land alienation and formation of

SPV and yet this condition was inserted in the letter dated 7.3.2019.

But, this condition, a bare reading of it would suffice, was of such a

nature as had no bearing upon performance by the Selected Bidder

and the Concessionaire of the obligations resulting from acceptance

of it's bid in terms of clause 3.3.5. We may reiterate here that letter

dated 7.3.2019 has all the characteristics of LoA as envisaged under

the clauses 3.3.5, 3.3.1 and 3.3.6 of the RFP. These characteristics

were in the nature of the highest bidder being appointed as the

Selected Bidder, the requirement of clause 3.3.5 coming into

operation upon such selection, communication of acceptance of bid

in duplicate via sending a letter, which is of the date 7.3.2019 here

thereby requiring the petitioner no.1 to return the duly signed

duplicate copy of the letter within seven days of it's receipt, calling

upon the petitioner no.1 to execute the Concession Agreement

within the stipulated period and also to furnish performance security

52 wp1723.20.odt

within the time prescribed in the concession agreement. All these

requirements of clause 3.3.5 r/w. Clauses 3.3.1 and 3.3.6 were met

in the present case except for two deviations discussed earlier. The

first deviation is of the GoI approval and the second of the reckoning

of the time of sixty days from the intimation about GoI approval,

instead of from the date of issuance of the letter. But, this departure

from the RFP, going by the principles of law referred to earlier, was

not permissible and was unreasonable, there being no extra-ordinary

reason to justify it, on the touchstone of Article 14. Even on their

own merits, these deviations at the most cast a duty on respondent

no.1 to obtain the approval of the GoI at the earliest, which was

almost a formality, and in their worst consequence, the consequence

of rejection of the approval, the fall out would have been that of

inexecutability of the contract for reasons attributable to the GoI and

not the petitioner no.1, though that possibility never saw the light of

the day, as there was no refusal of approval anytime by the GoI. But,

for that matter, there is no gain saying that by issuing the letter

dated 7.3.2019, no conclusion of contract visited the parties as an

inevitable consequence of it.

43. Under Section 7 of the Indian Contract Act, 1872, in order

53 wp1723.20.odt

to convert a proposal into a promise, acceptance must be absolute

and unqualified and it should be expressed in some usual and

reasonable manner and if manner of expression of acceptance is

prescribed in the proposal, the acceptance has to be made in the

prescribed manner. In this case, the manner of acceptance of

proposal was prescribed in clause 3.3.5 of the RFP and it ought to

have been followed by the respondent no.1. But, the proposal of

petitioner no.1 was accepted by respondent no.1 subject to the

further approval of the GoI. This acceptance was nevertheless

substantially in the manner prescribed in clause 3.3.5, except for

insertion of condition of GoI approval. Even this condition was

accepted by petitioner no.1 in an unqualified manner when it

signified it's such unconditional acceptance by it's signing the

duplicate copy of the letter and returning it to the respondent no.1

within seven days. This act of the petitioner no.1 fulfilled the

requirements of Section 7 of the Contract Act.

The discussion thus far made has impelled us to find that

the letter dated 7.3.2019 is nothing but a Letter of Award in terms of

clause 3.3.5 of the RFP.

54 wp1723.20.odt

44. At this juncture, we would like to elaborate upon the

aspect of the condition of the GoI approval, though in some measure

it may sound to be an exercise in repetition of what we have said

earlier. But, that seems necessary, in our considered view. The

condition of further approval of the GOI had no bearing whatsoever

upon the performance of obligations of the Selected Bidder and

Concessionaire like the petitioner no.1 so appointed by the letter in

question and the burden was only upon the respondent no.1 to

obtain the requisite approval. But, pending such approvals, could it

be said that no binding contractual relations flowing from a

concluded contract between the parties came into being ? After all,

there is a difference in forging of a contact between the parties and

it's execution being frustrated by something not within the control of

the parties to the contract. It would then mean that if the approval is

obtained, the contract is on and the Concessionaire has to take

further steps which in this case would be such as furnishing of

performance security, execution of the Concession Agreement and

actual execution of the awarded contract in the manner prescribed

under the terms and conditions of the Concession Agreement. If the

approval is rejected, it would only lead to frustration of the contract

with attendant consequences. But, here, in this case, it is an

55 wp1723.20.odt

established fact that not a single letter was sent by the respondent to

the GOI seeking it's specific approval regarding land alienation. An

explanation has been given in this regard that considering the

observations made in the meeting subsequently held on 30.8.2019,

chaired by the Secretary of MoCA at New Delhi, such approval was

not sought. In fact, after issuance of the letter dated 7.3.2019, which

was done upon due evaluation of the offer of highest revenue share

by the petitioner no.1 from out of two bidders; due consideration of

implications of the offer; and due deliberations over the offer, made

in the meeting of the PMIC held on 5.3.2019, there was no reason for

questioning the financial viability of the project, as was done in the

meeting of the PMIC held on 30.8.2019, which as a fact has come out

for the first time in the reply of respondent no.1. We wonder if this

was done as an after thought or an excuse to not abide by the rules of

the game. Whatever be the intent, giving of reason of financial

impracticability of the offer after it's acceptance, was something

which was external to the whole bidding process rendering it

meaningless and aimless thereby raising a question why on earth it

was initiated at all and taken to it's logical end in issuance of letter

accepting the highest bid, substantially in terms of clause 3.3.5 of the

RFP ? But, the fact remains that the bidding process was initiated as

56 wp1723.20.odt

per the RFQ and RFP and was concluded by issuance of the letter

dated 7.3.2019 substantially in terms of the RFP. The condition of

the GoI approval was a post-bid condition, not a part of the bidding

documents and was almost a formality in view of earlier discussed

background facts, and in any case, it having been accepted as it is by

the petitioner no.1, it was to be fulfilled only by the respondent no.1

and not by the petitioner no.1, all of which did not prevent the

binding contract from coming into existence. In such a case, we are

of the view that it does not lie in the mouth of respondent no.1 to say

that the letter of acceptance dated 7.3.2019 is conditional and

qualified and therefore, does not result into any concluded contract

between the parties. If it is conditional, it is so only from the view

point of the respondent no.1 and not the petitioners. But even this

argument pales into obscurity once we consider the unqualified

acceptance given by the petitioner to the said additional post-bid

condition.

45. Apart from what is stated above, letter dated 7.3.2019

leaves no choice with the petitioner no.1 to reject it without suffering

the consequence of forfeiture and appropriation of the bid security

amount furnished by the petitioner no.l with no claim available

57 wp1723.20.odt

against the respondent no.1 as regards such forfeiture. This is really

a Hobson's choice; a choice to show on face but a compulsion

beneath the face. This condition of letter dated 7.3.2019 was in

accordance of clause 3.3.5, and it being what it was, the petitioner

no.1 accepted as it was. Now, can the respondent no.1 justifiably say

that letter dated 7.3.2019 was a harmless communication only

informing petitioner no.1 that it's bid was accepted and nothing

more? The answer is no, given the consequences that are threatened

to visit petitioner no.1, if it rejected the acceptance. It, therefore,

does not matter that the letter dated 7.3.2019 does not contain the

sentence "Letter of Award is issued to you". It is the intention of the

parties which, together with spirit and substance of an act, decides

the nature of an act. The forfeiture clause together with the contents

of the said letter and attending circumstances clearly points out that

the intention of the parties was to treat the said letter as Letter of

Award and they proceeded further considering it to be so,

irrespective of it's nomenclature and some play of words in it.

46. We, therefore, find that the letter of acceptance dated

7.3.2019 is indeed a Letter of Award and not a letter merely

communicating that the bid is accepted and this Letter of Award has

58 wp1723.20.odt

resulted into a concluded contract between the parties.

47. The conclusion so reached by us is further fortified by the

subsequent conduct of the parties showing the real intention of the

parties in issuance and acceptance of the letter dated 7.3.2019. We

have made an elaborate discussion of such conduct of the parties in

the later paragraphs of this judgment. Suffice it to say it here that

respondent no.1, by giving it's concurrence to the petitioner no.1 to

incorporate petitioner no.2 as SPV for execution of the CA and

implementation of the project, by exchanging draft CA and

requesting the petitioner no.1 to extend the Bank Guarantee from

time to time and so on, and petitioner no.1 positively responding to

same, has made it's intention loud and clear that the letter dated

7.3.2019 is not a letter which merely informs the petitioner no.1 that

it's bid has been accepted and nothing more. In fact, this letter, as

guaged from the conduct of the parties post it's issuance, accentuates

the intention of the respondent no.1 rather than slighting it, that the

respondent no.1 as well as the petitioner always meant, understood

and acted upon it like a Letter of Award resulting into a concluded

contract between the parties.

59 wp1723.20.odt

48. Now, let us turn to the cases relied upon by respondents

to support their case that the letter dated 7.3.2019 is not a Letter of

Award. They are :

(I) Rishi Kiran Logistics Private Ltd. vs. Board of Trustees Kandla Port Trust and Others, (2015) 13 SCC 233.

(II) Padia Tumber Company Private Limited .vs. Board of Trustees of Vishakhapatnam Port Trust, (2021) 3 SCC 24.

(III) PSA Mumbai Investment PTE. Ltd. vs. Board of Trustees of the Jawaharlal Nehru Port Trust and another, (2018) 10 SCC 525.

49. In the case of Rishi Kiran Logistics Private Ltd. (supra), the

Hon'ble Supreme Court has held in the facts of that case that there

was no concluded contract having come into existence as a matter of

fact and even if it was assumed for the sake of argument that there

was indeed such a contract, mere termination thereof could not be

considered as arbitrary, as a concluded contract when terminated in

a bona fide manner may amount to breach of contract and certain

consequences may follow thereafter under the Law of Contract, and

then the remedy for breach thereof would not be by invoking Writ

jurisdiction but by approaching a Civil Court.

60 wp1723.20.odt

50. The facts in the case of Rishi Kiran Logistics Private Ltd.

would, however, show that they are different from the facts of the

present case. In that case, the tenders were invited by Kandla Port

Trust for allotting it's plots on leasehold basis for a period of 30 years

for the purpose of enabling the allottees to put up construction of

liquid storage tanks. After considering the bids of various tenderers,

the letters of intent were issued to various successful bidders. The

letter of intent, however, mentioned that "formal letter" will be

issued after receipt of CRZ clearance. It was in the context of these

facts, the Hon'ble Apex Court held that the letter of intent which said

that the final allotment would be made later by issuing a "formal

letter" after obtaining of CRZ and other clearances, only displayed an

intention to enter into a contract at a later stage. In the present case,

there was no rider stated in the letter dated 7.3.2019 that "final letter

of acceptance or award of contract would be issued after obtaining

the approval from the GOI." Therefore, to this extent, in our

respectful submission, no assistance could be sought by the

respondents from the said case of Rishi Kiran Logistics Private Ltd.

But, even in this case, the Hon'ble Supreme Court has held that

whenever a case involves public law element, the Writ jurisdiction of

the High Court would be available.

61 wp1723.20.odt

51. In the case of Padia Timber Company Private Limited

(supra), it was held on facts that there being a conditional acceptance

of offer, there was no concluded contract between the parties, when

the condition was not accepted by any of the parties. The facts of this

case disclose that the contract that was to be awarded was for supply

of the sleepers to the Port Trust and offer of the lowest bidder therein

was accepted by the Port Trust subject to the condition that the

bidder would have to make delivery of the wooden sleepers at the

place of the Port Trust by transporting them by road at his cost and

final inspection would be made at the general store of the Port Trust.

These conditions were not as per the bidders offer and were not

accepted by the bidder. In this context of the facts, it was held that

the acceptance of offer of the bidder was conditional and the

condition not having been accepted by the bidder, no concluded

contract between the parties flowed from the conditional acceptance

by the Port Trust. We have already noted the facts of the present

case which are different from the said facts of Padia Timber

Company Private Limited and therefore, in our humble opinion, the

case of Padia Timber Company Private Limited would render no

assistance to the case of the respondents.

62 wp1723.20.odt

52. The respondents placing heavy reliance upon the case of

PSA Mumbai Investments PTE. Limited (supra), have maintained that

ratio of this case squarely applies to this case. In the said case, it is

held that under Section 7 of the Indian Contract Act, 1872, a

proposal would not be converted into promise unless the acceptance

is absolute and unqualified. It is further held on facts of the case that

there was no absolute and unqualified acceptance by the Letter of

Award. Learned Senior Advocate for respondent nos. 1 and 2 has

submitted that the decision in the case of PSA Mumbai Investments

PTE. Limited clinches the issue involved here in favour of the

respondents. He has submitted that the RFP documents which were

considered in the case of PSA Mumbai Investments PTE. Limited

contained almost similar clauses as the RFP which governs the

present case and the Hon'ble Supreme Court, after considering

various clauses thereof, has found that the bidding process was not

concluded therein. It would be, therefore, necessary for us to

consider the facts of the case of PSA Mumbai Investments PTE.

Limited (supra).

53. The facts of the afore-stated case would show that there

63 wp1723.20.odt

was a Consortium of appellant and respondent no.2 which had

submitted it's bid for award of contract of Fourth Container Terminal

Project on DBFOT basis at Jawaharlal Nehru Port and since it's offer

was found to be most favourable from the financial view point, Letter

of Award dated 26.9.2011 was issued by respondent no.1, the

Jawaharlal Nehru Port, to the Consortium of appellant no.1 and

respondent no.2. Some problem as to exact stamp duty between the

parties arose as a result of which there was some delay in signing the

agreement document. The facts further show that respondent no.2

therein opted out of the bid process and on being informed about the

same, respondent no.1 therein, by letter dated 30.4.2012, indicated

to the appellant therein that the appellant would be left as the sole

bidder and, therefore, it should be ready to form Special Purpose

Vehicle for entering into and execute the contract in the form of Draft

Concession Agreement. However, this letter was made conditional

upon the Ministry of Shipping according it's approval. The appellant

therein anticipated that such approval would be given and therefore,

by letter dated 30.5.2012, the appellant therein informed the

respondent no.1 therein that it had, in fact, incorporated another

Special Purpose Vehicle to execute and perform the Concession

Agreement. However, as things turned out to be, the Ministry of

64 wp1723.20.odt

Shipping refused to accord it's approval and the appellant was

informed by letter dated 30.8.2012 that the Ministry of Shipping had

refused to grant it's approval regarding change of constitution of the

bidder as from a Consortium to a single entity. Thereafter, on

18.9.2012, the bid security given by the consortium was encashed by

respondent no.1 therein for recovery of which, a suit was filed by the

appellant therein. At that stage, the respondent no.1, by show cause

notice dated 12.9.2012, called upon the Consortium to perform it's

part of bid as originally agreed to and since this was not done, by the

letter dated 16.10.2012, the Letter of Award that was accorded and

acknowledged by the appellant therein on 29.6.2011 was

"withdrawn" by respondent no.1. Consequent to this, respondent

no.1 therein also claimed a sum of Rs.446.28 Crores by way of

damages against the Consortium and sent an arbitration notice

stating that, according to it, Clause 19 of the draft Concession

Agreement being an arbitration clause governed the parties and so

the dispute would be resolved by resorting to it. Respondent no.1

therein also indicated the name of the arbitrator that it intended to

appoint. The appellant therein did not agree that there was any

scope for arbitration, there being no agreement having been entered

into between the parties. However, by taking recourse to the

65 wp1723.20.odt

arbitration clause in the Draft Concession Agreement, the respondent

no.1 therein declared that the arbitrator appointed by it would be the

sole arbitrator to ad-judicate upon the dispute between the parties.

The arbitrator agreed with the contention of the appellant therein

and against his decision, the respondent no.1 therein filed an appeal

before the High Court under Section 37 of the Arbitration and

Conciliation Act, 1996 ,wherein the High Court held that there was a

concluded contract between the parties as the Letter of Award had

been accepted by the appellant therein and since the arbitration

clause formed part of the bid documents between the parties, the

arbitration clause governed the dispute between the parties.

54. Against this decision of the High Court, the appellant

came before the Hon'ble Supreme Court and the Hon'ble Supreme

Court, against the background of the above referred facts and

circumstances, held that the acceptance being not absolute and

unqualified, there was no Letter of Award resulting into a concluded

contract between the parties. It also held that the RFP only showed

that there was a bid process which was going on between the parties

and that the conditional acceptance by itself was not a contract

concluded between the parties, that the bid process would conclude

66 wp1723.20.odt

upon the Draft Concession Agreement finally becoming an

agreement between the respondent no.1 and the Special Purpose

Vehicle, and that the bid process might be annulled without giving

any reason whatsoever by the respondent no.1, as it had not been

concluded therein. It was in this context that it was found that there

was neither any concluded contract between the parties nor any

Concession Agreement having been executed between the parties

which would give rise to an enforceable arbitration clause.

55. In the present case, we have already found for the reasons

stated earlier that the letter dated 7.3.2019 is a Letter of Award,

which has been issued after acceptance of the bid of the petitioner

no.1 offering highest revenue share in terms of clause 3.3.5 r/w.

Clauses 3.3.1 and 3.3.6 of the RFP together with such condition as

would have no bearing upon the performance of any obligations

under the contract by the petitioner. We have also found that

intention of the parties gathered from their subsequent conduct was

that the said letter was intended to be and was in fact treated to be

the Letter of Award by the parties and that it resulted into a binding

contract between the parties, though the executability of the contract

as such depended on respondent no.1 fulfilling it's obligation to

67 wp1723.20.odt

obtain the necessary approval of the GoI. Such being not the facts of

PSA Mumbai Investments PTE. Ltd (supra), in our respectful

submissions, it would have no application to the facts of this case.

Then, in PSA Mumbai Investments PTE. Limited (supra), as the

letter of acceptance had not become the Letter of Award, the bidding

process was alive and therefore, it was held that right uptil the stage

of entering into the agreement, the bid process may be annulled

without giving any reason. In the present case, the bidding process

was terminated on reaching the stage of issuance of Letter of Award

and therefore, what was required to be done thereafter was in the

nature of further steps given in clause 3.3.6 of the RFP. These facts

also distinguish themselves from the facts involved in PSA Mumbai

Investments PTE. Limited.

56. Now, let us consider what assistance the two cases namely

the case of Har Shankar and Others and the case of Proactive In and

Out Advertising Pvt. Ltd. vs. Pune Mahanagar Parivahan

Mahamandal Ltd. reported in 2018 (6) Mh.L.J. 561 relied upon by

the petitioners, offer to us in the present case.

57. In the case of Har Shankar and Others (supra) relied upon

68 wp1723.20.odt

by the petitioners, those interested in running liquor vends offered

their bids voluntarily in the auction held for grant of licences for the

sale of country liquor. The Government accepted the bids of willing

bidders and it was held that on such acceptance the contract between

the bidders and the Government became concluded and a binding

contract came into existence between them. It was noticed that after

coming into existence of binding agreements between the parties, the

successful bidders also granted licences evidencing the terms of

contract between the bidders and the Government under which they

became entitled to sell liquor. The licencees also exploited the

respective licences presumably in expectation of the profit. However,

this venture was found later on by the appellant therein as not

profitable and that they were unable to meet the conditions of the

license, and fell in arrears. The State Government threatened to

cancel the licences granted to the appellants unless they paid the

arrears. Matter came to Supreme Court. The Hon'ble Apex Court

held that commercial considerations may have revealed an error of

judgment in the initial assessment of profitability of the adventure,

but that is a normal incident of trading transactions. It further held

that those who contract with open eyes must accept the burden of

contract along with its benefits. It further held that reciprocal rights

69 wp1723.20.odt

and obligations arising out of the contract do not depend for their

enforceability upon whether the contracting party finds it proper to

abide by the terms of contract or not or otherwise no contract could

ever have any binding force.

58. In our view, the observations of the Hon'ble Supreme

Court and what it has held in the said case of Har Shankar and

Others squarely apply to the facts of the present case. Here, the bid

of petitioner no.1 was accepted by respondent no.1 and a letter

accepting the bid was issued substantially in accordance with clause

3.3.5 of the RFP, a duplicate copy of which was duly signed by

petitioner no.1 and returned to respondent no.1. This resulted into a

binding agreement coming into existence between the parties. Once,

a contractual relationship is built between the parties, a party thereto

cannot say that the contract ought not to have been entered into,

doubting it's profitability, as has been done in this case, and that the

validity of a binding contract between the parties here cannot be

made dependent upon what a party thinks about propriety of a

contract nor can it be judged by uncertainty of it's enforceability

resulting from imposition of a post-bid condition, which is accepted

unconditionally by the petitioner no.1 and which is for the

70 wp1723.20.odt

respondent no.1 only to fulfill.

59. In the second case of Proactive In and Out Advertising Pvt.

Ltd. vs. Pune Mahanagar Parivahan Mahamandal Ltd. and Others

reported in 2018 (6) Mh.L.J. 561 referred to us by the learned Senior

Advocate for the petitioners, it was held by the Hon'ble Apex Court

that once the letter of intent issued by the respondent therein was

accepted by the petitioner therein and the petitioner promised the

respondent therein to furnish a Bank Guarantee, it was not open for

the respondent therein to cancel the tender and issue a fresh tender.

These observations would show that upon acceptance of the letter of

intent with all conditions stated therein by the bidder, a binding

agreement would come into being between the parties and

thereafter, a reverse turn is not permissible. The facts of this case

being similar to the facts involved here, in our respectful

submissions, the ratio of the case of Proactive In and Out Advertising

Pvt. Ltd. would govern the instant case.

60. In view of above, we find that the letter dated 7.3.2019

cannot be treated as a communication by the respondent no.1 which

merely informs the petitioner no.1 that the bid is accepted, rather the

71 wp1723.20.odt

said letter, in our opinion, amounts to a Letter of Award which has

led to a concluded contract between the parties. The questions (a),

(b) and (c) are answered accordingly.

Part Two

61. Now we would take up the remaining two questions,

question (d) and question (e), for their answers. These questions are

about the arbitrariness, unreasonableness and unfairness or

otherwise of the action of respondent no.1 in annulling the bidding

process by the impugned communication and involvement of

disputed questions of facts and enforceability of contractual

obligations by invoking Writ jurisdiction of this Court.

62. The impugned communication sent by the respondent

no.1 to the petitioner no.1 dated 19.3.2020 is just a three liner which

informs the petitioner no.1 that pursuant to the directives received by

the Government of Maharashtra dated 16.3.2020 and in accordance

with clause 2.16 of RFP, respondent no.1 decided to annul the

bidding process without award of contract. The petitioners have

assailed this communication on several grounds while the

72 wp1723.20.odt

respondents have stoutly defended it saying it to be within the

parameters in law.

63. Upon consideration of the contents of the impugned

communication, the conduct of parties post issuance of letter dated

7.3.2019 by the respondent no.1, the law governing the field and

also in view of our finding that the letter dated 7.3.2019 is actually a

Letter of Award which has resulted into a concluded contract

between the parties, we would say that the argument advanced on

behalf of the respondent no.1 and adopted by the respondent no.2,

does not hold any water. We have stated the reasons for this

conclusion in the following paragraphs.

64. The letter dated 7.3.2019 which amounts to the Letter of

Award has created rights in favour of the petitioner no.1 to execute,

through the SPV formed for the purpose, a Concession Agreement

and implement the project in accordance therewith. Once a binding

agreement comes into existence between the parties, as held in the

case of Har Shankar and Others (supra), it would not be open for the

employer of the contract to go back on it's promise and cancel the

contract. Sometimes financial projections and commercial

73 wp1723.20.odt

considerations of one party to the contract may be found out

subsequently to be wrong but just because of that the party which

thinks it's such calculations have gone wrong, is not permitted in law

to cancel the contract and if it does so, it must suffer the

consequences therefor. In Har Shankar and Others (supra), the

Hon'ble Supreme Court has succinctly summed up the position of the

parties to the contract when it observed, "those who contract with

open eyes must accept the burden of the contract along with its

benefits" and also when it said, "reciprocal rights and obligations

arising out of contract do not depend for their enforceability upon

whether a contracting party finds it prudent to abide by the terms of

the contract. By such a test no contract could ever have a binding

force".

65. Apart from what is stated above, the figures of profit

shown by the respondent no.1 are seriously disputed by the

petitioners and therefore, nothing can be said about their being based

upon any realistic calculations. In any case, the consideration of

financial viability of the contract arising from issuance of LoA to

petitioner no.1 cannot be made a subject matter of judicial review,

this Court not being an expert and well equipped to deal with the

74 wp1723.20.odt

same and so, we would refrain from going into it. Suffice it to say

that when such consideration is turned into one of the grounds for

annulment of the bidding process by the employer of the contract,

which is respondent no.1 here, a question arises about it's

permissibility and tenability in law on the basis of principles of

Wednesbury unreasonableness and procedural fairness when the

State or it's instrumentality is the employer of the contract. The

principle of Wednesbury unreasonableness would require a party to

contract to shun irrelevant and extraneous considerations to direct

it's actions (See Raunaq International Ltd. vs. I.V.R. Construction Ltd.

And Others, (1999) 1 SCCC 492). The principle of procedural

fairness would confine the Court to only examine whether the parties

have followed the prescribed procedure equally and without

discrimination and to not consider what is right or what is wrong or

whether the decision taken should and ought to have been taken or

not (see Tata Cellular vs. Union of India, (1994) 6 SCC 651).

66. When these parameters are applied to the present case,

what we find here is an instance of procedural unfairness and also

unreasonableness. The clauses of RFP are very clear on the subject.

Clause 2.16.1 is the clause relied upon in the impugned

75 wp1723.20.odt

communication. A careful consideration of this clause is, therefore,

necessary. It reads thus :

"2.16 Rejection of Bids :

2.16.1. Notwithstanding anything contained in this RFP, the Authority reserves the right to reject any Bid and to annul the Bidding Process and reject all Bids at any time without any liability or any obligation for such acceptance, rejection or annulment, and without assigning any reasons therefor. In the event that the Authority rejects or annuls all the Bids, it may, in its discretion, invite all eligible Bidders to submit fresh Bids hereunder. "

67. It would be clear from the above referred clause that it

empowers the Authority to annul the bidding process only when it

exercises it's right to reject any bid or all bids. It does not give any

right to the respondent no.1 to annul the bidding process

independent of it's right to reject a bid. It indicates that annulment

of bidding process may follow upon rejection of a bid or all bids at

any time. The position here, however, is quite different from the

situation contemplated in clause 2.16.1. Here, the respondent no.1

had already accepted the bid of the petitioner no.1 and therefore,

76 wp1723.20.odt

there was no question of annulment of the bidding process under this

clause. The impugned communication, however, says that the

respondent no.1 has decided to annul the bidding process without

award of contract in accordance with clause 2.16 of the RFP and also

in accordance with the directives it received from the GoM vide letter

dated 16.3.2020. This reliance on clause 2.16 shown in the

impugned communication is wrong and to the knowledge of

respondent no.1, could not have been made by it. Yet it was made.

68. There is one more clause in the RFP i.e. clause 2.6.3.,

which speaks about disqualification of a bidder or termination of LoA

issued to the Concessionaire. Under this clause, disqualification or

the termination of the LoA is possible on meeting it's requirement.

The requirement is of the bidder not fulfilling the pre-qualification

conditions or the bidder making material misrepresentations or

giving materially incorrect or false information. If any of these

requirements are met, the consequence will be of disqualification of

the bidder to whom no LoA is issued or the termination of the LoA

and also the CA, when the LoA is issued and the CA, if any, is

executed. So, here at the most, the LoA could have been terminated

on any of the grounds stated in Clause 2.6.3. But, no ground being

77 wp1723.20.odt

available thereunder, there was no termination of the LoA under

clause 2.6.3, and rightly so.

69. In the impugned communication, respondent no.1 has

also given the reason of directions issued by GoM vide it's letter

dated 16.3.2020 regarding re-tendering of the work following which

the impugned communication was issued. Learned Senior Advocate

for the respondent no. 1 has taken us through this communication

and also the minutes of the meeting held on 30.8.2021 under the

Chairmanship of Secretary, MoCA, record note of discussions in

respect of PMIC meeting held on 14.10.2019 and the documents

reflecting the calculations made by respondent no.1 with the help of

it's Auditor and Transaction Advisor regarding financial viability of

the contract.

70. We must point out here that the GoM was not a party to

the bidding process as could be seen from the RFQ and RFP and it

could not have been a party in view of object and purpose for which

the JVC i.e. respondent no.1 was formed and the sole authority given

to the respondent no.1 to be the anchor, driver and master of the

process of development of Nagpur Airport to be undertaken by it by

78 wp1723.20.odt

selecting a Developer. A detailed narration of the relevant facts in

this regard has already been made by us in the Historical Facts

chapter of this Judgment. We are, therefore, of the opinion that the

GoM could not have taken upon itself to decide about re-tendering of

the project and should have left it to the discretion of the JVC i.e.

respondent no.1 to decide about it in accordance with the rules of

game as regulated by the RFQ and RFP. But, the GoM in fact did it,

albeit without any authority or right in law or under the contract, at a

time when the contractual obligations had come into play. This

action on the part of the GoM was arbitrary and unreasonable and

therefore, was not within it's Constitutional power.

71. Besides, all the acts as reflected in above-referred

documents having been not contemplated in any manner under the

RFQ and RFP, which together constitute a framework of rules within

which the tender process was required to be proceeded and

completed, could not have been made any basis for taking a decision

to annul the bidding process. All the acts as evidenced by these

documents are external and irrelevant for completion of the bidding

process as per the rules prescribed and the procedure laid down in

the RFP, in as much as, limits of our power of judicial review, would

79 wp1723.20.odt

not permit us to go into them. This is where we find that there is a

fundamental flaw in the procedure adopted by the respondent no.1

in cancelling the bidding process which has amounted to cancellation

of the LoA issued in favour of the petitioner no.1. Then, the

respondent no.1 knew that the grounds that it were taking to annul

the bidding process could not have been taken by it under the terms

and conditions prescribed in the RFP and also under the law

governing the field. But still, it resorted to those grounds while

issuing the impugned communication. Therefore, we are of the view

that the impugned communication suffers from the vice of

arbitrariness and unfairness as contemplated by Article 14 of the

Constitution of India. It also exhibits unreasonableness of the degree

required for attracting the principle of Wednesbury

unreasonableness, as irrelevant considerations were taken into

account and relevant considerations as governed by the RFP were

ignored while arriving at a decision of cancellation of the bidding

process and the LoA issued to the petitioner no.1.

72. In the case of Smt. S.R.Venkataraman .vs. Union of India

and another reported in (1979) 2 SCC 491, the Hon'ble Supreme

Court has held that legal malice means such malice as may be

80 wp1723.20.odt

assumed from the doing of a wrongful act done intentionally but

without just cause or excuse, or for want of reasonable or probable

cause. In another case of State of A.P. and Others vs. Goverdhanlal

Pitti reported in (2003) 4 SCC 739, it is held by the Hon'ble Supreme

Court that legal malice or malice in law means "something done

without lawful excuse". In other words, the Hon'ble Apex Court held,

"it is an act done wrongfully and wilfully without reasonable or

probable cause, and not necessarily an act from ill-feeling and spite.

It is a deliberate act in disregard of the rights of others."

73. Facts noted above would show that the impugned

communication is also hit by the principle of legal malice as

explained in above referred cases. The respondent no. 1 knew that it

could not annul the bidding process under clause 2.16.1 without first

rejection of the bid, that it could not draft in decision of a party

stranger to contract to cancel the LoA; and yet it did after acceptance

of the bid, without any lawful cause and in a deliberate disregard of

the rights of the petitioner no. 1.

74. There is another aspect of the impugned communication.

It relates to the conduct of the parties. On 20.3.2019, an email was

81 wp1723.20.odt

sent by the respondent no.1 to the petitioner no.1 wherein it

forwarded in pdf format the final Concession Agreement

incorporating the corrigendum issued by it to the petitioner no.1.

There is a correspondence between the respondent no.1 and the

petitioner no.1, copies of which are filed on record and about which

there is no dispute. It shows that the bank guarantee issued towards

bid security to be furnished by the petitioner no.1 was renewed from

time to time at the request of respondent no.1 with last email sent in

this regard by the respondent no.1 to the petitioner no.1 being on

30.1.2020, in response to which, the petitioner no.1 got extended the

Bank Guarantee till 30.4.2020. An email sent on 29.5.2019 by the

respondent no.1 to the petitioner no.1 showed that as per the request

of petitioner no.1, the respondent no.1 sent to it a soft copy of the

Concession Agreement to enable the petitioner no.1 to make the

necessary corrections in the draft Concession Agreement. The letter

dated 13.6.2019 sent by the petitioner no.1 to respondent no.1

disclosed that the list of discrepancies observed in the final draft

Concession Agreement and the list of details to be filled in at the time

of signing of the Concession Agreement, were exchanged between

the parties and it was informed that necessary changes in MS-Word

version of draft Concession Agreement were incorporated by the

82 wp1723.20.odt

petitioner no.1. By the letter dated 29 th July, 2019, the petitioner

no.1 made a request to the respondent no.1 to grant it's concurrence

to proceed with the SPV formation so as to enable the petitioner no.1

to sign the Concession Agreement at a short notice upon receipt of

intimation from respondent no.1 as mentioned in the LoA. By the

letter dated 5th August, 2019 addressed by the respondent no.1 to the

petitioner no.1, no objection regarding incorporation of a Company

by name GMR Nagpur International Airport Ltd. (petitioner no.2) for

the purpose of execution of Concession Agreement with respondent

no.1 subject to fulfillment of other conditions stated in the letter

dated 7.3.2019 and the RFP was communicated to petitioner no.1. By

the letter dated 16.8.2019, the respondent no.1 communicated to the

Ministry of Corporate Affairs, Government of India that it had no

objection for the proposed GMR Nagpur International Airport Ltd. to

use address "1st Floor, Old Terminal Building, Dr.Babasaheb

Ambedkar International Airport, Nagpur" as it's registered Office

address. By this very letter, the respondent no.1 also gave it's no

objection that the said "GMR Nagpur International Airport Ltd."

would carry out it's business activities from the said address. It also

certified that the respondent no.1 was in possession of the premises

located at the said address. By the letter dated 24.8.2019, the

83 wp1723.20.odt

petitioner no.1 informed the respondent no.1 that it has promoted

and incorporated a wholly owned subsidiary Company named "GMR

Nagpur International Airport Limited", which would execute the

Concession Agreement with the respondent no.1 as a Concessionaire.

It also sent therewith a copy of Certificate of Incorporation of the said

subsidiary Company, which was SPV as contemplated under the RFQ.

75. Of course, there is an objection taken by the learned

Senior Advocate regarding formation of SPV in terms of the RFQ and

the RFP. He draws our attention to clause 2.2.6 of the RFQ and the

footnote appearing below it, which clarifies that Mihan Limited

Nagpur i.e. respondent no.1 and the Selected Bidder i.e. petitioner

no.1 shall, subject to and in accordance with the bidding documents,

subscribe to such shareholding in the subscribed and paid up capital

of the SPV as required to own and hold, legally and beneficially, to

the extent of 26% and 74% respectively in the share capital of the

SPV. He submits that in the SPV so incorporated, the condition of

26% and 74% share holding of the respondent no.1 and the

petitioner no.1 respectively has not been fulfilled and therefore, the

SPV has not been properly formed. The contention, in our opinion, is

incorrect. The SPV has been formed with due approval given by the

84 wp1723.20.odt

respondent no.1 and while giving the approval, the respondent no.1

never questioned the composition of shareholding and never put any

condition about the shareholding at the time of formation of SPV.

Respondent no.1 has given it's no objection to the petitioner no.1 to

use it's Office address and carry out it's business activities from it's

premises at Nagpur. Not only that, the respondent no.1 also

accordingly informed the Ministry of Corporate Affairs, Government

of India regarding formation of the SPV. In none of these letters, the

respondent no.1 raised any issue about percentage of shareholding.

Such a conduct of respondent no.1 together with what is indicated by

footnote below clause 2.2.6 of the RFQ would show that the issue of

shareholding was not to come in the way of formation of SPV and it

was to be sorted out later on. Such a conclusion is further bolstered

up by what is stated in clause 5.4.1 of the draft Concession

Agreement which, as per the RFP, is part of the bidding documents.

"5.4 Obligations relating to Shareholding of the Authority :

5.4.1. The Concessionaire and the Selected Bidder shall execute an agreement with the Authority, substantially in the form specified at Schedule S ("Shareholders' Agreement"), providing for the issue and allotment of one

85 wp1723.20.odt

non-transferable equity share of the Concessionaire ("Authority's Share") in favour of the Authority and/or its nominee, and shall inter-alia also provide for the following:

(a) appointment of nominee(s) of the Authority on the Board of Directors of the Concessionaire;

(b) an irrevocable undertaking that the rights vested in the Authority shall not be abridged, abrogated or in any manner affected by any act done or purported to be done by the Concessionaire or any of its Associates or Affiliates;

(c) an irrevocable undertaking that any divestment of Equity in the Concessionaire shall not in any manner affect the rights of the Authority herein and that the successors, assigns and substitutes of the Selected Bidder and the Concessionaire shall be bound by such undertaking; and

(d) any other manner mutually agreed upon between the Parties. "

76. This clause stipulates that the Concessionaire and the

Selected Bidder shall execute an agreement with the Authority i.e.

respondent no.1 substantially in the form specified in Schedule S

86 wp1723.20.odt

(Shareholder's agreement), providing for the issue and allotment of

one non-transferable equity share of the Concessionaire ("Authority's

Share") in favour of the Authority and/or its nominee and also other

mutually agreed matters. It would then follow that the SPV was duly

formed by the petitioner no.1 with the object of execution of the

Concession Agreement and implementation of the project as

contemplated by the RFP and the issue of shareholding could be

mutually sorted out later.

77. Reverting to the conduct of the parties post issuance of the

LoA dated 7.3.2019, as revealed by the earlier mentioned

documents, we would say that the only conclusion that is possible

from such conduct is that the parties not only intended that the

letter dated 7.3.2019 be the Letter of Award which awards the

contract, but the parties also acted upon it pushing forward the

contract towards execution of the Concession Agreement by the

petitioner no.2. It further showed that believing in the promise given

by the respondent no.1, the petitioner no.1 altered it's position and

incorporated the SPV. Petitioner no.1 went on to carry out several

other acts as a consequence to the issuance of LoA. It obtained no

objections regarding use of Office address and Office space of

87 wp1723.20.odt

respondent no.1 at Nagpur and got extended the Bank Guarantee

given towards bid security at the request made by the respondent

no.1 from time to time. Such conduct of the petitioner no.1, we have

to say, would give rise to application of principle of promissory

estoppel against the respondent no.1 which is an instrumentality of

the State, and now the respondent no.1 is estopped from going back

on it's promise to award the contract, which in fact it already has

given.

78. In the case of M/S. Motilal Padampat Sugar Mills Co. Ltd.

(supra), the Hon'ble Supreme Court held that where the Government

makes a promise knowing or intending that it would be acted upon

by the promisee and, in fact, the promisee acting in reliance of it,

alters his position, the Government will be held bound by the

promise of the promisee, notwithstanding that there is no

consideration for the promise and the promise is not recorded in the

form of a formal contract as required by Article 299 of the

Constitution. It also held that if the Government makes a promise

and the promisee acts in reliance upon it and alters his position,

there is no reason why the Government should not be compelled to

make good such promise like any other private individual. It was

88 wp1723.20.odt

observed that the law cannot acquire legitimacy and gain social

acceptance unless it accords with the moral values of the society. It

also held that the doctrine of promissory estoppel being an equitable

doctrine, it would yield when the equity so requires and that means if

it is shown by the Government that having regard to the facts of the

case it would be inequitable to hold Government liable to the

promise made by it, the Courts would not raise equity in favour of

the promisee and enforce the promise against the Government.

These observations appear in paragraph 24 of the Judgment. For the

sake of convenience, a portion of para 24 is extracted as below :

"The law may, therefore, now be taken to be settled as a result of this decision, that where the Government makes a promise knowing or intending that it would be acted on by the promisee and, in fact, the promisee, acting in reliance on it, alters his position, the Government would be held bound by the promise and the promise would be enforceable against the Government at the instance of the promisee, notwithstanding that there is no consideration for the promise and the promise is not recorded in the form of a formal contract as required by Article 299 of the Constitution. It is elementary that in a republic governed by the rule of law, no one, howsoever high or low, is above the law. Every one is subject to the

89 wp1723.20.odt

law as fully and completely as any other and the Government is no exception. It is indeed the pride of constitutional democracy and rule of law that the Government stands on the same footing as a private individual so far as the obligation of the law is concerned: the former is equally bound as the latter. It is indeed difficult to see on what principle can a Government, committed to the rule of law, claim immunity from the doctrine of promissory estoppel. Can the Government say that it is under no obligation to act in a manner that is fair and just or that it is not bound by considerations of "honesty and good faith"? Why should the Government not be held to a high "standard of rectangular rectitude while dealing with its citizens"? There was a time when the doctrine of executive necessity was regarded as sufficient justification for the Government to repudiate even its contractual obligations, but let it be said to the eternal glory of this Court, this doctrine was emphatically negatived in the Indo-Afghan Agencies case and the supremacy of the rule of law was established. It was laid down by this Court that the Government cannot claim to be immune from the applicability of the rule of promissory estoppel and repudiate a promise made by it on the ground that such promise may fetter its future executive action. If the Government does not want its freedom of executive action to be hampered or restricted, the Government need not make a promise knowing or intending that it

90 wp1723.20.odt

would be acted on by the promisee and the promisee would alter his position relying upon it. But if the Government makes such a promise and the promise and the promisee acts in reliance upon it and alters his position, there is no reason why the Government should not be compelled to make good such promise like any other private individual. The law cannot acquire legitimacy and gain social acceptance unless it accords with the moral values of the society and the constant endeavor of the Courts and the legislatures must, therefore, be to close the gap between law and morality and bring about as near an approximation between the two as possible. The doctrine of promissory estoppel is a significant judicial contribution in that direction. But it is necessary to point out that since the doctrine of promissory estoppel is an equitable doctrine, it must yield when the equity so requires. If it can be shown by the Government that having regard to the facts as they have transpired, it would be inequitable to hold the Government to the promise made by it, the Court would not raise an equity in favour of the promisee and enforce the promise against the Government."

79. In the present case, there is no equitable ground for the

respondent no.1 to take recourse to, to wriggle itself out of the

obligations which have come into play on issuance of Letter of

91 wp1723.20.odt

Award. The LoA spoke about approval of GoI in respect of

alienation of land and formation of SPV. As regards formation of

SPV, the Ministry of Corporate Affairs was duly informed by the

respondent no.1 and there being no disapproval having been given

by the GoI, it can be taken that part of the condition regarding GoI

approval of SPV has been fulfilled. In respect of other part of the

condition, respondent no.1 did not make any attempt to seek

approval of GoI as it never wrote to it specifically in that regard. No

ducment seeking approval for land alienation in a specific manner

has been placed before us. Then, it is not the case of respondent

no.1 that such approval has been refused by the GoI. All these facts

and circumstances of the case would show that there is not available

any equitable consideration for not applying the principle of

promissory estoppel. Rather, these very facts and circumstances of

the case have tilted the balance of equity in favour of the petitioner

no.1. Then, the reason of the award of contract being not a very

profitable and financially unviable proposition, apart from it being

questionable on merits considering the objections taken by the

petitioner no.1, is itself irrelevant and extraneous to various clauses

of RFP which have delineated the contingencies in which and the

conditions on which the bidding process could be annulled, and

92 wp1723.20.odt

these clauses nowhere incorporate the factor of unprofitability and

financial non-viability found subsequently after the LoA is acted

upon, as a ground for taking a reverse turn and cancel the bidding

process. On the contrary, we would say that when the LoA is issued

by communicating acceptance of bid, and in a manner prescribed in

the bidding document, which we have found substantially to be the

case here, it is presumed that the LoA has been issued by the

employer only on being satisfied about the profitability, and

workability of the bid offered by the tenderer and therefore, if the

employer seeks to wriggle himself out from such acceptance, he

could do so only on legally permissible grounds such as fraud,

misrepresentation, misconception of facts, change in law and the

like, but never on re-evaluation of the bid on merits post issuance of

LoA, as has been done here. Therefore, this ground taken

subsequently is hit by the principle of Wednesbury

unreasonableness. All these factors, in our view, make the

application of principle of promissory estoppel a reality and

necessity and accordingly, we find that the respondent no.1, which

is a State instrumentality, must be held bound by it's promise given

under LoA and as such, the LoA would be enforceable at law.

                                93                           wp1723.20.odt

80.           There       is   a    curious   thing   about      the     impugned

communication.           It states two reasons for annulment of bidding

process and cancellation of LoA and both these reasons have already

been found by us to be arbitrary and not permissible to be taken in

view of the procedure prescribed in the RFP. The first reason relates

to GoM issuing directives to re-tender the work. These directives

have been accepted and acted upon by the respondent no.1 when it

cancelled the bidding process. This shows it's non-application of

mind. The GoM was not a party to the whole bidding process and

therefore, it could not have issued such directives as elaborated by

us earlier. Then, all the documents starting from the MoU dated

18.12.2006 through the Joint Venture Agreement dated 22.2.2009

to the bidding documents including RFQ and RFP would show that,

the development of Nagpur Airport was to be carried out by the

proposed JVC, which in fact was formed and after it's formation it

was for the JVC, which is respondent no.1, to select a Developer

through competitive bidding process at highest revenue share

arrived at by standard methodology based upon standard

documents including the RFQ and the RFP already approved by the

GoI. The RFQ and the RFP also showed that it were the respondent

no.1 only which was in-charge of and master of the bidding process.

94 wp1723.20.odt

Against such overwhelming authority existing in favour of

respondent no.1 to embark upon and complete the bidding process,

there was no reason for the GoM to step in and issue directives for

re-tending of the work and even if it had, there was no reason for

the respondent no.1 to implement it without thinking about the

clauses of the RFP which authorised it to cancel the bidding process

only when those conditions were met. The respondent no.1,

however, simply implemented the directives and we would say it

did so mechanically and without any authority of law. The

impugned communication is, therefore, a no decision in the eye of

the law and it smacks of legal malice.

81. The respondent no.1 has also attempted to support it's

decision to cancel the bidding process by giving reason of

questionable financial viability of the contract. In support,

respondent no.1 has produced on record several documents to

demonstrate as to how true have been it's projections about

decrease in profitability and it's consequent increase in profitability,

if LoA is cancelled and the work is re-tendered. The impugned

communication, however, makes not even a whisper about all these

projections and therefore, they cannot be taken into account on the

95 wp1723.20.odt

basis of the principle that when a statutory functionary makes an

order based on certain grounds, its validity must be judged by the

reasons so mentioned and it cannot be supplemented by fresh

reasons in the shape of affidavit or otherwise as propounded in the

case of Mohinder Singh Gill and Others vs. the Chief Election

Commissioner, New Delhi and Others reported in (1978) 1 SCC 38.

That apart, it does not lie within the power of this Court to examine

them in any manner, this Court not being a financial expert.

82. There are also other factors which must be considered. If

any query has been raised in the meeting held on 30.8.2019 at New

Delhi, and justification was sought regarding post bid negotiations,

changes made in the eligiblity criteria at the RFQ and the RFP stage,

deviation from the standard documents and the current financial

standing of respondent no.1 and justification to lease out the

Airport, we ask a question - Would it not have been appropriate for

respondent no.1 to have called upon the petitioner no.1, being a

Concessionaire in whose favour the LoA dated 7.3.2019 has been

issued and much water has flown from under the bridge after

issuance of the LoA dated 7.3.2019, to submit it's say in respect of

these issues. The answer has to be given in the affirmative. By

96 wp1723.20.odt

issuance of the LoA dated 7.3.2019, a civil right regarding execution

of Concession Agreement and implementation of the project through

the SPV had arisen in favour of the petitioner no.1 and therefore,

there was a possibility of the petitioner no.1 being adversely affected

by some decision that may have been taken in the said meeting.

But, the petitioner no.1 was never asked to submit it's explanation

regarding the doubts expressed by the MoCA and this does not

speak of good governance on the part of the respondent no.1, which

it is obliged to exhibit, it being bound by rule of law. In the case of

Mohinder Singh Gill and another (supra), it is held that when a civil

right is likely to be adversely affected, an invocation of audi alteram

partem rule is a necessity. But, this rule, in the peculiar facts and

circumstances of this case, though attracted, was ignored.

83. At this stage, we would like to deal with the argument

made by learned Senior Advocate that by not extending the Bank

Guarantee beyond 30.4.2020 and not furnishing any performance

security, the petitioner no.1 has acquiesced in the decision of the

respondent no.1 to cancel the bidding process. He has also

submitted that even the Concession Agreement was not executed by

the petitioner no.1 and therefore, the fault also lay with the

97 wp1723.20.odt

petitioner no.1. The argument is incorrect and deserves to be

rejected. Performance security could not have been furnished till

the CA was executed and the CA could not have been executed

unless written intimation of approval was given to the petitioner

no.1 and therefore, what was not in the hands of the petitioner no.1

cannot be made a ground to find any fault with the petitioner no.1.

There is also no question of acquiescence for the reason that even

after cancellation of the bidding process for about more than a

month, the Bank Guarantee had remained valid and the annulment

of bidding process having had taken it's toll on the petitioners, there

was no reason for them to get extended the Bank Guarantee just for

the heck of it. The argument is, therefore, rejected.

84. The respondents have also taken an objection to the

petitioners' not making GoI through MoCA a party. The objection

carries no weight and has no meaning as the petitioners have not

asked for anything from the GoI or MoCA, which could be seen from

the prayers made in the petition. Besides, they have not done

anything which has affected the rights of the petitioner. Whatever

the MoCA did was to ask for some justification from the respondents

which was not given by them and a decision was straightway taken

98 wp1723.20.odt

not by the MoCA but by the respondent no.2 to cancel the bidding

process and re-tender the project, which was put into effect by

respondent no.1. They are, therefore, not necessary parties.

85. An argument has also been made in support of the

decision to cancel the bidding process that when for two years of

2018-19 and 2019-20 Nagpur Airport was operated by the

respondent no.1, good profit was earned and estimated, it made no

sense to allot Nagpur Airport for it's development, operation and

management to an outside agency. Alternatively, it has also been

argued that re-tendering is required to be done by adopting some

new model. It is also stated that already there is a long gap of five

years since commencement of the bidding process and now going

ahead with the same, may not be practicable.

86. All these submissions, in our considered view, do not appeal

to reason. When it is said that self-operation of Nagpur Airport

generates more revenue, it does not explain the decision taken by the

GoM. The decision is to re-tender the project, which goes against the

argument of self-operation and more revenue. When it is said that re-

tendering will be done by adopting some new model, again, it does not

99 wp1723.20.odt

explain as to how would it be possible when the only approved model so

far, as per the JVA, RFQ and RFP, is of competitive bidding on the basis

of highest revenue share by adopting standard methodology. If this

methodology of highest revenue share is to be changed, the respondents

would be required to start right from amendment of the JVA. In any

case, it has not been explained to us as to the likely nature of new model

and whether or not the new model has been approved by the GoI and

MoCA. As regards the practicability of implementation of the project

through the petitioners after a long gap of about five years since

commencement of the bidding process, we must say that the delay is

entirely on the part of the respondents and not on the side of the

petitioners. We do not understand as to why the ground of practicability

of award of the project after a gap of five years has been raised by the

respondents when the respondents know it well that they themselves are

responsible and even if it is assumed for the sake of argument that they

are not responsible, they must be held responsible for not acting

responsibly in issuing the Letter of Award on 7.3.2019 about more than

three years after the bidding process began and cancelling the bidding

process and intimating the decision about cancellation of bidding process

and re-tendering the project about five months after the PMIC had taken

a decision in that regard and an year after the issuance of Letter of

100 wp1723.20.odt

Award. All the submissions are, therefore, rejected.

87. Now we would consider some more cases, which we find as

supporting the conclusions made by us regarding the arbitrariness and

unreasonableness of action of respondent no.1 in annulling the bidding

process and also about enforceability of contractual obligations. The

consideration is made in ensuing paragaphs.

88. In the case of State of Orissa vs. Dr. (Miss) Binapani Dei

and Others reported in AIR 1967 SC 1269, the Hon'ble Supreme

Court held that when an order by the State is to the prejudice of a

person in derogation of his vested rights, it may be made only in

accordance with basic rule of justice and fair play. In the present

case, basic rule of justice and fair play required the respondent no.1

to atleast give an opportunity to the petitioner no.1 to submit an

explanation in respect of doubts raised by the MoCA before it went

ahead to cancel the bidding process by issuing the impugned

communication. Then, it is not the case that it were the MoCA which

had confirmed it's doubts about financial viability. It had only sought

justification to lease out the Airport in view of current financial

standing of the MIL and surprisingly enough, the respondent no.1

101 wp1723.20.odt

did not send any justification to MoCA and straightway took a

decision through the PMIC and on the directives of the GoM, to

cancel the bidding process. Such an action of respondent no.1 is not

one of fair play; not the least of justice part.

89. In the present bidding process what was involved was

not a mere award of contract for completion of some work but

something which was for achieving a long term goal of development

of Nagpur Airport to world class standard which would usher in

economic development of Maharashtra in general and Vidarbha

region in particular. Master of the bidding process was an

instrumentality of the State and it was bound by such documents as

MoU dated 18.8.2006, JVA dated 22.2.2009, in-principle approval

given by the Union Cabinet for approval of Dr.Babasaheb Ambedkar

Nagpur Airport to the JVC i.e. respondent no.1, which all spoke

about developing the Nagpur Airport to world class Multi Modal

International Passenger and Cargo Hub which would lead to

improvement in tourism and international trade in the region and

would also enable optimum utilisation of the Airport and in this

way, would fulfill the long cherished demand of the people of the

Vidarbha region. The respondent no.1 was also bound by the RFQ

102 wp1723.20.odt

and the RFP, which laid down the frame work within which the

bidding process was to be completed or aborted. All these factors

necessarily involved a public law element in the whole process and

therefore, this could not have been a case involving mere

enforcement of contractual obligations requiring the petitioner no.1

to shun the public law remedy of Writ Petition before this Court

and take recourse to a civil law remedy for resolution of it's

grievance as held in the case of Rishi Kiran Logistics Private Ltd.

(supra). Therefore, this Writ Petition is maintainable. Besides, this

case, as we have seen from the narration of facts made earlier, does

not involve any disputed question of fact.

90. In the case of ABL International Ltd. and another .vs.

Export Credit Guarantee Corporation of India Ltd. And Others

reported in (2004) 3 SCC 553, it has been held by the Hon'ble

Supreme Court that in an appropriate case a Writ Petition as against

the State or an instrumentality of the State arising out of a

contractual obligation is maintainable and not only that, even a Writ

Petition involving a consequential relief of monetary claim is also

maintainable. It is further held that when an instrumentality of the

State acts in contravention of Article 14, a Writ Petition can lie for

103 wp1723.20.odt

setting right such arbitrary action. The observations in this regard

are to be found in paragraph nos. 23 and 24. The relevant portions

of paragraph nos. 23 and 24, for the sake of convenience, are re-

produced as below :

"23.It is clear from the above observations of this Court, once the State or an instrumentality of the State is a party to the contract, it has an obligation in law to act fairly, justly and reasonably which is the requirement of Article 14 of the Constitution of India. Therefore, if by the impugned repudiation of the claim of the appellants the first respondent as an instrumentality of the State has acted in contravention of the abovesaid requirement of Article 14, then we have no hesitation that a writ court can issue suitable directions to set right the arbitrary actions of the first respondent."

"24.It is clear from the above two objects of the company that apart from the fact that the company is wholly a Government-owned company, it discharges the functions of the Government and acts as an agent of the Government even when it gives guarantees and it has a responsibility to discharge such functions in the national interest. In this background it will be futile to contend that the actions of the first respondent impugned in the writ petition do not have a touch of public function or

104 wp1723.20.odt

discharge of a public duty. Therefore, this argument of the first respondent must also fail.

91. There is another perspective to the issue involved here,

which we find it necessary to dwell upon. Awarding of a contract of a

project of immense public interest, which is the case here, is

ultimately a new form of property in the shape of Government

largesse, declared the Hon'ble Supreme Court in the case of Ramana

Dayaram Sheetty .vs. the International Airport Authority of India and

Others reported in (1979) 3 SCC 489. In this very case, the discretion

of the Government in grant of such largesse has been held to be not

unlimited; in that Government cannot give largesse in it's arbitrary

discretion or at it's sweet will or on any such terms as it chooses in

it's absolute discretion. The Hon'ble Supreme Court further held that

there are, however, two limitations imposed by law which structure

and control the discretion of the Government in this behalf with the

first being in respect of the terms on which largesse may be granted

and the other being in regard to the persons who may be recipients

of such largesse. Hon'ble Supreme Court in the case of M/s. Kasturi

Lal Lakshmi Reddy, represented by it partner Shri Kasturi Lal, ward

no.4, Palace Bar, Poonch, Jammu and Others .vs. State of Jammu and

105 wp1723.20.odt

Kashmir and another reported in (1980) 4 SCC 1 has held that in

granting the largesse, the State cannot act as it pleases. It further

held that whatever be its activity, the Government is still the

Government and is subject to restraints inherent in its position in a

democratic society and therefore, the Constitutional power conferred

on the Government would require it to act reasonably and in public

interest even in contractual matters. The observations of Hon'ble

Apex Court made in this regard appear in paragraph 11 of the said

Judgment, which reads thus :

"So far as the first limitation is concerned, it flows directly from the thesis that, unlike a private individual, the State cannot act as it pleases in the matter of giving largesse. Though ordinarily a private individual would be guided by economic considerations of self-gain in any action taken by him, it is always open to him under the law to act contrary to his self-interest or to oblige another in entering into a contract or dealing with his property. But the Government is not free lo act as it likes in granting largesse such as awarding a contract or selling or leasing out its property. Whatever be its activity, the Government is still the Government and is, subject to restraints inherent in its position in a democratic society. The constitutional power conferred on the Government

106 wp1723.20.odt

cannot be exercised by it arbitrarily or capriciously or in an unprincipled manner; it has to be exercised for the public good. Every activity of the Government has a public element in it and it must therefore, be informed with reason and guided by public interest. Every action taken by the Government must be in public interest; the Government cannot act arbitrarily and without reason and if it does, its action would be liable to be invalidated. If the Government awards a contract or leases out or otherwise deals with its property or grants any other largesse, it would be liable to be tested for its validity on the touch-stone of reasonableness and public interest and if it fails to satisfy either best, it would be unconstitutional and invalid."

93. The law laid down in above-referred cases applies to the

facts of this case. The facts of this case discussed earlier show that

the present bidding process involves a public law element and,

therefore, the requirement of law for a party like the respondent

no.1, an instrumentality of the State, is to act reasonably and in

public interest and not arbitrarily or capriciously. Even in a

contractual matter like the present one, necessity for the State and

it's instrumentality to act reasonably and fairly is an intrinsic part of

Article 14 of the Constitution of India and it along with Article 21

107 wp1723.20.odt

channelises the exercise of Constitutional power into a vibrant and

life sustaining stream of rule of law. The impugned communication,

as we have seen, is arbitrary, unreasonable and unfair, and has,

therefore, breached the stream of rule of law. It has thereby

adversely affected the rights vested in the petitioner no.1 by virtue of

issuance of LoA to it. Such an action of respondent no.1 is against

public interest as it is not taken reasonably, and fairly. We,

therefore, find that the action of respondent no.1 in annulling the

bidding process by the impugned communication is arbitrary,

unreasonable and unfair.

94. About the objection of disputed questions of facts being

involved here, we must say that this case is mainly based on the

record created by the parties and it's correctness has not been

doubted by the parties. As such, there are no disputed questions of

fact which have troubled us here. About the availability of Civil court

remedy for enforcement of contractual obligations, we have already

made ourselves clear that this petition involving a public law element

and further elements of unreasonableness and lack of fair play in

State action, is maintainable here.

                                 108                                wp1723.20.odt

95.           In    view        of    above,     we   find     that     the     impugned

communication is arbitrary, unfair and unreasonable and, therefore,

it deserves to be quashed and set aside. We further find that in this

case there are no such disputed questions of facts as would shut out

the Writ jurisdiction of this Court. We also find that this case does

not involve a mere enforcement of contractual obligations simplicitor,

but involves an issue of enforcement of public law right arising out of

contractual obligations. This petition is, therefore, maintainable.

Questions (d) and (e) are answered accordingly.

Interlude

96. Before parting with the Judgment, we find it necessary to

deal with some more cases relied upon by the respondent no.1. They

are as follows :

a) Jagdish Mandal vs. State of Orissa and Others, (2007) 14 SCC 517.

b) Gupta Sugar Works vs. State of U.P. and Others, 1987 (Supp) SCC 476.

c) Reliance Telecom Limited and another .vs. Union of India and another, (2017) 4 SCC 269.

d) Municipal Council, Neemuch .vs. Mahadeo Real Estate and Others, (2019) 10 SCC 738.

109 wp1723.20.odt

97. In the case of Jagdish Mandal vs. State of Orissa and

Others reported in (2007) 14 SCC 517, it is held that evaluating

tenders and awarding contracts are essentially commercial activities

and principles of equity and natural justice stay at a distance. It is

further held that if the decision relating to award of contract is bona-

fide and is in public interest, Courts will not exercise power of

judicial review. In the instant case, we have found that the decision

as manifested through the impugned communication suffers from the

vice of arbitrariness and unreasonableness and it is hit by the

doctrines of promissory estoppel and legal malice and that it is not

found to be taken in public interest and therefore, on the parameters

of said case of Jagdish Mandal (supra), judicial review of the

impugned decision is permissible.

98. In the case of Gupta Sugar Works .vs. State of U.P. and

Others reported in 1987 (Supp) SCC 476, it is held that price fixing is

neither a function nor a forte of the Court and the Court only

examines whether the price determined was with due regard to the

considerations provided by the Statute and whether extraneous

considerations, have been excluded from determination, as the Court

not being an expert cannot substitute it's decision for that of an

110 wp1723.20.odt

expert. Same principle of law is laid down in the case of Reliance

Telecom Ltd. and another vs. Union of India and another, (2017) 4

SCC 269. By applying these principles of law only that we have

made our enquiry and given our answers here.

99. In the case of Municipal Council, Neemuch .vs. Mahadeo

Real Estate and Others reported in (2019) 10 SCC 738, it is held that

the scope of judicial review of an administrative action is very

limited. It is further held that unless the Court comes to a conclusion

that the decision-maker has not understood the law correctly that

regulates his decision-making power or when it is found that the

decision of the decision-maker is vitiated by irrationality and that too,

on the principle of "Wednesbury reasonableness" or unless it is found

that there has been a procedural impropriety in the decision-making

process, it would not be permissible for the High Court to interfere in

the decision-making process. It is further held that it is not

permissible for the Court to examine the validity of a decision but the

Court can examine only the correctness of the decision-making

process. What we have examined here is the correctness or otherwise

of the decision making process by following these principles of law.

                                  111                         wp1723.20.odt




                                Conclusion And Final Order



100. In the result, we find that the impugned communication is

not sustainable in the eye of law and it deserves to be quashed and

set aside. We further find that a direction to the respondents is

necessary to take further steps in the matter. The petition is,

therefore, allowed.

The impugned communication dated 19.3.2020 is hereby

quashed and set aside.

The respondents are directed to take further necessary

steps as prayed for in prayer clause (b) of the petition within six

weeks of the Judgment and Order.

In the facts and circumstances of this case, there shall be

no order as to costs.

                                JUDGE                          JUDGE

jaiswal





                                112         wp1723.20.odt





                                113         wp1723.20.odt





                                114         wp1723.20.odt





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter