Citation : 2017 Latest Caselaw 7332 Bom
Judgement Date : 20 September, 2017
1 /34 ARAPP-125-05.doc
Ladda R.S.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION APPEAL No. 125 of 2005
IN
ARBITRATION PETITION No. 28 of 2003
Vilayati Ram Mittal (P) Ltd. ]
505, Belscot Tower, ]
Lokhandwala Complex, ]
Link Road, Andheri (West) ]
Mumbai-400 058. ] .. Appellant.
(Orig. Respondent)
Versus
Reserve Bank of India, ]
constituted under the ]
Reserve Bank of India Act, 1934, ]
through the Premises Department, ]
Western Zone, Garment House, ]
Worli, Mumbai-400 018. .. Respondent.
(Orig. Petitioner)
Mr. Sarosh Bharucha a/with N.C. Parekh and Sunil Vyas i/by
Mansukhlal Hiralal & Co. for the Appellant.
Mr. Phiroz Palkhiwala a/with Debojit Banerjee i/by Udwadia &
Udeshi for the Respondent.
CORAM: NARESH H. PATIL &
SMT. BHARATI H.DANGRE, JJ.
RESERVED ON: 3 rd August, 2017.
JUDGMENT PRONOUNCED ON: 20 th Sept, 2017.
Ladda R.S.
2 /34 ARAPP-125-05.doc
JUDGMENT (Per: Smt. Bharati H. Dangre, J):-
(1) The present appeal challenges the judgment dated
30th August, 2004 delivered by the learned Single Judge
thereby setting aside the Award mainly on two counts, namely
that there was accord and satisfaction in between the parties
as the amount was accepted towards full and final settlement
by the claimant without any demur and secondly rejecting the
claim for no damages in view of Clause 18 of the Agreement
between the parties which dis-entitle the contractor from
claiming any compensation for any loss suffered.
For adjudicating the challenge to the order passed
by the learned Single Judge, it would be necessary to avert to
certain essential facts:-
(2) The Reserve Bank of India, (RBI) constituted under
the Reserve Bank of India Act, 1934 invited tenders for
construction of eighty Class III Quarters and one hundred and
twelve Class IV Quarters and a Community Hall at Kharghar,
Navi Mumbai. The appellant (hereinafter referred to as the
"claimant") is a Private Limited Company engaged in the
Ladda R.S.
3 /34 ARAPP-125-05.doc
business of construction submitted its offer which was
accepted by the RBI being the lowest and the letter of
acceptance was issued to the claimant on 25 th June, 1993. An
Agreement was signed between the parties on 14 th September,
1993 in which the date of commencement was specified as 5 th
July, 1093 and the period of completion was fixed as 20
months. The total value of work awarded was Rs.
4,89,94,854/-.
(3) Though the date of completion was specified as 5 th
July, 1993, the conditional extension was regularly granted
and time for completion of the project was finally extended till
31st January, 1997. The virtual completion certificate was
granted on 31st March, 1997. The claimant raised final bill in
regard to the work carried out by them on 4th May, 1998 which
was scrutinized by both the parties, certified by the Architect
and finally the claimant accepted the amount of final bill of
Rs.4,16,51,201/- towards full and final settlement of their
dues (except PVA). Subsequently, even the PVA Bill relating
to escalation was scrutinized and claimant received an amount
Ladda R.S.
4 /34 ARAPP-125-05.doc
of Rs. 76,23,930/- as full and final claim. The claimant raised a
dispute and sought reference of the same to the Arbitrater by
virtue of Clause 34 of the contract and Shri Prabhakar
Shankar Ambike was the sole arbitrator to whom the dispute
was referred. The claimant raised claims under 17 Heads.
The respondent/RBI raised issue of jurisdiction of Arbitrator to
entertain the alleged claims and claimed that accord and
satisfaction had taken place between the parties, bringing the
contract to an end and, therefore, no arbitrable dispute exists
to be referred to the Arbitrator. It was also a ground of the
respondent that there was no compliance of the provisions of
arbitration clause having not followed the procedure under
clause 34 while referring the matter to the arbitration. The
Reserve Bank of India also raised a counter claim before the
Arbitrator. The Arbitrator declared his Award on 30 th
September, 2002 and awarded a sum of Rs. 47,55,507.00
against the 17 claims but rejected the counter claims of the
respondent in totality. The Arbitrator further awarded future
simple interest @ 12% per annum on the award amount from
the date of publishing award till the date of decree or date of
Ladda R.S.
5 /34 ARAPP-125-05.doc
payment, whichever is earlier.
(4) Being aggrieved by the said Award, RBI filed
Arbitration Petition which was numbered as 28 of 2003 before
the learned Single Judge of this Court praying for quashing
and setting aside the award alleging that the Arbitrator had
no jurisdiction to entertain the claims in view of accord and
satisfaction reached between the parties and that the amount
granted by the Arbitrator ought not to have been granted
under the various Heads as the learned Arbitrator had failed
to appreciate that the various claims which were raised by the
claimant fell under the category of "excepted matters" under
the contract on which decision of the Architect is final and
there is no appeal.
(5) The learned Single Judge by judgment dated 30 th
August, 2004 was pleased to allow the arbitration petition and
set aside the impugned award.
This is how the present appeal is before us.
(6) We have extensively heard Advocate Shri Sarosh
Bharucha a/with N.C. Parekh and Sunil Vyas i/by Mansukhlal
Hiralal & Co. for the Appellant and Advocate Shri. Phiroz
Ladda R.S.
6 /34 ARAPP-125-05.doc
Palkhiwala a/with Debojit Banerjee i/by Udwadia & Udeshi for
the Respondent.
(7) Advocate Shri Sarosh Bharucha appearing for the
appellant argued in extenso that the order passed by the
learned Single Judge does not fall within the purview of
Section 34 of the Arbitration Act and the learned Single Judge
could not have substituted the view of the Arbitrator unless
and until he recorded a finding of perversity. It is argued by
him that the learned Arbitrator's finding that after considering
the facts of the case, terms of the contract and evidence on
record there was no accord and satisfaction, has been
substituted by the learned Single Judge on the ground that the
Arbitrator's finding was based on no evidence which is ex facie
perverse and contrary to the evidence on record. Further it is
also argued by Mr. Bharucha that the finding of the learned
Single Judge that the appellant did not demonstrate any case
of "financial hardship" on count of delay in release of
payments was not established and no pleadings to that effect
were raised nor it was proved by any cogent evidence, is also
an incorrect finding not based on facts and to demonstrate so
Ladda R.S.
7 /34 ARAPP-125-05.doc
the learned counsel took us through the documents contained
in the form of letters which specifically refer to the
correspondence prior to completion of work and after
completion of work but prior to receipt of payment, which
according to him was sufficient proof of financial hardship and
coercion. In order to substantiate his contention that the
learned Single Judge should not have substituted his view for
that of the Arbitrator in exercise of powers under clause 34,
he placed reliance upon a judgment of the Apex Court in the
case of T.P. George 1 Vs. State of Kerala and Anr to urge
that it was not permissible for the High Court to substitute its
views for those of the arbitrator as it could not be said that the
view taken by the arbitrator is unreasonable or one which
cannot be arrived at by a reasonable person. He also placed his
reliance on the case of Numaligarh Refinery Ltd 2 Vs.
Daelim Industrial Co. Ltd. Shri Bharucha also argued that
the finding of the learned Single Judge on clause 18 debarring
claimant from raising any claim is also an incorrect finding he
attempted to demonstrate before us that the said clause is
1 (2001) 2 Supreme Court Cases 758.
2 (2007) 8 SCC 466.
Ladda R.S.
8 /34 ARAPP-125-05.doc
violative of Section 28 of the Indian Contract Act and such
existence of a clause in the Agreement binds the parties but do
not bind the Court. In support of his submission he refers to
the following judgments of the Hon'ble Supreme Court.
1) (2009) 10 SCC 354
Asian Techs Ltd Vs. Union of India.
2) (2009) 16 SCC 705
Bharat Drilling & Foundation Treatment Pvt Ltd. Vs. State of Jharkhand & Ors.
3) (1996) 1 SCC 516 Board of Trustees for the Port of Calcutta Vs. Engineers-DE-SPACE-AGE
According to him, the clause dealt by the Apex
Court in the aforesaid judgments is of similar nature as clause
No.18 and according to him, existence of such a clause will not
bind the Arbitrator or even the Court. It is the contention of
the learned Counsel that the respondent has not filed an
appeal challenging the impugned order and if at all the
respondent was aggrieved by the said order on the ground that
it had failed to take into consideration various other grounds
raised in his petition, it was open for the respondents to
Ladda R.S.
9 /34 ARAPP-125-05.doc
challenge the impugned order to that extent and having failed
to do so the respondents are precluded from raising the said
grounds in the appeal which is filed by the appellant.
(8) As against the claim of the appellant, learned
Counsel Shri Palkhiwala appeared on behalf of the
respondents and argued the matter at length. He placed
reliance on the judgment of the Hon'ble Apex Court
demonstrating the powers of the Court to interfere with and
setting aside an arbitral award under section 34 of the
Arbitration Act and by placing heavy reliance upon the
judgment of the Apex Court in Oil & Natural Gas
Corporation 3 Vs. Saw Pipes Ltd , he argued that an award
can be set aside if it is in contravention of the provisions of the
Act or any other substantive law governing the parties and is
contrary to the fundamental policy of the Indian Law. He
relied upon the judgment of the Apex Court in the case of
Delhi Development Authority 4 Vs. R.S.Sharma & Co.
and according to the learned counsel the following grounds
permit interference in an arbitral award :-
3 2003 (5) SCC 705 4 2008 (13_ SCC 80
Ladda R.S.
10 /34 ARAPP-125-05.doc
(a) An award which is contrary to the substantive
provisions of law or the said Act, (b) an award which is
against the specific terms of the contract, (c) an award which
is patently illegal, (d) an award which is prejudicial to the
rights of the parties, (e) an award contrary to the fundamental
policy of Indian Law and (f) an award which is so unfair and
unreasonable that it shocks conscience of the Court. He also
placed reliance on the judgment of the Apex Court in the case
of Associate Builders 5 Vs. Delhi Development
Authority, wherein the Hon'ble Apex Court had interpreted
the term "fundamental policy of Indian Law" to include the
principles which the Arbitrator must follow and adopt "a
judicial approach". The said judgment also mandates the
Arbitrator to follow the principles of natural justice and
recording of reasons in support of the decision has been held to
be fundamental policy of Indian law. The Apex Court has also
included the perversity or irrationality of decision to be tested
on the touchstone of Wednusbury's Principle of
Reasonableness to be included within the purview of
"fundamental policy of Indian Law".
5 2015 (3) SCC 49
Ladda R.S.
11 /34 ARAPP-125-05.doc
(9) The learned Counsel advanced argument to the
effect that Arbitrator is bound to follow due process, to comply
with the requirement of natural justice, fair play and must
apply his mind and consider all relevant material before
arriving at his findings and if he does not do so, his Award is
liable to be set aside on that ground alone. According to him, if
findings of Arbitrator are shown to be contrary to law,
patently illegal or contrary to the contract, or based on no
evidence, or shocks judicial conscience, or are prejudicial to
the rights of parties, or contrary to policy of Indian Law, then,
such an award needs to be set aside.
(10) Shri Palkhiwala also referred two letters dated 28 th
November, 1998 and 10th December, 1998 which acknowledge
the receipt of the amount towards final bill and the PVA bill
(i.e. Escalation bill) and he also contended that the amount
thereunder in fact has been paid to the appellant. According to
him, on such demand and acceptance, all rights and
obligations of the parties came to an end, and accord and
satisfaction had taken place with respect to the subject
contract. He relied upon the following judgments of the
Ladda R.S.
12 /34 ARAPP-125-05.doc
Hon'ble Supreme Court and this Court to demonstrate that
when accord and satisfaction is reached, the contract comes to
an end and there is no scope for arbitration.
i. Union of India v Ajit Mehta and
Associates: AIR 1990 Bombay 45.
ii. P. K. Ramaiah and Co. v Chairman and
Managing Director, National Thermal
Power Corporation: 1994 Supp (3) SCC
iii. Nathani Steels Ltd v Associated
Constructions: 1995 Supp (3) SCC 324.
iv. National Insurance Company Limited v
M/s Boghara Polyfab Pvt Ltd.: AIR 2009
Supreme Court 170.
v. Cauvery Coffee Traders, Mangalore v
Hornor Resources (International)
Company Limited: (2011) 10 SCC 420.
vi. Union of India and Others v Master
Construction Company: (2011) 12 SCC
vii. New India Assurance Company Limited v
Genus Power Infrastructure Ltd: (2015) 2
Ladda R.S.
13 /34 ARAPP-125-05.doc
SCC 424.
(11) Shri Palkhiwala also strenuously attempted to
demonstrate that the Arbitrator has chosen to ignore all the
relevant and germane arguments put forth by the respondent
to the effect that no evidence was led to prove alleged coercion
or financial hardship and the same was neither pleaded nor
proved. He further argued that the Arbitrator has relied upon
several trade practices to come to a conclusion that final bill
should have been paid within six months from the date of
virtual completion. However, no opportunity was given to the
respondent to deal with trade practice or to negate the same
and moresoever his precise argument is that even if such
trade practices exist, it cannot override the specific provision
in the contract between the parties. He therefore submitted
that the learned Single Judge has rightly set aside the award
though on a limited ground of accord and satisfaction being
reached between the parties.
(12) Mr. Palkhiwala, however, attempted to demonstrate
before us that the award was liable to be set aside on several
Ladda R.S.
14 /34 ARAPP-125-05.doc
other grounds; namely, it being contrary to specific terms of
the contract and the fact that the arbitrator has misconducted
himself in allowing the claim and not considering the objection
raised by other party and also on the ground that the
arbitrator being a creature of contract must operate within
four corners of the agreement and cannot travel beyond it.
According to him, an act of the arbitrator in allowing claims
relating to delayed damages are also contrary to the specific
terms of the contract and specific reliance is placed on clause
18 of the contract between the parties. He also assailed the
award on the ground that the claimant had not followed the
procedure for reference to arbitration under the contract
which was prescribed in terms of clause 34 of the contract and
according to him said clause created a contractual allegation
for the purpose of reference to the arbitration and the
reference to the arbitration according to him, itself is
unsustainable. He also argued that there was no arbitral
dispute at the time of reference. Mr. Palkhiwala also dealt in
detail with the individual claims granted by the arbitrator
under various heads namely from claim no.1 to claim no.17
Ladda R.S.
15 /34 ARAPP-125-05.doc
and in detail. He demonstrated as to how grant of such claims
by the arbitrator cannot be sustained. When we specifically
questioned the learned Counsel as to whether this Court while
exercising power under section 37 of the Arbitration Act, can
look into the award and sit in appeal over the award, which
was in fact put to test before the learned Single Judge and the
learned Single Judge though on a limited ground found that
the award to be not sustainable and has set aside the award
and whether it is permissible for this Court to deal with all his
arguments. The learned counsel argued that the Court is
exercising the appellate power conferred under section 37 of
the Arbitration Act and the said section do not in any manner
expressly or by necessary implication restrict the power of the
Appellate Court. According to the learned counsel, provisions
of section 107 of the Code of Civil Procedure will apply fully
even to appeals under section 37 of the Arbitration Act and the
this Court is required to consider all aspects and contentions
to arrive at its conclusion, whether or not the impugned award
is required to be set aside.
Ladda R.S.
16 /34 ARAPP-125-05.doc
(13) We have carefully considered the submissions
advanced on behalf of both the parties and also perused the
judgment of the learned Single Judge dated 30 th August, 2004.
It is not in dispute that the contract was entered into between
the claimant and the RBI in pursuance of acceptance of a bid
by the former for the construction of residential quarters and
Community hall for the later at Belapur with an estimated cost
of Rs.483.64 lakhs. The agreement executed between the
parties contained several clauses including the clauses for
payment to be made to the claimant, the phase and manner of
such payments apart from the technical specifications of the
work to be carried out by the contractor. As per clause 31, the
contractor is to be paid from time to time an amount by the
employer by instalments under interim certificates to be
issued by the Architect to the contractor on account of the
works executed. According to clause 33 of the Agreement, the
decision, opinion, direction, certificate for payment issued by
the Architect was final and conclusive and binding on the
parties. Clause 34 of the contract provides for settlement of
disputes arising out of or in connection with contract or
Ladda R.S.
17 /34 ARAPP-125-05.doc
carrying out of the work to be referred and decided by the
arbitrator to be agreed upon by both the parties. The existence
of the arbitration clause is not in dispute. However, the dispute
in the present matter revolves around the date when the
payment was due and the period of honouring the certificates
of payment. According to the agreement, defective liability
period was for 12 months and the period of final measurement
is prescribed as three months from the date of virtual
completion. The period of honouring the certificate of payment
was prescribed as one month for running account bill and
three months for final bill. According to the respondent RBI,
the work under the tender was to be completed within 20
months i.e. by 4th March, 1995 but there was delay in
execution of the work and extension was granted from time to
time for completion of the said work and the period for
execution was extended upto 31st January, 1997, virtual
certificate was issued on 31st March, 1997 subject to certain
conditions. It appears that the claimant raised the final bill
with regard to the work carried out by them on 4 th March,
1998. The virtual completion certificate issued on 27 th August,
Ladda R.S.
18 /34 ARAPP-125-05.doc
1997 mentions that the works were to be considered virtually
completed on 31st March, 1997 subject to rectification of
defects as per respondent's letter of 10 th June, 1997 and other
cited instructions and it also mention that the defect and
liability period would start from the date of handing over
buildings after rectification of defects. On 6 th October 1997 the
RBI asked the appellant to rectify the defects and hand over
the buildings in the phased manner. On 1 st May, 1998 the final
bill was submitted by the appellant and on 14 th July,1998 ad-
hoc payment of Rs.17,57,471/- was made by the respondent to
the appellant. On 16th July, 1998 the respondent noted serious
lapse on the part of the appellant in failing to furnish the water
proof guarantee. On 30th September, 1997 the RBI recorded
that there is a delay on the part of the contractor for
rectification, taking measurement and handing over of the
premises and in the same letter it asked the contractor to
depute their representative to discuss and finalize the final
bill on 9th October, 1998 the meeting took place for discussion
of the final bill to be cleared pending rectification with an
assurance that the rectification would be completed before
Ladda R.S.
19 /34 ARAPP-125-05.doc
settlement of final bill failing which the respondent could
retain a reasonable amount from the final bill towards
rectification of defects. It was on 9th October, 1998 the final bill
was certified for payment by the Architect. On 16th October,
1998 the respondent paid the balance 50% of the retention
money to the appellant. We have noted that on 28 th November,
1998 the appellant unequivocally accepted the amount of final
bill scrutinised by the respondent and admitted that the same
was correct and the appellant accepted the amount mentioned
in the said bill as full and final settlement except for the PVA
Bill amount relating to escalation which was to be certified and
paid separately. In pursuance of the said letter on 1 st
December, 1998 the RBI paid the amount mentioned in the
said bill to the appellant and on 10th December, 1998 the
appellant issued a letter accepting that the scrutinised
escalation bill was corrected and accepted the amount
thereunder as full and final settlement. On 10 th December,
1998 the escalation bill amount was paid towards full and final
settlement, retaining amount of Rs. 50,000/- for non-
compliance by the appellant as far as attending to the defects
Ladda R.S.
20 /34 ARAPP-125-05.doc
and deficiencies.
(14) We have noted that the appellant referred the
dispute to the arbitration on 23.1.1999 and submitted his
statement of claim before the Arbitrator on 21.8.1999. The
respondent submitted their reply in response to the claim on
15th November, 1999 and on 1st December, 1999 the rejoinder
was filed by the appellant in which for the first time they
protested/stated that the letter dated 28th November, 1998
and 10th December, 1998 accepting the amounts towards full
and final settlement were obtained by coercion and pressure.
It was only when the respondent in the written statement
pointed out that "accord and satisfaction" had taken place in
view of two letters and the payment having been made and
accepted by the appellant, there was no question of arbitrator
entertaining the claims and there was no arbitrable dispute. In
rejoinder the appellant, for the first time, contended that the
said letters had been obtained by causing extreme financial
hardship and coercion and is therefore invalid in law. Thus,
the allegations that the acceptance of the amount towards full
and final settlement was on account of free will was made for
Ladda R.S.
21 /34 ARAPP-125-05.doc
the first time on 1st December, 1999. However, it is noteworthy
to mention that there are no particulars given about any
financial hardship or coercion except making bald statements.
The Arbitrator brushed aside the said objection which was
duly raised by the respondent RBI. The arbitrator after noting
dates of virtual completion certificate as on 31.3.1997
observed that as per normal trade practice the final bill is
required to be certified and finalized within reasonable time
and normally the final bill should have been paid within six
months' time. The Arbitrator also observed that the
respondent could have on its own prepared the final bill after
giving notice to the claimant and there is a practice that the
payment was actually released as latest on 31.12.1998. The
arbitrator did not accept the contention of the respondent in
respect of "accord and satisfaction" and concluded that looking
to the chronology of the events the amount of final bill
involved in releasing retention bill and also bill as PVA one
would think that the claimant were under pressure so far as
getting their legitimate dues are concerned. The arbitrator
therefore agreed with the claim of the claimant that "no claim
Ladda R.S.
22 /34 ARAPP-125-05.doc
certificate" was procured as delay in payment was causing
financial hardship to the claimant and in the circumstances, if
the claimants have accepted the final bill without murmur, it is
not necessary that it is by way of accord and satisfaction. The
learned Single Judge has rightly dislodged the conclusion of
the arbitrator on the said point. The learned Counsel for the
respondent has rightly relied upon the judgment of the Apex
Court in the case of Union of India and Anr. Vs. Master
Construction Co wherein the Court has held that the bald plea
of fraud, coercion, duress or undue influence is not enough and
the party who sets up such a plea must prima facie establish
the same by placing material before the Chief Justice/
designated. In New India Assurance Co 6 . Ltd vs. Genesis
Infrastructure Ltd, the Apex Court observed as follows :-
10. "In our considered view, the plea raised by the respondent is bereft of any details and particulars, and cannot be anything but a bald assertion. Given the fact that there was no protest or demur raised around the time or soon after the letter of subrogation was signed, that the notice dated 31-3-2011 itself was
6 (2015) 2 SCC 424,
Ladda R.S.
23 /34 ARAPP-125-05.doc
nearly after three weeks and that the financial condition of the respondent was not so precarious that it was left with no alternative but to accept the terms as suggested, we are of the firm view that the discharge in the present case and signing of letter of subrogation were not because of exercise of any undue influence. Such discharge and signing of letter of subrogation was voluntary and free from any coercion or undue influence. In the circumstances, we hold that upon execution of the letter of subrogation, there was full and final settlement of the claim. Since our answer to the question, whether there was really accord and satisfaction, is in the affirmative, in our view no arbitrable dispute existed so as to exercise power under section 11 of the Act. The High Court was not therefore justified in exercising power under section 11 of the Act."
(15) In the case in hand, the appellant did not plead as to
how he was under the financial hardship which coerced him to
accept the amount towards full and final settlement and in fact
the plea that the amount has been accepted under coercion
was raised for the first time after a period of one year from
writing such letters. In case, if it was the case of the appellant
that he was coerced to accept the amount and he was
Ladda R.S.
24 /34 ARAPP-125-05.doc
undergoing a financial hardship which prompted him to accept
the amount that ought to have been the case of the appellant
while filing his claim before the arbitrator. It is, however, only
when the reply was filed by the respondent, wherein an
objection was raised about "accord and satisfaction" being
reached between the parties, the plea has come forth. No
evidence is adduced to demonstrate the financial hardship and
it is very apparent that the said plea is merely an after thought
to counter the case of the respondent of reaching accord and
satisfaction. The learned Single Judge has rightly recorded in
paragraph 6 of the judgment that the requirement of giving
particulars of coercion is a basic requirement of compliance
and no particulars whatsoever of alleged financial hardship or
coercion are given. The learned Single Judge has also observed
that what circumstance can operate as coercion in relation to
one person may not so operate in relation to another person
and it was for the respondent to give particulars of the alleged
financial hardship and coercion and in the absence of the same
being pleaded or proved, mere delay in preparation of final bill
will not itself amount to financial hardship or coercion. The
Ladda R.S.
25 /34 ARAPP-125-05.doc
learned Single Judge has therefore proceeded to conclude that
the findings recorded by the arbitral tribunal was based on no
evidence and therefore has rightly set aside the same.
(16) As regards the contention of the respondent that
there was no arbitrable dispute which called for the reference
to arbitration, since there was "accord and satisfaction", we
have carefully analysed the position of law on the said aspect.
Though for a considerable time there was an issue as to
whether in spite of full and final settlement of the claim, the
arbitration clause in the contract can be invoked which
provide for reference to arbitration in case of existence of an
arbitrable dispute. The trend of judgment took a view that
Court need not refer the dispute to the arbitrator, if it did not
exist at all. In case of Steel Authority of India Ltd 7 . Vs.
J. C. Budharaja, it was held that once there is full and final
settlement in respect of any particular dispute or difference in
relation to matter covered under arbitration clause in the
contract and that dispute or difference is finally settled by and
between the parties, such a dispute or reference does not
remain to be arbitrable dispute and arbitration clause cannot
7. AIR 1999 S.C. 3275
Ladda R.S.
26 /34 ARAPP-125-05.doc
be invoked even though for certain other matter contract may
be in existence. The Apex Court further observed that once
parties have carried out the settlement in respect of any
dispute arising under a contract and that dispute or difference
is amicably settled by way of final settlement, unless that
settlement is set aside in appropriate proceeding, it cannot lie
in the mouth of one party to the settlement to spurn it on the
ground that it was mistake and to proceed to invoke
arbitration clause and if this is permitted sanctity of contract,
settlement also being a contract would be wholly lost and it
would be open to one party to take benefit under the
settlement and question the same on the ground of mistake
without having the settlement set aside.
The divergence of views was put to rest by the Apex
Court in the case of National Insurance Co. 8 Vs. M/s
Boghra, where the Apex Court in paragraph 24 observed as
follows:-
24. "We thus find that the cases referred fall under two categories. The cases relied on by the appellant are of one category where the court after considering the facts, found
8. AIR 2009 SCC 170
Ladda R.S.
27 /34 ARAPP-125-05.doc
that there was a full and final settlement resulting in accord and satisfaction, and there was no substance in the allegations of coercion/ undue influence. Consequently, this Court held that there could be no reference of any dispute to arbitration. The decisions in Nav Bharat and Nathani Steels are cases falling under this category where there were bilateral negotiated settlements of pending disputes, such settlements having been reduced to writing either in the presence of witnesses or otherwise. P.K. Ramaiah is a case where the contract was performed and there was a full and final settlement and satisfaction resulting in discharge of the contract. It also falls under this category. The cases relied on by the respondent fall under a different category where the court found some substance in the contention of the claimants that `no due/claim certificates', or `full and final settlement Discharge Vouchers' were insisted and taken (either in a printed format or otherwise) as a condition precedent for release of the admitted dues. Alternatively, they were cases where full and final discharge was alleged, but there were no documents confirming such discharge.
Consequently, this Court held that the disputes were arbitrable. None of the three cases relied on by the appellant lay down a proposition that mere execution of a full and final settlement receipt or a discharge voucher is a bar to arbitration, even when the validity thereof is challenged by the claimant on the ground of fraud, coercion or undue influence. Nor do they lay down a proposition that even if the discharge of contract is not genuine or legal, the claims cannot be referred to arbitration"
Ladda R.S.
28 /34 ARAPP-125-05.doc
Ultimately, the Apex Court held that whether there
was a "full and final satisfaction" is also an issue which has to
be looked into by the Arbitrator and it would depend on the
facts and circumstances of each case and the Chief Justice/
Designate would consider while exercising jurisdiction under
Section 11 as to whether there was really "accord and
satisfaction" or "discharge of contract by performance". If the
answer is in the affirmative, he will refuse to refer the dispute
to the arbitration, however, if he comes to conclusion that full
and final settlement received/or discharged, was a result of
any fraud/ coercion / undue influence he will have to hold that
there was no discharge and refer the dispute to arbitration.
In view of the aforesaid legal position, facts and
circumstances of the case would have to be looked into to
determine, whether the arbitrable dispute existed and cause
for reference to arbitration. In the present case, after the
claim was raised though after period of almost a year, the
appellant raised a plea of fraud and coercion it was looked into
by the arbitrator and concluded that it was a case of "financial
hardship" and it cannot be said that there was no case of
Ladda R.S.
29 /34 ARAPP-125-05.doc
"accord and satisfaction" and the claim was entertained. The
learned Single Judge also dealt with the issue of accord and
satisfaction and held that there was, one in the form of
acknowledgement receipt. In such circumstances, we do not
feel it necessary to conclude that the dispute was not
arbitrable.
(17) The learned Single Judge has also made reference to
the clause 18 of the contract and it was argued by the Counsel
for the appellant that existence of such a clause which
prevented the claim to be entertained, in any event, did not
bind the arbitrator or the Court. He had relied upon judgment
in case of Asian Techs Ltd. Vs. Union of India (2009)
10 SCC 354 to canvass that a clause on similar nature did
not preclude adjudication in the said case. The referable
clause reads as under :-
(C) "No claim in respect of compensation or otherwise howsoever arising as result of extensions granted under condition (A) & (B) above shall be admitted."
Ladda R.S.
30 /34 ARAPP-125-05.doc
In recording a finding the Hon'ble Apex Court
referred to its earlier judgment in the case of Board of
Trustees for the Port of Calcutta 9 Vs. Engineers-DE-
SPACE-AGE and Bharat Drilling & Foundation
Treatment Pvt Ltd. 10 Vs. State of Jharkhand & Ors.
cited supra.
"Clause 1.21.4 reads as under : No claim shall be entertained for delays in communicating decision drawing or specifications by the Department. The Department may however consider the grant of extension of time in completion of work. If there is any such genuine reason of it."
The principle of law discernable from the aforesaid
judgment reveals to us that it is for the arbitrator to decide
the effect of the said clause and deal with the issue.
Per contra, Shri Palkhiwala had relied upon the
judgment of the Apex Court in the case of Associated
Engineering Co.11 Vs. Government of Andhra Pradesh and
Ramnath International Construction (P) Ltd.12 Vs. Union of
9 (1996) 1 SCC 516.
10. (2009) 16 SCC 705
11 (91) 4 SCC 93
12 (2007) 2 SCC 453
Ladda R.S.
31 /34 ARAPP-125-05.doc
India, wherein the Apex Court has held that any derogation
from terms of contract is not sustainable and award of
damages ignoring the terms of contract amounted to legal
misconduct on the part of Arbitrator. In the present case,
clause 18 reads as follows :-
18. "The contractor shall not be entitled to any compensation for any loss suffered by him on account of delays in commencing or executing the work, whatever the cause of delays may be, including delays arising out of modifications to the work entrusted to him or in any sub- contract connected therewith or delays in awarding contracts for other trades of the project or in commencement or completion of such works or in procuring Government controlled or other building materials or in obtaining water and power connections for construction purposes or for any other reason whatsoever and the Employer shall not be liable for any claim in respect thereof. The Employer does not accept liability for any sum besides the tender amount, subject to such variations as are provided for herein."
By virtue of said clause, the contractor is not held
entitled for any compensation for any loss suffered on account
of delays, whatever may be cause, the arbitrator has to operate
Ladda R.S.
32 /34 ARAPP-125-05.doc
within the parameters of the agreement and is bound by its
terms and if the clause provide that the contractor will not be
entitled for any claim, it binds both the parties since the
agreement was signed by both the parties and now it is not
open to the appellant to construe clause No.18 so as to seek
benefit and contend that the clause is binding between the
parties but do not bind the arbitrator or the Court. The
judgment cited by the Counsel for the appellant does not
support him for the said proposition which he had attempted
to canvass. If the clause specifically prohibits any claim on
account of delay, on any ground whatsoever, by ignoring the
said clause 18, arbitrator has travelled beyond his jurisdiction
as his existence depends upon the agreement and his function
is to act within its limits. It is settled law that arbitrator is
creature of the contract between the parties and if he ignores
the specific terms of the contract, it would be question of a
jurisdictional error on his part which could be corrected by
Court.
(18) We find that the learned Single Judge has rightly
construed clause No.18 and arrived at a conclusion that the
Ladda R.S.
33 /34 ARAPP-125-05.doc
contractor is not entitled to claim any interest or damages and
in fact the arbitrator has excluded from his consideration
clause no.18 which was relevant for deciding the claim for
damages.
The learned counsel Shri Palkhiwala is not successful in
persuading us to look into various other flaws, which the
arbitrator has committed, because according to us, our
jurisdiction is appellate one, where an appeal is carried against
the judgment of the learned Single Judge and therefore we will
confine ourselves to the findings of the learned Single Judge,
who has set aside the Award. The respondents did not carry an
appeal against the judgment of the learned Single Judge and
rightly so, since the purpose of respondent in the arbitration
petition is achieved by setting aside of the Award. The
Arbitration Act contains provision for supervision by the
Courts over the specially created Forum of Arbitrator, only
with a view to ensure fairness. The jurisdiction of the Court
under Section 34 is not appellate in nature and it is not open to
the Court to interfere with the Award, merely because other
view is possible if the arbitrator has taken a plausible view on
Ladda R.S.
34 /34 ARAPP-125-05.doc
facts, evidence and pleadings before him. The extent of judicial
scrutiny under section 34 of the Act is limited and under
Section 37 it is further narrower. Appeal under section 37 is in
the nature of second appeal, and where there are concurrent
findings of facts and law, first by the Arbitraral Tribunal which
are then confirmed by the Court, while scrutinizing it under
Section 34, the Scope of the Appellate Court is minimal. In our
opinion, the learned Single Judge has rightly set aside the
award since it suffered from patent illegality and found it to be
unfair and unreasonable. We do not propose to enhance the
scope of Section 37 to sit in appeal over the Award once again
and we refrain to advert to the arguments advanced by the
learned Counsel Shri. Palkhiwala for setting aside the Award
on grounds other than the one which are reflected in the
impugned judgment passed by the learned Single Judge.
In the result, we uphold the order and judgment of the
learned Single Judge and dismiss the appeal.
The appeal is dismissed.
(SMT. BHARATI H.DANGRE,J) (NARESH H. PATIL,J.)
Ladda R.S.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!