Citation : 2017 Latest Caselaw 7251 Bom
Judgement Date : 18 September, 2017
wp1697.07.J.odt 1/7
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR
WRIT PETITION NO. 1697 OF 2007
Maharashtra State Electricity Distribution
Company Limited,
A successor of the erstwhile
Maharashtra State Electricity Board,
Through its Dy. Executive Engineer,
O & M Sub-Division-II, Tukum,
Chandraur Desk-I, Chandrapur. .....PETITIONER
...V E R S U S...
1] Avinash Bajirao Khokale,
Aged about 40 years, R/o-Wadgaon
Ward, Chandrapur, Tahsil and
District - Chandrapur.
2] Appellate Authority under Section
127 of the Electricity Act, 2003,
Through the Chief Engineer (Electrical)
Public Works Department, Government
of Maharashtra, Administrative Bldg.
Third floor, Ramkrishna Chemburkar
Marg, Chembur (East) Mumbai. ...... RESPONDENTS.
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
Shri R. E. Moharir, Advocate for the Petitioner.
=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-=-
CORAM : S. C. GUPTE, J.
th DATE : 18 SEPTEMBER, 2017.
ORAL JUDGMENT :
Heard learned counsel for the petitioner. The respondent
is absent though served.
wp1697.07.J.odt 2/7
02] The petition challenges an order passed by the appellate
authority under Section 127 of the Electricity Act, 2003 ("Act").
The petitioner is an Electricity Distribution Company. It is the case
of petitioner that respondent No.1, who was its consumer, was
running a hotel at Chandrapur. There were two commercial meters
having connected loads of 5.13 kw and 4.72 kw installed at the
hotel which was run by respondent No.1 since 5 th September, 2002.
On 4th June, 2003 and 5th June, 2003, a flying squad of the
petitioner visited the premises of respondent No.1 and found that
the meter seals were tampered and there was a hole on the front
side of meter body. As a consequence of these findings, the
petitioner assessed respondent No.1 provisionally for two meters
respectively for 20690 units (at Rs.1,60,545/-) and 4404 units (at
Rs.33,317/-). The provisional bills was later finalized. The final
assessment by the Superintending Engineer, O & M Circle,
Chandrapur, was at Rs.1,85,076/-. A First Information Report was
also lodged by the Deputy Executive of the Flying Squad of the
petitioner with Ramnagar Police Station, Chandrapur in this behalf.
Respondent No.1 challenged the final assessment order of the
petitioner before the Appellate Authority under the Act. In the
meanwhile, pending such challenge, respondent No.1 paid the
wp1697.07.J.odt 3/7
assessed bill in installments under protest. By its impugned order
dated 29th September, 2005, the Appellate Authority quashed and
set aside the final assessment order of the petitioner and directed it
to prepare a six month bill for loads respectively of 5.13 kw and
4.72 kw connected loads with load factor of 0.6 and working hours
per day as 13 hours and working days per month as 26 days and
accordingly, assess the energy consumption of 6306 and 5742 units
by applying commercial tariff at one and half times the normal rate.
03] The Appellate Authority accepted the petitioner's case
that there was unauthorized use of electricity through tampered
meter as the meter seals were damaged and a hole was found in the
meter body. The Appellate Authority held that whilst the petitioner
had proved unauthorized use of electricity, it had failed to establish
that there was theft of energy. (The theft of electricity is covered by
Sections 135 and 136 of the Act. Incidentally, the First Information
Report filed by the Flying Squad of the petitioner finally resulted in
the acquittal of respondent No.1 from the charge of theft of
electricity.) Commenting on the assessment by the petitioner, the
Appellate Authority was of the view that the assessment of energy
consumption was made without any details of calculation for the
wp1697.07.J.odt 4/7
connected load, the working hours, the diversity factor or load
factor, the working days of the month etc., all of which are crucial
elements of assessment of energy consumption. In the absence of
these particulars, the Appellate Authority itself went into the
various aspects of assessment. It considered the load factor as per
the circular of CBIP for the type of load in establishment like the
respondent's as 0.6. It also considered working hours for hotel type
of consumption which can be about 13 hours in a day and 26 days
in a month. Accordingly, taking into account the connected loads
respectively of 5.13 kw and 4.72 kw of the two meters, it worked
out the number of units per month in case of each of the two
meters and accordingly, the aggregate consumption for six months.
In the case of one meter (having load 5.13 kw), the energy
consumption worked out to 1051 units per month (i.e. 5.13 x 0.6 x
13 x 26). The consumption for six months, thus, worked out to
6306 units. For the second meter (with connected load of 4.72
kw), the monthly consumption was worked out at 957 units (i.e.
4.72 x 0.6 x 13 x 26), and six months' consumption at 5742 units.
Based on this assessment, the Appellate Authority quashed and set
aside the final assessment order and directed the petitioner to
prepare two six months bills respectively of 6306 and 5742 units as
wp1697.07.J.odt 5/7
per the working shown in its order.
04] Learned counsel for the petitioner could not assail this
assessment on the part of the Appellate Authority at the hearing of
the petition on the basis of the material on record. Learned counsel
submitted that the petitioner had taken out a civil application for
permission to file additional documents. According to learned
counsel, these documents would establish that the case was really a
case of theft of electricity and enable the Court to make an
appropriate assessment of the bill on that basis. Learned counsel
submitted that the petitioner's case of theft of electricity within the
meaning of Section 135 of the Act was borne out by these
documents. Learned counsel submitted that the documents would
show the modus operandi adopted by respondent No.1 for
committing theft of electricity. I am afraid that is not a course open
to this Court. I say so for two reasons. Firstly, none of these
documents was before the Appellate Authority when it passed the
impugned order. There is no justification shown as to why these
documents could not be produced before the Appellate Authority in
the appeal. It is not permissible, in the premises, for the writ Court
to apply its mind afresh to these new documents. Secondly and
wp1697.07.J.odt 6/7
more importantly, there is no proof of the case of theft of
electricity. In fact, it is not in dispute that respondent No.1 has
been acquitted of the charge of theft of electricity in the Criminal
case based on the First Information Report lodged by the Flying
Squad of the petitioner. The Appellate Authority, which is a final
fact finding authority in this behalf, has come to a categorical
finding that the case of theft of electricity is not proved. Nothing is
indicated in the impugned order of the Appellate Authority which
could show the findings as perverse. The impugned order is
supported by evidence. There is no irrelevant or non germane
material considered by the Appellate Authority whilst arriving at its
conclusion. Likewise, no relevant or germane material in this
regard in disregarded whilst coming to its finding. It is not
permissible, in the premises, to the writ Court to reassess the
material, and that too completely new material produced for the
first time, and see if theft of electricity is made out in the facts of
the case.
05] There is, accordingly, no merit in the writ petition. The
petition is dismissed. No order as to costs.
wp1697.07.J.odt 7/7
06] Since there was no stay of the final assessment pending
the challenge before the Appellate Authority, respondent No.1 has
paid the entire assessed bill. Pending the present petition,
respondent No.1 filed an application seeking an order of refund of
the amount of Rs.1,13,603/- paid by him in excess, having regard
to the impugned order of the appellate authority. This Court, by its
order dated 22nd July, 2009, directed the petitioner to deposit this
amount in the Court. Liberty was given to respondent No.1 to
withdraw the amount by furnishing security to the satisfaction by
Registrar (Judicial) of this Court. Accordingly, the petitioner
deposited a sum of Rs.1,13,603/- in this Court. On a security bond
and solvency certificate to the extent of Rs.1,50,000/- and
furnishing of an undertaking, respondent No.1 was permitted to
withdraw the amount. Since the petition has now been dismissed,
the security bond and undertaking shall stand cancelled.
JUDGE PBP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!