Citation : 2017 Latest Caselaw 8287 Bom
Judgement Date : 31 October, 2017
201-WP-5097-2007.DOC
Jsn
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 5097 OF 2002
Yogesh Tukaram Shetty,
Age Adult, Occ. Service, Manager, Shri
Krishna Upahargriha, Bombay Agra Road,
Thane. ...Petitioner
Versus
1. The Maharashtra State Electricity
Distribution Company Ltd.
Having its Registered Office at Hongkong
Bank Building, Mahatma Gandhi Road,
Fort, Mumbai 400 001.
2. The Chief Engineer,
Maharashtra State Electricity Distribution
Company Ltd., having its office at 7th
Floor, MSEDC, Building, Wagle Estate,
Opp. Passport Office, Thane. ...Respondents
Mr. K.K. Malpathak, for the Petitioner.
Mrs. Anjali R. Shiledar - Baxi, for Respondent Nos. 1 and 2.
CORAM: VASANTI A. NAIK &
RIYAZ I. CHAGLA, JJ.
DATED: 31ST OCTOBER 2017.
O R A L J U D G M E N T :- (Per Riyaz I. Chagla J.)
1. The Petitioner has filed this Petition under Article 226 of
the Constitution of India challenging the final assessed bill of
201-WP-5097-2007.DOC
Rs.1,78,614.19 issued by Respondent No.4 and has sought a
direction from this Court against Respondent No.1 to refund
to the Petitioner the amount of Rs.1,78,614.19 alleged to be
illegally recovered from the Petitioner and to pay the same to
the Petitioner along with interest at 18% p.a. from the date of
recovery till payment.
2. The Petitioner is running a hotel as manager in the
name and style of Shrikrishna Upahargriha at Thane. It is the
Petitioner's case that the Respondent No.1 had on 17th July
1999 checked the Petitioner's electricity meter in the hotel
and had reported that the same was in working condition on
On 2nd June 2000, the officers of Respondent No.1 carried
out a spot inspection of the meter and found the meter to be
in an OK condition. The meter box had thereafter been
sealed on 3rd January 2001 by the officers of MSEB by
affixing paper stickers. The Flying Squad of Respondent No.1
had again visited the hotel of the Petitioner on 18th July, 2001
and made inquiry in respect of the electricity meter and in
respect of power consumed in the hotel. It was alleged by
the Flying Squad that the meter was not in proper condition
201-WP-5097-2007.DOC
and showing less consumption than the actual. The paper
stickers which had been affixed to seal the meter were
claimed by the Flaying Squad to be duplicate and claimed
that this was a case of theft of the electricity. It is the
Petitioner's case that no evidence of illegal abstraction of
electricity was found by the officers of Respondent No.1. The
Petitioner refused to comply with the alleged illegal demands
of the officers of Respondent No.1, who thereafter
disconnected the electricity meter and took the meter away.
Respondent No.4 thereafter raised a provisional bill to the
tune of Rs.8,79,426/- for the period of 19th July 1998 to 18th
July 2001. The bill was challenged in the Court by the
Petitioner. In Civil Revision Application filed by the Petitioner
challenging the order of the lower Appellate Court, this Court
by order dated 16th August, 2001 directed the Petitioner to
deposit 20% of the amount claimed in the provisional bill and
Respondent No.4 was directed to determine the final bill and
the Petitioner was granted liberty to approach the appropriate
authority. The Respondents were directed to restore the
electricity. The Petitioner complied with the said order and
deposited 20% of the provisional bill amount i.e.
201-WP-5097-2007.DOC
Rs.1,75,886/-. The Respondent No.4 heard the application of
the Petitioner and determined the final bill to the tune of
Rs.8,64,792.16. Being aggrieved, the Petitioner filed an
Appeal on 14th September, 2001 to Respondent No.2 against
the order of Respondent No.4. Respondent No.2 by order
dated 18th October 2001, finally assessed the bill and found
that an amount of Rs.7,86,614.19 was payable. This was
communicated to the Petitioner by Respondent No.4 vide
letter dated 29th October, 2001. The Petitioner was called
upon to pay the balance amount of Rs.18,052/- which was
computed after taking into account the amount of
Rs.1,75,886/-, which had already been paid by the Petitioner,
on or before 31st October, 2001 failing which the Petitioner's
supply would be disconnected without prior notice. The
Petitioner in response addressed a letter dated 30th October,
2001 to Respondent No.2 stating that the final assessed bill
issued was on the basis of 19 KW instead of 17.17 KW as
allegedly informed by the Flying Squad of the MSEB. It was
mentioned that the earlier assessment had also been done
on the 17 KW load. In response to the letter of the Petitioner,
the MSEB by letter dated 4th December 2001 stated that
201-WP-5097-2007.DOC
connected load of 19 KW was considered for final
assessment as per the inspection report of the Deputy
Executive Engineer (Inspection), Bhandup Urban Zone and a
copy of the report has been enclosed. The Petitioner was
therefore, called upon to make payment of the final assessed
bill. Hence this Petition.
3. Mr. Malpathak, the learned counsel for the Petitioner
has submitted that the final assessed bill of Rs.1,78,614.19 is
erroneous as Respondent No.4 has improperly calculated the
load in the final assessed bill on the basis of 19 KW load
instead of 17.17 KW as informed by the Flying Squad of the
MSEB and despite the earlier assessment being done on 17
KW load. He has referred to clause 31 of the Maharashtra
State Electricity Board conditions and miscellaneous charges
for supply of electrical energy and has stated that for LT
consumers under the heading pilferage, the formula is set out
viz. the connected load to be taken into account is that which
is found at the time of inspection in KW multiplied by the
diversity factor and load factor and number of working hours
per day day 7 as well as number of days in a month. For
201-WP-5097-2007.DOC
non-commercial, which the Petitioner's hotel fell under the
diversity factor into load fact or is mentioned as 50% and the
number of working hours / days is mentioned as 6 and
number of days per month as 25. He has stated that if this
calculation had been done according to the connected load
as per 17.17 KW which was found at the time of inspection by
the Flying Squad of the MSEB then the bi-monthly units
would be 2576 units. He has submitted that the Respondent
No.1 had taken connected load to be 19 KW and thus came
to a total of 6650 units as the bi-monthly units. He has
submitted that if the correct computation had been taken into
account on the basis of 17.17 KW then the Petitioner has
already deposited an amount of Rs.1,75,886/- and hence
there was nothing payable to the Respondents. On the
contrary the Respondents ought to have refunded the amount
paid by the Petitioners. He has submitted that the
Respondents could only assess for the period between 3rd
January 2001 to 18th July 2001 as the meter had been
sealed on 3rd January 2001 and MSEB had found that there
had been tampering of the sealed meter. He has contended
that the Respondents have incorrectly taken the assessment
201-WP-5097-2007.DOC
period to be from 17th September 1999 to 18th July 2001
when they themselves have assessed the period of illegal
extraction from 3rd January 2001 to 18th July 2001. He has,
therefore, submitted that this Petition ought to be allowed.
4. Ms. Shiledar the learned counsel for Respondent Nos.
1 and 2 has supported the final assessed bill. She has
submitted that the said clause 31 had been complied with
and hence there was no merit in the Petition.
5. We have carefully considered the submissions. We are
of the view that the Petitioner has raised disputed questions
of facts viz. whether 19 KW load instead of 17.17 KW load
was to be the basis for the final assessed bill. The Petitioner
has claimed that the basis should have been 17.17 KW as
according to the Petitioner this had been informed by the
Deputy Executive Engineer of the Flying Squad of MSEB
when they took inspection. This has been disputed by the
Respondents who claim that the connected load was 19 KW
which was considered for calculating the final assessed bill
payable by the Petitioner and this load was according to the
201-WP-5097-2007.DOC
Respondents in as per the inspection report of the Deputy
Executive Engineer (Inspection), Bhandup Urban Zone and is
also verified with that printed on the energy bill. We are of the
view that, it will not be appropriate for this Court in Writ
jurisdiction to determine these disputed facts and that the
Petitioner ought to have availed of the appropriate remedy
available to the him. We are therefore of the view that this
Petition is liable to be dismissed.
6. We accordingly dismiss the present Petition with no
order as to costs. Rule stands discharged.
( RIYAZ I. CHAGLA J. ) ( VASANTI A. NAIK, J )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!