Friday, 17, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Chaucer Capital Limited vs Maharashtra Maritime Board And 2 ...
2017 Latest Caselaw 8213 Bom

Citation : 2017 Latest Caselaw 8213 Bom
Judgement Date : 13 October, 2017

Bombay High Court
Chaucer Capital Limited vs Maharashtra Maritime Board And 2 ... on 13 October, 2017
                                 1                     WP-1051-15

        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
           ORDINARY ORIGINAL CIVIL JURISDICTION
                  WRIT PETITION NO.1051 OF 2015

Chaucer Capital Limited
through its Constituted Attorney
Mr.Sitaram Teravankar 
office at 402, Raheja Chambers,
Nariman Point, 
Mumbai 400021.                              ..  Petitioner


                Versus


1   Maharashtra Maritime Board 
     Indian Mercantile Chambers,
     3rd floor, Ramjibhai Kamani Marg,
     Ballard Estate, Mumbai 400038.

2   Minister (Ports),
     Home Department,
     Government of Maharashtra,
     Mantralaya, Mumbai 400 032.

3   JSW Infrastructure Limited
     having its office at Jindal Mansion,
     5A, Dr.G.Deshmukh Marg,
     Mumbai - 400026.

4   Department of Atomic Energy
     Anushakti Bhavan, CSM Marg,
     Mumbai 400001.

5   Union of India
     having its office at CGO Building, 
     Queens Road, Marine Lines 
     Mumbai.                                ..  Respondents


Tilak




  ::: Uploaded on - 14/10/2017                ::: Downloaded on - 15/10/2017 01:35:17 :::
                                     2                          WP-1051-15



                                ...
Mr.Aspi   Chinoy,   Senior   Counsel   with   Rohan   Rajadhyaksha 
with   Tanmayi   Rajadhyaksha   with   Mohanish   Chaudhari   i/b 
Mohanish Chaudhari for the petitioner.

Mr.Gaurav Joshi, Senior Counsel with Rahul Sinha i/b DSK 
Legal for respondent no.1.

Ms.Geeta   Shastri,   Addl.Government   Pleader   for   respondent 
no.2.

Mr.Janak   Dwarkadas,   Senior   Counsel   with   Mr.Rahul 
Narichania,   Senior   Counsel,   Ms.Bindiya   Raichura   and 
Ms.Smriti Jha i/b Mulla & Mulla & Craigie Blunt & Caroe for 
respondent no.3.

Ms.Aswini R. Singh for respondent nos.4 and 5.


                             CORAM:  DR. MANJULA CHELLUR, CJ. & 
                                         G.S.KULKARNI, J

                RESERVED ON :  11th SEPTEMBER, 2017
          PRONOUNCED ON :  13th OCTOBER, 2017


JUDGMENT (Per Dr.MANJULA CHELLUR, CJ):

1 The petitioner herein is before this Court seeking

reliefs as under :

(A) To set aside the impugned order dated 27.05.2014 of respondent no.2 which came to be passed in terms of direction of this Court by order dated 8th January 2014.



Tilak





                                      3                           WP-1051-15




        (B)      To quash the impugned LOI dated 19.10.2011 

issued to respondent no.3 followed by Lease Deed dated 3.12.2011 executed between Respondent No.1 and Respondent no.3, as well as modifications dated 04.04.2013 and 17.07.2014.

(C) To prohibit Respondent no.1 from granting further rights or permission to develop the site earmarked for proposed Alewadi Port Project.

(D) To direct Respondents No.1 and 2 to complete the selection procedure which started in the year 2007 in terms of 1996 port policy and not to subject the petitioner to any new tender process.

FACTS :

2 The petitioner being a private equity fund known

as "Chaucer Capital Limited" incorporated under the laws of

the United Kingdom is before us. The first respondent is the

Maharashtra Maritime Board (for the sake of convenience and

brevity referred to as "MMB'"), a statutory Board constituted

under MMB Act. The second respondent is the Minister

(Ports) Home Department, Government of Maharashtra.

Third respondent is JSW Infrastructure Limited, a Company

registered under Companies Act of 1956.


Tilak





                                    4                          WP-1051-15

Contention of the petitioner:-

3                 In   pursuance   of   the   policy   of   Government   of 

Maharashtra dated 15th March 1996, so far as the

construction of jetties and multipurpose ports, such

construction was to be given to private sector in order to

develop non-major ports (for short "1996 Policy"). Alewadi

was considered as a promising site in Tarapur area for

establishment of multipurpose port. When no satisfactory

responses were received for global tenders for development of

Alewadi port, the methodology evolved for the development

of ports was through Memorandum of Understanding.

Accordingly, Government of Maharashtra evolved procedure

for selection of developers; one for 'Self-controlled Captive

Jetty', another for 'Multipurpose Jetties and Cargo

Terminals'(for short "2005 Policy"). Initially, several

developers expressed their interest so far as development of

Alewadi port, but in due course of time, they withdrew their

offers. In the year 2006, petitioner learnt that Alewadi

project was still available. Therefore, on 6 th January 2007,

petitioner expressed its interest to develop an All Weather and

Tilak

5 WP-1051-15

Multipurpose port at Alewadi with the coordinates "latitude

19° 46" 30 North and longtitude 72° 50 East".

4 A Techno Economic Feasibility Study Report along

with necessary fee came to be sent on 7 th February 2007. On

25th February 2007, petitioner undertook development after

taking advise from Hauers - a Specialist Port Consultancy in

India and overseas from Ocean Shipping Consultants - a UK

based Port and Shipping Consultant. Accordingly, petitioner

sought issuance of LOI. Subsequently, petitioner also

informed MMB - the first respondent that a well known

International Port Operator M/s.International Container

Terminal Services was appointed as its strategic partner for

the above project and further informed that they have entered

into a Joint Venture agreement with the above said

International Port Operator for the development of Alewadi

Project which involved US$ 1.25 million (Rs.6.87 crores).

5 According to the petitioner, several meetings were

held in the month of July 2007 between the stakeholders,

Tilak

6 WP-1051-15

wherein petitioner was assured that LOI would be awarded

shortly. The doubts raised in the said meeting were clarified

by submitting documents and information. First respondent

even addressed a letter on 17th July 2007 that the case of the

petitioner is under consideration, and the same is being

evaluated. Petitioner even informed the support for the said

project assured by M/s.ICTSI ICL Financial Services Ltd and

Societe Generale Bank who were ready to invest US$ 200

million to US$ 500 million.

6 According to the petitioner, repeated requests by

them and assurances by the first respondent went on for

about 2 years. In the month of February 2009, petitioner

addressed a letter to first respondent reiterating its request

for LOI and the MMB officers assured that LOI would be

issued. Even in June 2009, petitioner sought allotment of

Alewadi port.

7 According to the petitioner, through the impugned

order dated 27th May 2014 of second respondent, they learnt

Tilak

7 WP-1051-15

that on 18th June 2009, on account of security concern raised

by Department of Atomic Energy (hereinafter referred to as

"DAE") regarding proximity of the proposed port to the

Tarapur Atomic Power Station, Alewadi port project was

dropped in the 51st Board Meeting of MMB. Several letters

were addressed by the petitioner to the MMB in January 2010

to issue LOI subject to obtaining security clearance within 36

months. Second Techno Economic Feasibility Study Report

was submitted on 14th June 2010. Petitioner learnt that

except the petitioner, none of the other previously qualified

and interested parties responded to the request for re-

submission of TEFS report.

8 However, in the month of August 2010,

Government of Maharashtra laid down a revised Port Policy

(hereinafter referred to as " 2010 Policy") which provided for

the permission of Greenfield Port/Multi purpose jetty/cargo

terminals wherein a tender process was suggested instead of

MOU route.




Tilak





                                    8                         WP-1051-15

9                 In February 2011, according to the petitioner,  on 

the submission of the proposal by third respondent to the first

respondent for construction of an All Weather Captive Port,

the third respondent was permitted to develop captive

port/jetty at Nandgaon, by issuing impugned Letter of Intent,

a lease deed followed by a Modification of Lease deed, which

lies on the approximate latitude 19º 46' North and 72° 41'

East. The said project happens to be exactly on the same

coordinates with the Alewadi port proposal of the petitioner

which is clearly depicted at Annexure A-28. Petitioner

contends that there was no compliance of port policies of

either 2005 or 2010. According to the petitioner, under the

guise of captive jetty facility, third respondent intends to

operate a port, and this is evident from the report of TEFS

submitted by respondent no.3 wherein they declare that the

proposal was for a Captive Port Facility which has all the

logistical advantages of large ports. The proposal further

states that not only it could handle the cargo of nearby plants

of respondent no.3, but also can meet the requirements of

adjoining areas for import and export purposes. On 16th

Tilak

9 WP-1051-15

March 2011, through the Solicitor of the petitioner they urged

Transport Secretary to award the Alewadi port to the

petitioner and in this letter, they had stated that issuance of

LOI to construct a jetty with the long term objective of

turning it into a port would amount to circumvention of

Government Policy of 2010. They further admit that in

November 2011, a representation was made to the then Chief

Minister of Maharashtra, contending that their case would not

fall within the scope of New 2010 Port Policy since their

proposal was submitted in 2007 in terms of earlier port policy,

therefore, it can be undertaken only through 'MOU route'.

They clarified the objection raised by Department of Atomic

Energy stating that DAE was under the mistaken impression

that the proposed Alewadi Project was within 3 kms radius

from Tarapur Power Plant, and in fact it was approximately 9

kms from the power plant.

10 Petitioner further contends that clarification of

DAE on 18th April 2012 with regard to development of a port

or jetty at Alewadi subject to certain terms and conditions

Tilak

10 WP-1051-15

being complied with, was never brought to the notice of the

petitioner. They further contend that they learnt about it

only from the impugned order. According to petitioner, upto

August 2012, they were pursuing their offer to develop the

Port at a distance of 6 kms South of the original location, and

were ready to comply with any conditions that may be

imposed by Tarapur Atomic Power Station in relation to the

port development at Alewadi. According to petitioner,

when petitioner was pursuing their offer of development of

port at Alewadi impugned lease deed was executed referring

to the project as 'port' and later in April 2013, Modification

Deed was executed granting additional 2500 meters of water

front along with land comprising inter-tidal and under water

area at the coast line of Nandgaon and Alewadi behind the

back of the petitioner.

11 On 31st July 2013, they raised serious objections

before MMB that development of a jetty at Nandgaon by third

respondent would seriously prejudice the development of port

at Alewadi since two entities cannot operate within the same

Tilak

11 WP-1051-15

location. Thereafter, WP(L) No. 3278 of 2013 came to be

filed wherein by an order dated 8th January 2014, the Bench

directed 2nd respondent to decide the petitioner's

representation dated 31st July 2013 expeditiously. It further

directed the 2nd respondent not to take a final decision in

respect of the development of Alewadi Port till the

representation of the petitioner is decided. Subsequently,

after conducting a cursory hearing without much opportunity

to petitioner, second respondent passed impugned order on

27th May 2014. It is contended that impugned order is an

illegal one directing for a correction to be made in the

documents executed in favour of respondent no.3 without

amending any of the terms of the document. Petitioner was

directed to submit a proposal to respondent no.1 for

development of a port at a site other than Alewadi in terms of

new 2010 policy. According to the petitioner, inspite of several

requests and demands including the lease deed between

respondent nos.1 and 3, the minutes of 51st Board Meeting, so

also objection letter of the DAE on 2nd August 2014, MMB

supplied only part of the documents without copy of the

Tilak

12 WP-1051-15

impugned lease deed which showed the location, size and

plan of the Port. On 17th July 2014, reiterating that it was

willing to comply with the conditions laid down by DAE, and

it was not interested in relocating the development of the port

to Satapati or Shirgaon, sent a letter to 2 nd respondent. On

17th July 2014, when things stood as stated, Modification of

Lease Deed replacing the word 'Port' with 'Jetty' in terms of

the orders of the second respondent came to be made. From

25th July 2014 till 15th December 2014, petitioner addressed

letters and met Officers of MMB enquiring whether they

would continue to refuse petitioner's request to have access to

the documents. Ultimately, on 15th December 2014, in a

meeting at MMB's office, petitioner was informed that no

further documents would be provided.

12 Petitioner contends that MMB falls within the

definition of State under Article 12 of the Constitution and

MMB violated Article 14 of the Constitution, therefore, Part III

of the Constitution for enforcement of fundamental rights

could be invoked. According to petitioner, when the

Tilak

13 WP-1051-15

objections of DAE were subsequently lifted, the petitioner's

offer ought to have been considered as alive, and ought to

have been granted in terms of 2000 Port Policy.

13 It is further contended the lease entered into

between first and third respondents is not in consonance

either with 2005 Jetty Policy or the 2010 Port Policy. The case

of the third respondent ought to have been in terms of 2005

Policy meant for multipurpose jetty requiring tender process.

The requirement of minimum distance between two

multipurpose jetties/ports was also not maintained since the

site of petitioner is within 5 kms distance from the site of 3 rd

respondent. They also contend that while keeping the

petitioner's application pending for 7 years without any

follow-up action by the respondents, hastily approved the

proposal of respondent no.3 to develop a port at Nandgaon

which came to be submitted only in the year 2011. This is

nothing but discrimination against petitioner.




Tilak





                                  14                            WP-1051-15

14              According   to   the   petitioner,   security   concerns 

raised with regard to Tarapur Atomic Power Plant would

equally apply to Alewadi and Nandgaon. Similarly, restriction

imposed on movement of foreign ships and chemical cargo in

the Alewadi area applies to the case of respondent no.3.

Totally ignoring above facts, proposal of respondent no.3 was

granted without fair opportunity to represent being given to

the petitioner. According to petitioner, respondent nos.1 and

2 did not consider repeated concern raised by petitioner that

sanctioning a jetty at Nandgaon would render proposal of

petitioner to establish a port at Alewadi, infructuous.

15 Petitioner further raises a grievance that the

request of the petitioner to proceed with its application

subject to a ''No Objection Certificate" from DAE, was not

responded. Similarly, the proposal of petitioner to shift the

location of port from Alewadi to a distance of 6 kms South of

original location even after DAE lifted the restrictions, was

not considered.




Tilak





                                  15                           WP-1051-15

16              According to petitioner, there is lack of application 

of mind by 2nd respondent in passing the impugned order and

the reasoning is vague and erroneous. They further contend

that first respondent has failed to take into account the

breach of various Port Policies. It is further contended that

without tender process or expression of interest route,

proposal of third respondent was hastily and erroneously

granted totally ignoring that petitioner was qualified for the

Alewadi port. It is further contended there is an effort to

confer on 3rd respondent to operate a port under the guise of

captive jetty which is clear from the observations made by

second respondent in the impugned order. By changing the

terminology, captive port facility to captive jetty facility, there

is no rectification of violation of the terms and conditions of

policies. There is no intelligible differentia upon which

differential treatment of the two classes of individuals in the

same situation came to be considered.

17 It is further contended that policy of MMB was to

develop a port at Alewadi in terms of 1996 policy. However,

Tilak

16 WP-1051-15

they kept the proposal of the petitioner pending from 2007

onwards and according to petitioner, it was alive till

Nandgaon was sanctioned in favour of third respondent

without following proper procedure. This is nothing but

colourable exercise of power on the part of respondent nos.1

and 2. With the above pleadings and arguments, petitioner is

before us contending that there is no delay and laches in

approaching the Court.

Contentions/Reply on behalf of Respondent no.1 -

MMB.

18 Per Contra, MMB denies all the allegations made

against the first respondent. Preliminary objection is that

there was no privity of contract between the petitioner and

respondents, hence, petitioner has no locus standi to maintain

the writ petition. Therefore, the petitioner cannot challenge

the veracity of a contract/agreement/LOI executed by and

between respondent no.1 and respondent no.3 since

petitioner is not a party to the said contract.




Tilak





                                   17                             WP-1051-15

19              It is further contended that the petitioner without 

substantiating its claim on any valid, binding or concluded

agreement cannot come before the Court on the basis of a

false, baseless and frivolous claim sought to be invoked in the

Writ Petition. At no point of time, there existed any promise

made or held to grant approval of proposed Alewadi port.

The relief seems to be specific performance of a contract

which does not exist and cannot be granted in a writ

jurisdiction.

20 According to the MMB, since the alleged claim is

based on disputed questions of facts, on assumptions and

presumptions no relief can be granted in a writ jurisdiction

under Article 226 of the Constitution, since there is no cause

of action in favour of petitioner against the MMB.

21 They also contend that the petition is bad for

delay and laches on the part of the petitioner since the

agreement between the MMB and third respondent came to

be entered into in 2011 which has been acted upon. These

facts were matter of public knowledge. The writ petition

Tilak

18 WP-1051-15

which came to be filed on 9th March 2015 seeking

cancellation of agreement without explaining the gross delay

and laches in filing the present petition as well as the earlier

litigation, there cannot be creation of a fresh cause of action

on the ground of impugned order of the second respondent.

22 According to the MMB, Government of

Maharashtra came out with 1996 policy inviting private

sector companies etc. to undertake the development of Ports

through public tender process. Initially, 7 ports were

identified and Tarapur in Thane district was included when

Global tenders were invited for development of Alewadi after

carrying out Techno Economic Feasibility Study (TEFS)

through the Consulting Engineering Services Pvt. Ltd. MoU

route with private developers was evolved when there was no

effective response to global tenders. In 2002, when

Maharashtra Infrastructure Summit took place, no one came

forward to develop Alewadi port. The policy of 1996 was

amended in 2002 wherein specific terms of agreement had to

be entered into with the port developers.

Tilak





                                   19                             WP-1051-15

23              When   things   stood   as   stated   above,   in   the   year 

2005, Government took a decision to notify the Self

Controlled Captive Jetty with the object of privatization of

minor ports in the State and it was in consonance with

privatization of minor ports in terms of 1995 policy in respect

of captive jetty. The signing of the agreement with the

entrepreneur for captive jetties was in terms of policy of

2005.

24 Along with the petitioner, one M/s.Videocon

Industries, M/s.Larsen & Toubro and M/s.SKIL Infrastructure

showed interest to develop Alewadi port. They were asked

to submit Techno Economic Feasibility Report (TEFS) along

with processing fee. TEFS reports of above four

entrepreneurs were got scrutinized through an independent

agency M/s.Deloitte. In the 48 th Board Meeting of the MMB,

Board was directed to submit a report to the State

Government and Principal Secretary (Transport) and the

proposal for selection of developer wherein they were

directed to indicate within how much time the tender process

Tilak

20 WP-1051-15

would be undertaken. Accordingly, the MMB submitted its

report to the State. The Home Department opined that the

process of tender for Alewadi port would take at least 23

weeks, and the same was to be placed before the next Board

Meeting. When the matter came up before 49th Board

Meeting, a decision was taken to refer the matter to High

Power Committee (HPC) who were in turn to submit

recommendations to the Government. Mean while, on 29 th

January 2009, DAE by its letter informed the State

Government the objection to the proposal for development of

Alewadi port raising the security concerns so far as Nuclear

Plant situate at Tarapur site. Therefore, the State Government

directed the MMB to examine the port proposal at Alewadi

vis-a-vis geographical details and also to discuss the same

with DAE. Respondent no.1 was also directed to intimate

interested developers to submit in writing if they were

interested in Alewadi port project, and after obtaining those

letters, they were to be submitted before the Board. On 18 th

June 2009, in 51st Board Meeting when the proposals of

Alewadi port came up for consideration, on account of

Tilak

21 WP-1051-15

security objections raised by DAE, a decision was taken not to

proceed with the development of Alewadi port project. An

alternative option to set a port North of Mumbai was also

directed to be examined. Written willingness of interested

developers were furnished to the State Government. On 11 th

June 2010, State Government informed respondent no.1 that

the development report of Alewadi port is based on 2002-

2003 data, therefore, it would not be conducive to consider

the said data in the year 2010. Respondent no.1 directed all

interested developers to submit fresh reports so as to get them

scrutinized through a consultant afresh. In response to the

request of respondent no.1 on 14th June 2010, petitioner

submitted its Techno Economic Feasibility Study Report.

Mean while, on 20th August 2010, State of Maharashtra came

up with a more dynamic investor friendly new port policy,

with special focus on corporate social responsibilities. On 16 th

November 2010 and 12th January 2011, Government directed

respondent no.1 to express its views on the objections raised

by DAE regarding security concerns.




Tilak





                                     22                        WP-1051-15




25              On   2nd         February   2011,   respondent   no.3 

approached respondent no.1 with a proposal to develop an

All Weather Captive Port facility for captive use by the third

respondent near Nandgaon since their Steel Plants are located

at Tarapur and Vashind. On 9 th February 2011, Respondent

no.1 addressed a letter to the Secretary (Transport Ports and

State Excise) suggesting shifting of the port location towards

South to Nandgaon area by 2 - 3 kms and further requested

the Government to take up the matter with DAE to allow the

development of port with additional security and safety

measures as required. In the month of September 2011,

proposal of respondent no.3 to develop captive port facility

at Nandgaon 3 kms South of Alewadi in accordance with

captive policy 1995 and 2005, GRs, was considered. This was

with a view to reduce burden of rail and road infrastructure.

In December 2011, respondent no.1 signed a Lease Deed with

respondent no.3 for development of captive jetty at

Nandgaon. In April 2012, DAE conveyed conditional

clearance for development of port/jetty at Alewadi/Nandgaon

Tilak

23 WP-1051-15

which declared that no foreign vessel will be called at the

proposed port/jetty. On 7th August 2012, petitioner submitted

a letter proposing to develop port on an alternate site

between village of Satpati and Shirgaon. However, no

feasibility study report was submitted. In the month of

January 2013, respondent no.3 requested modification of

lease deed for waterfront area for the development of an All

Weather Port facility, wherein they clearly indicated that after

signing the lease in the month of December 2011, extensive

study of the area conducted by respondent no.3 suggested

construction of two breakwaters, one in the North and other

in the South to make captive port facility operational for more

than 220 days in a year. Therefore, Deed of Modification

came to be signed in April 2013.

26 At this stage, petitioner filed a Writ Petition

bearing WP (L) No. 3278 of 2013 before this Court against

first and second respondents herein. MMB was not separately

served. On 8th January 2014, a direction was issued against

respondent nos.1 and 2 to decide the representation of

Tilak

24 WP-1051-15

petitioner dated 31st July 2013 within 12 weeks after giving

personal hearing. After hearing was conducted on 12 th

February 2014, a detailed order was passed on 27 th May 2014

directing the MMB to make necessary amendments in the

agreement signed between respondent no.1 and respondent

no.3 clarifying and restricting the captive jetty at Nandgaon

for the use of captive purpose only. Further, petitioner was

allowed to submit a proposal to respondent no.1 for alternate

location in lieu of Alewadi port development. It further said

that such proposal of petitioner, if any, has to be in terms of

provisions of New Port Policy of 2010. Accordingly, in July

2014, a Deed of Modification came to be executed between

respondent no.1 and respondent no.3 to substitute 'captive

port facility' with the word 'captive jetty'. In October 2014,

MMB received notice from the petitioner proposing intended

application to the Government under India United Kingdom

Bilateral Investment of Protection Agreement (BIPA). This

indicated that the petitioner was choosing to proceed with an

alternative remedy. According to first respondent, for the

reasons stated above, petitioner had no locus standi to file the

Tilak

25 WP-1051-15

present petition apart from there being no cause of action in

the absence of privity of contract between the parties.

Contentions/Reply of respondent no.2.

27 According to 2nd respondent, there was no cause

of action against 2nd respondent since order dated 27th May

2014 by the 2nd respondent was made only after giving fair

opportunity of hearing to the petitioner in terms of directions

of the High Court by order dated 8th January 2014, and the

impugned order is a self- speaking order.

28 Second respondent contends that State of

Maharashtra has set up Maharashtra Maritime Board (MMB)

- respondent no.1, a statutory body under the Maharashtra

Maritime Board Act, 1996. They administer and promote

maritime projects for Greenfield ports and various types of

jetties, coastal shipping, etc. in terms of Indian Ports Act

1908, and the Inlands Vessel Act, 1917. Policies are laid

down by the Government of Maharashtra and the day-to-day

administration of the policy is carried out by respondent no.1.

Tilak





                                  26                            WP-1051-15

They are empowered to execute lease deed, sale and purchase

of property, apart from granting concessions for various port

projects applicable in terms of policy. Policies were with the

main object of promoting maritime sector in the State from

time to time. In the year 1996, as per Exhibit-A, a G.R was

issued notifying private sector companies to develop ports

through public tender process which included Tarapur in

Thane district. Global tenders were initially invited for

development of Alewadi Port after carrying out Techno

Economic Feasibility Study, but no sufficient response were

received. On 28th November 2000, Government of

Maharashtra issued notification for developing Dighi and

Rewas ports by entering into MOU with private developers,

and also stated that the port development would be on the

basis of Build, Own, Operate, Share and Transfer ("BOOST").

The main object was to develop the ports in a time bound

manner. Policy of 1996 was further amended in the year

2002 wherein specific terms of agreement have to be entered

into with the Port developer in terms of Exhibit-1. Mean

while, in the year 2005, Government Resolution was issued

Tilak

27 WP-1051-15

for Self Controlled Captive Jetty. The main component of Port

Policies have been privatization of minor port in the State as

laid down in the 1995 Policy in respect of captive jetty in the

State as laid down in the G.R of 19 th August 2005 giving

sanction to the signing of the agreement with entrepreneur

for captive jetty before the G.R dated 23 rd January 2005.

Those policies are Exhibit-2, 2A and 2B.

29 By indicating special focus on corporate social

responsibilities, a new port policy came to be declared on 20 th

August 2010 to make it more dynamic and investor friendly.

As per Exhibit-3, various policies have been laid down

separately for Greenfield port and captive jetties. Under the

said policy, a clear distinction has been made between green

field ports and jetties. Both projects have similar purpose of

handling cargo and vessels and many elements of

infrastructure such as wharf, approach channel, capital and

maintenance dredging, cargo, handling gear, breakwater,

ancillary facilities may be common to both. However, the

specific element of infrastructure needed for jetty or for port

Tilak

28 WP-1051-15

depend upon site conditions and business plan of the

promoters. Government has separate policies for port

projects. Captive jetty is different from a port which is mainly

intended to handle inward and outward cargo of a specific

large industrial unit whereas port generally handles public

cargo. Any industrial unit planning a captive jetty can do

only at a logistically convenient and proximate location on

the coastline.

30 The State government was making continuous

efforts to develop a port north of Mumbai in order to

decongest the existing Mumbai port and to provide additional

cargo handling capacity. There were continuous efforts to

develop a port at Alewadi. According to them, mere

submission of TEFS even if on two occasions, does not confer

any right on the petitioner or anyone for that matter.

However, said project could not take off on account of

security objections raised by DAE. In its letter dated 18 th

February 2009, State Government directed respondent no.1 to

examine the port proposal at Alewadi vis a vis geographical

Tilak

29 WP-1051-15

details and discuss the same with DAE. They were further

directed to intimate interested developers to submit in writing

if they were interested in the said Alewadi project, and after

obtaining the details, proposals should be placed before the

Board. On 11th June 2010, State Government addressed a

letter to the MMB that the development of port of Alewadi is

based on 2002-2003 data, therefore, directed to obtain fresh

reports from all interested developers.

31 Mean while, DAE conveyed conditional clearance

for development of captive jetty at Alewadi/Nandgaon which

includes that no foreign vessel will be called at the proposed

port or jetty. Government also directed the MMB in October

2010 to follow up the proposal of Port Policy of 2010 for

selection of a promoter for Alewadi port. It suggested to

follow EOI route by competitive bidding. Therefore, the

petitioner whose proposal was much prior to 2010 port policy,

was not ipso facto entitled for award of the project

concession. Subsequent to the conditional clearance by DAE

to the project in 2012, it would not have been legal and

Tilak

30 WP-1051-15

proper to consider petitioner's application merely on the basis

of persuasion when 2010 port policy was very much in force.

Respondent no.1 has given permission to respondent no.3 for

captive jetty at Nandgaon for handling their cargo for their

Steel Plant at MIDC, Tarapur. On 2nd August 2016, the State

Government gave a direction to respondent no.1 to ensure

that the existing policy of captive jetty is followed while

scrutinizing the Detailed Project Report of Nandgaon jetty.

Contentions/Reply of respondent no.3.

32 In the reply affidavit of respondent no.3, all the

allegations made against respondent no.3 are denied as false

and incorrect. The prime objection of respondent no.3 is with

regard to gross delay of more than 14 months on the part of

the petitioner in approaching the Court from the date of

passing of the impugned order.

33 They contend that in 2011 itself, notices were

published inviting comments or objections with regard to

Nandgaon project before any development is carried out.

Tilak





                                    31                             WP-1051-15

Similarly, several newspapers carried the news on 5th

September 2012 by Maharashtra Pollution Control Board

notifying the public at large to hear on the Environmental

Issues so far as development of Nandgaon port. Hence, third

respondent contends that petitioner though had prior

knowledge in the year 2011 itself of Nandgaon project being

granted to respondent no.3 since all the events were within

the public domain and knowledge, still, petitioner makes

dishonest statements against respondent nos.1 and 2 stating

that petitioner was not informed that respondent no.3 has

been given permission to construct port/jetty at Nandgaon.

According to third respondent, petitioner was very much

aware of the development of Nandgaon port much prior to

2015 since any commercial entity in the business is expected

to have such knowledge.

34 Similarly, the very conduct of the petitioner

disentitles it to get the relief by making false and reckless

allegations against respondent no.2 alleging a cursory, hasty,

formal hearing without giving fair opportunity of being heard

Tilak

32 WP-1051-15

to the petitioner. Such allegations are concocted since they

are raised at a belated stage, and it is nothing but an after-

thought. By letter dated 30th June 2014, when Advocate for

the petitioner sought copies of the documents and material

relied upon by the second respondent, no allegations were

made against anyone.

35 According to third respondent, petitioner

deliberately with malafide intention did not make the third

respondent as a co-respondent in the earlier WP(L) 3278 of

2013 before this Court, even though petitioner was fully

aware of respondent no.3 entering into a Lease Deed with

the respondent no.1 on 3rd December 2011. This was only

with an intention to snatch orders behind the back of third

respondent by resorting to unfair tactics. The intention was to

make an ex-parte representation before respondent no.2

which is clear from the observations made in the impugned

order dated 27th May 2014.




Tilak





                                  33                             WP-1051-15

36              Third respondent refers to the representation by 

letters dated 18th April 2012 and 23rd May 2012 made by the

petitioner before the MMB identifying alternate site between

villages of Satpati and Shirgaon for development of a port

which is about 5.4 kms to 8 kms from the site at which

respondent no.3 is constructing the captive jetty at Nandgaon.

Third respondent contends that there is concealment of

several facts which were within the knowledge of

petitioner,therefore it amounts to dishonest conduct on the

part of the petitioner.

37 In terms of Policy dated 26th June 1995 made by

Government of Maharashtra, the captive jetty project was

allotted to respondent no.3. Such privilege was already

extended to several companies like (i) Ambuja Cements,

(ii)Ispat Industries, (iii)Vikram Ispat Ltd, (iv)Finolex

Industries Ltd and (v)Ratnagiri Gas and Power LNG Naptha

Pvt.Ltd, etc. Respondent no.3 along with its sister concerns

have taken the steps in furtherance of object of constructing

the Captive Jetty by expending about Rs.70 crores.

Tilak





                                   34                            WP-1051-15

38              According to third respondent, the proposal of the 

petitioner to construct a commercial port falls under 2010

GR/Port policy which does not apply to the respondent no.3.

This is quite contra or opposite or in contrast to the

construction of captive jetty to handle captive cargo

undertaken by respondent no.3. 1995 Policy of the

Government was introduced with the avowed objective to

enable industry to flourish by importing raw material directly

or in close proximity to the activity carried out by the

industries. Respondent no.3 in fact has Steel Plant, Power

Plant at MIDC Tarapur as well as Vashind which are in close

proximity to the captive port facility proposed by respondent

no.3. It also operates as a deep water hub port for JSW Steel

Works at Dolvi, which operates out of a riverine port.

39 Letter of Intent of respondent no.1 in favour of

respondent no.3 is dated 19th October 2011 for the

development of All Weather Captive Port facility at Nandgaon

which has to be used subject to terms and conditions

mentioned in the LOI. A lease deed dated 3rd December 2011

Tilak

35 WP-1051-15

for development of All Weather Captive Port at Nandgaon is

also executed. Extensive campaign for collecting field data

on Hydraulic parameters, soil profile, seabed profiles etc, was

undertaken. With mathematical precision, model studies

were conducted and a detailed feasibility study report was

prepared and submitted. Its intention is to construct Captive

Port Facility. Inter-Tidal land and waterfront for Captive Port

facility was accordingly leased. This is initially for a period of

five years since the project is on Build, Operate Transfer basis

("BOT"). Required agreements and MOU are already entered

into between respondent no.1 and respondent no.3 for land

filling which are required for the development of the captive

port. Several lands are purchased by respondent no.3 nearby

where the captive port is being constructed and the details

are at Exhibit-F. Allotment of Nandgaon project in favour of

third respondent was under G.R of 1995 which requires no

bidding process as contended by the petitioner. In terms of

order dated 27th May 2014, by respondent no.2, modifications

were brought to the lease deed to convert the permission to

operate as a 'captive jetty' instead of 'captive port'.

Tilak





                                  36                             WP-1051-15

40              They   further   contend   that   they   have   invested 

considerable financial investments in the project engaging

contractors, man power equipment by expending Rs.57 crores

for purchasing the land in the villages for back-up and lay

down storage. A Development Guarantee was executed in

favour of respondent no.1 for Rs.5 crores for a span of five

years. One time security deposit of Rs.10.10 lakhs is also

paid. Huge amounts are spent for various surveys,

investigations, studies, so also contracts with several

contractors, suppliers and third parties. Therefore, respondent

no.3 has made substantial investments and altered its position

to the detriment in the development of captive jetty by

entering into various contracts with third parties for various

services. According to third respondent, despite having

knowledge of all this, petitioner without taking any steps

immediately, waited for 14 months after the impugned order.

41 The case of respondent no.3 is distinguishable

from the case of petitioner since respondent no.3 is intending

to develop only a captive jetty and not a commercial port

Tilak

37 WP-1051-15

unlike the petitioner. Both State of Maharashtra and Gujarat

have such captive/private jetties in terms of 1995 Policy. In

terms of State Policy, it empowers the State to permit

construction and maintenance of jetties to private

entrepreneurs and also to allot land under water (Inter-Tidal

land) and waterfront for the said purpose. Ownership is to

vest with the Government after completion of lease or licence

period in favour of third parties which could be for 25 to 30

years for handling their captive cargo. At the discretion of the

Government of Maharashtra, such lessee or licensee can also

handle third party cargo, but it is subject to terms and

conditions in the G.R dated 26 th June 1995. There is no

requirement or mandate of any bidding or tendering the

process so far as captive jetty is concerned. About 29 such

jetties are operating on Gujarat Coastline. The sole purpose is

to encourage port based industries to construct captive jetties

to cater to the export and import requirement. In the year

2005, Government of Maharashtra came up with a G.R with

respect to multipurpose terminals/jetties to be constructed

within the limits of small ports in the State. However, the

Tilak

38 WP-1051-15

policy of the State in relation to the construction and

operation of jetties continued to be governed by 1995 Policy

& 2005 Policy. After several consents, compliances, including

impact of reclamation of coastal line by spending huge

amounts, third respondent has proceeded to develop the

captive jetty.

42 After conducting studies regarding Marine

Ecology distribution of Benthic organism, Air, water and noise

pollution etc, report was submitted to Environment Impact

Assessment (EIA). All required studies needed for the same

were conducted including impact of reclamation activities on

coastal environment etc. Central Marine Fisheries Research

Institute (CMFRI) was appointed as agency for assessment of

impacts on the fish production due to the project. NOC is

issued by Commissioner of Fisheries, State of Maharashtra.

Requisite consent of Maharashtra Pollution Control Board

came to be issued on 10th July 2013. No Objection Certificate

with respect to Coastal Regulatory Zone was also issued by

Maharashtra Coastal Zone Management Authority by letter

Tilak

39 WP-1051-15

dated 24th February 2015. At this belated stage, the petitioner

approaching this Court cannot prejudice the interest of

respondent no.3, is the stand of the respondent no.3.

43 On behalf of respondent nos.4 and 5, a reply

affidavit is filed contending that in the month of August 2008,

the DAE informed MMB to set up a captive jetty at village

Navapur, Taluka Palghar, District Thane which is at an aerial

distance of about 3 kms from the boundary of Tarapur Atomic

Power Station. They also informed that due to strategic

location of the jetty, there could be implications on the

Security of the Tarapur Atomic Power Station (TAPS) vide

letter dated 1st October 2008. Nuclear Power Corporation of

India sought clearance of respondent no.4 for establishing

port/jetty at Village Alewadi near MIDC, Tarapur on the

request made by respondent no.3 vide their letter dated 8 th

September 2008 addressed to Station Director, TAPS. In the

said letter, it is stated that matter has been referred to their

Corporate Planning Group for scrutiny from the site selection

point of view and Corporate Planning Group confirmed that

Tilak

40 WP-1051-15

Alewadi village falls outside the Sterile Zone, and no

restriction has been imposed by the Nuclear Power Plant on

use of land which is beyond Sterile Zone. It further stated

that the matter, however, may kindly be scrutinized from the

security point of view at the earliest for forwarding the

necessary clearance to M/s.JSW Steel Ltd. At no point of

time, neither the petitioner nor respondent no.1 nor

respondent no.2 had ever approached respondent no.4 with

full facts regarding development of port near Tarapur Power

Station. The issue was only raised when respondent no.4 was

intimated by Central Agency about the development of port

being undertaken at an aerial distance of 3 kms from Tarapur

Atomic Power Station from safety and security point of view.

After receiving the said letter, respondent no.4 sought views

on the issue for establishing a port/jetty at Alewadi near

MIDC Tarapur from Bhabha Atomic Research Centre, Atomic

Energy Regulatory Board and Nuclear Power Corporation of

India. Similarly, views were sought from central agency and

subsequently, after considering all the points raised by all the

concerned authorities, on 29th January 2009, intimated the

Tilak

41 WP-1051-15

Chief Secretary, Govt. of Maharashtra that Tarapur site of the

DAE is located at an aerial distance of about 3 kms from

proposed site/location. The site has 4 nuclear power plants

apart from certain critical facilities of DAE. The establishment

of port/jetty being close to the above coast based installations

of DAE, will have security implications of a grave nature.

According to them, nature of material handled in the vessels,

ships visiting the jetty close to the shores of DAE installations,

and engagement of a possibly large labour force would pose

security threat/risks. The release of explosives would also

have an impact on the nuclear installations. Therefore, the

proposal for the Alewadi port/ jetty was directed to be

dropped keeping in view the security implications for the

nuclear power station at Tarapur site. Therefore, respondent

no.4 intimated Government of Maharashtra that the above

concern was only advisory and not binding on respondent

no.1 and respondent no.2.

44 After a span of 2 years, Chief Secretary of

Maharashtra again sent a letter dated 26th August 2011 to

Tilak

42 WP-1051-15

Secretary of respondent no.4 to reconsider the objections

raised with regard to development of port/jetty at Alewadi as

it is the suitable site North of Mumbai for development of

port as the aerial distance between Alewadi site and Tarapur

installation is about 7 to 8 kms and not 3 kms as perceived by

DAE. The State expressed that it was keen to develop port at

said site as it may form part of Delhi - Mumbai Industrial

Corridor which will enable the State to get the benefit of

Dedicated Freight Corridor between Delhi and Mumbai. They

also requested the respondent no.4 to prescribe any

additional safety measures which may be required. Again,

respondent no.4 sought recommendations and views from

various authorities as stated above. The Central Agency in

response to the above request informed that Government of

Maharashtra can reconsider the proposal subject to certain

conditions which, inter alia, included no foreign vessel should

be allowed to call on for any purpose, and that the activities

at the jetties should be carried out under the supervision of

responsible officer of Government of Maharashtra. After

securing responses from various Authorities, 4th respondent

Tilak

43 WP-1051-15

issued NOC to Government of Maharashtra by letter dated

18th April 2012 stating that the matter was examined afresh in

consultation with various authorities, and after taking into

considerations of security as well as safety aspect of

respondent no.4, installations at Tarapur DAE has no

objection for the proposed project of Alewadi port/jetty if it is

developed beyond south side of Dandi village with certain

conditions and activities/works at the port needs to be

checked with certain aspects in terms of the letter.

45 In rejoinder affidavit to the affidavit of respondent

no.2, petitioner contends that MMB is required to act under

the instructions and decisions of respondent no.2 being a

Minister of Ports as the Chairman. Under those

circumstances, in the order dated 8 th January 2014, the Court

recorded that the second respondent had informed the Court

that the process of appointment (of a developer for Alewadi

Port) had not begun, and that, in any case, it was not possible

to appoint any person within three months. Therefore, a

direction was given to respondent no.2 to decide the

Tilak

44 WP-1051-15

petitioner's application to grant LOI for the development of

the Alewadi port. However, in the year 2009, the application

made by respondent no.3 for setting up an All Weather

Captive Port at the said location was also addressed by them

to the Minister of Ports. The petitioner further contends that

All Weather Port is completely distinct from a jetty, captive or

otherwise and the two have also been dealt with separately

under the Policies/Guidelines of the Government. They

categorically denied that ports and jetties have similar

purpose of handling cargo and vessels. They have also denied

that many elements of infrastructure such as wharf, approach

channel and maintenance dredging, handling gear, break

water, ancillary facilities may be common to both. According

to the petitioner, surreptitiously while delaying the

consideration of LOI to the petitioner with regard to "Alewadi

Port", granted permission to respondent no.3 to set up an All

Weather Port at Nandgaon. An All Weather Port should have

large tranquil harbor/water area in which a number of jetties

and berths can exist. Whereas a jetty is located in protected

waters. The captive jetties can also handle cargos of third

Tilak

45 WP-1051-15

party. Therefore, the distinction between captive jetty

handling cargo of a specific industrial unit and the port which

handles cargo generally is lost. The lease deed dated 3 rd

December 2011 read with the plan issued in favour of

respondent no.3 indicate permission to construct only a single

long jetty and the modification lease deed dated 4 th April

2013 records that the jetty could only be operational 220 days

or less in a year. This also provided construction of a North

and South breakwater to provide necessary tranquility inside

the port area. The lease deed also refers to granting

permission by respondent no.1 for setting up and establishing

an All Weather Captive Port facility along with necessary

back up infrastructure. Therefore, it is clear that what had

been proposed by respondent no.3 and permitted by

respondent nos.1 and 2 was not a mere 'jetty', but a large all

Weather Multipurpose Port with a capacity and dimensions

substantially greater than the petitioner's proposal.

46 The MMB decided not to proceed with the

development of Alewadi Port in view of DAE's objections,

Tilak

46 WP-1051-15

however, the 2nd respondent directed MMB in 2010 to

proceed with the development/call for fresh TEFS Report

from interested parties, and had taken up the matter with the

DAE for reconsideration. The petitioner's proposal was kept

pending, but entertained application of respondent no.3 to set

up an All Weather Captive Port in the form of an extended

jetty/ Southern breakwater at Nandgaon which is a mile

south of the petitioner's proposed Alewadi Port. In 2012, NOC

for setting up of a port was obtained from DAE subject to

some conditions including the exclusion of foreign cargos.

Under these circumstances, according to the petitioner,

respondent no.2 made a submission to the High Court on 8 th

January 2014 that process of appointment of a developer for

Alewadi Port has not yet begun, and it is not possible to

appoint any person within three months. Before respondent

no.2, MMB falsely contended that in view of DAE's objection,

MMB had decided at its 51st Board Meeting in June 2009 to

cancel or not to proceed with the Alewadi project. The order

of respondent no.2 on both aspects denying the petitioner an

LOI to develop Alewadi port only on the ground that MMB

Tilak

47 WP-1051-15

had in 2009 decided not to proceed with Alewadi Port and

holding that respondent no.3 had only been permitted to set

up a Captive Jetty at Nandgaon on the Southern side of

Alewadi is ex-facie perverse, discriminatory and arbitrary. On

the other hand, petitioner was the only party which had

submitted revised/updated TEFS to MMB within the time

stipulated. The observation of respondent no.2 that it would

not have been legal and proper to consider the petitioner's

application since Port Policy of 2010 required competitive

bidding is ex-facie incorrect, and appears to be part of

respondent nos.1 and 2's efforts to stop the application of the

petitioner while discriminatorily favouring respondent no.3.

Since application of the petitioner was made much prior to

new Policy of 2010, announcement of Policy of 2010 did not

result in the abrogation of the old policy. In fact, the

Environmental Impact Assessment report of respondent no.3

and the clearance showing the proposed All Weather Port, by

renaming the same as 'captive jetty' cannot change the

position that the capacity of respondent no.3's project is

larger than the petitioner's proposed Alewadi port having

Tilak

48 WP-1051-15

multiple berths and a dimensions.

47 So far as affidavit in rejoinder to respondent

no.3's affidavit, petitioner contends that the area covered by

Government of Maharashtra's tender of 1996 for Alewadi Port

covered a large area from 19° 44' 24" to 19° 50' 44" more

than six nautical miles north to south.

48 The third respondent's application and TEFS

report of 2011 fixed the location of their All Weather Captive

port at 19° 46'. The breakwater/jetty permitted was located at

19° 45' 20" which arched northwards approximately half a

nautical mile. In the mean while, MMB's Modification of the

lease in 2013 comprised a tranquil water area enclosing 19°

46' and North breakwater located at 19° 47'. Therefore, the

third respondent's All Weather Port purported to be permitted

almost overlaps the area of the petitioner's proposed Alewadi

port. Maharashtra Coastal Zone Management Authority

(MCZMA) recommendation to MOEF of JSWs All Weather

Multi Cargo Port refers to it as located between 19° 45' 44"


Tilak





                                  49                            WP-1051-15

and    19°   46'   30",   having   North   breakwater   of   6.5   kms,   a 

South breakwater of 5.2 kms and 6 berths for solid cargo

handling, a dedicated berth for coal and three berths for

liquid cargo, LNG and chemicals.

49 In the additional affidavit of respondent no.1, it is

stated that the footnote of performance audit of CAG reflects

understanding of the difference between a jetty and a port by

CAG, cannot be of any relevance since the understanding of

CAG is contrary to the factual position. Further, it is not an

appropriate body to distinguish the basic/fundamental

integrities of the maritime industry. The availability of a jetty

or port is purely an operational matter depending upon fair or

foul weather. One can have all weather jetties with break

waters as well as ports which may not have breakwaters or be

operational throughout the year.

50 The purpose of a breakwater is to prevent the jetty

or port from exposure to rough wind/seas which make the

jetty or port vulnerable to the weather. Therefore,the need of

Tilak

50 WP-1051-15

breakwater depends upon the geographical location of a jetty

or a port and is not a ground for distinguishing a jetty from a

port or vice-versa. Mere existence of breakwater does not

mean that a jetty is a port or vice-versa. They also narrate

illustrations of some ports and jetties with or without

breakwaters, while Mumbai Port is a natural harbor and does

not require any breakwater, similarly, Dighi port because of

protection provided by cliff/hill from south westerly direction,

it does not require a breakwater. The old jetty of MMB at

Bhagawati Bunder, Ratnagiri which is now run by a third

party is open to weather and has a breakwater. Respondent

no.3 proposed to construct two breakwaters i.e. one in South

and other in North to make the captive jetty facility

operational for more than 220 days in a year since unless

tranquility inside the area for optimal utilization of Captive

Facilities is made, the jetty cannot be utilized to optimum

level. Hydrodynamics and soil profile of the area suggested

that the base of southern breakwater be shifted northwards.

Therefore, proposal of the modification lease deed in favour

of respondent no.3 was accepted.

Tilak





                                  51                             WP-1051-15




51              In the additional Affidavit of respondent no.3, it 

took a stand that maritime boards of various states have

allotted captive jetties to investors which are "All Weather" in

nature. Gujarat Maritime Board has given several such All

Weather Captive Jetties. Captive Jetties can also handle third

party cargos, and Gujarat Maritime Board had granted such

permission to Essar Bulk Terminal and others in Gujarat.

According to them, if third party cargos are to be handled, it

will have to do so with the prior permission of the MMB, and

if permission is granted, respondent no.3 is required to bear

the existing cargo related charges payable to the Government.

CAG is not the authority to declare as to whether captive

jetties can or cannot operate All Weather, therefore, credence

cannot be given to their report.

52 They further contend that magnified Navigational

Chart No.210 published by the National Hydrographic Office,

Dehradun, plotting the relevant locations/sites and distances

in question, clearly indicate following.


Tilak





                                   52                            WP-1051-15

   (i)          Encircles   5   km   radius   of   sterile   zone   from 
                Tarapur reactor

   (ii)          The lines of the port limits of Alewadi as per 

the instructions to Bidders issued by the Government of Maharashtra, Commissioner Water Transport, May 1996 (page No.618 of Petitioners Rejoinder dated 6th November 2015);

(iii) The limits of Nandgaon allotted to respondent no.3 as per the respondent no.1's affidavit dated 2nd December 2016 read with the plan annexed to the amended Lease Deed executed between Respondent NO.1 (Maharashtra Maritime Board) and respondent no.3 (page Nos.1204 - 1205 Exhibit C to Respondent NO.1's affidavit dated 2nd December 2016).

53 It further says that the distance from Tarapur

Atomic Power Station is 5 kms as encircled on the annexed

chart. The north limit of Alewadi Port is within the 5 kms of

sterile zone of TAPS)

Discussion and reasoning:-

54 With the above pleadings and contentions, what

exactly one understands from 1995 captive facility policy

which was modified from time to time. We also have to

analyze what is 1996 port policy and what are the

modifications made to it?

Tilak





                                  53                             WP-1051-15

55              One has to see under which policy the case of the 

petitioner falls and similarly to which policy the case of

respondent no.3 is attracted. In terms of G.R dated 26 th June

1995, privatization of non-major ports in Maharashtra

(Captive Jetty facility) to encourage participation of private

sector for the development of the port in terms of new

industrial policy, the policy was evolved.

56 However, the privatization of minor ports in State

of Maharashtra as a Captive Jetty facilities for port

development has to come through Water Transport

Commissioner. The private component is required to prepare

general outline of construction of jetty. They also have to

prepare hydraulic calculations in consultation with Central

Water and power Research Station (CWPRS) and then, seek

approval from the Water Transport Commissioner. It is also

the responsibility of the private component to get the design

approved from the consultant appointed by the MMB. If

Captive Jetty facility were to be extended to third parties

(other industries) the same has to be with prior permission of

Tilak

54 WP-1051-15

Water Transport Commissioner subject to other terms and

conditions, including the charges/taxes, fee payable. The

main character of 1995 Captive Policy was to give Captive

facility to private entrepreneurs which could be made use for

its industry. On 19th August 2005, the Government of

Maharashtra issued a resolution thereby amending the policy

in respect of captive jetties providing that permission would

be granted to developers to handle third party cargo, in

addition to the handling of their own cargo from captive jetty,

subject to the rates fixed for handling third party cargo i.e.

1.5 times than the rates fixed for captive jetties. Further,

such permissions would be applicable till the period of

agreement entered with the MMB in respect of captive jetties.

57 Additional criterion was that such benefit would

be binding only upon the entrepreneur who have already

entered into an agreement prior to the issuance of such

resolution. Since third respondent secured LOI only in 2011,

and there was no agreement prior to 19 th August 2005 in

favour of third respondent for captive jetty, the benefit of

Tilak

55 WP-1051-15

handling third party cargo automatically would not come to

the benefit of the third respondent unless they take prior

permission from respondent nos.1 and 2. Subsequently, on

20th November 2005, the Government Resolution sets out the

duration with the entrepreneur of captive jetties which has to

be indicated in the agreement and the captive jetty has to be

constructed on Build, Operate Transfer (BOT) Basis.

58 So far as 1996 Policy, Government of Maharashtra

has enacted Maharashtra Maritime Board Act, 1996 to make

provisions for establishment of MMB for minor ports in State

of Maharashtra and it is vested with the administration,

control and management of special ports. So also to provide

for matters connected therewith and incidental thereto.

MMB was established on 17th January 1996 in terms of

Section 3 of the MMB Act and Minister of Ports is Ex-officio

Chairman. In terms of Section 24, MMB has power to enter

into contract for lease, and specific provision under Section

24B and 24C of the MMB Act says that no contract for leasing

waterfront, jetty, waterway, and corresponding infrastructural

Tilak

56 WP-1051-15

facilities thereof for a term exceeding 5 years shall be made

unless it is previously approved by the Government on such

terms and conditions as it may think fit. Further, no contract

for the acquisition of sale of immovable property or for the

lease of any such property for a term exceeding 30 years,

shall be made unless it is previously approved by the

Government on such terms and conditions as it may think fit.

It is also not in dispute that State Government lays down

frame work of the policy, be it captive jetty, or multipurpose

ports, but the day to day administration in terms of the

respective policy is regulated by the MMB.

59 On 15th March 1996, Government of Maharashtra

came out with a policy in respect of development of minor

ports through public tender process. In other words, it laid

scheme for down growth and development of multipurpose

ports. Initially, seven ports were enlisted including Tarapur

in Thane district. In the month of May 1996, instead of

Tarapur, Alewadi was chosen as a suitable site. Global

tenders were invited for development of Alewadi port after

Tilak

57 WP-1051-15

carrying out Techno economic feasibility survey through its

Engineering department. However, there was no positive

response. Mean while, in the month of November 2000,

Government of Maharashtra issued notification for

development of Dighi and Rewas Ports with an understanding

with private developers on the basis of BOOST. The purpose

was to develop the ports in time-bound manner.

60 Subsequently, by Government Resolution dated

15th March 1996 and 28th November 2000, policies were

amended on 24th April 2002 providing for specific terms of

agreements to be entered into with the port developers. The

Government of Maharashtra issued a revised port policy for

promotion of green field ports/multipurpose jetties/cargo

terminals on 20th August 2010 inter alia providing as under :

"The concessions under the 2010 policy shall also be applicable to the existing (where concession agreement have been extended) Greenfield Port Projects, Cargo Terminals (Ro-Ro services) and Multipurpose Jetties for the remaining works for a period of 5 years from the date of signing of an amended agreement to that effect".

Tilak

58 WP-1051-15

These concessions shall also be applicable to projects of Multipurpose Jetties/Cargo Terminals to be set up in future.However,Wharfage charges would be levied for Cargo Terminals (Ro-Ro services) and Multipurpose Jetties in a different manner and shall be promulgated separately through a Notification.

The procedure for selection of Developers for the Multipurpose Jetties and Cargo Terminals (Ro- Ro service) will be governed by the existing 2005 G.R and shall have the same concession period as mentioned in this Resolution.

The annexure to the GR provided as under:

Procedure for selection of Port Developer (New Port Projects) Expression of Interest (EOI) should be called for selection of the port developer instead of directly taking the MOU route.

Developers should be selected through a transparent process of bidding from financially capable and truly interested bidders in Port Development coming through EOI. The standard concession document of the Central Government should also be referred to for this purpose.

If required response is not received from EOI, then MOU route should be followed.

Letter from State Government to CEO, MMB stating that instead of selecting person through MOU route it should invite expressions of interest. It refers to the DAE letter dated 29.09.2009 and states that the onus of taking clearances from DAE will be on the Port developer. It further states that only after receiving all clearances should development of port begin.

Tilak





                                    59                             WP-1051-15



61              On   4th  February   2016,   New   Port   Development 

policy of 2016 was introduced by a Government

Resolution. In the said policy, different sections are provided

for (i) Greenfield Ports and connectivity (ii) Jetties provided

for Captive Jetty (3) MMB owned Jetties and multipurpose

Jetties. In terms of 2016 policy, captive jetty can handle

third party cargo subject to following conditions :-

(i) Cargo from the third parties should not exceed 25% of the total cargo handled by the captive jetty in a year.

(ii) The charges applicable on the cargo handled for third parties will be 1.5 times the charges specified the rates.

(iii) There is no non-major port available, with desired facilities, within a distance prescribed by the MMB through notifications.

62 From the above material placed on record, it is

seen that 1995 Government Resolution is in respect of

privatization of minor ports in Maharashtra (including captive

jetty facility) and 1996 Policy is in respect of construction of

multipurpose ports for growth and development of ports.

From time to time, as indicated above, the policy of the

Tilak

60 WP-1051-15

Government was changed in respect of both captive facilities

as well as multipurpose facilities. It is made clear on more

than one occasion that in the policy of Government

Resolution dated 15th March 1996, Government Resolution

date is mentioned as "6th June 1995" instead of "26th June

1995".

63 According to the petitioner, under the guise of

captive jetty port facility (All Weather facility) is granted in

favour of third respondent in order to scuttle the project of

the petitioner. According to the petitioner, there was a

concluded contract in their favour and therefore, indirectly to

overcome the said contract, Nandgaon location is chosen so

far as respondent no.3 is concerned, and ultimately, in view of

the policy restricting two ports working within a distance of 5

kms, petitioner's proposal cannot be granted. Therefore, by

entering into lease agreement with third respondent, the right

accrued in favour of the petitioner is interfered with.




Tilak





                                    61                             WP-1051-15

64              According   to   the   petitioner,   respondent   no.3 

applied for All Weather Port which in fact, meant to be all

purpose in the month of February 2011 at a latitude 19° 46'.

They also referred to the lease deed entered into in December

2011 to show that the long strip at Nandgaon as indicated at

page nos.67, 71 and 72 of the writ papers indicating that

stage by stage, the so called captive jetty became All Weather

Port. It is nothing but same project for which petitioner

acquiesced a right since petitioner was the earlier applicant

than the third respondent. It is further contended that this is

clear from the conduct of the parties, especially modification

terms of lease deed in April 2013 allowing setting up of a

port. According to the petitioner, throughout the documents,

it is referred to as 'port', therefore it was not at all a captive

jetty in fact.

65 It is also contended on behalf of the petitioner

that the DAE's objection raised in 2009 as one of the reasons

against the proposal of petitioner, is ex-facie perverse,

arbitrary and discriminatory because the so called DAE's

Tilak

62 WP-1051-15

objection of 2009, and the decision of MMB not to proceed

with Alewadi project in June 2009 in 51 st Board Meeting is

only a ruse to deny the petitioner's claim since the

development of Alewadi port remained under active

consideration of the Government as well as MMB even after

2009. They rely upon the correspondence between the

Government and DAE in 2010, 2011 and contend that the

very fact of DAE reviewing its decision in 2012 by

communication dated 18th April 2012 indicating its NOC for

the development of Alewadi port subject to certain conditions

would indicate Alewadi port proposal was alive. Therefore,

according to them, both MMB and Government by April 2013

permitted the respondent no.3 to set up a full fledged port at

the very same location proposed by petitioner under the guise

of permitting captive jetty in favour of third respondent.

66 In order to appreciate these contentions of the

petitioner, we have to see whether there was malafides and

systematic exercise on the part of the first and second

respondents as contended by the petitioner to set at naught

Tilak

63 WP-1051-15

the project of the petitioner by granting captive jetty facility

to third respondent (in fact meant to be a multipurpose port

as contended by the petitioner). We also have to see whether

petitioner had any concluded contract in its favour so far as

multipurpose port proposed by them way back in 2007. We

also have to see whether there is direct or indirect assurance

on behalf of respondent nos.1 and 2 that petitioner would be

getting sanction for multipurpose port at Alewadi. Whether

there was conscious and genuine decision on the part of the

MMB to take a decision in its 51 st Board Meeting not to

proceed with Alewadi project in view of DAE's objections also

to be seen. We also have to see whether granting permission

to have two breakwaters South and North in favour of the

third respondent would automatically mean,the infrastructure

meant for a port is granted in favour of third respondent,

therefore, under the guise of captive jetty, third respondent

would be running a multipurpose port. Whether the

contention of the respondent nos.1 to 3 that the words "jetty"

and "port" are interchangeable, and they are loosely termed

not only in the documents pertaining to the controversy

Tilak

64 WP-1051-15

before us, but also in several projects of Maritime Board all

over the country including Mumbai and other projects.

67 Based on the pleadings of the parties, we also

have to examine whether there is delay and laches on the part

of the petitioner in approaching the Court, and whether by

conduct of the petitioner i.e. concealing several facts which

were within its knowledge, has not come to Court with clean

hands in the first round of litigation intentionally by not

making third respondent as a party to the proceedings.

According to respondents, on account of malafides on its part,

petitioner is not entitled for any of the reliefs sought in the

present petition. They further contend that even in the

present litigation, many material facts are concealed by the

petitioner.

68 Coming to the proposal of the petitioner, it is not

in dispute that a tender notice was issued by Government of

Maharashtra inviting global tenders, but there was no positive

response. Though the port policy was revised to allow

Tilak

65 WP-1051-15

selection of developers through MOU route, no one came

forward so far as Alewadi project till 2006. Development

occurred only after the ports at Dighi and Rewas were

entrusted for the development. Four potential developers,

including the petitioner showed interest in Alewadi port

development. Techno Economic Feasibility Study Reports

were called from all these developers. Expression of Interest

to develop an All Weather and Multipurpose port at Alewadi

came from the petitioner in 2007. On 7 th February 2007,

petitioner submitted its Techno Economic Feasibility Study

Report followed by a request on 25 th February 2007 to issue a

formal Letter of Intent. It is also not in dispute that petitioner

informed respondent no.1 that they had entered into joint

venture with a well known port operator i.e. M/s.

International Container Terminal Services. Meetings were

held between the petitioner, and Dy. Minister of Ports in the

month of July 2007 wherein discussions were held with

regard to awarding of LOI. In order to take a decision so far

as selection of developer for Alewadi port, reports were got

scrutinized through independent agency M/s.Deloitte. In the

Tilak

66 WP-1051-15

48th Board meeting of the MMB, proposal for selection of

developer was placed. In the said meeting, Board directed

the first respondent to submit the report to State Government

and Principal Secretary. Along with the summary evaluation

of independent agency M/s.Deloitte, the reports were

submitted to State Government. Petitioner gave

representation to Hon'ble Chief Minister and other authorities

to consider their proposal in the month of December 2007. In

the 49th Board Meeting held on 25th April 2008, as per the

direction of the Government, the issue of development of

Alewadi port was kept before the Board. In the said meeting,

it was decided to take the development of the Alewadi port by

Memorandum of Understanding route through a High Power

Committee (HPC) for approval of the Government.

Therefore, discarding the tender process, the MOU route was

adopted for development of Alewadi project.

69 It is clear from record that even in the month of

April 2008, there was no final decision on the proposal of

development of Alewadi port. It was still at the stage of what

Tilak

67 WP-1051-15

route or procedure would be adopted for allowing the

development of Alewadi port. Neither first respondent nor

second respondent gave any positive accord, consent or

approval for development of Alewadi port to the petitioner.

A letter dated 29th January 2009 which is in the compilation

of documents filed on behalf of respondent no.1 - MMB at

page 57, indicate that it was addressed to Chief Secretary,

Government of Maharashtra, Mantralaya from DAE, Mumbai

with regard to setting up a port/jetty to be developed by

M/s.JSW Steel Pvt.Ltd (not the third respondent). In this

letter, at paragraph no.2, it is mentioned that Tarapur site of

the DAE is located at an aerial distance of 3 kms from the

proposed site location, and the said site has four nuclear

power plants apart from critical facilities of DAE. The

establishment of a port/jetty at Alewadi village, the location

proposed by MMB being close to the above coast based

installations of DAE, there would be security implications of a

grave nature. The nature of material handled, transported

vessels and ships visiting the jetty close to the shores of DAE

installation, and engagement of a possibly large labour force

Tilak

68 WP-1051-15

would pose security risk and threats to Tarapur site of the

DAE. They also expressed apprehension with regard to

impact on the nuclear installations if there is to be release of

chemicals or triggering of explosives. Therefore, they advised

the State Government to drop the proposal for the

development of port/jetty at Alewadi village for the reasons

stated above.

70 On 18th February 2009, State Government wrote a

letter to the MMB to examine the port proposal at Alewadi vis

a vis geographical details and discuss the same with DAE.

Respondent no.1 was directed to intimate interested

developers to submit in writing if they were interested in the

said Alewadi project. They were directed to place the

proposals before the Board. On 18 th June 2009, 51st Board

Meeting was held, the Minister for Ports, Principal Secretary,

Transport Representative of Finance, Principal Secretary

(Finance), Indian Navy representative, Ashwin Kumar - Chief

Executive Officer, Member Secretary were all present.

Agenda  item no.13  was with regard to Alewadi port.     On 

Tilak





                                   69                              WP-1051-15

account of the objections raised by Nuclear Power

Department of the Central Government on the proposed

development of Alewadi port, it was unanimously resolved

that there was no need to take further action for the present.

An appropriate alternative site should be thought of to

develop a port to the North of Mumbai. Therefore, it is very

clear that even on 18th June 2009 there was no concluded

contract or even inclination of consent or permission in

favour of petitioner. However, Government of Maharashtra

continued to follow up the effort to develop a port to the

North of Mumbai in order to decongest existing Mumbai port

and provide additional cargo handling capacity. Inspite of

objection dated 18th June 2009 by DAE, the State Government

directed MMB to examine port proposal at Alewadi after

discussing the same with DAE. Further directed to seek in

writing if developers were still interested in Alewadi project.

MMB informed the State Government by forwarding the

willingness of 4 interested developers, and all the four entities

by different letters had expressed their interest in Alewadi

port project. On 11th June 2010, respondent no.2 informed

Tilak

70 WP-1051-15

respondent no.1 that development report of Alewadi port is

based on 2002 and 2003, therefore, they directed to obtain

fresh report and scrutinize the report through consultants.

Petitioner submitted project report on 14th June 2010, and so

also M/s.Larsen & Toubro had expressed their willingness for

submission of their project report while M/s.Videocon

Industries had requested for extension of time for submission

of project report. By 20th August 2010, Government of

Maharashtra revised port policy for development of non-

major ports/multipurpose jetties/ cargo terminals and

selection of developers was through competitive bidding

process. On 13th October 2010, respondent no.2 directed

respondent no.1 to invite Expression of Interest by following

new policy of 2010. The Government of Maharashtra made it

clear that No Objection Certificate from DAE has to be

secured by port developer in view of the objections raised by

DAE. Between 16th November 2010 and 9th February 2011,

there was correspondence between Government of

Maharashtra and MMB with regard to the objections raised

by DAE. They were contemplating change of location in view

Tilak

71 WP-1051-15

of DAE's objection regarding security. Such letters are dated

16th November 2010 by Government of Maharashtra and

reply is dated 9th February 2011 by MMB to the Government

of Maharashtra. Ultimately, feasibility of shifting location of

port towards South of Nandgaon by 2 - 3 kms, they were of

the opinion that DAE may not have objection, and therefore,

they thought of shifting the location towards South to

Nandgaon by 2 - 3 kms. Respondent no.1 requested

respondent no.2 to take up the issue with DAE. They also

made it clear that as per the Navigational Chart No.210

published by the National Hydrographic Office, Dehradun, the

aerial distance between Alewadi site and Tarapur installation

is about 7 - 8 kms and not 3 kms as perceived by DAE. On 3 rd

September 2011, State Government wrote a letter to

reconsider the objections of DAE to develop port/jetty at

Alewadi. Only on 18th April 2012, DAE gave conditional

clearance for development of port jetty at Alewadi/Nandgaon

which includes no foreign vessel will be called at the

proposed port/jetty. Till this time also, there was no

concluded contract between the petitioner and the MMB for

Tilak

72 WP-1051-15

development of port or jetty at Alewadi. Mere calling for

Techno Economic feasibility Study Report for the second time

from petitioner would not vest the petitioner with any right to

say that they had a concluded contract in their favour.

Techno Economic feasibility Study Reports were sought not

only from the petitioner, but also from other three proposers

who showed interest to develop the multipurpose All Weather

Port at Alewadi. The proposal of the MOU route was again

revisited by revised port policy for permission of greenfield

ports/multipurpose jetties and cargo terminals in 2010.

Mean while, for the captive use of respondent no.3, the

proposal to develop All Weather Captive Port/jetty facility

near Nandgaon was granted since they have their steel plants

located at Tarapur and Vashind. By this time, MMB suggested

shifting of the port location towards Southwards to Nandgaon

by 2 - 3 kms. While taking such a decision, the State

Government was also pursuing simultaneously to have

revisitation of the proposal at Alewadi. On 20 th September

2011, there was approval of the proposal of respondent no.3

to develop captive facility at Nandgaon which was about 3

Tilak

73 WP-1051-15

kms South of Alewadi in accordance with captive jetty policy

of 1995. At many places, in the correspondence lease deed,

modified lease, they have used the words "port" and "jetty".

Irrespective of user of word "port" or "jetty", ultimately, we

have to see what was the proposal of respondent no.3, and

what was the proposal of the petitioner. Petitioner was all

along interested to develop multipurpose All Weather Port at

Alewadi. The proposal of the respondent no.3 is for

development of a captive facility whether it is called captive

jetty or port and it was at Nandgaon' since they have their

industrial establishment i.e. steel plants located at Tarapur

and Vashind. Therefore, they wanted All Weather Captive

Port/Jetty facility. All along, the proposal of respondent no.3

was only in pursuance of 1995 policy and nothing to do with

1996 policy. Even now, by virtue of the impugned order, the

respondent no.2 has made it clear that respondent no.3 will

have only the captive jetty establishment in terms of 1995

policy which is revised from time to time in accordance with

the guidelines pertaining to captive jetty and not in terms of

All Weather multipurpose greenfield port policy.

Tilak





                                  74                             WP-1051-15

71              On   18th  April   2012,   DAE   after   required 

consultation conveyed clearance for development of

port/jetty at Alewadi. By this time, the proposal of the third

respondent was fructified into lease deed on 3rd December

2011. At that point of time also, there was no concluded

contract or offer in the form of consent or permission either

from respondent no.1 or respondent no.2 in favour of the

petitioner. Even otherwise, petitioner was not keen to subject

itself to revised port policy of 2010 which required tender

process for development of multipurpose port. There was no

concluded contract for development of a multipurpose port by

the petitioner in terms of 1996 policy when respondent no.1

signed a deed of lease in favour of respondent no.3 for

development of captive port/jetty at Nandgaon on 3 rd

December 2011. The impugned order is not even challenged

by respondent no.3 on the ground that they were granted a

port development proposal in terms of 1996 policy. Instead,

the petitioner is aggrieved by the direction of respondent no.2

to change the word 'captive port' to 'captive jetty' in the lease

document between respondent no.1 and respondent no.3.

Tilak





                                  75                             WP-1051-15

This would indicate that from the time of proposal submitted

by respondent no.3, till impugned order was passed by

second respondent, third respondent was interested in having

a captive facility in terms of 1995 policy, and they have

nothing to do with 1996 policy.

72 In order to appreciate the stand of the petitioner

that the very conduct of the respondent nos.1 and 2 in calling

upon them to furnish a techno economic feasibility report

even after decision to give up development of Alewadi port in

2009, gave indication that they were still inclined to develop

the port. If petitioner were to submit its proposal on the lines

of 1996 policy since there was no concluded contract or least

assurance on behalf of respondent nos.1 and 2 that the

petitioner would be considered favourably and positively for

the development of Alewadi port, as on the date of the

impugned order passed by second respondent on 27th May

2014, only 2010 Policy was in existence and not 1996 policy.

In fact, in 2012, petitioner did enquire whether there is

possibility of developing a port between Satpati and Shirgaon.

Tilak





                                  76                           WP-1051-15

This would further indicate that by 2012, they gave up the

proposal of development of Alewadi port and were thinking

of an alternate proposal. This clearly indicates the petitioner

was aware of objections raised by DAE, its inability to

effectively run commercial port at Alewadi since they could

not allow foreign vessels near Tarapur Power Station.

Therefore, they were ready to develop a port between Satpati

and Shirgaon. Only in the month of July 2014, they wrote a

letter dated 18th July 2014 expressing their unwillingness to

relocate to Satpati and Shirgaon. Apparently, techno

economic feasibility study report for the same never came to

be submitted.

73 Mean while, 2010 revised port policy for

permission of Greenfield Port/Multi purpose jetty/cargo

terminals was again revised by 2016 to introduce Greenfield

Ports and connectivity, Jetties providing for Captive Jetty,

MMB owned Jetties and multipurpose Jetties. Therefore, by

the time they offered their willingness to develop port at an

alternate site in 2012, port policy was changed, and as on

Tilak

77 WP-1051-15

today, there is port development policy of 2016. The

clearance from DAE subsequent to 2010 policy indicate that

no foreign vessel is allowed and Expression of Interest is to be

called and not Memorandum of Understanding. Apparently,

petitioner was intending to start a multipurpose port

(commercial port at Alewadi). Since foreign vessels cannot be

allowed within certain radius from Nuclear power plant, there

is no question of any commercial port functioning near

Alewadi. Even if petitioner were to seek development of a

port at alternate site, it can be only in terms of the existing

policy.

74 It is also clear from the record that now the

captive jetty facility of respondent no.3 is at Nandgaon having

breakwaters. Therefore, we are of the opinion it may not be

possible to allow any port/jetty being developed near Alewadi

for commercial purpose. There is one more reason which

goes against the petitioner. The petitioner is a Private Equity

Fund and is engaged in the business activities of venture and

capital Investment. Apparently, it is incorporated under the

Tilak

78 WP-1051-15

laws of United Kingdom, and is engaged in the business of

investment and development of infrastructure. Petitioner

has only a correspondence address at Mumbai which is clear

from the affidavit of respondent no.3, and also the supporting

documents. When the petitioner's main interest is to make a

commercial port for container handling in collaboration with

ICL Financial Services Ltd and ICD Terminals, Inc. (both

foreign companies), there is nothing on record to show that

these two companies who were interested to invest major

portion of money for the Alewadi project in 2007 are still

interested to take the project as a joint venture. It is also

petitioner's case that International Container Terminal

Services Inc (ICTSI) was to operate the port on completion of

the proposed Alewadi port. There is nothing on record to

show that this port operator continued to have interest in the

Alewadi project as on today.

75 It is pertinent to note that till reply affidavit of

respondent nos.1 to 3 came to be placed on record, the

petitioner did not even whisper about the existence of 1995

Tilak

79 WP-1051-15

captive facility policy of the Government of Maharashtra. At

page 456 of MMB's compilation of documents annexed to

their reply affidavit, policy of 1995 dated 20 th June 1995 is

placed on record. In the introduction, it is said that Konkan

region being a difficult territory for transport, water transport

is an important facility for the development of minor ports.

Port facilities have received unique importance for industrial

use as also for rapid development of Konkan region.

Participation of private sector for the development of the port

in the new industrial policy was encouraged considering the

availability of funds, advanced technology and essential

machinery to create facilities for the development on the 48

ports exist on the coast line. Expected response was received

from private entrepreneurs and the Government was

contemplating what facilities should be created for the private

entrepreneurs, and what should be the terms and conditions

for the use of the ports. After great discussion, the decision to

execute prescribed agreement with the Water Transport

Commissioner by the private component, came into existence.




Tilak





                                  80                           WP-1051-15

76              At clause (d), it says that ownership of the jetty 

shall be with the Government, but the jetty shall be given to a

private Company on lease or licence for 25 to 30 years,

subject to terms and conditions including permission to give

the facility of jetty to other industrial units for use with the

prior permission of Water Transport Commissioner.

77 The resolution governed by 2010 Policy G.R.

dated 20th August 2010 indicate that after detailed discussion

with all the stakeholders involved in the process of

development of maritime activities, existing policy frame

work of other adjoining states like Karnataka, Andhra Pradesh

was examined, and comprehensive changes were made and a

revised policy frame work was placed before the cabinet

which approved the port policy of 2010 applicable to the new

greenfield ports/cargo terminals and multipurpose jetties. It

further says that the procedure for selection of developers for

the multipurpose jetties and cargo terminals will be governed

by existing Government Resolution dated 19th August 2005.

Apparently, the multipurpose jetties would mean jetties other

Tilak

81 WP-1051-15

than having captive facility which can be used for various

purposes just like multipurpose port. The third respondent is

now given the facility of All Weather Captive Jetty. No doubt,

in terms of Government policy, third respondent can also

permit handling third party cargo subject to payment of

prescribed fee and also permission of MMB, apart from other

terms and conditions like restriction on foreign vessel within a

particular radius from Tarapur Power Station on account of

security reasons. The case of the third respondent is not a

stand-alone case providing captive jetty facilities. As stated

above, several industrial entities are given such facilities by

Maritime Board not only in the State of Maharashtra, but also

by Maritime board in the neighboring States - Gujarat,

Karnataka and Andhra Pradesh. The details are already

referred to above.

78 The location of Nandgaon is chosen by the third

respondent because of existence of its industrial units at

Navapur and Vashind etc. One cannot find fault with the

entrepreneur to take advantage of the captive facility in terms

Tilak

82 WP-1051-15

of existing policy of the government if it were to be cost

effective so far as the private entrepreneur is concerned. It is

also policy of the State that industrial policy should

comprehend with the maritime policy so as to assist the State

Government to boost the economy of the State, so also to

encourage private entrepreneurs to undertake captive facility

which would be cost effective, both for the State and the

private entrepreneur. Captive facility is permitted only if they

were to have industrial unit which require import and export

of raw material and also other related activities. The very

term 'captive' means the usage and benefit is restricted to that

particular private entrepreneur, therefore, it would not be out

of place to opine that primarily the captive jetty benefit was

to boost the private entrepreneurs to come forward to have

captive jetties on the Konkan coastline to benefit their

industrial units. Every private entrepreneur may not be

interested in seeking captive facility due to various reasons

including financial burden. Therefore, if smaller industrial

units which are not capable of having their own captive

facility and were to depend on captive facility given to a

Tilak

83 WP-1051-15

private entrepreneur, subject to terms and conditions evolved

by the policy makers, one has to appreciate the forward step

of the State for encouraging the development of industries by

providing such facilities. Therefore, the charges for allowing

third party to a particular percentage of handling is altogether

at a different rate from the normal rates for handling cargos.

The policy of the Government regulated through MMB clearly

indicate captive facility was primarily meant for the benefit of

private entrepreneurs for the purpose of its own industrial

use, but later, extended the same to a particular limit for the

use of third parties. Therefore, captive facility sanctioned to

third respondent cannot become a commercial cargo venture

equivalent to the proposal of the petitioner by merely

allowing it to handle third party cargo in terms of revised

policy of the State.

79 It would be relevant to refer to the decision of

larger Bench of the Supreme Court in Villianur Iyarkkai

Padukappu Maiyam Vs. Union of India 1 The lis pertains to

1 2009 (7) SCC 561 Tilak

84 WP-1051-15

challenge to contract for development of a port at the

instance of Government of Pondicherry inviting Expression of

Interest for preparation of feasibility study report for

development of Pondicherry Port. Several parties responded

for the development of Pondicherry port including "S" seeking

permission to participate in the process of development of

port. On account of paucity of funds, Government accepted

offers and awarded contract for development of the port to

"S". A person who had neither participated in the process of

selection of consultant/developer of land, nor had expressed

desire to develop the port, filed Writ Petition before the High

Court challenging the award of contract in favour of "S" on

the ground of arbitrariness. It was also contended by the said

person that the award of contract was contrary to the earlier

decision of Government to get feasibility report before taking

development of the port. Various other issues with regard to

Impact of the Project on the Environment on the ground of

interest of the local people were raised. Their Lordships

opined that the State in a given situation may chose to change

its earlier policy if it turns out to be advantageous for the

Tilak

85 WP-1051-15

State to do so. In such situation, State would not be

committing breach of any constitutional obligation. They

further opined that State is not obliged to tell respondent

therein :

"please wait I will first advertise, see whether any other offers are forthcoming and then after considering all offers, decide whether I should get the port developed through you"

80 The State must be free in such a case to negotiate

with the private entrepreneur with a view to induce him to

develop the port. Under such circumstances, the Court must

only see whether the State had acted out of improper or

corrupt motive, or was interested to promote the private

interest of a private entrepreneur.

81 In the present case, the issue of captive facility to

be provided to private industrial units was in existence right

from 1995. In order to develop the Mumbai - Delhi Express

Corridor, the State also was pursuing development of non-

major ports and one of them was Navapur and not even

Alewadi. On account of security reasons concern raised by

Tilak

86 WP-1051-15

DAE, MMB abandoned proposal of Alewadi. However, State

Government was still pursuing Alewadi proposal. Therefore,

between 2009 to 2012, respondent nos.1 and 2 were not able

to pursue the proposal of Alewadi. Mean while, third

respondent proposal came for captive port, their requirement

being primarily their own industry. Even if the third

respondent had asked for multipurpose port/All Weather

Port/Captive Port, ultimately their request was considered in

terms of 1995 Port Policy of the State to provide captive

facility. We do not find any improper or corrupt motive on

the part of the State or MMB in approving the project of the

respondent no.3.

82 Whether the interchangeable word as contended

by respondent nos.1 and 3 i.e. 'jetty' for 'port', 'port' for 'jetty',

and permission to have two breakwaters for the purpose of

tranquility to make the captive facility of third respondent

workable or usable atleast for 220 days in a year would

amount to expansion of the facility extended to third

respondent.

Tilak





                                  87                            WP-1051-15




83              Was it only to encourage respondent no.3  on the 

part of the respondent no.1 to discourage the proposal of

petitioner? The contention of the petitioner is that jetty

would mean a long pier, and there is no need to have

breakwaters. They mainly rely upon the footnote of

performance audit submitted by Central Audit General which

is part of petitioner's compilation of documents filed along

with affidavit in rejoinder at page nos.1009 to 1011.

84 Whether the opinion of CAG officer or their

understanding would decide the controversy of the third

respondent being a captive facility or the multipurpose

facility. We should refer to the material placed on record by

respondent nos.1, 2 and 3. MMB is justified in saying that

CAG is not the expert to give opinion how one should

understand the difference between a jetty and a port.

Apparently, MMB is the authority who deals with the

regulation and day-to-day administration of non-major ports.

According to them, one can have All Weather Jetties with

Tilak

88 WP-1051-15

breakwaters, and similarly, there can be ports which may not

have breakwaters or be operational throughout the year.

Breakwaters would mean a construction or a facility which

would be capable of preventing the jetty or port from its

exposure to wind/rough water, thereby preventing the jetty or

port exposed to rough water making the jetty or port

vulnerable depending upon weather conditions and nature of

water. There is possibility of having jetty or port without any

breakwater. It could be in a situation where there is a natural

hill or a cliff which prevents wind, thereby there is tranquility

in the water. If jetty or port were to function without

breakwater in the absence of natural protectors, it may not be

possible to utilize jetty or the port to its optimum level since

there would be constraints and restraints. Geographical

location of a jetty or port would decide whether there is a

need for breakwaters, but mere provision of breakwater may

not decide the factor, whether it is a port or jetty. Therefore,

mere existence of a breakwater would not make a location a

port or jetty. Breakwater is a requirement which mainly

dependent on the geographical requirement.

Tilak





                                   89                            WP-1051-15




85              According   to   the   petitioner,   third   respondent   is 

proposing and having been permitted to set up the

multipurpose All Weather Port which is substantially larger

than the petitioner's proposed Alewadi port. To substantiate

this contention, they refer to the proposal of 2011 of

respondent no.3 where it was All Weather Captive Port. They

also refer to lease deed dated 3 rd December 2011. But the

allotment is for a jetty for captive use. They also refer to the

Deed of Modification dated 3rd April 2013 executed between

MMB and 3rd respondent to show that land was leased for

"setting up and establishing an All Weather Captive Port

facility along with necessary backup Infrastructure and other

relevant facilities". Therefore, All Weather Port with North

and South breakwaters, and multiple berths/jetties in the

enclosed tranquil area was given is the contention. They also

contend that mere changing words "Captive Port Facility" in

the lease deed with the words "Captive Jetty", it would not

mean it is a captive jetty since in fact it is captive port facility

because it has facility of North and South breakwaters.

Tilak





                                   90                            WP-1051-15




86              Report   of   CAG   on   MMB's   activities,   was   mainly 

relied upon by the petitioner to opine that Captive jetties are

to be for the exclusive use of the concerned industry and are

not to be operational during the monsoon. CAG says that a

"Jetty" is a single pier or wharf jutting out into the water and

used for berthing vessels and also loading and unloading of

cargo. A jetty is not protected by breakwaters and mainly is

not operational during the monsoon. They also opine that in

some cases, jetties are located in naturally protected waters,

and they can operate even during the monsoon months. This

means jetty can be operated in monsoon if the location is

naturally protected i.e. hill or cliff as stated above. A Port in

contradistinction, according to CAG, has a large area of

tranquil water either natural or created by erecting

breakwaters having a number of berths/jetties with all

infrastructure facilities needed for operation of the port.

87 The illustrations given by first respondent, with

regard to some ports and jetties with or without breakwaters,

Tilak

91 WP-1051-15

would establish and clarify the factual position. They are

Mumbai Port - a natural harbor which does not require

breakwaters. Similarly, port at Dighi because of protection

provided by cliff/hill from south westerly direction, it does

not require a breakwater. The old jetty of first respondent at

Bhagawati Bunder, Ratnagiri being open to weather in fact

has a breakwater. The photographs of the said jetty is

exhibited at Exhibit-B at page 1126 to the additional affidavit

of MMB filed on 5th July 2016. According to third

respondent, they have never suppressed any fact, and they

say that they did ask for an All Weather Captive Port facility at

Nandgaon by their application dated 2nd February 2011.

Apparently, respondent no.1 never replied to respondent no.3

that such a facility would be ultra vires to the MMB Act or

1995 policy. On the other hand, on 20 th November 2011,

respondent no.3 was permitted to set up All Weather Captive

Port. On 19th October 2011, respondent no.3 conveyed

approval to set up an All Weather Captive Port facility.

According to them, the words "jetty" and "port" have been

used interchangeably in the 1995 policy. Apparently, there is

Tilak

92 WP-1051-15

nothing on record either by way of policy or procedure or

decision of respondent no.1 that there cannot be a jetty which

can be All Weather. On the other hand, material goes to show

that Gujarat Maritime Board has allotted All Weather Captive

jetties to various industries like Essar Bulk Terminal (Salaya),

Dahej Harbour Infrastructure Ltd, Ambuja Cements Ltd etc.

which are annexed to additional affidavit of respondent no.3

dated 29th June 2016. The word "All Weather" cannot be

equated with the word "All purpose" or "multipurpose". All

Weather means it can be functional through the year if

needed. Therefore, respondent no.3 is not the only Company

which is given All Weather Captive facility. They are given

permission to develop captive facility at Nandgaon which is

about 3 kms South of Alewadi in accordance with captive

jetty policy of 1995. The policy clearly indicate the words

"port" and "jetty" are interchangeable, and in fact, were used

interchangeably. According to respondent no.1, respondent

no.3's proposal to construct two breakwaters, one in South

and one in North was only to make captive jetty facility

operational for more than 220 days in a year, since the

Tilak

93 WP-1051-15

industrial unit of respondent no.3 work throughout the year.

Therefore, one cannot find fault with them if they were to

make the captive facility operational, whether you call as a

captive port/captive jetty functional for more than 220 days

in a year. After considering the request of respondent no.3

which is mainly based on the scientific survey and opinion i.e.

on the basis of Hydrodynamics and soil profile of the sea,

they decided to shift the base of the southern breakwater

towards northwards. This was accepted by the MMB.

88 It is pertinent to mention at this stage, there was

no concluded contract in favour of the petitioner. Even if we

presume that the captive facility now granted to respondent

no.3 would be operational and functional, equivalent to a

port, one has to see whether any vested right was in existence

in favour of the petitioner at the relevant point of time when

the proposal of respondent no.3 was accepted, fructified into

agreement, lease deed and modification of lease deed, etc.

From the material placed on record with regard to allegation

of respondent no.3's project, not being a port within the

Tilak

94 WP-1051-15

notified limits of port under the Indian Ports Act as contended

by the petitioner, it is seen apparently, is within the Navapur

Port, which is a notified port. Item nos.19 and 20 of the First

Schedule which is notified as "Port" under Part X of the First

Schedule of the Indian Ports Act refer to Navapur and

Tarapur. Prior to notification dated 15 th February 1996,

Navapur was notified as a port under Section 5 of the Indian

Ports Act. On the other hand, Alewadi has never been

notified as a port under Indian Ports Act, 1908. In clause

2.1.2 of the tender notice, as could be seen from petitioner's

compilation, port limits of Alewadi Port was still to be

notified. Before anything could happen, the proposal for

development of Port at Alewadi was unanimously abandoned

in the 51st Board Meeting on account of DAE's objection. In

the initial plan submitted by respondent no.3 for the

waterfront, the storage area for the port was envisaged to be

located on the shore. After verification, when they found that

the land near the coastline was not available due to various

local reasons, they addressed a letter to respondent no.1 on

25th January 2013 requesting to permit them to reclaim the

Tilak

95 WP-1051-15

inter-tidal area. The modification of the lease deed in April

2013 is with regard to waterfront area, and there was no

change so far as user of the port as captive facility. The

captive port or jetty was only for the respondent no.3 cargo,

so far as third party cargo, it can handle only with prior

permission of MMB subject to other terms and conditions.

From the documents placed on record by MMB pertaining to

Gujarat and other neighboring states as well as the material

placed on record by respondent no.3, it is clear that by mere

existence of breakwater, one cannot call the project as a

multipurpose port. It can never be changed from captive

facility to multipurpose facility because of it being "All

Weather". Similarly, by loosely using the words "jetty" and

"port" also cannot make the facility provided to respondent

no.3 as multipurpose facility (like a commercial port) since it

was always meant to be captive facility, and it is now made an

All Weather Captive facility in terms of 1995 policy which is

revised from time to time.




Tilak





                                  96                             WP-1051-15

89              Whether the location of the proposal of petitioner 

and  respondent   no.3 would overlap?    Apparently, from  the 

plan and map provided by the petitioner and the MMB, there

is likelihood of overlapping of the area so far as All Weather

Captive Facility extended to respondent no.3 since the North

breakwater permitted would cover a portion of area proposed

by the petitioner.

90 In the absence of a concluded contract, even to

think that petitioner falls within the arena of doctrine of

legitimate expectation, in the present petition, one has to see

what exactly the doctrine of legitimate expectation, and when

it can be invoked. In the voice of Apex Court reported in the

case of Ram Pravesh Singh and others Versus State of

Bihar, (2006) 8 SCC 381, legitimate expectation is not a

legal right. It is only an expectation of a benefit, relief or

remedy that may ordinarily flow from a promise or

established practice. In order to attract the definition of

legitimate expectation, apart from the expectation, it should

also be reasonable, logical and valid expectation. It further

Tilak

97 WP-1051-15

says that legitimate expectation occurs only if the decisions

passed by administrative authority affecting the person by

depriving him of some benefit or advantage which either

(i) he had in the past being permitted by the decision maker

to enjoy and which he can legitimately expect to be permitted

to continue to enjoy until it has been communicated to him

on some rational grounds for withdrawing it if he had been

given an opportunity to comment; or (ii) he has received

assurance from the decision-maker that they will not be

withdrawn without giving him first an opportunity of

advancing reasons for contending that they should not be

withdrawn.

91 It was also held in Union of India Vs. Hindustan

Development Corporation1, however sincere a wish, a desire

or a hope may be, and however, confidently one may look to

them to be fulfilled, they by themselves cannot amount to an

assertable expectation, and a mere disappointment does not

attract legal consequences. Therefore, their Lordships opined

1 1993(3) SCC 499,

Tilak

98 WP-1051-15

that such expectation which could be a legitimate one, should

be justifiably legitimate and protectable because every

legitimate expectation cannot result into a right becoming a

conventional right in its sense. One cannot conclude that

petitioner either acquired a vested right or a concluded

contract in its favour. One cannot even opine that it had in

fact, a legitimate expectation in its favour, since none of the

conditions required for legitimate expectation are available.

Further, legitimate expectation is not a legal right in its

conventional sense.

92 We have to see whether mere proposal or mere

receipt of techno economic feasibility study report on more

than one occasion would vest the petitioner with any right

with regard to proposal of Alewadi port. Proposal of Alewadi

port was directed to be abandoned on account of DAE's

concern of security reasons. On persuasion from the MMB

and the State, DAE relaxed and suggested it could be down 3

kms South from proposed Alewadi port. Even in the area of

operation extended to respondent no.3, no foreign vessel is to

Tilak

99 WP-1051-15

be allowed close to the Tarapur Power Plant. They may have

to have their own arrangement how to get the cargo from

high sea to the shores. There cannot be any relaxation of

such restriction, as long as such restrictions by DAE continues

to exist.

93 Next consideration is whether petitioner concealed

relevant and important material facts which would disentitle

it for any relief even if we presume that they were to be in

line with the case of third respondent, it is seen respondent

no.3 entered the scene somewhere in 2011 and sought rights

to develop a Captive facility near Nandgaon, 3 kms South of

Alewadi. In the month of February 2011, MMB addressed a

letter to Home Department, Government of Maharashtra

suggesting shifting of port location towards southwards at

Nandgaon area by 2 to 3 kms. It also requested Government

of Maharashtra to take up the said matter with DAE to allow

the development of port with additional safety measures as

required. They also pointed out that distance of Tarapur

installation from Alewadi site was about 7 - 8 kms and not 3

Tilak

100 WP-1051-15

kms as perceived by DAE. In August 2011, a request was

made to DAE to reconsider its objection for development at

Alewadi port since the aerial distance between Alewadi and

Tarapur is about 7 - 8 kms. Government of Maharashtra

informed the DAE that they are interested to develop the port

at Alewadi as it may form part of Delhi - Mumbai industrial

corridor, and will be able to have a dedicated fright corridor

between Delhi - Mumbai.

94 Mean while, proposal of respondent no.3 was

allowed in September to develop captive facility at Nandgaon

which was about 3 kms South of Alewadi. This was in

accordance with captive jetty policy of 1995 of Government of

Maharashtra. Later on, a lease deed came to be executed in

December thereby respondent no.3 acquired a vested right to

develop a captive jetty/port at Nandgaon. Again, in

December, NPCIL, AERB and BARC wrote letters to DAE to

reconsider the objections contained in DAE's letter dated 29 th

January 2009. Thereafter, in April 2012, a conditional "No

Objection Certificate" was given to Government of

Tilak

101 WP-1051-15

Maharashtra, wherein they allowed proposed project of jetty

or port if it is developed beyond south side of Dolvi village.

95 According to respondent no.3, all along, petitioner

was aware of the abandonment of Alewadi port by MMB and

application of respondent no.3 for development of a captive

facility at Nandgaon village. Approval of the proposal of

respondent no.3 at Nandgaon village as well as a lease deed

in favour of respondent no.3 being in the knowledge of the

petitioner, petitioner in fact abandoned their claim to Alewadi

by expressing their option for two other sites between

Shirgaon and Satpati.

96 Apparently, Alewadi port came to be abandoned in

2009 on account of security apprehension raised by DAE.

Whether petitioner was aware of such fears raised by DAE,

and whether petitioner was aware that someone else is

already considered for a location 3 kms below Alewadi i.e.

Nandgaon. Respondent no.3 relies on Exhibit A-31 page 322,

letter written by the petitioner's Solicitor to Transport

Tilak

102 WP-1051-15

Secretary wherein it expresses its knowledge that some other

developer intends to attempt the construction of a jetty on the

same site with long term intention of converting the jetty

into a full service port. This letter is much prior to LOI being

granted in favour of respondent no.3 in October. At page 37

of the present Writ Petition, petitioner contends that

petitioner repeatedly conveyed to respondent nos.1 and 2 that

sanctioning a jetty at Nandgaon would render a port at

Alewadi infructuous as both are in the same location.

According to the petitioner, despite the concern of petitioner,

respondent no.1 proceeded to illegally grant an LOI to

respondent no.3 for Nandgaon. Apart from this, on 5 th

September 2012, public notices in Times of India, Lokmat,

Sakal were published by Maharashtra Pollution Control Board

with regard to development of Nandgaon project, calling

public opinion and objections. According to petitioner, even

much prior to the LOI being issued at Nandgaon, he was

opposing sanction of jetty at Nandgaon, how the petitioner

now can seek protection of ignorance of public notices, or can

he now say that they all pertain to Nandgaon, therefore, he

Tilak

103 WP-1051-15

did not object. In all probability, petitioner was convinced

that Nandgaon is at a different location than Alewadi, and the

proposal of respondent no.3 is for a captive facility, unlike the

commercial port proposal of the petitioner, it might not have

objected. First Deed of Modification came into effect in the

month of April 2013. Schedule contains modified water front

area. From the pleadings of the petitioner, it is clear that

petitioner was complaining of the fact that additional seafront

was allotted to other developer, but still it was claiming

ignorance of the identity of the developer. Third respondent

is justified in saying that unless the petitioner had access to

the documents and knowledge of the details, such averments

could not have been made in the first petition which is

annexed to the writ petition. Even in the affidavit in

rejoinder, petitioner claims that till and after August 2014,

petitioner was unaware that respondent no.3 had been

permitted to set up a multipurpose port at the same location

as that of Alewadi. For the first time, in the present Writ

Petition, petitioner states that it is learnt that respondent no.3

being allotted Nandgaon project. This is somewhere in July

Tilak

104 WP-1051-15

2013. If petitioner had any knowledge or doubt of setting up

a jetty or port since March 2011, why petitioner kept quiet

without demanding any details either from respondent no.1

or respondent no.2 to identify the name of project proponent,

the location or the category of the proposal. This could have

been done by petitioner with a simple application under

Right to Information Act. Much later, they contend that if

only they were aware of such facility being given to third

respondent, and if only they were intimated about the

possibility of constructing a jetty on the site of the very same

port proposal, they could have also applied for the same.

Apparently, there is nothing on record that there was any such

demand from the petitioner to know the details of the site or

proposal prior to the filing of the first Writ Petition. For the

reasons best known to the petitioner, respondent no.3 was not

even made a party. Even in the first petition, nothing

prevented the petitioner seeking the details of the so-called

jetty proposal which was within their knowledge in the month

of March 2011 itself. There is no explanation why petitioner

was keeping quiet from March 2011 without making any

Tilak

105 WP-1051-15

effort to know what was happening in and around the site

proposed by them at Alewadi. On the other hand, they also

came up with a proposal of alternate site in 2012 between

Shirgaon and Satpati much prior to filing of the earlier Writ

Petition. This would clearly go to show that as far back as in

2011 itself, petitioner knew that someone else was already

given the work of development of a captive jetty and

deliberately respondent no.3 was not made a party to the first

writ petition. On the other hand, on 8 th January 2014, after

hearing only the Government Advocate, the Bench disposed

of the earlier Writ Petition passing the following order:

"1. Petitioner is seeking an appropriate writ, order or direction, directing Respondents to decide its representation dated 31st July, 2013 after giving the Petitioner personal hearing expeditiously within a time bound schedule. Since this is the only relief pressed by the Petitioner at this stage, Petition can be conveniently disposed of by directing the Respondents to decide the said representation dated 31st July, 2013 as expeditiously as possible on merits and in accordance with law after giving personal hearing to the Petitioner within a period of 12 weeks from today.

2. We are informed that the process of appointment has not yet begun and that, in any case, it is not possible to appoint any person

Tilak

106 WP-1051-15

within a period of three months. We, however, direct the Respondents not to take final decision in respect of development of the port till the representation of the Petitioner is decided.

3. Petition is disposed of accordingly."

97 The entire order refers to site at Alewadi and not

Nandgaon. If petitioner had knowledge of a jetty/port being

developed by someone else in and around the site for

Alewadi, why petitioner did not pursue the matter further

seeking better particulars/details from respondent nos.1 and

2 in the first round of litigation. Why petitioner did not even

bother to wait till MMB was served and appeared before the

Bench. There was no need to take an order like 8 th January

2014 as stated above in the earlier Writ Petition. The

petitioner seems to have taken such order dated 8 th January

2014, in all probability, to cover up the delay and laches on

the part of the petitioner so that petitioner could again file

the present petition contending that it was ignorant of

development of captive facility being granted to respondent

no.3. It knew the existence of such third party in the month

of March 2011. If only respondent no.3 was made a party to

Tilak

107 WP-1051-15

the earlier writ petition, respondent no.3 could have

challenged the matter by raising the contention of delay and

laches then itself. They allowed the Court to pass the above

order taking a commitment from the Government Advocate

that the State would consider the proposal of petitioner for

the site at Alewadi i.e. development of a multipurpose port,

and till such consideration, they would not consider the

proposal of Alewadi. Both MMB and respondent no.3 were

not in the scene to explain or give better particulars to the

Court. In all probability, for this reason, respondent no.3 was

not heard before the second respondent at the time of passing

impugned order. Yet, petitioner claims that there has been no

delay and laches on the part of the petitioner in approaching

the Court in the present petition. There is unexplained delay

and laches on the part of the petitioner in filing the present

Writ Petition. Inspite of knowledge of existence of third party

(third respondent), right from March 2011, the petitioner

kept quiet and has come in the present petition. Between

March 2011 and filing of the present petition, rights are

created in the third respondent and third respondent has

Tilak

108 WP-1051-15

acted further in the matter of captive facility and its position

is totally altered. After Environmental clearance granted to

respondent no.3 on 16th March 2016 for the construction of a

jetty, the petitioner, according to respondent no.3 moved the

Court for interim order. However, the Court opined that the

writ petition has been filed in 2013, the lease was executed in

2011, hence, there was no urgency in the matter, and no case

was made out for grant for ad-interim injunction. The lease

deed entered in favour of third respondent is only for a period

of five years. After completion of five years, MMB has to

further consider extending the same for 30 years and such

situation has not yet come according to the MMB.

98 Inspite of knowledge of the petitioner in the

month of March 2011 that a third party developer is

attempting to get the construction of the jetty in the same site

sought by petitioner on a longer term basis with an intention

of converting the jetty into a full service port, petitioner did

not take any steps. In the mean while, LOI was granted to

third respondent in October 2011 which was within the

Tilak

109 WP-1051-15

knowledge of the petitioner and still did not act in time by

taking recourse to any legal proceedings. As a matter of fact,

in the present petition, in so many words, petitioner makes it

clear that it kept on objecting respondent nos.1 and 2 in

sanctioning a jetty at Nandgaon which would render its

proposal at Alewadi, infructuous. This would clearly indicate

that petitioner was aware of the project at Nandgaon even

prior to the issuance of LOI to respondent no.3 in the month

of October 2011. The third respondent has altered its

position by incurring an expenditure of Rs.70 crores on

Nandgaon project, as stated in the affidavit in reply of

respondent no.3.

99 According to respondent no.3, the correspondence

between the petitioner and respondent no.1 makes it

abundantly clear that they were aware of the proposal of

respondent no.3, and that a lease was granted to respondent

no.3 (including modifications being made by grant of

additional seafront), Respondent no.3 contends that

intentionally respondent no.3 was not made a party to the

Tilak

110 WP-1051-15

proceedings in Writ Petition No.3278 of 2013 which came to

be filed after a gap of three years since the execution of deed

of lease in favour of respondent no.3. On account of

petitioner expressing to shift their proposal to alternate site,

Minister directed in the impugned order to consider awarding

them a port at one of the alternative sites under 2010 policy.

The request for alternate site between Shirgaon and Satpati

was made, and this would only go to show that petitioner was

no longer pursuing Alewadi port, and it abandoned the

proposal. Apparently, 2010 policy mandates that the port

developer to have a joint venture with the Government on the

basis of 89 : 11% share in the arrangement. According to 3 rd

respondent, in all probability, the petitioner abandoned and

changed their mind opting for an alternate site since 2010

policy was invoked, and the procedure under 1996 policy was

not in existence any more.

100 To substantiate the above contentions, letter dated

7th August 2012 written by petitioner to respondent no.2 is

relied upon saying they are prepared to develop the Alewadi

Tilak

111 WP-1051-15

port project on an "as is basis where is basis", and further all

the terms and conditions of the DAE is acceptable to them.

Even on this date, petitioner requested respondent no.2 to

issue LOI on the condition that they will comply with the

security conditions. Strangely, they do not mention that they

were no longer interested in Shirgaon or Satpati. Again,

petitioner in 2013 writes to respondent no.1 referring to

earlier letters by letter dated 31 st July 2013 requesting for

allotment of the port at Alewadi. Again, a request was made

for award of the LOI for development of the port at Alewadi

prior to filing earlier Writ Petition in December 2013. At no

point of time, petitioner sought for consideration of their

proposal in terms of 2010 policy. Subsequent to

abandonment of Alewadi port in 2009, nothing could be

considered so far as 1996 policy. The new proposals have to

be in terms of 2010 port policy, whereas in all the

notifications of Government in respect of captive jetty policy,

they maintain that captive jetty policy would be in terms of

1995 policy subject to modifications, from time to time, with

regard to terms and conditions.

Tilak





                                  112                           WP-1051-15




101             Writ   Petition   (L)  No.3278  of  2013    filed  by  the 

petitioner   was   served   on   the   State   Government.     First 

respondent - MMB was not yet served when it came to be

disposed of on 8th January 2014. Apparently and surprisingly,

respondent no.3 was not made a party to the Writ Petition.

According to respondent no.3, petitioner was very well aware

that respondent no.3 was awarded Nandgaon location which

could affect the project proposed by the petitioner at

Alewadi. However, on 8th January 2014, Writ Petition was

disposed of by directing the Respondents not to take final

decision in respect of development of the port till the

representation of the Petitioner is decided.

102 Subsequently, the impugned order came to be

passed. Apparently, third respondent was not directed to

appear for hearing before respondent no.2. Petitioner was

allowed to submit a proposal to respondent no.1 for an

alternate location instead of Alewadi port. In the impugned

order of respondent no.2, it is made clear that M/s.JSW

Tilak

113 WP-1051-15

Infrastructure Ltd is allowed the benefit of captive jetty at

village Nandgaon and the permission is only for use of captive

jetty, and therefore, proper corrections must be made in the

agreement. Further, petitioner was permitted to submit a

proposal for alternative place instead of Alewadi port project.

Admittedly, petitioner is not a port developer, and it is only a

private equity fund having only a correspondence address in

India. The so-called proposal of 2007 was a joint venture in

collaboration with 2 or 3 other entities. Apparently, neither

the petitioner nor any other contenders secured the

development of Alewadi port. Petitioner claims throughout

the petition as if it had acquired a vested right to get the

Alewadi port i.e. the right to construct the port. Petitioner

was not the only party which had submitted techno economic

feasibility study report. The affidavit of first respondent filed

in December 2016 clearly indicate that petitioner was

standing fourth amongst other entities when a fresh techno

economic feasibility study report was called on 11 th June

2010. As per this, petitioner was not even the most eligible

amongst the other applicants. Inspite of change of earlier

Tilak

114 WP-1051-15

port policy which was revised in 2010, the petitioner was the

only project proponent who was not willing to submit

expression of interest under 2010 policy, and it was insisting

for consideration of the proposal under Old policy. As a

matter of fact, Government opined that all the three

companies i.e. Videocon Industries, M/s.Larsen & Toubro,

petitioner etc. have to be considered. However, L & T did not

submit its report. M/s.Deloitte which was the consultant of

first respondent, questioned the petitioner's proposal on the

ground that no financial data had been provided. An annual

report of Chartered Accountant was also not submitted and

they were not in a position to evaluate petitioner's proposal

on account of lack of authenticity of financial data. Under

these circumstances, we fail to understand how petitioner

could claim vested right over Alewadi port. Petitioner in the

present petition in the absence of any commitment being

made to it by respondent no.1, cannot be held to have locus

to file the present petition for the reliefs sought. The entire

petition is pursuing the private interest of the petitioner, and

not a Public Interest Litigation.

Tilak





                                     115                             WP-1051-15

103             Similarly,   the   claim   of   the   petitioner   that   it   has 

been discriminated, violating their right to develop a

commercial port which is nothing but violation under Article

14 of the Constitution, in the absence of issuance of LOI, and

in the absence of no contract being awarded or promised to

any of the four contenders, including the petitioner - Chaucer

Capital, one cannot opine either the petitioner or any of the

contenders had acquired any vested right. Apparently, in the

absence of vested right to award the Alewadi port, we cannot

compare petitioner with any other person to consider the

ground of discrimination. In order to opine that petitioner

was discriminated, there has to be another party who is

successful in getting the proposal to set up Alewadi port.

Apparently, petitioner was not competing with respondent

no.3 to set up a private jetty or captive facility. Like

respondent no.3, petitioner has no facility of industry near

Nandgaon or Alewadi. Petitioner is intending to construct

the commercial port but port will be operated by someone

and not the petitioner. On the other hand, the captive

facility to handle cargo of third respondent which has plants

Tilak

116 WP-1051-15

at Tarapur, Vashind and Dolvi has come forward to have the

captive facility at Nandgaon. Therefore, there is no question

of discrimination against the petitioner by favouring

respondent no.3 in respect of 1996 port policy.

104 The allocation of any project being the sole

prerogative of the State, petitioner cannot claim the same as a

matter of right. Respondent no.3 got the project only after

the State was being satisfied with the compliance of various

parameters. Petitioner cannot seek the selection of allotment

of port without undergoing the tender process in terms of

2010 policy. Allocation and construction of captive jetty is in

terms of 1995 GR/policy whereas the construction of a port

and the terms and conditions thereunder in relation to the

selection of the developer was in terms of initially 1996 port

policy revised by port policy of 2010. Purportedly, petitioner

has not annexed G.R dated 26th June 1995 which pertains to

the construction of captive jetties, wherein it does not

contemplate any bidding process for the allotment of captive

jetty.

Tilak





                                   117                              WP-1051-15

105             Petitioner's   project   is   a   commercial   venture. 

Nandgaon project allotted to respondent no.3 is a captive

jetty. The allegation that both sites are located at the same

site, is false. Nandgaon jetty is located at a distance of

approximately 7 kms from Tarapur Atomic Power Station.

Therefore, no objections are raised to the project of the third

respondent. The proposal of respondent no.3 at Nandgaon is

located about 3 kms South of Alewadi port. Petitioner is a

body corporate, incorporated under the laws of United

Kingdom. The Policy of the State dated 20 th November 2000

relied upon by the petitioner appears to be with regard to a

decision to develop Dighi and Rewas ports by a Memorandum

of Understanding with the developer. The policy of 2005

pertains to multipurpose terminals/jetties and cargo

terminals. This has no application to the captive jetty of the

respondent no.3. As a matter of fact, 2005 policy explicitly

mentions that the captive jetties shall continue to be governed

by 1995 Policy. The question of maintaining minimum

distance of 5 kms on the sea front between two multipurpose

terminals does not apply to the respondent no.3 since no

Tilak

118 WP-1051-15

decision was taken to develop Alewadi port when third

respondent was issued with LOI. Respondent no.3 cannot be

faulted for deficits in the communication between the

petitioner and the MMB. Nothing on record would indicate

that there was positive consideration of the project of the

petitioner by respondent nos.1 and 2. On the other hand, the

letter produced by the petitioner dated 3 rd July 2007 and the

letter of respondent no.1 dated 17 th July 2007 indicate that

petitioner itself in the said letter referred to the concern of the

respondent no.1 with regard to the financial credibility of the

petitioner.

106 The location of the project is entirely different

from the location of the proposed port of petitioner. The

distance between the two locations is about three

kilometers. None of the policies relied by the petitioner

i.e. 2005 nor 2010 apply to the case of the petitioner. The

details of letters dated 18th April 2012 and 23rd May 2012

seeking alternate site between Satpati and Shirgaon are not

placed on record by petitioner. There is no illegality,

Tilak

119 WP-1051-15

whatsoever, either in the execution of the lease deed, or

modification deeds which came into existence subsequently.

From the beginning, petitioner was aware of captive jetty

permission given to respondent no.3. There is no question of

accepting proposal of respondent no.3 rejecting the

application of petitioner. Intention of respondent no.3 was

not to develop port under the guise of a jetty at the site

Nandgaon. The question of respondent nos.1 and 2 favouring

respondent no.3 instead of petitioner, does not arise. The

proximity of Alewadi project to the Tarapur Atomic Power

Station, due to security concern, the project of the petitioner

could not be considered, and the same is a document of

record.

107 For the reasons best known to the petitioner,

petitioner has kept quiet till he filed present writ petition

without making the third respondent as a party to the

proceedings. Petitioner did not even attempt to know the

details of the project proponent at Nandgaon.




Tilak





                                  120                           WP-1051-15




108             We are of the opinion that the petitioner lacks any 

legal right much less has any concluded contract in its favour

to file the present writ petition and seek the prayers as made

in the petition. Hence, petitioner cannot maintain the present

petition.

109 For the discussion and reasons mentioned above,

petition deserved to be dismissed and is accordingly

dismissed.

110             Parties to bear their own costs.



     (G.S. KULKARNI, J.)                      (CHIEF JUSTICE)




Tilak





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter