Citation : 2017 Latest Caselaw 2340 Bom
Judgement Date : 5 May, 2017
1 APPEAL NO.804 of 99
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 804 OF 1999
IN
ARBITRATION PETITION NO.77 OF 1994
MUNICIPAL CORPORATION OF
GREATER BOMBAY, a Statutory
Corporation, constituted under
the provisions of Bombay Municipal
Corporation Act, 1988 having
their office at Mahapalika Building,
Mahapalika Marg, Mumbai 400 001. ...APPELLANT/
Orig. Petitioners
VERSUS
1. Bharat Construction,
a Registered firm, carrying on
their business at D/2-92, Bharat
Nagar, Grant Road,
Mumbai - 400 007.
2. D.V. Deshpande, Indian Inhabitant
residing at 11, Vishwak Artek
apartment, Bandra (East),
Mumbai - 400 051.
3. Bharat Infrastructure & Engineering
Pvt. Ltd., a private Limited Company
having its registered office at 601,
Shree Amba Shanti Chambers,
Off. Church Road, Opp. Hotel Leela,
Andheri-Kurla Road, Andheri (E),
Mumbai - 400 059. ...RESPONDENTS/
...
Mr. Kevic Setalwad, Sr. Adv. a/w. Mr. Ameya Kulkarni i/b.
Sandeep Patil for Appellant.
Mr. M.M. Vashi, Sr. Adv. a/w. Ms. Panthi Desai, i/b. M.P. Vashi
& Associates for Respondents.
...
::: Uploaded on - 05/05/2017 ::: Downloaded on - 07/05/2017 00:55:33 :::
2 APPEAL NO.804 of 99
CORAM: ANOOP V. MOHTA AND
P.R. BORA, JJ.
...
DATE OF RESERVING THE JUDGMENT : 02.02.2017 DATE OF PRONOUNCING THE JUDGMENT : 05.05.2017 ...
JUDGMENT: (Per P.R.Bora, J.)
1. This is an appeal against the order of the learned
Single Judge dismissing the appellants petition under Section
30 of the Arbitration Act, 1940 for setting aside an award dated
22.06.1993 passed by the sole Arbitrator.
2. In May 1989, the appellant-corporation had invited
tenders for the work of re-construction of Zakariya Bunder road
from Sewree gate no.8 to Cotton Green Station (Part 2) in
cement concrete. In response to the tenders so invited, the
respondent no.1 submitted its percentage rate tender on
12.05.1989. The appellant-corporation accepted the tender
submitted by the respondent no.1 on 23.09.1989 and directed
the respondent no.1 to make preliminary arrangements, so as
to commence the work in right direction earnest from
11.10.1989, which date was to be taken as the date of
commencement of the said work and from which date the
contract period of eight months was to be reckoned.
3. Some delay was caused in commencing the tender
work. According to the contractor lack of due co-operation
from the officers of Municipal Corporation was the reason that
the work could not be commenced on the stipulated date and
also did not progress further in the manner and proportion it
ought to have been. Differences went on increasing which
ultimately resulted in stoppage of work.
4. Since, disputes and differences arose between the
appellant-corporation and the respondent no.1, the same were
referred to the sole Arbitration of respondent no.2 under
Clause-97 of the General Conditions of Contract for Civil Works,
which runs as under:
"97. Arbitration:
All disputes or differences whatsoever which shall at any time arise between the parties hereto touching or concerning the works or the execution or maintenance thereof or this contract or the construction, execution, or maintenance thereof or this contract of the construction meaning operation or effect thereof or, to the rights or liabilities of the parties or arising out of or in relation thereto whether during or after completion of the contract or whether before or after determination, foreclosure or breach of the contract (other than those in respect of which, the decision of any person is by the contract expressed to be final and binding) shall after written notice by either party to the contract to the other of them specify the nature of such dispute or difference and call for the point or points at issue to be referred to the arbitration...........
The Arbitrator shall give a separate award in respect of each dispute or difference referred to him.
5. The learned Arbitrator vide award passed on
22.06.1993 determined an aggregate sum of Rs. 30,51,565/- to
be paid by the appellant-corporation to respondent no.1.
6. The award so passed was challenged by the
appellant-corporation by filing Arbitration Petition No. 77 of
1994, before the learned Single Judge. It was the contention of
the appellant-corporation before the learned Single Judge that,
by virtue of Claus-94 of the General Conditions of the Contract,
respondent no.1 was not entitled to claim any amount towards
the compensation for losses suffered on account of over head
expenses or idle labour and machinery and/or reduced
productivity. It was also the contention of the appellant-
corporation that, the learned Arbitrator was not having any
authority to adjudicate the claims raised by the respondent
no.1 as they were beyond the scope of reference. As against it,
it was the contention of the respondent no.1 that, Clause-94 of
the General Conditions of Contract was not applicable in the
case and the disputes were referred to arbitration under
Clause-96 and 97 and, as such, the Arbitrator was having every
authority to adjudicate the said claims.
7. The learned Single Judge after having considered
the submissions advanced before her dismissed the petition
filed by the appellant-corporation and passed a decree in terms
of the award with further interest @ 18% per annum from the
date of decree till the payment/realisation. Aggrieved by, the
appellant-corporation has preferred the present appeal.
8. Shri Kevic Setalwad, the learned senior counsel
appearing for the appellant-corporation, assailed the impugned
judgment on several grounds. The learned senior counsel
submitted that, the learned Single Judge failed to appreciate
that, under Clause-94 of the General Conditions of Contract
there was a prohibition for making or awarding any claim for
profit or compensation. According to the learned senior
counsel, claim nos. 1 and 2 were, therefore, not arbitrable. The
learned senior counsel further submitted that, the Arbitrator
had exceeded his jurisdiction and had travelled beyond the
scope of contract by entertaining such claims. The learned
senior counsel submitted that, the learned Single Judge failed in
appreciating that, claim nos. 1 and 2 were even otherwise
overlapping claims and damages could not have been awarded
twice under Section 73 of the Contract Act, as held by the
Hon'ble Supreme Court in the case of Union of India V/s.
Jain Associates reported in 1994 (4) SCC 665. The learned
senior counsel further submitted that, the judgment delivered
by Justice K.G. Shah in Arbitration Petition No. 151 of 1994 was
not binding, since it was per incuriam. The learned senior
counsel submitted that, the judgment of the Hon'ble Apex Court
in the case of Union of India V/s. Jain Associates cited
(supra) was not brought to the notice of Justice K.G. Shah.
The learned senior counsel further submitted that, the learned
Single Judge failed to appreciate that, the Arbitrator was bound
to give speaking award, in view of the fact that, a public body
like the appellant-corporation was a party to the arbitration
proceedings. The learned senior counsel further submitted
that, when a specific objection was raised by the appellant-
corporation in respect of arbitrability, the Arbitrator was duty
bound to decide the said issue, whereas, the Abirtrator without
deciding the said issue passed a non-speaking award. The
learned senior counsel submitted that, the learned Single Judge
on this ground alone ought to have set aside the arbitration
award. For the aforesaid reasons, the learned senior counsel,
prayed for setting aside the order passed by the learned Single
Judge and consequently the award passed by the Arbitrator.
9. Shri M.M. Vashi, the learned senior counsel
appearing for respondent no.1 resisted the contentions raised
on behalf of the appellant-corporation. The learned senior
counsel submitted that, having regard to the facts involved in
the present case, Clause-94 of the General Conditions of the
Contract, is not attracted and there was no impediment for
passing of an award by the Arbitrator for loss of profit and
overhead expenses etc. The learned senior counsel submitted
that, the claims raised by the contractor and awarded by the
Arbitrator were well within the scope of arbitration clause. The
learned senior counsel submitted that, the award which has
been passed after considering voluminous documentary
evidence, cannot be faulted with. The learned senior counsel
further submitted that, the learned Single Judge has rightly
dismissed the arbitration petition filed by the appellant-
corporation. The learned senior counsel, therefore, prayed for
dismissal of the appeal.
10. We have carefully considered the submissions made
on behalf of the learned senior counsel appearing for the
respective parties. We have also perused the award passed by
the Arbitrator and the order passed by the learned Single Judge
in the arbitration petition. The award passed by the Arbitrator
is mainly challenged on the ground that, when the appellant-
corporation had foreclosed the subject work under Clause-94 of
the General Conditions of Contract for Civil Works, the
Arbitrator could not have entertained the claims raised by the
Contractor not falling within the scope of the said clause. Since
the controversy revolves around Clause-94. We deem it
appropriate to re-produce the said cause which reads thus:
94. Foreclosure of contract in full or in part.
If at any time after acceptance of the tender the Commissioner shall decide to abandon or reduce the scope of the works for any reasons whatsoever and hence not require the whole or any part of the works to be carried out, he shall inform the contractor in writing to that effect and the contractor shall have no claim to any payment or compensation or otherwise whatsoever, on account of any profit or advantage which he might have derived from the execution of the works in full but which he did not derive in consequence of the foreclosure of the whole or part of the works.
The contractor shall be paid at the contract rates full amount for works executed at site, and in addition, reasonable amount as certified by the Engineer for the value of such material (which material thereupon become the property of the Corporation) and also such further allowances as the Engineer may think reasonable and fair in respect of (a) any expenditure incurred by the contractor towards preliminary works etc. and (b) other reasonable and proper engagement the contractor may have entered into for carrying out the work. (c) such compensation as considered equitable under the circumstances.
11. Now it has to be seen, as to who has foreclosed the
work, whether the Commissioner of the appellant-corporation
or respondent no.1. As has been argued by the learned senior
counsel appearing for the appellant-corporation, the corporation
foreclosed the work. Respondent No.1 has disputed this fact.
It is the contention of respondent no.1 that, because of the
adamant and non co-operative approach adopted by the
appellant-corporation the contract work stood foreclosed.
12. The record of the case shows that vide order passed
on 19.07.2007, the present appeal was dismissed by the
Division Bench, as in its opinion the controversy was covered by
an earlier decision of this Court in Appeal No. 1148 of 1997
given on 27.01.2005 (Municipal Corporation of Greater
Bombay V/s. Atul Raj Builders Pvt. Ltd.). The appellant-
corporation filed an appeal before the Hon'ble Apex Court
against the aforesaid judgment and the Hon'ble Apex Court has
set aside the said order in Civil Appeal No. 5168 of 2009 arising
out of (SLP (C) No. 16133 of 2007) decided on 07.08.2009.
Perusal of the order passed by the Hon'ble Apex Court in the
aforesaid appeal reveals that, a submission was made before
the Hon'ble Apex Court by the appellant-corporation that, it
foreclosed the contract and contractor was accordingly
intimated that, the corporation will not make any payment for
any loss suffered on account of inability on the part of the
contractor to complete the contract within the stipulated time.
In view of the submission so made on behalf of the appellant
Corporation, the Honourable Supreme Court held that the
matter needs to be re-examined by the Division Bench afresh.
The Honourable Apex Court has, therefore, remitted the matter
back by keeping all the contentions of the parties open, to be
agitated before this Court. Accordingly, the matter was heard
afresh.
13. After having considered the submissions made on
behalf of the learned Counsel appearing for the respective
parties and on perusal of the material on record, we find it
difficult to accept the contention raised by the appellant
corporation that it foreclosed the subject work by invoking
clause 94 of the General Conditions of Contract for Civil Works.
14. In the proceedings before the Arbitrator appellant
Corporation had submitted its written statement. In paragraph
nos.5 (b) and 5 (c) of the said written statement, the appellant
Corporation has averred thus:
"5 (b) Under the terms and conditions of the contract incorporated in the above documents, the Claimants contractor were required to carry out the work in a phased manner including completion of certain pre-limineties as required under the Special Directions / Special Conditions of the Contract before commencement of the work. The sequential work was not carried out by the Claimants, as a result of which there has been delay in completing the work within the stipulated period of time. The Claimants were thereafter given an option to complete the work after the monsoon of 1990 on the same terms and conditions of foreclose the contract and the CLAIMANTS HAVE OPTED TO foreclose the contract as they refused to complete the work on the same terms and conditions and therefore, asked for 30% rise in the contract amount which is clearly impermissible as the contract postulates no escalation whatsoever.
(c) In these circumstances, the contract stood foreclosed under the terms and conditions of the contract. In view of the provisions of Clause 94 of the General Conditions of Contract it is clear that for any reason whatsoever if the work is abandoned or foreclosed, the contractor shall have no claim whatsoever to any payment or compensation or otherwise on account of any profit or advantage which he might have derived from the exclusion of the work in full but which he did not derive in consequence of the foreclosure of the whole or part of the work. From the above clause 94 of the General Conditions of Contract is clear that the Claimants' claim is clearly impermissible. "
15. The contentions raised by the appellant corporation
in paragraph Nos. 50, 52 and 57 also have some bearing on the
plea raised by the appellant Corporation as about application of
clause 94. We, therefore, deem it appropriate to reproduce
hereinbelow the said portion in the written statement of the
Corporation:
"50. With reference to paragraph 45 these respondents state that the respondents offered an opportunity to all the agencies working, including claimants to show their willingness to continue the work after monsoon on same rates, terms and conditions or foreclose the same. Many agencies opted to work on the same rates, terms and conditions and other, opted foreclosure. However, the Claimant opted to demand the increased rates (30%), which were not acceptable to Respondent and, therefore, that request was rejected.
52. With reference to paragraph 47 these respondents state that the claimants refused to work with the same terms and conditions after monsoon and therefore contract stood foreclosed.
57. With reference to paragraph 52 these respondents state that the claimant's statement is not correct. The work, left incomplete by the claimant, was awarded to the other contractors by following the regular procedure of inviting tenders. Further, if the work would have been completed by the Claimants, within the contract period, the question of granting the incomplete work to other agency would not have arisen at all. In fact, due to fault on part of the claimants, the Respondent is put to loss and the claimant do not deserve any compensation and, instead, are liable for penalty and make up the loss to the Respondents. "
16. Considering the contentions raised and the plea
taken by the appellant Corporation in its written statement as
reproduced herein-above, we are unable to accept the
contention raised on behalf of the appellant Corporation that it
abandoned the subject work or foreclosed the said work by
invoking clause 94. What transpired from the pleadings of
the appellant Corporation is the fact that the circumstances so
arose that the subject work stood foreclosed. From the
averments in paragraph No.5(b) of the written statement,
reproduced herein above, it is quite evident that it was the case
pleaded by the appellant Corporation before the Arbitrator that
the contractor opted to foreclose the contract by refusing to
complete the work on the same terms and conditions. Neither
in paragraph No.5(b) nor in paragraph No.5(c) any such
unambiguous and concrete case is made out by the Corporation
that the Commissioner of the Corporation abandoned or
foreclosed the subject work by invoking clause 94. It is
nowhere asserted by the appellant Corporation that the
Commissioner of the appellant corporation took conscious
decision to foreclose the subject work and communicated the
said decision to the contractor i.e. respondent no.1.
17. The averments in paragraph no.57 of the written
statement leave no doubt that there was no abandonment of
the subject work by the appellant Corporation as contemplated
under clause 94 of the General Conditions of Contract and Civil
Works. On the contrary, in the Arbitration Petition
No.77/1994, in paragraph no.9(g), it is the contention of the
appellant Corporation that the contractor abandoned the work.
We deem it appropriate to reproduce hereinbelow the
contention so raised in the said paragraph No.9(g) which reads
thus:
" ..... .... In fact, it has been established beyond a shadow of doubt that because of shortfall of labour and machinery, the work was not completed on time and respondent no.1 abandoned the work. "
18. It is further significant to note that in the present
appeal also it is the case put forth by the appellant Corporation
that both the parties i.e. the Corporation and the contractor
agreed to foreclose the contract under clause 94 of the General
Conditions of Contract. Ground `l' in the memo of appeal in
that regard reads thus:
"(l) The learned Single Judge ought to have appreciated that since there was no progress on the part of respondent No.1 in completing the work both the parties agreed to foreclose the contract under Clause 94 of the General Conditions of Contract. The appellants thereafter invited a fresh tender and awarded the work to a new contractor. The proposal of the respondent No.1 was conditional and was not acceptable to the appellants."
19. The contractor i.e. respondent no.1 has denied that
he had agreed to foreclose the contract under clause 94 as has
been canvassed by the appellant Corporation.
20. It was sought to be canvassed by the learned
counsel appearing for the appellant Corporation that the
contractor has not disputed the fact that the appellant
Corporation foreclosed the contract. Our attention was invited
by the learned Senior Counsel to paragraph No.47 of the
statement of claim submitted by the contractor and more
particularly to the first sentence of the said paragraph to the
effect that, "The respondent finally foreclosed the contract". To
establish that the foreclosure of the subject work falls within
the purview of clause 94, the primary burden was on the
appellant Corporation to prove the said fact with reasonable
certainty. However, as noted by us herein-above, the
Corporation has not come out with any such concrete case or it
is nowhere asserted by the appellant Corporation that the work
was foreclosed or abandoned by the decision of the
Commissioner of the appellant Corporation. As is revealing
from the material on record, an offer was given by the
appellant Corporation to respondent no.1 contractor to
complete the work on the same terms and conditions after the
period of Monsoon expires or to foreclose the contract. From
the offer so given also it is clear that the option to foreclose the
contract was given to the contractor. The material on record
further reveals that the contractor did not accept the said offer
and as has been contended by the appellant Corporation in
paragraph No.5(b) of its written statement reproduced herein-
above, "the claimants i.e. respondent no.1 contractor opted to
foreclose the contract".
21. From the facts as aforesaid, it is quite clear that the
option to foreclose the contract was not exercised by the
appellant Corporation. For invoking clause 94 mere
abandonment or foreclosure of the work is not enough; it has to
be further established that the abandonment or foreclosure of
the work was by the appellant Corporation. Though an attempt
has been made to suggest that respondent no.1 had agreed to
foreclose the contract under clause 94 of the General Conditions
of the Contract, respondent no.1 has flatly denied the said fact.
22. The appellant Corporation has thus failed in
establishing that it had abandoned or foreclosed the subject
work by invoking clause 94. As noted earlier, clause 94 would
come into operation only if the foreclosure of the work is by the
Commissioner of Municipal Corporation.
23. Thus, though before the Honourable Apex Court a
case was put forth by the appellant Corporation that it
foreclosed the contract and the contractor was intimated that
the Corporation will not make any payment towards loss
suffered by the contractor on account of the inability on the
part of the contractor to complete the contract within the
stipulated time, the Appellant corporation has utterly failed in
substantiating the said fact. In the circumstances, obviously,
clause 94 of the General Conditions of the Contract would not
have any application. The learned Single Judge has rightly
rejected such contention raised by the appellant Corporation.
We do not see any reason to cause any interference in the
finding so recorded by the learned Single Judge.
24. In view of the finding recorded by us that clause 94
would not be applicable in the present case, the other objection
pressed on behalf of the appellant Corporation that the
Arbitrator did not decide arbitrability of the claim as set up by
the contractor and disputed by the appellant Corporation loses
its significance.
25. Another objection raised by the appellant
Corporation is that the learned Single Judge has failed in
appreciating that though the amount claimed by respondent
no.1 vide claim no.2 is, in fact, covered in claim no.1, the
Arbitrator has awarded the claim under both the heads and,
thus, for one claim, amount has been awarded twice. Learned
Counsel submitted that in view of the provisions under Section
73 of the Contract Act, such course is impermissible. The
submission so made, of course, has been denied by respondent
no.1.
26. In the statement of claim filed before the Arbitrator
respondent no.1 has claimed an amount of Rs.60,87,435/-
towards compensation for losses on account of overheads and
profits. As per the particulars provided in paragraph no.61 of
the statement of claim, the contract sum is shown as
Rs.2,89,83,931/-. Respondent no.1 has calculated his profit at
25 per cent which comes to Rs.72,45,995/-. The value of the
work executed during the stipulated period, is shown to the
tune of Rs.46,34,160/-. The profit, which could have been
derived from the value of the works so executed is shown as
Rs.11,58,540/-. It is calculated at the rate of 25 per cent of
the work executed. Deducting the said amount from the total
estimated profit, the total loss on account of overheads and
profits is shown to be Rs.60,87,435/- (Rs.72,45,995/- (minus)
Rs.11,58,540/- = 60,87,435/-). Towards claim no.1, the
Arbitrator has awarded the amount of Rs.17,10, 903/-.
27. In paragraph no.62 of the statement of claim
submitted by respondent no.1 before the arbitrator, he has
provided the particulars in regard to claim no.2 towards the
losses suffered on account of the labour and machinery and / or
reduced productivity. In the particulars so provided, cost of
the work put up to tender is the same i.e. Rs.2,89,83,981/-.
Below the said amount, the sum of Rs.40,00,000/- is shown by
way of provision made for machinery and equipment. Value of
the work done during the stipulated period is again the same
i.e. Rs.46,34,160/-. Then the pro rate payment received is
shown to the tune of Rs.6,48,776.80 and the net loss suffered
on account of the labour and machinery and reduced
productivity is shown to the tune of Rs.33,51,224/-. The
Arbitrator has awarded a sum of Rs.10,35,166/- towards the
said claim.
28. Though neither in the statement of claim nor in the
award passed by the Arbitrator it is clarified as to in what
manner the loss was assessed for claim no.2, it appears that
respondent no.1 had made the provision of Rs.40,00,000/- for
machinery and equipments and from out of the work executed
by him in the stipulated period to the extent of Rs.46,34,120/-,
the proportionate profit or return was shown by respondent
no.1 to the tune of Rs.6,48,776.80 and thus, the net loss for
the labour, machinery and reduced productivity was claimed to
the tune of Rs. 33,51,224/-. In fact, some explanation and
some more particulars must have been provided by the learned
Arbitrator while allowing the respective claims and passing the
award in that regard. Admittedly, no such reasons are
assigned and the award passed is a non speaking award. No
doubt, this Court has certain limitations while examining a non
speaking award, however, as held by the Honourable Apex
Court in the case of State of J & K and another Vs.
Devdatta Pandit ( (1999) 7 SCC 339), there is no complete
bar in examining whether the award is in terms of the
Reference or in terms of the contract.
29. As is revealing from the material on record,
respondent no.1 contractor was supposed to keep engaged the
required number of labours and machinery exclusively for the
contract work. In the circumstances, even if the contract was
not allowed to be performed fully, and respondent no.1 had to
keep his machinery and labour idle in the relevant period, the
losses suffered on account of the idle labour and machinery
which are claimed under claim no.2 could not have been
awarded separately for the reason that all these claims are
obviously covered by claim no.1. It appears to us that when
the estimated loss in profit was claimed by respondent no.1
vide claim no.1, it was not open for respondent no.1 to again
claim the losses suffered on account of the idle labour and
machinery separately under claim no.2. Even otherwise, had
the work been not abandoned, the respondent contractor must
have utilized the said labour as well as machinery since
according to his own case, the same was earmarked specifically
for the subject work. In the circumstances, the claim awarded
towards claim no.2 by the Arbitrator cannot be sustained.
Learned Single Judge has failed in appreciating this aspect and
has wrongly held that claim no.1 and claim no.2 were
independent of each other. We set aside the finding recorded
by the learned Single Judge.
30. One more objection has been raised by the
appellant Corporation which relates to grant of interest as
awarded by the Arbitrator at the rate of 18 per cent per annum
which has been confirmed by the learned Single Judge. We find
substance in the objection so raised. Having regard to the fact
that the award is passed against a local body and the project
which was the subject matter of the contract was not a profit
making project, we deem it appropriate to award the interest at
the rate of 10 per cent per annum instead of Rs.18 per cent
per annum as awarded by the learned Single Judge. We are,
therefore, inclined to partly allow the present appeal. Hence,
the following order:
ORDER
i) The Appeal is partly allowed.
ii) The Award dated 22nd June, 1993, so far as it
relates to claim no.2, stands quashed and set aside.
iii) We hold respondent no.1 entitled to receive the
amount awarded by the learned Arbitrator towards
claim nos. 1, 4 and 6 with interest thereon at the
rate of 10 per cent per annum from the date of
award till its realization.
iv) The Appeal stands allowed in the aforesaid terms.
( P.R.BORA) (ANOOP V.MOHTA)
JUDGE JUDGE
mub
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!