Citation : 2017 Latest Caselaw 1349 Bom
Judgement Date : 31 March, 2017
1 wp4640.15
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
AURANGABAD BENCH, AURANGABAD
WRIT PETITION NO. 4640 OF 2015
1] Prakash Dada Dalvi,
age 48 years, occ. Agril.
And business, R/o Hanga,
Tq. Parner, Dist. Ahmednagar,
2] Jalindar Lahu Shinde,
age Major, occ. Agril.,
R/o as above,
3] Sachin Bhaskar Pawar,
age Major, occ. Agril.,
R/o as above ...Petitioners
VERSUS
1] The Maharashtra State
Industrial Development
Corporation, through
its Managing Director,
2] The Regional Officer,
The Maharashtra State
Industrial Development
Corporation, Nashik Division,
Office of the Regional Office
MIDC Audyogik Vikas Mandal,
Udyog Bhavan, 2nd Floor,
Satpur, Nashik,
3] The Area Manager,
MIDC, Ahmednagar ...Respondents
.....
Shri N.V.Gaware, advocate for the petitioners
Shri S.S.Dande, Advocate for respondent no.1
Respondent nos. 2 and 3 served
.....
::: Uploaded on - 31/03/2017 ::: Downloaded on - 01/04/2017 01:12:36 :::
2 wp4640.15
CORAM : S.V.GANGAPURWALA
AND
K.L.WADANE, JJ.
DATE OF RESERVING
THE JUDGMENT : 2.3.2017
DATE OF PRONOUNCEMENT
OF THE JUDGMENT : 31.3.2017
JUDGMENT (Per K.L.Wadane, J.)
Rule. Rule is made returnable forthwith.
With the consent of the learned counsel for the
parties, taken up for final hearing.
2. It is the case of the petitioner that
respondent no.1 has taken decision to set up M.I.D.C.
at villages Hanga and Supa of Parner Taluka in
Ahmednagar District, for which agricultural land of
petitioner no.1 was acquired.
3. On 2.7.2005 the petitioners have registered a
partnership firm named and styled as 'M/s Hangeshwar
Ware House'. Consequently, the petitioners have
submitted an application in the requisite form for
3 wp4640.15
the allotment of the plot in the said industrial area
for setting up a Ware House. The proposal of the
petitioners was scrutinized and same was found to be
fit. The Area Manager, M.I.D.C., Pune had issued
allotment letter in favour of the petitioners thereby
allotting the land admeasuring 5748 square meters
bearing Plot No. X-34 in Supa-Parner Industrial Area
subject to the conditions.
4. On 29.5.2007 the petitioners have paid the
entire premium amount including earnest money and
further the sanction was accorded to the said
allotment by the Area Manager of M.I.D.C.
5. On 23.10.2008 the respondent no.3 Area
Manager issued a communication in favour of the
petitioners in respect of Plot No. X-34/1 thereby
shrinking the size of the said plot to 2998 square
meters and accordingly on 8.4.2008 the possession
receipt was issued in favour of the petitioners. The
petitioners were put to actual possession of the said
plot No. X-34/1.
4 wp4640.15
6. On 23.10.2008 the respondents have called
upon the petitioners to execute the agreement with
respondent no.1 in pursuance to the allotment of
plot. An agreement was executed between the
petitioners and respondent no.1. The petitioners had
paid entire amount of Rs.2,99,800/- before execution
of the lease deed. Thus, the petitioner became
lawful allottee and holder of the said plot.
7. On 23.7.2012 the Deputy Engineer of M.I.D.C.
had accorded fresh approval to the building plan of
proposed industrial building on plot no. X-34/1 of "X
block". The petitioners had carried out the
construction of ware house strictly in accordance
with the approved plan and the drawings submitted by
them for the construction of ware house and they
started the business activities. The Deputy Engineer
of M.I.D.C. issued completion certificate in favour
of the petitioners.
8. On 27.10.2014 the respondent no.2 Regional
5 wp4640.15
Officer has abruptly issued a communication thereby
shrinking/reducing the size of the plot to 2000
square meters in stead of 2998 square meters. The
respondent no.2 has passed the said order in utter
disregard and against the principles of natural
justice without issuing any sort of notice and
without offering the opportunity of being heard. It
is further contended by the petitioners that pursuant
to the agreement between the petitioners and
respondent no.1 certain rights were created in favour
of the petitioners. The impugned communication has
been passed behind the back of the petitioners. The
petitioners have submitted representations on
18.11.2014 and 8.12.2014 against the impugned
communication, however, both the representations were
rejected. Hence, this petition.
9. On behalf of respondent nos. 2 and 3
affidavit in reply is filed and it is contended that
at the time of initial allotment of the plot the lay
out plan was not at all sanctioned and despite the
same, the allotment has been made by the then Officer
6 wp4640.15
of the Corporation without verifying the said aspects
and issued the offer letter and accepted the earnest
money. It is further contended that in some cases
the allotment orders were also passed and when the
allottee made representations to the higher
authorities for allotment of the plot, the matter was
noticed and thereafter the competent authority
directed to make the inquiry. In some of the cases
the offers and allotment orders were issued of more
than required area as per the project report. The
competent authority of M.I.D.C. directed to
reconsider the said offers and allotments and
accordingly a Committee was constituted for the same.
The said Committee after calling upon all the
interested persons including the petitioners
submitted its report to the competent authority.
Considering the report of the land allotment
committee and project report, fresh offer and
allotment letters were issued to the proposed
allottees. The Committee found that the petitioners
are eligible for the area of 2000 square meters as
per the project report and as per initial demand of
7 wp4640.15
the petitioner No.1.
10. It is further contended that the petitioners
have suppressed some material facts from this Court
i.e. the petitioners were called for the meeting of
the Land Allotment Committee. The petitioners
attended such meeting and after verifying the aspect
of the project report an area of 2000 square meters
was allotted to the petitioners. The petitioners
have deliberately suppressed this fact. The
petitioners were given information about the same and
the petitioners have also attended the said meeting
and after hearing the petitioners the impugned
communication is issued to them.
11. The respondent/authority has power to
reconsider the allotment as per the suitability based
upon the project report. Accordingly, the
respondents have allotted the plot admeasuring 2000
square meters to the petitioners. With this, the
respondents have prayed to dismiss the Writ Petition.
8 wp4640.15
12. We have heard Mr. N.V.Gaware, learned counsel
for the petitioners and Mr. S.S.Dande, learned
counsel for respondent no.1.
13. Mr. Gaware, learned counsel for the
petitioners has argued that the respondent no.1 has
executed an agreement in favour of the petitioners
and thereby allotted a plot admeasuring 2998 square
meters. The possession of the said plot was already
handed over to the petitioners. The petitioners have
constructed thereon a ware house as per the approved
plan. Completion certificate was also issued in
favour of the petitioners. Therefore, according to
Mr. Gaware, learned counsel, the right is created in
favour of the petitioners and subsequent alteration
by way of shrinking the plot is an illegal act of the
respondents.
14. As against this, Mr. Dande, learned counsel
for respondent no.1 has argued that earlier allotment
made was without approval of the lay out. Certain
irregularities were committed by the then Officer of
9 wp4640.15
the M.I.D.C. The Officer without verifying these
aspects has offered certain plots to the allottees.
When these irregularities were noticed by the higher
authorities, the Land Allotment Committee was
constituted. The Committee has examined all the
allotments and after considering the project report
of the allottees they have reconsidered and taken
decision to allot plot as per the requirement based
upon the project report and the respondents have
every authority to alter the area of the plot given.
Even the respondents have every authority to cancel
such allotment.
15. We have perused the record. On perusal of the
same, it appears that petitioner No.1, in the year
2003-2004, requested the respondents to allot him
Plot admeasuring 2000 square meters. This was his
initial demand as per requirement of his business.
Subsequently, by filing another application on
25.02.2005, the petitioner No.1 demanded Plot No. X-
34, admeasuring 5478 square meters. However, the
petitioner was unable to deposit the required amount
10 wp4640.15
with the respondents, therefore that offer was
cancelled by the respondent authority. Subsequently,
Plot No.X-34/1, Admeausring 2998 square meters was
allotted to the petitioner. However, such allotment
was without sanction of lay out plan. Such allotment
was made in favour of the petitioner by the then
Officer of the MIDC without verifying the said aspect
and issued offer letter and accepted the earnest
money from the petitioner. In some cases, allotment
orders were also passed and when the allottee made
representation to the higher authority for the
allotment of the plots, the mater was noticed and it
has been further noticed by the competent authority
that there is no lay out plan sanctioned and despite
that the offers and allotments of the plots were
made. In some cases, the offers and allotment
orders were issued more than the required area as per
the project report. Further, it reveals from the
record that after noticing such irregularities,
the Land Allotment Committee was constituted. The
said committee examined near about 18 allotments and
found that such allotments were made without
11 wp4640.15
sanction of the lay out plan and also the plot were
of more area than required.
16. For allotment of plots, the respondents have
considered the establishment of industry in the area,
nature of its activities, its requirement, the
environmental norms and after examination of such
aspects, allotment of the plots were made to the
allottees, including the petitioner. The petitioner
requested for allotment of plots and submitted a
project report for ware house as partnership firm and
considering the project report, the Committee found
the petitioner eligible for the area of 2000 square
meters for setting up the activity. Based upon such
report, Plot X-34/1 admeasuring 2000 square meters is
allotted to the petitioner. The petitioner
acknowledged the same. But this fact has not been
mentioned by the petitioners in the writ petition.
Respondent Nos. 2 and 3 have specifically contended
that the petitioner has suppressed the material
facts.
12 wp4640.15
17. Considering the rival contentions of the
parties, it reveals that earlier allotment of the
plots admeasuring 2998 square meter was without
sanction of the lay out plan. Allotment of a
particular area without sanction of the layout plan
is meaningless and without any base. Therefore the
respondents, after scrutiny of the proposals,
reallotted the plots as per eligibility of the
allottees. In fact, the respondents have removed
the irregularities in the allotment. Therefore, it
cannot be said that such act of respondents is
illegal.
18. The petitioners have relied upon the
observations of this Court in PIL No. 68/2013,
wherein, this Court has issued certain directions
about handing over of possession of the plots which
are carved without there being sanctioned lay out
plan and further directed to auction plots on which
the production activity is going on. In fact, the
above observation is in favour of the respondents,
since the earlier allotment of plot in favour of
13 wp4640.15
the petitioner was without sanction of lay out plan.
19. Furthermore, the respondents have relied
upon the provisions of Section 15 (f) (ii) of the
Maharashtra Industrial Development Act, 1961, which
reads as follows:
"15. Subject to the provisions of this Act,
the Corporation shall have power -
(f) (ii) To modify or rescind such allotments,
including the right and powers to evict the
allottees concerned on breach of any of the
terms or conditions, of their allotment;"
As per this provision, the respondents have
power to cancel the allotment, in case of breach of
any of the provisions of the Act. In the present
case, initial allotment of plot was basically
without there being sanctioned lay out plan.
Therefore, it was in contravention of the scheme.
The respondents have rightly cancelled the earlier
allotment and have allotted plot, admeasuring 2000
square meters, considering the entitlement of the
14 wp4640.15
petitioners, based upon the project report.
20. It is thus clear from the above facts and
circumstances and the reasons mentioned that no case
is made out by the petitioners. Writ petition is
accordingly dismissed. Rule discharged. No order as
to costs.
21. Status quo granted on 30th November, 2016
to continue till 14.04.2017.
(K. L. WADANE, J.) (S. V. GANGAPURWALA, J. )
JPC
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!