Citation : 2017 Latest Caselaw 4036 Bom
Judgement Date : 5 July, 2017
WP 4606/11 1 Judgment
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, NAGPUR.
WRIT PETITION No. 4606/2011
M/s BGR Energy Systems Limited,
a company incorporated under the
provisions of the Companies Act, 1956
through its General Manager (Finance & Accounts)
having its Registered Office at A-5,
Pannamgadu Industrial Estate, Ramapuram
Post, Sullurpet Taluk, Andhra Pradesh-524401
and Corporate Office at 443, Anna Salai, Teynampet
Chennai 600 018, work site - 2 X 500 MW
Expansion Project, Unit No.8 & 9, Chandrapur
Super Thermal Power Station,
MAHAGENCO, Chandrapur-442404,
Dist. Chandrapur, Maharashtra. PETITIONER
.....VERSUS.....
1. The Tahsildar, Chandrapur,
Sub-Divisional Magistrate Office Compound,
Railway Station Road, Chandrapur,
Maharashtra - 442 406.
2. The Sub-Divisional Officer, Chandrapur,
Sub-Divisional Magistrate Office Premises,
Railway Station Road, Chandrapur: 442 406.
3. The District collector, Chandrapur,
Railway Station Road, Chandrapur -
442 406, Maharashtra.
4. Maharashtra State Power Generation
Company Limited (MAHAGENCO),
company incorporated under the
provisions of Companies Act, 1956,
having its Registered Office at
Prakashgad, 3rd Floor, Plot No.G-9,
Bandra (East), Mumbai - 400 051
Work site - MAHAGENCO-Civil
Construction Circle, Unit No.8 & 9,
Chandrapur Super Thermal Power Station,
Chandrapur - 442404, Maharashtra.
5. Ministry of Finance,
through the Under-Secretary,
Revenue Section, Mantralaya,
Mumbai 400 032.
6. State of Maharashtra,
through its Secretary,
Department of Revenue & Forest,
Mantralaya, Mumbai - 32. RESPONDENTS
::: Uploaded on - 15/07/2017 ::: Downloaded on - 28/08/2017 09:08:09 :::
WP 4606/11 2 Judgment
Shri A.C. Dharmadhikari, counsel for the petitioner.
Shri K.L. Dharmadhikari, Assistant Government Pleader for the respondent nos.1 to 3, 5
& 6.
Shri D.M. Kale, cousnel for the respondent no.4.
CORAM :SMT.VASANTI A NAIK AND
A.D. UPADHYE, JJ.
DATE : 5 TH JULY, 2017.
ORAL JUDGMENT (PER : SMT.VASANTI A NAIK, J.)
By this writ petition, the petitioner challenges the order of the
Tahsildar, dated 16.03.2011 directing the petitioner to pay the royalty
and penalty for the illegal excavation of earth, under Section 48(7) of the
Maharashtra Land Revenue Code, 1966.
2. The petitioner was awarded a contract by the respondent
no.4-Maharashtra State Power Generation Company Limited for the
construction of 2X500 MW Thermal Power Project at Chandrapur. In
terms of the contract, the petitioner was required to erect buildings and
structures for setting up of the power project. While erecting the
structures as per the contract, the petitioner was required to dig the
project site and excavate the earth for the purpose of laying the
foundation of the structures. When the project reached at the stage of
completion, the Tahsildar served a notice on the petitioner asking it to
show cause as to why penalty should not be imposed on the petitioner for
illegally excavating the earth from the construction site without
permission. The petitioner replied to the said notice and denied the
WP 4606/11 3 Judgment
liability. The respondent no.1-Tahsildar by the impugned order, dated
16.03.2011 directed the petitioner to pay the royalty of Rs.52,86,200/-
and the penalty of Rs.1,58,58,600/-. The aforesaid order was challenged
by the petitioner before the Sub-Divisional Officer and the Collector but
the appeals filed by the petitioner were dismissed. The petitioner has
impugned the said orders in the instant petition.
3. Shri A.C. Dharmadhikari, the learned counsel for the
petitioner, submitted that ordinary earth was not included within the
definition of the term 'minor mineral' under Section 3(e) of the Mines and
Minerals (Development and Regulation) Act, 1957. It is submitted that
the Central Government by the notification, dated 03.02.2000, declared
that ordinary earth used for the purpose of filling and levelling purposes
in construction of embankments, roads, railways, buildings would be
considered as a minor mineral. It is submitted that the earth excavated
by the petitioner while executing the work for the power project was
stacked by the petitioner in the site of the power company and the same
was utilized for filling up the pits and the other areas that were dug up
during the construction. It is submitted that even assuming that the
ordinary earth that was excavated from the site was utilized by the
petitioner for filling a pond which was allegedly at a distance of two
kilometers from the site from where the earth was excavated still, the
excavated earth cannot be brought within the fold of the term 'minor
WP 4606/11 4 Judgment
mineral' as defined under the provisions of Section 3(e) of the Mines
and Minerals (Development and Regulation) Act and the notification,
dated 03.02.2000. It is submitted that the notification dated 03.02.2000
clearly declares that only ordinary earth used for filling or levelling
purpose in construction of embankments, roads, railways, buildings could
be treated as minor mineral. It is submitted that it is not the case of the
revenue authorities that the petitioner had utilized the excavated earth
for filling or levelling purposes as are mentioned in the notification, dated
03.02.2000. It is submitted that in the circumstances of the case, the
judgment of the Hon'ble Supreme Court reported in 2015(12) SCC 736
(Promoters and Builders Association of Pune Versus State of
Maharashtra & Others) would help the petitioners in assailing the
impugned orders.
4. Shri K.L. Dharmadhilari, the learned Assistant Government
Pleader appearing for the revenue authorities, has supported the orders of
the authorities. It is submitted that the petitioner had not only excavated
the earth from the construction site but had carried it to the pond which
is at a distance of two kilometers away from the site. It is submitted that
the royalty and penalty is sought to be imposed upon the petitioner under
the provisions of Section 48(7) of the Maharashtra Land Revenue Code as
the excavation and transportation of the earth by the petitioner was
without permission of the revenue authorities.
WP 4606/11 5 Judgment
5. On hearing the learned counsel for the parties and on a
perusal of the judgment of the Hon'ble Supreme Court reported in
2015(12) SCC 736 (Promoters and Builders Association of Pune Versus
State of Maharashtra & Others) as also the impugned orders, it appears
that the impugned orders cannot be sustained. Ordinary earth was not
included within the definition of the term 'minor mineral' till it was
brought within the fold of the said term by the notification, dated
03.02.2000 issued by the Central Government under the provisions of
Section 3(e) of the Mines and Minerals (Development and Regulation)
Act. The relevant part of the notification issued by the Central
Government, dated 03.02.2000 reads thus:-
NOTIFICATION
"GSR 95(E). -- In exercise of the powers conferred by clause (e)
of Section 3 of the Mines and Minerals (Development and
Regulation) Act, 1957 (67 of 1957), the Central Government
hereby declared the 'ordinary earth' used for filling or levelling
purposes in construction of embankments, roads, railways,
buildings to be a minor mineral in addition to the minerals
already declared as minor minerals hereinbefore under the said
Clause."
On a perusal of the notification, it is clear that ordinary earth used only
for filling or levelling purposes in construction of embankments, roads,
WP 4606/11 6 Judgment
railways, buildings could be considered as minor mineral in addition to
the minerals mentioned in Section 3(e) of the Act of 1957. It is apparent
from a reading of the notification dated 03.02.2000 that ordinary earth
used for any purposes other than the purpose of filling or levelling as
mentioned in the notification is not brought within the fold of the term
'minor mineral' under section 3(e) of the Act. It is not the case of the
respondent-Authorities that the petitioner had utilized the excavated
earth for the purpose of filling or levelling of embankments, roads,
railways or buildings. According to the respondent-Authorities, as could
be seen from the impugned order as also the affidavit-in-reply filed on
behalf of the respondent-Authorities, the excavated earth was utilized by
the petitioner for the purpose of filling a pond which is at a distance of
two kilometers away from the site from where the earth was excavated.
The purpose for which the excavated earth was utilized by the petitioner
is not a purpose that is specified in the notification, dated 03.02.2000.
The end use of the excavated earth in the case of the petitioner is not for
the purposes mentioned in the notification, dated 03.02.2000. Since it is
not the case of the respondent-Authorities that the petitioner had utilized
the ordinary earth excavated from the project site for filling or levelling of
embankments, roads, railways, buildings the excavated earth could not
have been considered as a minor mineral. Since the ordinary earth used
for filling and levelling purpose for construction of embankments, roads,
railways, buildings, etc. is a minor mineral and since in the instant case,
WP 4606/11 7 Judgment
the petitioner had not used the ordinary earth in the construction of
embankments, roads, railways and buildings, the ordinary earth
excavated by the petitioner could not have been considered to be a minor
mineral so as to invoke the provisions of Section 48(7) of the
Maharashtra Land Revenue Code, 1966. It appears that the revenue
authorities did not consider the notification dated 03.02.2000 issued
under section 3(e) of the Mines and Minerals (Development and
Regulation) Act before passing the order imposing penalty on the
petitioner.
6. Hence, for the reasons aforesaid, the writ petition is allowed.
The impugned orders passed by the revenue authorities are hereby
quashed and set aside.
Rule is made absolute in the aforesaid terms with no order as
to costs.
JUDGE JUDGE APTE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!