Citation : 2017 Latest Caselaw 6010 Bom
Judgement Date : 16 August, 2017
BGD 1/13 902 carap 44.2016
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMM. ARBITRATION APPLICATION NO.44 OF 2016
Tatva Global Environment (Deonar) .... Applicant
Limited
Vs.
Municipal Corporation of Greater .... Respondent
Mumbai.
Mr. Shardul Singh i/by HVS Legal for the Applicant.
Ms. Vaishali Chaudhary a/w Mr. P.Y. Sirsikar for the Respondent.
Coram : G.S. KULKARNI, J.
Date : 16 August, 2017
P.C. :
1 Leave to amend to correct the date of the agreement is
granted. Reverification is dispensed with.
2 This is an application under Section 11(6) of the Arbitration
and Conciliation Act, 1996 (for short the 'Act') praying for appointment
of an arbitrator for adjudication of the disputes and differences that
have arisen between the parties under the Concession Agreement dated
31st October, 2011.
BGD 2/13 902 carap 44.2016
3 The facts can be summarised thus :
The Respondent-Municipal Corporation had floated a
tender inviting bids for works titled as "the partial closure and
maintenance of the Existing Dump Site and Design, Engineering, Operation
and Maintenance of Integrated Waste Management Facilities on Design,
Build, Own, Operate and Transfer (DBOOT) basis at Deonar, Mumbai".
The successful bidder would enter into a 'concession agreement' with the
respondent-Corporation. The applicant was the successful bidder. On
30th October, 2009, the respondent issued a Letter of Award in favour of
the applicant. Consequent to this, a concession agreement dated 31 st
October, 2011 came to be executed between the applicant and the
respondent. The duration of the contract was to be 25 years. The nature
of the project is defined in Clause 1.40 of the said agreement. The
agreement created obligations between the parties.
4 Under the above agreement in regard to the applicant's
monetary claims, disputes had arisen between the parties. The
applicant had invoked Section 11(6) of the Arbitration Act as the
respondent had failed to appoint an arbitrator by approaching this court
BGD 3/13 902 carap 44.2016
in Arbitration Application No. 15 of 2014. The Court considering the
rival pleas and considering the nature of the arbitration clause, by it's
order dated 19 March, 2015 allowed the applicant's application and
appointed a sole arbitrator to decide the disputes between the parties.
The applicants contend that it is the same arbitration clause which has
been invoked in the present application, however, on a different dispute.
5 The case of the applicant in the present application, is that
apart from the monetary disputes, in regard to other matters under the
agreement as raised by the applicant by its several letters, there was no
response from the respondent-Corporation. The applicant by it's letter
dated 28 February, 2014 made concrete efforts to bring the notice of the
respondent various breaches and issues, which were required to be
resolved. The grievance of the applicant was particularly as regards the
non-execution of lease deed or its alternative, for change in the effective
date of contract, technology options, assignment and protection of the
secured lender's rights etc. The applicant issued further
letters/representations dated 5 May, 2014 and 30 May, 2014 and 14
August 2015, setting out the breaches on the part of the respondent.
BGD 4/13 902 carap 44.2016
6 The respondent, however, instead of resolving the issues,
issued a pre-termination notice dated 8 September, 2015 to the
applicant, stated to be a notice as per Clause 17 of the said agreement.
The applicant was called upon to cure, the breaches to the satisfaction of
the respondent, within 60 days. On receipt of this notice, the applicant
filed Writ Petition (L) No. 2906 of 2015 in this court, seeking directions
against the State Government for issuance of land lease agreement. By
an order dated 27 October, 2015 passed by the Division Bench, the
applicant was permitted to make a representation to the State
Government as also submit a reply to the pre-termination notice. The
applicant, accordingly submitted a representation as also submitted a
detailed reply dated 5 November, 2015 to the pre-termination notice
pointing out that various breaches that have been committed by the
respondent and pointed out that the applicant was not in breach of any
of the provisions of the concession agreement. The applicant thus
contended that the pre-termination notice was bad in law. The
respondent however did not consider the applicant's reply to the pre-
termination notice and issued a termination notice dated 22 January
2016.
BGD 5/13 902 carap 44.2016
7 On the above background, the case of the applicant is that
the disputes have arisen between the applicant and the respondent on
account of illegal termination of the contract and that the applicant is
entitled to seek damages on the termination of the contract by the
respondent. The applicant therefore issued a notice dated 13 June,
2016 invoking the arbitration agreement being Clause 21 under the said
agreement dated 31 October, 2011, recording that disputes have arisen
between the parties. The applicant also suggested the names of two
independent arbitrators. Despite a lapse of 30 days, the respondent did
not respond to the said notice. However belatedly on 21 July 2016, the
applicant received a reply from the respondent whereby it refused to
accept one of the arbitrators nominated by the applicant or to nominate
its Arbitrator. The respondent however decided to constitute it's own
committee of three members to look into the dispute. This according to
the applicant was not appropriate, as the notice of the applicant was for
appointment of an Arbitrator as the contention of the applicant was that
Clause 21 of the concession agreement constituted an arbitration
agreement and it was obligatory on the part of the respondent to
appoint an independent arbitrator to resolve the dispute, that had arisen
between the parties. On this conspectus, the applicant is before this
BGD 6/13 902 carap 44.2016
court in the present proceedings.
8 Before adverting to the submission as made on behalf of the
learned counsel for the parties, it would be appropriate to note Clause
21 of the agreement, which speaks of 'dispute resolution' and Clause 23,
which provides for jurisdiction. These clauses read thus :
"21 DISPUTE RESOLUTION :
If any dispute, difference or claim arises by either party to any matter arising out of this Agreement, the aggrieved party may refer such dispute within a period of 7 days to the concerned Additional Municipal Commissioner, who shall constitute a committee comprising of three officers i.e. concerned D.M.C. Or Dir. (E.S. & P.), Chief Engineer other than the engineer of contract and concerned Chief Accountant. The committee shall give its decision within 60 days.
Appeal from the order of the committee may be referred to Municipal Commissioner within 7 days. Thereafter the Municipal Commissioner shall constitute the committee comprising of three Additional Municipal Commissioners including Additional Municipal Commissioner in-charge of finance department. The decision given by this committee shall be final and binding upon the parties.
23 JURISDICTION:
Subject to Clause 21, only the courts in Mumbai shall have jurisdiction to try all disputes and matters arising out of or under this Agreement, after reference to arbitration.
9 Mr. Singh, learned counsel for the applicant would submit
that Clause 21 constitutes an arbitration agreement between the parties.
Mr. Singh submits that Clauses 23 reinforces the intention of the parties
of reference of the disputes to arbitration under Clause 21. It is
BGD 7/13 902 carap 44.2016
submitted that Clauses 21 and 23 were subject matter of consideration
of this Court in Arbitration Application No. 15 of 2014 as decided by this
court by it's order dated 19 March, 2015, which pertained to the
monetary dispute between the parties under the same agreement. Mr.
Singh submits that considering the nature of Clause 21 (supra), the
court has come to a conclusion that said clause, would constitute a valid
and subsisting arbitration agreement between the parties and invoking
Clause 21 for reference of the disputes to an arbitral tribunal, would be
a legal and valid, for appointment of an arbitral tribunal. Mr. Singh
would submit that the said order passed by this Court was challenged by
the respondent by approaching the Supreme Court in S.L.P. (C) No.
20400 of 2016. The Supreme Court, by an order dated 28 October,
2016 rejected the S.L.P. of the respondent-Corporation not only on the
ground of delay but also on merits. Mr. Singh thus submits that in view
of said orders passed by this Court and having confirmed by the
Supreme Court, the respondent cannot oppose appointment of an
arbitrator to arbitrate the dispute in the present proceedings, which
arises under the same agreement.
BGD 8/13 902 carap 44.2016
10 On the other hand, learned counsel for the respondent-
Corporation would vehemently contest this petition. Learned counsel
for the respondent would not agree with the submission as made on
behalf of the applicant that Clause 21 having fell for consideration of
this court in the earlier round litigation, between the parties and the
orders by this being confirmed by the Supreme Court would conclude
the issue. The contention on behalf of the respondent is that the orders
passed by the learned Single Judge in Arbitration Application No. 15 of
2014 cannot be relied as the said order passed by the learned Single
Judge is not a decision of a judicial authority or a Court as defined
under Section 2(1)( C) of the Arbitration Act but by the Chief Justice or
his delegate. Learned counsel for the respondent would support this
contention relying on the decision of the Supreme Court in State of
West Bengal and others vs. Associated Contractors 1. The next
submission as made on behalf of the respondent is that Clause 21 is not
an arbitration clause, as Clause 21 provides for a mechanism by which
the departmentally dispute should be resolved between the parties. In
support of this proposition, learned counsel for the respondent has
placed reliance on the decisions in "Ved Prakash Gupta Vs. Municipal
1 (2015) 1 Supreme Court Cases 32
BGD 9/13 902 carap 44.2016
Corporation of Gr.Bombay, through the Municipal Commissioner &
Ors."2, "Vishnu(Dead) By LRS. Vs. State of Maharashtra & Ors. 3",
"State of Orissa & Ors. Vs. Bhagyadhar Dash" 4, and "P.
Dasaratharama Reddy Complex Vs. Government of Karnataka &
Anr.5. It is next submitted that the order passed by this court in
Arbitration Application No.15 of 2014 (Supra) though confirmed by the
Supreme Court does not take into consideration the clear position in law
as laid down in the above decisions as referred by the learned counsel
for the respondent. Thus the submission on behalf of the respondent is
that this application is required to be rejected by permitting the
respondent-Corporation to follow the mechanism as set out in Clause 21
of the agreement in question.
11 Having heard the learned Counsel for the parties and
having examined Clause 21 read with clause 23 of the Contract in
question, I am of the clear opinion that Clause 21 is an arbitration
agreement between the parties. As to what would constitute an
arbitration agreement and what would be the necessary constituents of
2 1999 (1) Bom. C.R. 112 3 (2014) 1 Supreme Court Cases 516 4 (2011) 7 Supreme Court Cases 406 5 (2014) 2 Supreme Court Cases 201
BGD 10/13 902 carap 44.2016
an arbitration agreement is now well settled (See."K.K.Modi Vs.
K.N.Modi"6 and "Jagdish Chander Vs. Ramesh Chander & Ors)."7 A
bare reading of Clause 21 clearly indicates that essential requirements as
necessary for the clause to be construed as an arbitration agreement are
very much present. The essentials being the parties agreeing to refer
present or future differences in connection with the agreement to a
private tribunal and the parties agreeing that the decision of such
dispute resolution shall be final and binding between the parties. There
is no dispute that the applicant and the respondent have executed such
an agreement as contained in clause 21. The intention of clause 21
being an arbitration agreement is further fortified by reading of clause
23, which specifically refers to arbitration between the parties. On
conjoint reading of clause 21 and 23 of the contract in question, it can
sufficiently be concluded that clause 21 is an arbitration clause. I am,
therefore, in complete agreement with the decision of the learned Single
Judge in Arbitration Application No.15 of 2014 in which the learned
Single Judge considering the position in law laid down in catena of
decisions of the Supreme Court has held Clause 21 to be an arbitration
agreement between the parties. It is further significant that the decision
6 1998(1) SCC 407 7 (2007)5 SCC 719
BGD 11/13 902 carap 44.2016
of the learned Single Judge has attained finality in view of dismissal of
Special Leave Petition by the Supreme Court on merits as noted above.
12 In view of the above discussion, the submission on behalf of
the respondent that the judgment of the learned Single Judge has no
precedential value, is of no consequence. The learned Counsel for the
respondent in making such submission has completely overlooked the
consequence of the judicial order passed by the Supreme Court
dismissing a Special Leave Petition filed under Article 136 of the
Constitution. In any event having concurred with the reasoning of the
learned Single Judge in the decision in Arbitration Application No. 15 of
2014, the reliance of the respondent on the decision in "State of West
Bengal & Ors. Vs. Associated Contractors" (supra) is of no avail.
13 As regards the reliance of the respondent on the decision in
"Ved Prakash Gupta Vs. Municipal Corporation of Gr.Bombay,
through the Municipal Commissioner & Ors."(supra), "Vishnu(Dead)
By LRS. Vs. State of Maharashtra & Ors."(supra), "State of Orissa &
Ors. Vs. Bhagyadhar Dash"(supra), "P.Dasaratharama Reddy
Complex Vs. Government of Karnataka & Anr."(supra), in my opinion,
BGD 12/13 902 carap 44.2016
it is clearly unfounded. These decisions as cited refer to specific clauses,
which deal with specific issues of designs etc. which pertain to issues in
the working and the progress of the contract, in which certain technical
decisions are required to be taken by the departmental officers.
Considering the nature of the clauses as considered in each of the said
decisions, the Court has come to a conclusion that these are not
arbitration clauses. However, the arbitration agreement in the present
case is in no manner comparable to the specific clauses considered in the
said decision.
14 In the light of the above discussion, this application is
required to be allowed by appointing a sole Arbitrator to adjudicate the
disputes that have arisen between the parties under the Concession
Agreement dated 31 October 2011. I propose to appoint Shri Justice
Mohit S. Shah, Former Chief Justice of this court to arbitrate the
disputes between the parties.
15 To enable the learned proposed Arbitrator to submit a
disclosure as per the requirement of Section 11 (8) read with 12(1) of
the Arbitration Act, stand over for four weeks.
BGD 13/13 902 carap 44.2016
16 Office to forward a copy of this order to Shri. Mohit S.
Shah, Former Chief Justice of this Court.
17 Stand over to 13 September 2017 to be listed under the
caption "for Directions".
(G.S. KULKARNI, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!