Citation : 2017 Latest Caselaw 5867 Bom
Judgement Date : 11 August, 2017
wp5435.04 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH
WRIT PETITION/ PIL NO. 5435 OF 2004
Madhusudan H. Roongta,
President, Industries Association,
Chandrapur. ... PETITIONER
Versus
1. The Collector, Chandrapur.
2. The Chief Engineer (Gen. & O. & M.)
Super Thermal Power Station
(CSTPS), Urjanagar, Chandrapur.
3. Union of India
through Secretary, Ministry of
Environment and Forest,
New Delhi.
4. Chief Engineer,
Corporate Environmental Health
and Safety Unit, Maharashtra State
Electricity Board, Prakashgad, 3rd
Floor, Bandra (East), Mumbai.
5. Maharashtra State Electricity Board,
Prakash Garh, Bandra-East, Mumbai
400 051.
6. The Member Secretary, Maharashtra
Pollution Control Board, Kalpana
Point, 4th Floor, Sion Matunga Scheme
Road No. 8, Sion (Circle), Sion (East),
Mumbai 400 002.
7. The State of Maharashtra
through the Principal Secretary,
Ministry of Energy and Environment,
::: Uploaded on - 16/08/2017 ::: Downloaded on - 17/08/2017 01:48:57 :::
wp5435.04 2
Mantralaya, Mumbai.
8. Maharashtra Pollution Control
Board, Sub-Regional Office,
Chandrapur, through its
Sub-Regional Officer, New
Administrative Building,
Block Nos. 13 & 14, Ground
Floor, In front of Hotel Palace,
Mul Road, Chandrapur 442 401.
9. Wester Coalfields Limited,
through its Chairman-cum-
Managing Director, having its
registered office at Coal Estate,
Civil Lines, Nagpur.
... RESPONDENT
Shri H.V. Thakur, Advocate for the petitioner.
Shri K.L. Dharmadhikari, AGP for respondent No. 1 & 7.
Shri R.E. Moharir, Advocate for respondent Nos. 2 & 5.
Shri A.M. Aurangabadkar, Advocate for respondent No. 3.
.....
CORAM : B.P. DHARMADHIKARI &
ARUN D. UPADHYE, JJ.
AUGUST 11, 2017.
ORAL JUDGMENT : (PER B.P. DHARMADHIKARI, J.)
Heard Shri Thakur, learned counsel for the
petitioner, Shri Dharmadhikari, learned AGP for respondent
Nos. 1 & 7, Shri Moharir, learned counsel for respondent Nos. 2
& 5 and Shri Aurangabadkar, learned counsel for respondent
No. 3.
2. The grievance has been entertained in public
interest. The petitioner points out air and water pollution due
to activity of production of electricity undertaken at Thermal
Power Station at Chandrapur by respondent Nos. 2 & 5.
3. After arguments, we find that fly ash generated in
the process and its storage/ handling may be adding to the
problem. The petitioner contends that even recent report of
Respondent No. 8 - Maharashtra Pollution Control Board
reveals utilization of only 45% of fly ash. He further points out
that it is stored in open and, therefore, is blown away by air
and flows in the streams and ponds, thereby contaminating
river.
4. Shri Moharir, learned counsel for respondent Nos. 2
& 5 submits that to prevent ash from being blown away, it is
kept wet and some slurry i.e. solution of ash and water, may be
generated in the process. He submits that adequate precautions
are being taken to see that it does not contaminate ground
water or then it does not affect ambient air quality.
5. The respective counsel had at one stage also agreed
that the matter may be required to be sent to the National
Green Tribunal.
6. The learned AGP and Shri Aurangabadkar, learned
counsel, however, submit that cognizance taken is about 13
years back and in recent years, several technologies have been
advanced. According to them, report of Maharashtra Pollution
Control Board in recent visit and technologies adopted by
Respondent Nos. 2 & 5, need to be looked into by this Court.
7. We have perused the document dated 07.06.2017
handed over by Shri Moharir, learned counsel (Visit Report
dated 07.06.2017 is taken on record and marked as Exh. "X").
It is visit report by Respondent No. 8 - Maharashtra Pollution
Control Board. Shri Thakur, learned counsel submits that he
has received the document today only and needs some time to
understand its exact implications.
8. Taking overall view of the matter, we find that even
Report dated 07.06.2017 of Respondent No. 8 - Board may not
show very satisfactory position. The petitioner may be required
to file additional affidavit to bring on record the implications
and import thereof.
8. We, therefore, find it proper to direct the Registry
of this Court to register a new Public Interest Litigation
mentioning Shri Madhusudan H. Roongta, as petitioner with
Shri H.V. Thakur, as his counsel. On the basis of this report
and other material, we grant leave to Shri Roongta to file fresh
memo, bringing on record up to date position. The copies
thereof shall be served on the respective counsel and
respondents. The respondents can file their reply to it within
four weeks after the memo is served upon them.
9. The objection about jurisdiction and need to send
the matter to National Green Tribunal is kept open and can be
looked into at that stage. We grant the petitioner time of four
weeks to file appropriate memo in this respect.
10. Accordingly, with these observations and directions,
we dispose of the present Writ Petition/ PIL. However, in the
facts and circumstances of the case, there shall be no order as
to costs.
JUDGE JUDGE
******
*GS.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!