Citation : 2017 Latest Caselaw 1993 Bom
Judgement Date : 25 April, 2017
1 WP4222-14
FARAD CONTINUATION SHEET No.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH AT NAGPUR
WRIT PETITION NO. 4222/2014
(APARNA INFRAENERGY INDIA PVT.LTD. VERSUS UNION OF INDIA & OTHERS)
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Office Notes, Office Memoranda of Coram, Court's or Judge's orders
appearances, Court's orders of directions
and Registrar's orders
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Shri Anand Jaiswal, Senior Counsel with Shri S. Khedkar, counsel for the
petitioner.
Mrs. M.R. Chandurkar, counsel for the R-1 and 2.
Shri S.P. Dharmadhikari, Senior Counsel with Shri M.Anilkumar, counsel for
the R-3 and 4.
CORAM : SMT. VASANTI A NAIK AND
MRS. SWAPNA JOSHI, JJ.
DATE : APRIL 25
, 2017.
By this writ petition, the petitioner-Aparna
Infraenergy India Private Limited, Nagpur seeks a declaration
that the action on the part of the respondent no.3-Western
Coalfields Limited of issuing the communication, dated
07.12.2013 as also the impugned order dated 27.06.2014
cancelling the letter of assurance issued in favour of the
petitioner-Company is arbitrary and violative of the provisions of
Article 14 of the Constitution of India. The petitioner has sought
a direction against the respondents to execute the fuel supply
agreement in favour of the petitioner as per letter of assurance
dated 16/17.07.2010 by holding that the petitioner has achieved
all the milestones as per the letter of assurance.
The petitioner is a private limited company
registered under the Indian Companies Act, 1956. The
2 WP4222-14
respondent no.1-Union of India/Ministry of Coal had floated a
new coal distribution policy on 18.10.2007 pertaining to the
allocation of coal to be made by the respondent no.3-Western
Coalfields Limited and its other subsidiaries. On 11.07.2008, a
partnership firm in the name of M/s Aparna Infraenergy was
formed wherein Shri Mitesh Bhangadiya, Shri Sanjay Shivankar
and Smt.Kiran Wadettiwar were the partners. The said
partnership firm desired to set up a power plant at Kawathala
and was desirous of securing coal linkage for the said purpose.
The partnership firm, therefore, applied to the Standing Linkage
Committee on 04.08.2008 seeking the allocation of coal. The
Standing Linkage Committee recommended to the Western
Coalfields Limited that a letter of assurance as per the new coal
distribution policy could be granted to the partnership firm. The
Western Coalfields Limited called upon the firm to submit
commitment guarantee for the issuance of the letter of
assurance. The partnership firm applied to the Register of the
Partnership Firm for the registration of the same and was
registered as such on 07.05.2010. On 24.05.2010, admittedly
seven new partners that were the subsidiaries of M/s Gammon
Infrastructure Projects Limited joined as partners in the firm.
The said partnership-deed was also registered and a
commitment guarantee to the tune of Rs.10,09,34,000/- was
3 WP4222-14
submitted by the said reconstituted firm to the Western
Coalfields Limited on 25.05.2010. A letter of assurance was
issued in favour of the partnership firm M/s Aparna Infraenergy
India Private Limited on 16.07.2010. On 05.01.2011, the three
partners that initially constituted the firm, viz. Shri Mitesh
Bhangadiya, Shri Sanjay Shivankar and Smt.Kiran Wadettiwar
retired from the firm and the firm comprised of only seven
partners that were included in the firm as partners on
24.05.2010. It is the case of the petitioner-Company that steps
were taken by the petitioner-Company for achieving the
milestones as per the letter of assurance issued in favour of the
partnership firm on 16.07.2010. It is stated that several
communications were exchanged between the Western
Coalfields Limited and the company pertaining to the
achievement of the milestones. On 10.08.2012, the Western
Coalfields Limited informed the company that the bank
guarantee submitted by the company would be forfeited as the
milestones were not achieved within the stipulated time.
However, the petitioner-Company wrote to the Western
Coalfields Limited vide several communications that are placed
on record pointing out that the milestones were achieved and
what was not achieved would be complied within the time
frame. Admittedly, the Western Coalfields Limited did not take
4 WP4222-14
any action against the company in respect of the forfeiture of the
bank guarantee as per its communication, dated 10.08.2012.
The Standing Linkage Committee took a decision on 01.07.2013
that the Western Coalfields Limited should look into the matter
pertaining to the cancellation of letter of assurance to the
petitioner-Company and report to the committee. By an order
dated 07.12.2013, the petitioner was informed by the Western
Coalfields Limited that the partnership firm had breached the
conditions in the letter of assurance, since there is an
assignment of the letter of assurance in favour of the company
in which none of the partners that had originally applied for the
letter of assurance are the partners. It was informed that the
taking over of the original firm by the petitioner-Company could
not be accepted. In pursuance of the said order, the letter of
assurance was cancelled as the original partners of the company
that had applied for the letter of assurance had assigned their
right and interest in the letter of assurance. By the impugned
communication and order dated 07.12.2013 and 27.06.2014
respectively, the letter of assurance awarded in favour of the
partnership firm on 16.07.2010 was cancelled. The action on
the part of the respondent-Western Coalfields Limited in
cancelling the letter of assurance is challenged by the petitioner
in the instant petition.
5 WP4222-14
Shri Jaiswal, the learned Senior Counsel appearing
for the petitioner-Company, submitted that as per the letter of
assurance, the power or the authority to cancel or withdraw the
letter of assurance could be invoked only under Clause 3.4.1 of
the letter of assurance, which provides that the cancellation
could be effected if the milestones are not achieved within the
specified time. It is stated that only if the milestones were not
achieved within the specified time under clause 3.4.1, there
could have been a cancellation or withdrawal of the letter of
assurance. It is stated that it is apparent from Clause 3.4.1 of
the letter of assurance that only when the letter of assurance is
cancelled due to non-achievement of the milestones, the bank
guarantee could be invoked. It is stated that in the instant case,
the Western Coalfields Limited has cancelled the letter of
assurance by the impugned order dated 24.07.2014 only on the
ground that the original partners had withdrawn from the
partnership firm and a new company with seven other
incorporated entities was formed. It is submitted that the
cancellation of the letter of assurance was permissible only if the
petitioner had failed to achieve the milestones and since the
cancellation of the letter of assurance is not due to non-
achievement of the milestones by the petitioner, the same is
liable to be set aside in view of Clause 3.4.1 of the letter of
6 WP4222-14
assurance. It is submitted that in any case, the respondent-
Western Coalfields Limited is not entitled to encash the bank
guarantee unless it comes to a conclusion that the petitioner-
Company has not achieved the milestones. It is submitted that
in the circumstances of the case, the impugned orders-
communications are liable to be set aside.
The learned counsel for the respondent no.1-Union
of India has denied the prayers made in the writ petition and
submitted that the respondent no.1 is under an obligation to
ensure that the scarce natural resource, such as coal is
distributed in a just, fair, unbiased and legal manner in order to
exclude any possibility of transfer of the Coal Linkage in an
unauthorized manner to a person or entity, who is not eligible
for the coal linkage or intends to acquire the linkage from the
holder of the linkage under the garb of reconstitution of
partnership firm/ corporate restructuring, etc. It is submitted
that initially an unregistered partnership firm comprising of only
three partners had sought a letter of assurance and it was
decided that the same could be granted to the firm. It is stated
that the commitment guarantee was submitted on 25.05.2010
by a partnership firm that was reconstituted on 24.05.2010,
including therein seven new partners, all of which were the
subsidiaries of M/s Gammon Infrastructure Projects Limited. It
7 WP4222-14
is submitted that on 05.01.2011, the seven partners that were
included in the partnership firm on 24.05.2010 continued to be
the partners in the newly constituted firm-company after the
removal of the three partners that initially constituted the firm
in the year 2008. It is submitted that the retiring partners, i.e.
the three partners that had initially formed the firm opted out of
the partnership after receiving a sum of Rupees Forty Crores as
consideration. It is stated that the said action is contrary to
Condition No.5 in the letter of assurance. It is stated that apart
from the illegal assignment, the petitioner could not achieve the
milestones within the stipulated time and the letter of assurance
has lapsed on 17.07.2012.
Shri Dharmadhikari, the learned Senior Counsel
appearing for the respondent-Western Coalfields Limited has
opposed the prayers made in the writ petition. It is submitted
that initially, the partnership firm comprised of three partners
Shri Mitesh Bhangdiya, Shri Sanjay Shivankar and Smt.Kiran
Wadettiwar and the partnership comprising of the said partners
had sought for the letter of assurance. It is stated that before
the letter of assurance was issued, the partnership firm inducted
seven more partners in the partnership firm that are the
subsidiaries of M/s Gammon Infrastructure Projects Limited
without informing the Western Coalfields Limited. It is
8 WP4222-14
submitted that on 24.05.2010, the partnership firm was
reconstituted and the commitment guarantee was tendered by
the said firm to the Western Coalfields Limited on 25.05.2010.
It is stated that thereafter on 05.01.2011, by accepting a sum of
Rupees Forty Crores from the seven subsidiaries of M/s
Gammon Infrastructure Projects Limited, that were inducted in
the partnership firm as partners on 24.05.2010, the three
partners that initially constituted the firm, i.e. Shri Mitesh
Bhangadiya, Shri Sanjay Shivankar and Smt.Kiran Wadettiwar
retired from the partnership firm. It is submitted that the
acceptance of Rupees Forty Crores towards consideration for the
assignment of the letter of assurance in favour of the
subsidiaries of M/s Gammon Infrastructure Projects Limited
would result in profiteering in coal allocation and would be a
fraud on the authority. It is submitted that Clause 5 of the letter
of assurance clearly provides that it would not be permissible for
the assured, i.e. the partnership firm in this case, in whose
favour the letter of assurance was decided to be granted, to
assign to any third person, the letter of assurance or any right,
benefit, obligation or interest therein or thereunder without the
express prior written permission of the Western Coalfields
Limited. It is submitted that it was necessary for the partnership
firm to have secured the prior consent of the Western Coalfields
9 WP4222-14
Limited before including or removing the partners in the firm. It
is submitted that in view of the minutes of the review meeting of
the Standing Linkage Committee, dated 18.04.2011, and
specially Clause (d) of (XVII), the letter of assurance holders are
required to apply to the Ministry of Coal for seeking change in
the name of the company due to various factors as a result of
change in management, change in shareholding pattern,
approval by the Registrar of Company (ROC), amalgamation,
demerger, court orders, etc. It is submitted that as per the
minutes of the meeting dated 18.04.2011 and Clause 5 of the
letter of assurance, it was necessary for the letter of assurance
holder to seek express prior written consent of the Western
Coalfields Limited as well as the Ministry of Coal before
assigning any right, benefit, obligation or interest under the
letter of assurance. It is submitted that since there is a breach of
Clause 5 of the letter of assurance, the letter of assurance issued
in favour of the firm on 16.07.2010 is rightly cancelled. It is,
however, stated by the learned Senior Counsel on instructions
from Ms Anuradha Mourya, the Deputy Manager (Sales and
Marketing) of the Western Coalfields Limited, who is present in
the Court today, that in respect of the encashment of the bank
guarantee and forfeiture thereof, the Western Coalfields Limited
would issue a notice to the petitioner asking it to show cause as
10 WP4222-14
to why the guarantee should not be forfeited and encashed. It is
stated that the bank guarantee would be encashed, if necessary,
only after granting an opportunity to the petitioner-Company.
In the circumstances of the case, we do not find that
the Western Coalfields Limited committed any illegality in
cancelling the letter of assurance. Initially, Shri Mitesh
Bhangadiya, Shri Sanjay Shivankar and Smt.Kiran Wadettiwar
had formed a partnership firm with a view to set up a power
plant at Kawathala. With the aforesaid object in view, the said
partnership firm comprising of the aforesaid partners applied for
the coal linkage. The coal linkage committee decided to grant a
letter of assurance in favour of the partnership firm. By the time
the letter of assurance could be granted to the partnership firm,
the partnership firm had inducted seven more partners in the
partnership firm that were the subsidiaries of M/s Gammon
Infrastructure Projects Limited. The partnership firm comprised
of ten partners with its reconstitution on 24.05.2010. The said
partnership firm submitted a commitment guarantee to the
Western Coalfields Limited on 25.05.2010 and the letter of
assurance was issued in favour of the said company on
16.07.2010. Certain milestones were required to be achieved by
the firm after the issuance of the letter of assurance and
communications are exchanged between the said firm and the
11 WP4222-14
Western Coalfields Limited in regard to the achievement/non-
achievement of the milestones within the specified time.
Though the Western Coalfields Limited had decided to forfeit
the bank guarantee vide communication, dated 10.08.2012 the
said order was not given effect to and we find that several
communications were exchanged between the parties thereafter
in regard to the achievement of the milestones. In the
meanwhile, the Western Coalfields Limited and the Ministry of
Coal realized that the partnership firm to which the letter of
assurance was granted on 16.07.2010 is reconstituted on
05.01.2011. It was noticed by the respondent no.1 and the
Western Coalfields Limited that on 05.01.2011, the original
partners retired from the partnership after accepting a sum of
Rupees Forty Crores from the seven other partners that were the
subsidiaries of M/s Gammon Infrastructure Projects Limited and
the firm, that was subsequently registered under the Companies
Act comprised only of seven partners which did not include any
of the partners that had initially constituted the firm in the year
2008 for the purpose of setting up a power plant at Kawathala.
There is an exchange of communications between the parties in
this regard and by the impugned order-communication, the
Western Coalfields Limited has cancelled the letter of assurance.
We do not find that the action on the part of the respondent-
12 WP4222-14
Western Coalfields Limited is bad in law, as the said action is in
consonance with the conditions of the letter of assurance.
Condition No.5 of the letter of assurance clearly stipulates that
the assured, i.e. the partnership firm in this case to which the
letter of assurance was issued on 16.07.2010 cannot without the
express prior written consent of the assurer (Western Coalfields
Limited) and the Coal India, assign to any third person the letter
of assurance or any right, benefit, obligation or interest therein.
We find that initially, the Standing Linkage Committee had
decided to grant the letter of assurance in favour of the
partnership firm which comprised of only three partners.
However, when the letter of assurance was granted, there was a
change in the constitution of partnership firm and seven other
partners were inducted. The Standing Linkage Committee had
decided to grant the letter of assurance in favour of the
partnership firm that comprised of three individual partners
only. On 24.05.2010, the partnership firm was reconstituted
and seven more partners were inducted in the firm that were the
subsidiaries of M/s Gammon Infrastructure Projects Limited.
The name of the firm continued to remain the same on
24.05.2010. It is not clear whether the Western Coalfields
Limited had the knowledge about this change in the constitution
of the partnership firm as the commitment guarantee was given
13 WP4222-14
by the partnership firm to the Western Coalfields Limited on the
immediate next day, i.e. 25.05.2010 and a letter of assurance
was issued in favour of the firm on 16.07.2010. It is surprising
that the three partners that had constituted the partnership firm
with a view to set up the power plant at Kawathala retired from
the firm after the letter of assurance was issued, precisely on
05.01.2011 after accepting a sum of Rupees Forty Crores from
the subsidiaries of M/s Gammon Infrastructure Projects Limited
and there was a re-constitution of the firm to which the
Standing Linkage Committee had decided to issue the letter of
assurance. We find that there is a clear assignment of the
interest, benefit or right in the letter of assurance by the three
original partners in favour of the seven subsidiaries of M/s
Gammon Infrastructure Projects Limited, who remained as
partners after the three original partners retired from the
partnership firm after accepting the said sum. Condition no.5 of
of the letter of assurance was clearly breached by the
partnership firm to which the letter of assurance was sought to
be granted. Not once was the interest or benefit assigned by the
original partners but, that was done twice. It is rightly
submitted on behalf of the respondents that this would be a case
of profiteering in coal allocation and would be a fraud on the
authority. In the circumstances of the case, we do not find any
14 WP4222-14
error in the action on the part of the respondent-Western
Coalfields Limited in cancelling the letter of assurance, dated
16.07.2010. While holding so, we are not inclined to accept the
submission made on behalf of the petitioner that the letter of
assurance could be cancelled only if the milestones are not
achieved. On a reading of the letter of assurance in its entirety,
it is apparent that the letter of assurance could have been
cancelled on the breach of the conditions in the letter of
assurance, including Clause 5 which clearly prohibits the
assignment of any right, benefit, obligation or interest in the
letter of assurance without the express prior written consent of
the Western Coalfields Limited and the Ministry of Coal.
Admittedly, no prior consent, much less a written consent was
secured by the firm before assignment of the right and interest
in the letter of assurance exclusively in favour of the seven
subsidiaries of M/s Gammon Infrastructure Projects Limited by
the three original partners of the firm.
It would not be necessary to decide whether the
Western Coalfields Limited could encash the bank guarantee on
the cancellation of the letter of assurance as the learned Senior
Counsel, appearing for the Western Coalfields Limited has made
a fair statement that the decision on the forfeiture and
encashment of the bank guarantees would be taken, only after
15 WP4222-14
granting an opportunity to the petitioner to show cause against
the forfeiture of the Bank guarantee. We have accepted the fair
statement made by the learned Senior Counsel for the Western
Coalfields Limited on instructions and that would be binding on
the Western Coalfields Limited.
With the aforesaid observations, we dispose of the
writ petition with no order as to costs.
JUDGE JUDGE
APTE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!