Citation : 2017 Latest Caselaw 1982 Bom
Judgement Date : 25 April, 2017
fa125.02
-1-
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
FIRST APPEAL NO. 125 OF 2002
WITH
CIVIL APPLICATION NO. 888 OF 2006
1. The State of Maharashtra
Through the Secretary,
P.W.D. Government of Maharashtra
Mantralaya, Bombay
2. Chief Engineer,
P.W.D. Aurangabad ...Appellants
versus
Shri Tilakaraj Malhotra,
Age 45 years, Occ. Contractor
R/o. Dadarao Plots, Parbhani
District Parbhani
(Through his General Power of
Attorney Holder,
Shri Bhagwantrao Gabaji Nawale,
Age 75 years, Occ. Pensioner
R/o. Padampura, Aurangabad ...Respondents
.....
AGP for the appellants: Mr. B.V. Virdhe
Advocate for respondent: Mr. S.S. Choudhari
.....
CORAM : V. K. JADHAV, J.
DATED : 25th APRIL, 2017
ORAL JUDGMENT:-
1. Being aggrieved by the order dated 3.12.2001, passed by the
learned IInd Joint, Civil Judge, Senior Division, Aurangabad in
arbitration application No. 58 of 1992, the original respondents preferred
this appeal.
fa125.02
2. Brief facts giving rise to the present appeal are as follows:-
a) The respondent/plaintiff had filed an arbitration application No.58
of 1992 under Section 20(4) of the Arbitration Act 1940 against the
appellants/original defendants. According to the respondent/ plaintiff,
he is registered contractor and in the year 1987-88, the Public Works
Department of the Government of Maharashtra, wanted to construct one
R.C.C. Box culvert 6v of 2M X 2M at Km 3.3 on Malsona Thora Road in
Parbhani district. Accordingly, the Executive Engineer, Command
Roads Division, Parbhani had invited tenders by issuing public notice to
that effect. The respondent/plaintiff had submitted his tender and the
same was accepted being lowest one. After completion of formalities,
the respondent/plaintiff started the work as per the instructions of the
Engineer in charge of the work and as per the directions given by the
department. However, during the course of execution of work, the
respondent/plaintiff had to incur the expenditure for extra work done on
de-watering of foundation beyond tender provision and also on some
other works. Furthermore, he had also suffered loss due to washing
away of his stacked material on work site due to unexpected rains and
floods of Nala water. Moreover, some amount also came to be
deducted from his bills by carrying out wrong calculations. On all these
counts, the respondent/plaintiff has suffered financial loss of Rs.54,400/-
and accordingly he requested the appellant-defendant to pay the
fa125.02
amount. However, his request was not considered, by the Executive
Engineer, who was in-charge of the work. The respondent plaintiff then
requested the next higher authority i.e. Superintending Engineer, World
Bank Project, Circle Aurangabad to consider and grant his claims. In
view of arbitration clause 53, the respondent/plaintiff being dissatisfied
with the decision taken by the Superintending Engineer, filed an
application bearing Arbitration application No. 58 of 1992 for various
prayers made therein.
b) The appellants/State and Chief Engineer have strongly resisted
the said application by filing their say. It has been contended that the
respondent/plaintiff did not prefer any appeal before the Chief Engineer
against rejection order of Superintending Engineer to consider his claim
as provided in clause 53 of the contract. It has also been contended
that as per clause 53 of the contract, if the contractor fails to prefer an
appeal before the Chief Engineer within 30 days, then the decision
taken earlier shall be final and binding on the contractor. It has also
been contended that the respondent/plaintiff within 30 days period from
the date on which he received the decision, shall offer his intention to
refer the matter for arbitration and failing therein, his application itself is
not maintainable.
c) After hearing both the parties, learned C.J.S.D., Aurangabad by
impugned order dated 3.12.2001, has observed that the dispute is
fa125.02
related to Government work carried out by applicant and not about
defect liability and further directed to the applicant to appear before the
sole arbitrator for settlement of dispute. Being aggrieved by the same,
the respondents have preferred this appeal.
3. Learned A.G.P. for the appellants submits that in terms of clause
53 of the tender documents, if the contractor is not satisfied with the
decision of the Executive Engineer, the contractor may within 15 days
after receiving the decision, prefer an appeal to the Chief Engineer, who
shall afford an opportunity to the contractor to be heard and also permit
him to adduce the evidence in support of his appeal. The Chief
Engineer shall give a decision within stipulated period of 60 days and
decide the matter. If the contractor, is not satisfied with the decision of
the Chief Engineer, within a period of 30 days, after receipt of the
decision of the Chief Engineer, the contractor shall indicate his decision
to refer the dispute to arbitration, failing which the said decision shall be
final and conclusive.
The learned A.G.P. in order to substantiate his contentions
placed reliance on the judgment in the case of State of Goa vs.
Praveen Enterprises, reported in 2011 AIR (SC) 3814.
4. Learned counsel for the respondent/plaintiff submits that the
respondent plaintiff has taken all steps correctly as per clauses 53 and
fa125.02
54 of the tender document. The respondent/plaintiff has referred his
claim to the Executive Engineer and Executive Engineer has refused his
claim on 24.6.1989. Thereafter, in terms of provisions of clause 53, the
respondent/plaintiff appealed to the higher authority i.e. Superintending
Engineer and the Superintending Engineer refused the claim of the
respondent/plaintiff as per letter dated 2.12.1989. Learned counsel
submits that there is no whisper in clause 53 of the tender document
that the contractor has to prefer an appeal to the Chief Engineer after
rejecting his claim by the Superintending Engineer. After rejecting his
claim by the Superintending Engineer, the respondent/plaintiff has
communicated his intention to refer the dispute for arbitration and as
such his application is rightly considered by the Court below. The
learned counsel submits that in terms of provisions of Section 39 of the
Arbitration Act 1940, this appeal itself is not maintainable. Learned
counsel submits that even otherwise also, the question whether the
claim was barred under certain clauses of tender documents, are not
required to be decided by the court before making reference and it is for
the arbitrator to take appropriate decision on it.
Learned counsel for the respondent-plaintiff in order to
substantiate his contentions, placed reliance on the judgment in the
case of Jai Chand Bhasin vs. Union of India and another, reported
in AIR 1983 Delhi 508.
fa125.02
5. I have heard learned counsel for both the parties. With their able
assistance, I have perused the pleadings, grounds taken in the appeal,
order of the lower court and reply filed by the respondent.
6. Clause 53 of the tender document is reproduced herein below:-
"53. SETTLEMENT OF DISPUTES
If the contractor considers any work demanded of him to be outside the requirements of the contract, or consider any drawings, record or fulling of the Executive Engineer on any matter in connection with or arising out of the contract or the carrying out of the work to be in acceptable, he shall promptly ask the Executive Engineer in writing or written instructions or decision. Thereupon the Executive Engineer shall give his written instructions or decision within a period of 15 days of such request.
Upon receipt of the written instructions or decision the contractor, shall promptly proceed without delay to comply with such instructions or decision.
If the Executive Engineer fails to give his instructions or decision in writing within a period of 15 days after being requested of if the contractor is dissatisfied with the instruction or decision of the Executive Engineer the contractor may within 15 days after receipt the instruction or decision appeal to higher authority of Department who shall afford an opportunity to the contractor to be heard and to offer evidence in support of his appeal. This officer, shall give a decision within a period of 60 days after the contractor has given the said evidence in support of his appeal.
fa125.02
If the contractor is dissatisfied with this decision, the contractor within a period of thirty days from receipt of the decision shall indicate his intention to refer the dispute to Arbitration, failing which the said decision shall be final and conclusive."
7. It appears that the respondent/plaintiff has made demand of the
money for carrying out the extra work, to the Executive Engineer. The
Executive Engineer is supposed to give written instructions or decision
within a period of 15 days on such request. It is a part of record that the
Executive Engineer has refused his request on 24.6.1989 and as such,
the respondent/plaintiff approached the Superintending Engineer by
filing an appeal, as contemplated in clause 53 of tender document. On
perusal of aforementioned clause 53, it appears that the appeal is
contemplated to the higher authority of the department and name and
designation of such higher authority is not mentioned in clause 53.
However, it is a part of the record that the Superintending Engineer has
entertained the said appeal and by letter dated 2.12.1989 in terms of
provisions of clause 53 of the tender documents, as mentioned above,
rejected the claim of respondent/plaintiff. Thus, the respondent/ plaintiff
dissatisfied with the said decision, indicated his intention to refer the
dispute to the arbitration and accordingly approached the court below
seeking appropriate orders in his application for appointment of
arbitrator, since the appellants have failed to comply with the provisions
of clause 54 of tender documents.
fa125.02
8. Section 39 of Arbitration Act 1940 prescribed the appeal against
certain orders. Section 39 of the said Act is reproduced herein below:-
"39. Appealable orders.- (1) An appeal shall lie from the following orders passed under this Act to the Court authorized by law to hear appeals from original decrees of the Court passing the order:-
An order-
(I) superseding an arbitration;
(ii) on an award stated in the form of a special case;
(iii) modifying or correcting an award;
(iv) filing or refusing to file an arbitration agreement;
(v) staying or refusing to stay legal proceedings where
there is an arbitration agreement;
(vi) setting aside or refusing to set aside an award;
Provided that the provisions of this section shall not apply to any order passed by Small Cause Court.
(2) No second appeal shall lie from an order passed in appeal under this section, but nothing in this section shall affect or take away any right to appeal to the Supreme Court."
9. In terms of the provisions of Section 39 of the Arbitration Act
1940, no appeal is provided against the non compliance of the
provisions of clause 54 of the tender documents.
10. It appears that the court below has correctly interpreted clauses
53 and 54 of the tender documents and accordingly passed the
fa125.02
impugned order. It is open for the parties to raise all points, including
the compliance or non-compliance of the provisions of clauses 53 and
54 of the tender documents before the arbitrator and the arbitrator can
deal with those questions in accordance with law.
11. In view of above, I do not find any merit in this appeal. The appeal
is liable to be dismissed. The appeal is accordingly dismissed. In the
circumstances, there shall be no order as to costs.
12. In view of dismissal of first appeal, pending civil application is also
disposed of.
( V. K. JADHAV, J.)
rlj/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!