Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Mah vs Tilakraj Malhotra
2017 Latest Caselaw 1982 Bom

Citation : 2017 Latest Caselaw 1982 Bom
Judgement Date : 25 April, 2017

Bombay High Court
The State Of Mah vs Tilakraj Malhotra on 25 April, 2017
Bench: V.K. Jadhav
                                                                              fa125.02
                                        -1-


               IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                          BENCH AT AURANGABAD

                          FIRST APPEAL NO. 125 OF 2002
                                      WITH
                        CIVIL APPLICATION NO. 888 OF 2006


 1.       The State of Maharashtra
          Through the Secretary,
          P.W.D. Government of Maharashtra
          Mantralaya, Bombay

 2.       Chief Engineer,
          P.W.D. Aurangabad                                 ...Appellants

                  versus


 Shri Tilakaraj Malhotra,
 Age 45 years, Occ. Contractor
 R/o. Dadarao Plots, Parbhani
 District Parbhani
 (Through his General Power of
 Attorney Holder,
 Shri Bhagwantrao Gabaji Nawale,
 Age 75 years, Occ. Pensioner
 R/o. Padampura, Aurangabad                                 ...Respondents

                                        .....
                       AGP for the appellants: Mr. B.V. Virdhe
                    Advocate for respondent: Mr. S.S. Choudhari
                                        .....

                                              CORAM : V. K. JADHAV, J.

DATED : 25th APRIL, 2017

ORAL JUDGMENT:-

1. Being aggrieved by the order dated 3.12.2001, passed by the

learned IInd Joint, Civil Judge, Senior Division, Aurangabad in

arbitration application No. 58 of 1992, the original respondents preferred

this appeal.

fa125.02

2. Brief facts giving rise to the present appeal are as follows:-

a) The respondent/plaintiff had filed an arbitration application No.58

of 1992 under Section 20(4) of the Arbitration Act 1940 against the

appellants/original defendants. According to the respondent/ plaintiff,

he is registered contractor and in the year 1987-88, the Public Works

Department of the Government of Maharashtra, wanted to construct one

R.C.C. Box culvert 6v of 2M X 2M at Km 3.3 on Malsona Thora Road in

Parbhani district. Accordingly, the Executive Engineer, Command

Roads Division, Parbhani had invited tenders by issuing public notice to

that effect. The respondent/plaintiff had submitted his tender and the

same was accepted being lowest one. After completion of formalities,

the respondent/plaintiff started the work as per the instructions of the

Engineer in charge of the work and as per the directions given by the

department. However, during the course of execution of work, the

respondent/plaintiff had to incur the expenditure for extra work done on

de-watering of foundation beyond tender provision and also on some

other works. Furthermore, he had also suffered loss due to washing

away of his stacked material on work site due to unexpected rains and

floods of Nala water. Moreover, some amount also came to be

deducted from his bills by carrying out wrong calculations. On all these

counts, the respondent/plaintiff has suffered financial loss of Rs.54,400/-

and accordingly he requested the appellant-defendant to pay the

fa125.02

amount. However, his request was not considered, by the Executive

Engineer, who was in-charge of the work. The respondent plaintiff then

requested the next higher authority i.e. Superintending Engineer, World

Bank Project, Circle Aurangabad to consider and grant his claims. In

view of arbitration clause 53, the respondent/plaintiff being dissatisfied

with the decision taken by the Superintending Engineer, filed an

application bearing Arbitration application No. 58 of 1992 for various

prayers made therein.

b) The appellants/State and Chief Engineer have strongly resisted

the said application by filing their say. It has been contended that the

respondent/plaintiff did not prefer any appeal before the Chief Engineer

against rejection order of Superintending Engineer to consider his claim

as provided in clause 53 of the contract. It has also been contended

that as per clause 53 of the contract, if the contractor fails to prefer an

appeal before the Chief Engineer within 30 days, then the decision

taken earlier shall be final and binding on the contractor. It has also

been contended that the respondent/plaintiff within 30 days period from

the date on which he received the decision, shall offer his intention to

refer the matter for arbitration and failing therein, his application itself is

not maintainable.

c) After hearing both the parties, learned C.J.S.D., Aurangabad by

impugned order dated 3.12.2001, has observed that the dispute is

fa125.02

related to Government work carried out by applicant and not about

defect liability and further directed to the applicant to appear before the

sole arbitrator for settlement of dispute. Being aggrieved by the same,

the respondents have preferred this appeal.

3. Learned A.G.P. for the appellants submits that in terms of clause

53 of the tender documents, if the contractor is not satisfied with the

decision of the Executive Engineer, the contractor may within 15 days

after receiving the decision, prefer an appeal to the Chief Engineer, who

shall afford an opportunity to the contractor to be heard and also permit

him to adduce the evidence in support of his appeal. The Chief

Engineer shall give a decision within stipulated period of 60 days and

decide the matter. If the contractor, is not satisfied with the decision of

the Chief Engineer, within a period of 30 days, after receipt of the

decision of the Chief Engineer, the contractor shall indicate his decision

to refer the dispute to arbitration, failing which the said decision shall be

final and conclusive.

The learned A.G.P. in order to substantiate his contentions

placed reliance on the judgment in the case of State of Goa vs.

Praveen Enterprises, reported in 2011 AIR (SC) 3814.

4. Learned counsel for the respondent/plaintiff submits that the

respondent plaintiff has taken all steps correctly as per clauses 53 and

fa125.02

54 of the tender document. The respondent/plaintiff has referred his

claim to the Executive Engineer and Executive Engineer has refused his

claim on 24.6.1989. Thereafter, in terms of provisions of clause 53, the

respondent/plaintiff appealed to the higher authority i.e. Superintending

Engineer and the Superintending Engineer refused the claim of the

respondent/plaintiff as per letter dated 2.12.1989. Learned counsel

submits that there is no whisper in clause 53 of the tender document

that the contractor has to prefer an appeal to the Chief Engineer after

rejecting his claim by the Superintending Engineer. After rejecting his

claim by the Superintending Engineer, the respondent/plaintiff has

communicated his intention to refer the dispute for arbitration and as

such his application is rightly considered by the Court below. The

learned counsel submits that in terms of provisions of Section 39 of the

Arbitration Act 1940, this appeal itself is not maintainable. Learned

counsel submits that even otherwise also, the question whether the

claim was barred under certain clauses of tender documents, are not

required to be decided by the court before making reference and it is for

the arbitrator to take appropriate decision on it.

Learned counsel for the respondent-plaintiff in order to

substantiate his contentions, placed reliance on the judgment in the

case of Jai Chand Bhasin vs. Union of India and another, reported

in AIR 1983 Delhi 508.

fa125.02

5. I have heard learned counsel for both the parties. With their able

assistance, I have perused the pleadings, grounds taken in the appeal,

order of the lower court and reply filed by the respondent.

6. Clause 53 of the tender document is reproduced herein below:-

"53. SETTLEMENT OF DISPUTES

If the contractor considers any work demanded of him to be outside the requirements of the contract, or consider any drawings, record or fulling of the Executive Engineer on any matter in connection with or arising out of the contract or the carrying out of the work to be in acceptable, he shall promptly ask the Executive Engineer in writing or written instructions or decision. Thereupon the Executive Engineer shall give his written instructions or decision within a period of 15 days of such request.

Upon receipt of the written instructions or decision the contractor, shall promptly proceed without delay to comply with such instructions or decision.

If the Executive Engineer fails to give his instructions or decision in writing within a period of 15 days after being requested of if the contractor is dissatisfied with the instruction or decision of the Executive Engineer the contractor may within 15 days after receipt the instruction or decision appeal to higher authority of Department who shall afford an opportunity to the contractor to be heard and to offer evidence in support of his appeal. This officer, shall give a decision within a period of 60 days after the contractor has given the said evidence in support of his appeal.

fa125.02

If the contractor is dissatisfied with this decision, the contractor within a period of thirty days from receipt of the decision shall indicate his intention to refer the dispute to Arbitration, failing which the said decision shall be final and conclusive."

7. It appears that the respondent/plaintiff has made demand of the

money for carrying out the extra work, to the Executive Engineer. The

Executive Engineer is supposed to give written instructions or decision

within a period of 15 days on such request. It is a part of record that the

Executive Engineer has refused his request on 24.6.1989 and as such,

the respondent/plaintiff approached the Superintending Engineer by

filing an appeal, as contemplated in clause 53 of tender document. On

perusal of aforementioned clause 53, it appears that the appeal is

contemplated to the higher authority of the department and name and

designation of such higher authority is not mentioned in clause 53.

However, it is a part of the record that the Superintending Engineer has

entertained the said appeal and by letter dated 2.12.1989 in terms of

provisions of clause 53 of the tender documents, as mentioned above,

rejected the claim of respondent/plaintiff. Thus, the respondent/ plaintiff

dissatisfied with the said decision, indicated his intention to refer the

dispute to the arbitration and accordingly approached the court below

seeking appropriate orders in his application for appointment of

arbitrator, since the appellants have failed to comply with the provisions

of clause 54 of tender documents.

fa125.02

8. Section 39 of Arbitration Act 1940 prescribed the appeal against

certain orders. Section 39 of the said Act is reproduced herein below:-

"39. Appealable orders.- (1) An appeal shall lie from the following orders passed under this Act to the Court authorized by law to hear appeals from original decrees of the Court passing the order:-

An order-

                  (I)     superseding an arbitration;
                  (ii)    on an award stated in the form of a special case;
                  (iii)   modifying or correcting an award;
                  (iv)    filing or refusing to file an arbitration agreement;
                  (v)     staying or refusing to stay legal proceedings where
         there is an arbitration agreement;
                  (vi)    setting aside or refusing to set aside an award;


Provided that the provisions of this section shall not apply to any order passed by Small Cause Court.

(2) No second appeal shall lie from an order passed in appeal under this section, but nothing in this section shall affect or take away any right to appeal to the Supreme Court."

9. In terms of the provisions of Section 39 of the Arbitration Act

1940, no appeal is provided against the non compliance of the

provisions of clause 54 of the tender documents.

10. It appears that the court below has correctly interpreted clauses

53 and 54 of the tender documents and accordingly passed the

fa125.02

impugned order. It is open for the parties to raise all points, including

the compliance or non-compliance of the provisions of clauses 53 and

54 of the tender documents before the arbitrator and the arbitrator can

deal with those questions in accordance with law.

11. In view of above, I do not find any merit in this appeal. The appeal

is liable to be dismissed. The appeal is accordingly dismissed. In the

circumstances, there shall be no order as to costs.

12. In view of dismissal of first appeal, pending civil application is also

disposed of.

( V. K. JADHAV, J.)

rlj/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter