Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Exe. Director, Godawari M.Wada ... vs Y.R. Reddy Engineers And Builders ...
2017 Latest Caselaw 1732 Bom

Citation : 2017 Latest Caselaw 1732 Bom
Judgement Date : 17 April, 2017

Bombay High Court
Exe. Director, Godawari M.Wada ... vs Y.R. Reddy Engineers And Builders ... on 17 April, 2017
Bench: T.V. Nalawade
                                               Arb.Appeal Nos.6 & 5/16
                                   1


                  IN THE HIGH COURT AT BOMBAY
              APPELLATE SIDE, BENCH AT AURANGABAD

                    ARBITRATON APPEAL NO. 6 OF 2016
                                  WITH
                   CIVIL APPLICATION NO. 8990 OF 2016
                                  WITH
                   CIVIL APPLICATION NO. 14314 OF 2016

 Executive Director,
 Godawari Marathawada Irrigation
 Development Corporation
 Aurangabad Through its
 Executive Engineer, Majalgaon
 Canal Division No. 7, Gangakhed,
 Dist. Parbhani (M.S.)            ....Appellant.

          Versus


 M/s. Y.R. Reddy Engineers and
 Builders, 843, Banjara Avenue,
 Banjara Hills, Hyderabad-34.          ....Respondent.


 Mr. A.C. Dharmadhikari h/f. Mr. B.R. Surwase, Advocate for
 appellant.
 Mr. S. Rajan h/f. Mr. M.D. Narwadkar, Advocate for respondent.


                                  WITH
                    ARBITRATON APPEAL NO. 5 OF 2016
                                  WITH
                   CIVIL APPLICATION NO. 14313 OF 2016

 Yeturu Rama Chandra Reddy
 Engineers and Builders,
 843, Banjara Avenue,
 Banjara Hills, Hyderabad-34.               ....Appellant.

          Versus

 Executive Director,




::: Uploaded on - 25/04/2017               ::: Downloaded on - 27/08/2017 23:38:36 :::
                                                               Arb.Appeal Nos.6 & 5/16
                                               2


 Godawari Marathawada Irrigation
 Development Corporation
 Aurangabad Through the
 Executive Engineer, Majalgaon
 Canal Division No. 7, Gangakhed,
 Dist. Parbhani (M.S.)                                     ....Respondent.



 Mr. S. Rajan h/f. Mr. M.D. Narwadkar, Advocate for appellant.
 Mr. A.C. Dharmadhikari h/f. Mr. B.R. Surwase, Advocate for
 respondent.
                                          CORAM : T.V. NALAWADE, J.
                                          DATED : April 17, 2017.


 JUDGMENT :

1) Both the appeals are admitted. Notice after

admission is made returnable forthwith. By consent, heard both

the sides for final disposal.

2) Arbitration Appeal No. 5/2016 is filed by the

Contractor, at whose instance Arbitrator was appointed by this

Court under section 11 of the Arbitration and Conciliation Act,

1996 (hereinafter referred to as 'the Act' for short). The other

appeal is filed by the Employer, which is State Government,

Corporation. Arbitrator had allowed all the claims of the

Contractor and this decision was challenged by filing Misc.

Application (RJE) No. 77/2011 by the Employer in the Court of

Principal District Judge, (hereinafter referred to as 'P.D.J.' for

Arb.Appeal Nos.6 & 5/16

short) Parbhani under the Act. By the decision dated

31.12.2015, the proceeding filed under section 34 of the Act by

the Employer is partly allowed and the award given in respect of

few claims is set aside. In view of these circumstances, both the

sides have challenged the decision given by the District Court,

Parbhani.

3) For deciding the challenges raised by both the sides

in the appeals, the nature of work and also the history of

previous arbitration proceedings in respect of the same work

needs to be mentioned.

4) The work of Majalgaon Right Bank Canal was a part

of Jaikwaid Project. This project was in respect of construction of

dam on river Godavari at Paithan, District Aurangabad and at

various places, the canals were to be constructed. Tender notice

of the work of Majalgaon Right Bank Canal from k.m. 72 to 87

and k.m. 88 to 99, which included earthwork (excluding

earthwork at k.m. 78 to 87) lining structure, tunnel at k.m. 90

and enroute reservoir at k.m. 91 was published by the

Corporation. The work was allotted to the appellant from

Arbitration Appeal No. 5/2016.

Arb.Appeal Nos.6 & 5/16

5) The cost of the work as per the tender was

Rs.700.84 lakh. The work order was issued on 20.1.1990 and

the period of work was fixed as 36 months from the date of

work order. From time to time, the Contractor applied for

extension of the period and extensions were granted by the

Employer. The total extension of 47 months was granted, which

expired in December 1996. Prior to that the Contractor

abandoned the remaining work. Initially pre-final bill was

prepared and it was finalised on 14.3.1998. The amount

mentioned in the final bill was accepted by the Contractor

without raising any protest.

6) During the execution of the work, the Contractor had

raised disputes as provided by General Conditions of Contract

(hereinafter referred to as 'G.C.C.' for short) and particularly, as

per the Clause No. 56. These disputes were raised in the year

1995. On most of the disputes, the incharge Engineer gave the

decision and it was communicated to the Contractor on

15.7.1995.

7) The Contractor was not satisfied with the decision

Arb.Appeal Nos.6 & 5/16

given by the incharge Chief Engineer and he referred the dispute

to Board of Arbitrators which was constituted as per Clause No.

57 of the G.C.C. As per the agreement, the Board was expected

to deliver reasoned award. The Contractor made claims under

eleven heads before Board of Arbitrators and all the claims were

contested by the Employer. In all 13 claims were made by the

Contractor before the department, but he prosecuted 11 claims

before the Board of Arbitrators. It is the case of Contractor that

the decision on claim Nos. 12 and 13 was likely to be taken

departmentally as per the terms and conditions of the contract

and so, he had preferred not to take decision on these claims

from Board of Arbitrators. The Board of Arbitrators gave award

in respect of 11 claims on 27.5.1998.

8) The reference was made to Board of Arbitrators as

per the procedure given in the agreement between the parties

and the provisions of Indian Arbitration Act, 1940 were

applicable. The award was filed as per the old provisions in the

Court and rule was made by the Court on the award. The award

and the decision of the Court have become final. The award of

amount of Rs.2,61,14,396/- was given in favour of the

Contractor and the cost of Rs. 1,21,721/- was also awarded in

Arb.Appeal Nos.6 & 5/16

favour of the Contractor. This amount was deposited in the Court

when the Employer failed in appeal which was filed in this Court

to challenge the award. The appeal was dismissed on 8.7.1999.

9) No decision was given by the Chief Executive

Engineer on the aforesaid two claims which were made with the

Department and which were not prosecuted before the Board of

Arbitrators by the Contractor. By the letter dated 6.2.2002, first

time the Contractor informed to the Department that he wanted

to refer the dispute to Arbitrator. Prior to that, the incharge

Executive Engineer and Superintending Engineer had rejected

these claims also.

10) The Contractor then gave the name of his nominee

for constitution of Board of Arbitrators by letter dated

21.3.2002. The Employer did not give the name of it's nominee

who was to work as the second Arbitrator. In the letter dated

21.3.2002 itself, the Contractor had informed to the Employer

that if the Employer does not appoint Arbitrator, the Arbitrator

appointed by the Contractor will work as the sole Arbitrator. As

per the procedure given in Clause 57 of the agreement, G.C.C.,

the Contractor had already requested the Chairman of the

Arb.Appeal Nos.6 & 5/16

Central Water Commission (C.W.C.) to see that the Board of

Arbitrators is constituted. However, by the letter dated

25.3.2002, the Contractor informed to the Chairman that his

letter dated 8.2.2002 made in aforesaid regard be ignored and

action should not be taken by the Chairman for constitution of

the Board of Arbitrators. Then the Contractor filed a proceeding

in the High Court bearing No. 5/2002 for appointment of

Arbitrator under the provision of section 11 of the Arbitration

and Conciliation Act, 1996. Due to the aforesaid correspondence

made by the Contractor, the Chairman of C.W.C. did not take

further action.

11) The Chairman of C.W.C. was not made party in the

proceeding filed under section 11 of the Act in the High Court.

This application was opposed by the Employer by contending

that the High Court had no power and the Board of Arbitrators

needs to be constituted as per the agreement. This Court

appointed retired Justice Shri. A.S. Bhate as the sole Arbitrator

by the order dated 10.7.2003. The Employer filed review

application by contending that it was necessary to create the

Board of Arbitrators as per the provisions of agreement and the

sole Arbitrator appointed by the High Court cannot get

Arb.Appeal Nos.6 & 5/16

jurisdiction to decide the dispute. In the review application, the

High Court again asked the parties to supply three names by

each of them. In the meantime, retried Justice Shri. Bhate

informed to the High Court that he was not willing to work as

sole Arbitrator. This Court then made appointment of one retired

District Judge Shri. R.G. Karmarkar as the sole Arbitrator. The

Employer had objection to appointment of Arbitrator under

section 11 of the Act, but he did not raise objection to the name

of Shri. Karmarkar. It is the case of Employer that it had not

given consent for appointment of sole Arbitrator and only

objection was not taken to the name suggested by the High

Court. After making of the appointment of Shri. Karmarkar, as

there was mention of consent of the Employer in the order,

application was moved by the Employer for making correction

and to remove that mention. The High Court did not accept that

contention. The application filed for correction was rejected by

the High Court on 4.3.2004. The order of appointment of Shri.

Karmarkar dated 9.10.2003 and the order dated 4.3.2004 were

challenged by the Employer in the Apex Court by filing Special

Leave to Appeal.

12) The Hon'ble Apex Court granted stay to the orders of

Arb.Appeal Nos.6 & 5/16

Hon'ble High Court on 14.3.2005. Before that date, Shri.

Karmarkar had started the proceeding. The claim statement was

filed and the written statement was also filed by the Employer.

The Employer took the defence that the Arbitrator had no

jurisdiction and he was not competent as his appointment was

not as per the agreement. Other objection was taken that the

claims were barred by the principle of res-judicata and they

were time barred. On merits also, the claims raised before the

sole Arbitrator were opposed.

13) Due to stay granted by the Apex Court, the

proceeding before Shri. Karmarkar remained stayed from

14.3.2005 to 28.11.2007. On 28.11.2007, the Apex Court

disposed of the Special Leave to Appeal with observations that

the point of jurisdiction can be decided by the Arbitrator himself

in view of the position of law prevailing at that time. Shri.

Karmarkar then expressed his enability to act as an Arbitrator.

Prior to that, in the year 2004, he had passed order on objection

of jurisdiction taken by the Employer. The names of retired

Justice Shri. S.C. Malte and retired Justice Shri. S.G. Mutalik

were suggested by High Court this time. The Employer

contended that such persons cannot be appointed as Arbitrator

Arb.Appeal Nos.6 & 5/16

in view of the agreement made by the parties. This Court then

appointed Shri. Mutalik as the sole Arbitrator. Before Shri.

Mutalik also, the Employer took aforesaid defences and

objections. The request was made to decide the point of

jurisdiction first, but Shri. Mutalik, Arbitrator expressed that this

point will be decided along with the dispute. Shri. Mutalik fixed

his fees as Rs.1,00,000/- for reading the papers and

Rs.70,000/- per meeting. The order with regard to aforesaid

charges and fees was also challenged by the Employer, but the

Employer did not succeed.

14) The learned Arbitrator has allowed all the claims of

the Contractor (7 +1 Claims). It is held by the learned Arbitrator

that there is no bar of principle of res-judicata to the claims.

Though issue was framed on the point of limitation and it was

clubbed with the issue of res-judicata, the award delivered by

the learned Arbitrator does not show that he had touched this

point. The learned Arbitrator has held that in view of the order

made by this Court under section 11 of the Act, he has

jurisdiction. The learned Arbitrator has held that the Contractor

is entitled to recover the amount of Rs. 11,24,60,651/- with

interest at the rate of 16% p.a. and has held that the interest

Arb.Appeal Nos.6 & 5/16

will be payable up to the period ending on 30.9.2003 and then

the interest will be payable from 4.2.2004 the date of filing of

the claims on the awarded amount then till the date of

realisation. The cost of Rs.10,00,000/- was imposed by the

learned Arbitrator on the Employer. This award was delivered on

3.4.2011.

15) In the decision given by the learned P.D.J., Parbhani

in Application (RJE) No. 77/2011, the learned P.D.J. has set

aside the award of Arbitrator in respect of claim Nos. 2 [2A and

2B], 3, 4 and 5. The award in respect of claim Nos. 1 and 6 is

confirmed by the P.D.J. The claim No. 7 was in respect of

interest and so, it can be said that interest is allowed in respect

of the claim Nos. 1 and 6. The learned P.D.J. has held that the

claim Nos. 2A, 2B, 4 and 5 cannot be allowed as they are hit by

the principle of res-judicata. The learned P.D.J. held that claim

No. 4 was time barred. The claim No. 3 is set aside by holding

that there is virtually no evidence and there is no justification in

awarding this claim when the award was required to be

reasoned award.

16) In the present matter, in view of the contentions

Arb.Appeal Nos.6 & 5/16

made and the arguments advanced, following points need to be

decided.

(i) Whether the present matters need to be decided

by Commercial Appellate Division constituted under the

Commercial Courts, Commercial Division and

Commercial Appellate Division of High Court Act,

2015 ?

(ii) Whether the learned Arbitrator Shri. Mutalik,

Retired Judge of this Court was competent in view of

the agreement ?

(iii) Whether claim Nos. 1, 2, 3 & 6 could have been

considered by the Arbitral Tribunal in view of the terms

and conditions of the contract ?

(iv) Whether the aforesaid claims [2A, 2B, 4 and 5]

are hit by the principle of res-judicata ?

(v) Whether claim Nos. 1, 4 & 6 are time barred?

(vi) Whether claim No. 3 was substantiated ?

(vii) Whether the award delivered by the learned

Arbitrator and the decision given by the learned P.D.J.

need to be interfered with in the appeals ?

Point No. 1 :-

Effect of the provisions of the Commercial Courts,

Arb.Appeal Nos.6 & 5/16

Commercial Division and Commercial Appellate Division of

High Court Act, 2015 on the jurisdiction of this Court :

17) The learned counsel for Contractor submitted that

for Aurangabad Bench of this Court, Commercial Appellate

Division of High Court is created under the aforesaid enactment

and so, the present matters need to be placed before the said

Court. For ascertaining as to whether this Court has jurisdiction,

this Court has seen the scheme of the aforesaid Special

Enactment carefully. It is true that the dispute of the present

matters falls under the definition of 'commercial dispute' given

under section 2(c) and the value of the dispute is more than Rs.

28 Crore.

18) Aurangabad Bench of Bombay High Court has no

ordinary original civil jurisdiction and so, there is no Commercial

Division of the High Court at Aurangabad Bench. Commercial

Appellate Division for Aurangabad Bench came to be constituted

under the aforesaid Act with effect from 30.6.2016. The present

proceeding was filed on 31.3.2016. The proceeding under

section 34 of the Act was decided by the learned P.D.J., Parbhani

on 31.12.2016 as "Court" under the Act. This is because first

Arb.Appeal Nos.6 & 5/16

time by Government notification dated 30.6.2016, the

Government constituted commercial Court at district levels

including for district Parbhani and High Court under letter dated

14.7.2016 appointed the Judges of District Court as Commercial

Courts. From the record, it can be said that for Parbhani district

and other districts, the Commercial Court actually started

functioning for district places on 16.7.2016. The aforesaid

Special Enactment was published by notification in official

gazette on 31.12.2015, but the Courts were constituted

subsequently and the proceeding under section 34 was decided

by the learned P.D.J. as the "Court" under section 34 of the Act

on 31.12.2015.

19) The matters which are required to be decided by

Commercial Appellate Division are mentioned in section 13 of

the aforesaid Special Enactment and the provision runs as under

:-

"13. Appeals from decrees of Commercial Courts and Commercial Divisions.- (1) Any person aggrieved by the decision of the Commercial Court or Commercial Division of a High Court may appeal to the Commercial Appellate Division of that High Court within a period of sixty days from the date of judgment or

Arb.Appeal Nos.6 & 5/16

order, as the case may be:

Provided that an appeal shall lie from such orders passed by a Commercial Division or a Commercial Court that are specifically enumerated under Order XLIII of the Code of Civil Procedure, 1906 (5 of 1908) as amended by this Act and section 37 of the Arbitration and Conciliation Act, 1996 (26 of 1996).

(2) Notwithstanding anything contained in any other law for the time being in force or Letters Patent of a High Court, no appeal shall lie from any order or decree of a Commercial Division or Commercial Court otherwise than in accordance with the provisions of this Act."

20) Section 3 of this Special Enactment shows that the

State Government is expected to constitute the Commercial

Courts by notification. It is required to be published in official

gazette and that was done on 30.6.2016. On the date of

decision of the matter filed under section 34 of the Act,

Commercial Court was not in existence and similarly,

Commercial Appellate Division was also not in existence when

the present appeals were filed in this Court. The provision of

section 15 takes care of the pending matters and this provision

shows that only the matters which are filed or were filed under

section 34 of the Act and which were still pending can be

Arb.Appeal Nos.6 & 5/16

transferred under the provision of section 15 and they are

required to be transferred either to Commercial Court or

Commercial Division. Neither in section 15 nor in any other

provision of the Special Enactment, there is provision for

transferring the appeals, which are filed against the decisions

given by the Courts as mentioned in section 34 of the Act to

Commercial Appellate Division of this Court. In view of this

position of law, it needs to be held that present appeals need to

be decided by this Court as appeals filed under section 37 of the

Act and not by Commercial Appellate Division of the High Court.

So, the point is answered accordingly.

21) On the aforesaid point, the learned counsel for

Contractor placed reliance on the observations made by

Commercial Appellate Division of this Court at Principal Seat in

Judgment of Commercial Appeal No. 7 of 2016 [Hubtown

Limited Vs. IDBI Trusteeship Service Limited] decided on

24.10.2016. This Court has carefully gone through the facts of

this case and observations made by the Commercial Appellate

Division. The facts were totally different and the order made by

the Commercial Division in Summons for Judgment was taken in

appeal before the Commercial Appellate Division. It was held

Arb.Appeal Nos.6 & 5/16

that appeal filed under section 13 of the Commercial Courts,

Commercial Division and Commercial Appellate Division of High

Courts Act, 2015 was tenable and the order of learned Single

Judge of Commercial Division in Summons for Judgment was set

aside. The maintainability of Commercial Appeal was in

question, but as the order of Commercial Division was taken

in appeal such decision was given. Thus, the observations made

in this case are of no use to the Contractor in the present

matter.

Point No. 2 - Compentency of the Arbitrator :-

22) To ascertain, whether the retired Judge of the High

Court Shri. Mutalik could have been appointed as Arbitrator

under section 11 of the Act, the provision of section 11 (relevant

portion) needs to be considered first. The relevant portions are

section 11(1) to 11(6), 11(8) of the Act and they run as under :-

"11. APPOINTMENT OF ARBITRATORS. -(1) A person of any nationality may be an arbitrator, unless otherwise agreed by the parties.

(2) Subject to sub-section (6), the parties are free to agree on a procedure for appointing the arbitrator or arbitrators.

(3) Failing any agreement referred to in sub-section (2), in an arbitration with three

Arb.Appeal Nos.6 & 5/16

arbitrators, each party shall appoint one arbitrator, and the two appointed arbitrators shall appoint the third arbitrator who shall act as the presiding arbitrator.

                        (4)    If the appointment procedure in sub-
               section (3) applies and-

(a) a party fails to appoint an arbitrator within thirty days from the receipt of a request to do so from the other party; of

(b) the two appointed arbitrators fail to agree on the third arbitrator within thirty days from the date of their appointment, the appointment shall be made, upon request of a party, by the Chief Justice or any person or institution designated by him.

(5) Failing any agreement referred to in sub-section(2), in an arbitration with a sole arbitrator, if the parties fail to agree on the arbitrator within thirty days from receipt of a request by one party from the other party to so agree the appointment shall be made, upon request of a party, by the Chief Justice or any person or institution designated by him.

                        (6)    Where,      under       an       appointment
               procedure agreed upon by the parties, -
                        (a)    a party fails to act as required under
               that procedure; or
                        (b)    the   parties,   or   the    two     appointed

arbitrators, fail to reach an agreement expected of them under that procedure; or

Arb.Appeal Nos.6 & 5/16

(c) a person, including an institution, fails to perform any function entrusted to him or it under that procedure, a party may request the Chief Justice or any person or institution designated by him to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

                        (7)    ........
                        (8)    The Chief Justice or the person or

institution designated by him, in appointing an arbitrator, shall have due regard to-

(a) any qualifications required of the arbitrator by the agreement of the parties; and

(b) other considerations as are likely to secure the appointment of an independent and impartial arbitrator."

23) In the present matters, the application under section

11 of the Act was filed in the year 2002 and the appointment of

retired Judge of this Court was made first time in the proceeding

on 10.7.2003. The subsequent appointments of sole Arbitrator

mentioned above were made only to replace the first sole

Arbitrator appointed by this Court. This decision was taken up to

Supreme Court by filing Special Leave Petition by the Employer.

The Apex Court referred the case of M/s. S.B.P & Co. Vs. M/s.

Patel Engineering Ltd. and Anr. [AIR 2006 SUPREME

Arb.Appeal Nos.6 & 5/16

COURT 450] and held that it will be open to raise the challenge

to jurisdiction of Arbitrator appointed by High Court before the

Arbitrator himself as provided in the Act. In the case of S.B.P. &

Co. cited supra also, the Apex Court had made it clear that if the

applications filed under section 11 of the Act were already

decided, it is to be presumed that in those cases, the

appointments were made as per the ratio of previous case of

Apex Court reported as M/s. Konkan Railway Corporation

Ltd. and Anr. Vs. M/s. Rani Construction P. Ltd. [AIR 2002

SUPREME COURT 778]. As the contrary view was taken in the

case of S.B.P. & Co., cited supra, the Apex Court made it clear

in the case of S.B.P. & Co. itself that in the matters in which

Arbitrators were already appointed as per the case of Konkan

Railway Corporation cited supra, in those cases all objections

with regard to jurisdiction of the Arbitrator need to be decided

under section 16 of the Act. This position of law needs to be

kept in mind while applying the provisions of section 11(1) to

11(6) of the Act to the present matters. Thus, the point of

competency of the Arbitrator is open in the present matter. In

view of the provision of section 16 (6) of the Act read with

provision of section 34 (2) (v) of the Act, this point could have

been considered by the Arbitrator and also the District Court. In

Arb.Appeal Nos.6 & 5/16

the appeal, this point can be again considered.

24) If the provisions of section 11(2) and 11(6) of the

Act are read together, they show that if there is agreement over

the procedure for appointment of arbitration and the procedure

provides other means for securing the appointment, the power

under section 11(6) of the Act cannot be used.

25) The provision of section 11(2) of the Act shows that

this provision is subject to the provision of section 11(6) of the

Act and so, if there is already agreement on procedure, there

cannot be new agreement on procedure by the parties to

appoint the Arbitrator. Similarly, if there is agreement on

procedure available, the provisions of sections 11 (3), 11 (4), 11

(5) cannot be used as those provisions are to take care of the

situation where there is no agreement on the procedure to

appoint Arbitrator. It needs to be kept in mind that in section

11(6) of the Act, there are two parts. The first part relates to

the lacuna in the procedure agreed. Due to such lacuna, if even

after following the procedure the Arbitrator cannot be appointed,

then the Court can take necessary measures as mentioned in

those provisions of law to see that Arbitrator is appointed.

Arb.Appeal Nos.6 & 5/16

However, the second part relates to the situation where there is

the procedure, and due to the failure on the part of the one or

more parties or due to other situation mentioned in clauses (b)

(c) of section 11(6) of the Act, the Arbitrator is not appointed,

but there is the procedure to take care of such situation and by

following that procedure the Arbitrator can be appointed. In the

present matters, procedure mentioned in second part of section

11(6) of the Act was available.

26) Clause No. 57 of the G.C.C. between the parties

reads as under :-

"57. ARBITRATION :

(1) All disputes or differences in respect of which the decision, if any, of the Engineer or Employer has not become final and binding as aforesaid, shall on the initiative of either party in dispute be referred to the adjudication of three arbitrators. One arbitrator is to be nominated by the Employer, one by the Contractor and the third by the President of the International Chamber of Commerce, in the case of foreign contractors and Chairman, Central Water Commission in the case of local contractors. If either of the parties fail to appoint its arbitrator within sixty days after receipt of notice for the appointment of an arbitrator then the President of the International Chamber of

Arb.Appeal Nos.6 & 5/16

Commerce or the Chairman, Central Water Commission as the case may be, shall appoint an Arbitrator. A certified copy of the appointment made by the 'President'/'Chairman' shall be furnished to both parties.

(2) The arbitration shall be conducted in accordance with the Rules of Conciliation and Arbitration of the International Chamber of Commerce, Paris in the case of foreign contractors and provisions of Indian Arbitration Act 1940 or any statutory modifications thereof in the case of local contractors and shall be held in either case at such place and time in India as the Arbitrators may determine. The decision of the majority of the Arbitrators shall be final and binding upon the parties and the expenses of the Arbitrators shall be paid as may be determined by the Arbitrators.

(3) The said arbitrator/s shall have full power to open up, revise and review any decision, opinion, direction, certificate or valuation by the Engineer, Neither party shall be limited in the proceedings before such arbitrator/s to the evidence or arguments put before the Engineer for the purpose of obtaining his said decision. No decision given by the Engineer in accordance with the foregoing provisions shall disqualify him from being called as a witness and giving evidence before the arbitrator/s on any matter whatsoever relevant to the dispute or difference referred to the arbitrator/s as aforesaid. The reference to

Arb.Appeal Nos.6 & 5/16

arbitration may proceed notwithstanding that the works shall not then be or be alleged to be complete provided always that the obligations of the Employer, the Engineer and the Contractor shall not be altered by reason of the arbitration being conducted during the progress of the works.

(4) Performance under the contract shall, if reasonably possible, continue during the arbitration proceedings and payments due to the Contractor by the Employer shall bot be withheld, unless they are the subject matter of the arbitration proceedings.

(5) All awards shall be in writing and in case of claims equivalent to Rupees one hundred thousand or more, such awards shall state reason for the amounts awarded.

(6) Neither Party is entitled to bring a claim to arbitration if its Arbitrator has not been appointed by thirty days after the expiration of the Maintenance period.

(7) The Term 'Indian Contractor' shall include Indian firm or group of Indian firms and Joint Venture consortia eligible for price preference as domestic tenderer."

Clause No. 57 (1) shows that the authority mentioned in the

Clause viz. the Chairman of C.W.C. was having power to appoint

the sole arbitrator if both or either party had failed to nominate

Arb.Appeal Nos.6 & 5/16

the Arbitrator as provided in first part of this clause. In the first

arbitral proceeding, both the sides had appointed their nominees

and the third Arbitrator was appointed by Chairman of C.W.C.

Thus, in the present matter also, it was possible to use this

procedure. Infact reference was already made to the Chairman

of C.W.C. and the matter was pending before the Chairman for

consideration. It is the Contractor, who had written to the

Chairman of C.W.C. to inform that he was not interested in

getting the Arbitrator appointed as per this clause as he wanted

to move High Court under section 11 of the Act. This fact of the

present matter and the position of law already quoted are

sufficient to hold that retired Justice Shri. Mutalik could not have

been appointed as Arbitrator under section 11 by this Court.

Both the learned Arbitrator and the Court under section 34 of

the Act have committed error in holding that retired Justice Shri.

Mutalik was appointed as per the provisions made in law. This

single ground is sufficient to set aside the entire award delivered

by the learned Arbitrator. So, the point No. 2 is answered

accordingly.

27) On the aforesaid point, the learned counsel for

Employer placed reliance on the observations made by the

Arb.Appeal Nos.6 & 5/16

Supreme Court in the case reported as 2016 (4) Mh.L.J. 101

[Huawei Technologies Company Ltd. Vs. Sterlite

Technologies Ltd.]. In this case, the Apex Court has

considered the provisions of section 11 and 15 (2) of the Act

and has laid down that the term 'Rules' mentioned in section 15

(2) relates to the provisions made in the agreement for

appointment of Arbitrator. It is laid down that on every occasion

including for occasion of filling vacancy of Arbitrator, the Rules in

that regard need to be followed. There cannot be dispute over

this proposition and this Court has quoted the relevant portion

of the agreement mentioned in the procedure for appointment of

Arbitrator.

28) The learned counsel for respondent/Contractor

placed reliance on the observations made by the Supreme Court

in Civil Appeal No. 6275/2014 [North Eastern Railway &

Ors. Vs. Tripple Engineering Works] decided on

13.8.2014. In this case and also in the case reported as 2013

(2) Arb.L.R. 105 (SC) [M/s. Deep Trading Company Vs.

M/s. Indian Oil Corporation and Ors.], the Apex Court has

discussed the provision of section 11 and has laid down that

when one party forfeited right to appoint his nominee for

Arb.Appeal Nos.6 & 5/16

constitution of Arbitral Tribunal, it is not open to the said party

to say that the Arbitrator cannot be appointed under section 11

of the Act. The facts of the two reported cases show that due to

failure of one party to nominate his Arbitrator, it was not

possible to constitute the Arbitral Tribunal. In view of that

circumstance, the Apex Court laid down that the provision of

section 11 can be used. The facts of the present matter are

totally different and this Court has already observed that even

after failure of one or both the parties, the Arbitrator could have

been appointed by the agency mentioned in the agreement. In

the present matter, the Contractor avoided to get constituted

the Tribunal from the said agency, the Chairman of C.W.C. The

relevant portion of section 11 of the Act is also discussed in this

regard and so, the observations made by the Apex Court in

these two cases are of no use to the Contractor.

Point No. 3 :-

29) Under this point, this Court is discussing all the

remaining points like point of limitation, point of res-judicata,

point of excepted matters and to some extent the merits of the

claim.

Arb.Appeal Nos.6 & 5/16

30) The relevant facts of the dispute between the parties

are already quoted and they show that while before December

1996, the Contractor had abandoned the work, though the

period for execution of work was expected by the department till

December 1996. In the year 1995, only 13 claims were raised

by the Contractor before the Employer as per the procedure

given in Clause 56 of G.C.C. Out of the said 13 claims, the

Contractor preferred to get decision from Board of Arbitrators on

11 claims. As per the record, pre-final bill was prepared on

30.6.1996 and then the final bill was prepared and singed on

14.3.1998. In view of the aforesaid facts, it can be said that no

more work was expected when pre-final bill and final bill were

signed by the parties. These bills were accepted by the

Contractor without raising any protest. These circumstances

need to be kept in mind while deciding the point of limitation,

and the point of res-judicata. In spite of these circumstances,

the Contractor raised new claims which were five in numbers

before the second Arbitrator. It can be said that there is no

record with the Contractor in respect of these new five claims to

show that they were made under the procedure given under the

agreement and particularly, Clause No. 56 of the agreement.

The award prepared by the learned Arbitrator in the present

Arb.Appeal Nos.6 & 5/16

matter shows that the learned Arbitrator considered one way

correspondence allegedly made by the Contractor with the

department for presuming that these new claims were raised

and they were pending with the department. It is already

observed that only 13 claims were raised as per the procedure

and the Contractor had preferred to take final decision on two

claims departmentally and he had filed claims statement in

respect of remaining 11 claims before the Board of Arbitrators

(first arbitration). The award delivered by the learned Arbitrator

in the present matter shows that there was virtually non

application of mind and the learned Arbitrator virtually accepted

all the contentions made by the Contractor as they were without

considering the effect of the principle of res-judicata, limitation

and also the presence or absence of the material with regard to

actual work done. There are many points, on the basis of which

it can be said that the Arbitrator had not considered the basic

concepts like res-judicata and for instance issue No. 6A can be

quoted in that regard.

"6A] Does the claimant prove that he is entitled to for payment of interest @ 16% p.a. from 13- 02-1993 to 15-7-1995 on all sums awarded under the Award dated 27-05-1998 ?"

Fortunately, in the reasoning other point is considered and decided.

Arb.Appeal Nos.6 & 5/16

31) The provision with regard to the procedure to raise

the claims and to make reference to arbitration can be found in

Clause Nos. 56 and 57 of G.C.C. Clause No. 57 is already

quoted. Clause No. 56 runs as under :-

"56. SETTLEMENT OF DISPUTES :-

If any dispute or difference of any kind whatsoever shall arise between the Engineer or Employer and the Contractor in connection with, or arising out of the Contract, or the execution of the works, whether during the progress of the works or after their completion and whether or after the termination, abandonment or breach of the Contract, it shall, in the first place, be referred to and settled by the Engineer-in-charge who shall, within a period of thirty days after being requested by the contractor to do so give written notice of his decision to the Contractor. Upon receipt of the written notice on decision of the Engineer the Contractor shall promptly proceed without delay to comply with such notice for decision.

If the Engineer-in-charge fails to give notice of his decision in writing within a period of thirty days after being requested, or if the Contractor is dissatisfied with the notice of decision of the Engineer-in-charge the Contractor may within thirty days after receiving notice of decision

Arb.Appeal Nos.6 & 5/16

appeal to the Superintending Engineer, who shall afford an opportunity to the Contractor to be heard and to offer evidence in support of his appeal. The Superintending Engineer shall give notice of his decision within a period of thirty days after the Contractor has given the said evidence in support of his appeal. Subject to arbitration, as hereinafter provided, such decision of the Superintending Engineer in respect of every matter so referred shall be final and binding upon the Contractor and shall forthwith be given effect to by the Contractor, who shall proceed with the execution of the works with all due diligence whether he requires arbitration, as hereinafter provided, or not. If the Superintending Engineer has given written notice of his decision to the Contractor and no claim to arbitration has been communicated to him by the Contractor within a period of thirty days from receipt of such notice, the said decision shall remain final and binding upon the Contractor. If the Superintending Engineer shall fail to give notice of his decision as aforesaid within a period of thirty days after being requested as aforesaid, or if the Contractor be dissatisfied with any such decision, then and in any such case the Contractor within thirty-days after receiving notice of such decision, or within thirty days after the expiration of the first-named period of thirty days, as the case may be, appeal to Chief Engineer who shall afford an opportunity

Arb.Appeal Nos.6 & 5/16

to the Contractor to be heard and to offer evidence in support of his appeal. The Chief Engineer shall give decision within a period of thirty days after the Contractor has given evidence in support of his appeal. If the Contractor is dissatisfied with this decision, the contractor within a period of thirty days from receipt of decision shall indicate his intention to refer the dispute to Arbitration, failing which the said decision shall be final and conclusive."

In view of the wording of Clause No. 56, it was necessary for the

Contractor to presume that his two claims, out of aforesaid 13

claims, were not accepted by the department. This presumption

is necessary as for every stage, the period is fixed in Clause No.

56. If he had taken the matter up to Chief Engineer and the

decisions were given against him by the incharge Engineer and

Superintending Engineer, then after expiry of period of 30 days

from raising the grievance before the Chief Engineer, it was

necessary for the Contractor to presume that the department

was not accepting the remaining two claims. It can be said that

the Contractor took the risk by presuming that he will be getting

the remaining two claims settled departmentally and the

Contractor did not stake claims under the two heads before the

Board of Arbitrators.

Arb.Appeal Nos.6 & 5/16

32) It is already observed that so far as the remaining

five claims are concerned from the present matter, they were

not prosecuted as per the procedure given in Clause No. 56 and

so, it can be said that these claims were never raised during the

execution of the work. Even if it is presumed that in the year

1995, the Contractor had made correspondence with regard to

new claims, in that case also the Contractor ought to have

prosecuted the matter under Clause No. 56 of G.C.C. Thus, it

needs to be inferred that the cause of action had already arisen

at the end of year 1995 in respect of the new claims also.

33) Clause 57 (6) of G.C.C. shows that matter needs to

be referred to arbitration within 30 days after expiration of the

maintenance period. Clause 5 of G.C.C. provides for

maintenance and defect liability period. This period was 180

days from the certified date of completion. It is already

observed that Contractor had abandoned the work and there

was no question of issuing certificate of completion. The record

shows that the Contractor never attempted to obtain completion

certificate to get absolved himself from the liability mentioned in

Clause 5 of G.C.C. If the work was not completed, then it can be

Arb.Appeal Nos.6 & 5/16

said that the period mentioned in Clause 5 can be counted from

the date of final bill. As final bill was signed by the Contractor

without protest on 14.3.1998, the period of limitation started to

run after expiry of 180 days from 14.3.1998.

34) The amendment to section 28 of the Contract Act,

which made agreement void if the agreement was limiting the

limitation period provided by General Law came in to force with

effect from 8.1.1997. In view of Clause No. 5 of G.C.C. if it is

presumed that benefit of amended provision of the Contract Act

needs to be given to the Contractor, in that case also, the period

of limitation started to run after completion of 180 days from

14.3.1998. If this amendment is not made applicable, then the

period had started to run as provided in Clause 56 of G.C.C.

Thus, even if the best possible case for the Contractor is

accepted, he ought to have raised the dispute within three years

from 14.9.1998 (14.3.1998 + 180 days).

35) For all the claims decided in the present matter, it

can be said that the Contractor took steps first time in the year

2002 by filing proceeding under section 11 of the Act. He filed

the claim before Arbitrator appointed by this Court in the year

Arb.Appeal Nos.6 & 5/16

2003. Due to these circumstances, this Court has no hesitation

to hold that all the claims decided by the learned Arbitrator in

the present matter were time barred.

36) So far as the point of res-judicata is concerned,

following points need to be kept in mind. Not only the principle

of res-judicata, but the principle of constructive res-judicata also

needs to be used in such matters. The contention of waiver was

made at all the stages for the Employer.

(i) The Board of Arbitrators came to be constituted

on 17.1.1996 and it had given direction to both the

sides to file statement of claims.

(ii) The first meeting of Board of Arbitrators was held

on 4.11.1996 and on that date, the decision was taken

as to which claims will be decided. Thus, it was open to

the Contractor to file the claims decided in the present

matter before the Board of Arbitrators also. In spite of

these circumstances, the Contractor preferred not to

file the claims before the Board of Arbitrators in the

first arbitration.

37) The Board of Arbitrators had given award on

Arb.Appeal Nos.6 & 5/16

following claims :-

(i) Revised rates for work executed after the original

scheduled period viz. for the work executed after

20.1.1993. The new rate was fixed by the Board of

Arbitrators as per the contract formula accepted in the

agreement by the parties viz. as per the price indices

as on 20.1.1993. This additional amount was given as

compensation for delay caused for execution of the

work.

(ii) Revised rates for extra items exceeding 30% of

the work over the tender quantities. The revised rates

were given in respect of this work done also even prior

to 20.1.1993. Similarly, under this head the revised

rate was given in respect of work done after

20.1.1993.

(iii) Damages on account of recovery of amount as

security deposit from running bills and interest at the

rate of 16% p.a. is given on such amount. Thus, the

claim of compensation in respect of retension of money

by the department during the work period was placed

before the Board of Arbitrators for consideration. The

Board of Arbitrators could have considered the present

Arb.Appeal Nos.6 & 5/16

claim of getting interest on amount of bank guarantee

for the period starting from 20.1.1993. But, this point

was not raised.

(iv) The payment of Rs.1.5 per bag cement was

awarded as the difference of rate as there was contract

to supply cement in jute bags to the Contractor by the

Employer and the cement was supplied in polythene

bags.

(v) Interest on all the amount due and demanded in

claims at the rate of 16% p.a. from the date of

occurrence till the date of realisation. The Board of

Arbitrators has awarded interest on the amount which

was due to the Contractor prior to 10.7.1995 and also

on the amount which became payable on 15.7.1995.

These dates are with regard to the demands made by

the Contractor under Clause 56 of G.C.C. Similarly past

and pendente-lite interest with reference to the date

4.11.1996, the date of first hearing of the Board of

Arbitrators is granted at the rate of 16% p.a. Further,

the order was made by Board of Arbitrators that if the

amount was not paid within two months from the date

of the award delivered by the Board of Arbitrators, the

Arb.Appeal Nos.6 & 5/16

department was liable to pay the interest at the rate of

18% p.a. This item again shows that it was open to the

Contractor to claim interest in respect of all the

amounts which were due to him, according to him,

before the Board of Arbitrators.

38) The Board of Arbitrators had rejected the following

claims made by the Contractor :-

(i) Loss of over heads and profits due to delay. This

was done as revised rate was given for entire work

done after 20.1.1993 by the Board of Arbitrators.

(ii) The compensation for extra lead charges for cut

spoils disposed of at the distant location. This claim

was rejected with reference to clauses of G.C.C. and

special terms and conditions of the contract.

(iii) The extra rate for hard rock excavation in canal

section. This claim was rejected as the Contractor

failed to prove that there was any such agreement.

Under this item, the present claim of control blasting

could have been considered and it can be said that it

needs to be presumed that such claim was considered.

(iv) Compensation for idle machinery and idle labour

Arb.Appeal Nos.6 & 5/16

charges due to stoppage of work for the same period.

This claim was rejected as the Contractor failed to

prove that at any time, his labour and machinery

remained idle and so, on merit it was rejected.

(v) Payment of rehandling charges for casing

material of k.m. 90 spoils used for embankment of

entire reservoir. This claim was rejected on the basis of

the material available and terms and conditions of the

contract.

(vi) Extra item of every overcuts of hard rock at k.m.

89 and 90 beyond normal pay line and also back filling

of the same. This is also rejected on merits and it can

be said that present item and control blasting could

have been raised under this claim also by the

Contractor.

39) Aforesaid circumstances show that all the so called

extra items except the two claims which were specifically

withdrawn by the Contractor were placed before the Board of

Arbitrators, first arbitration. The following were the two items

which were specifically withdrawn by the Contractor.

(i) Hard rock excavation involving controlled

Arb.Appeal Nos.6 & 5/16

blasting. It was the case of Contractor that radius was

changed due to geography and existence of the

structures in the vicinity. On this point also, it needs to

be observed that as per the terms and conditions of

contract, it was necessary for the Contractor to visit

the site and make assessment, estimate before quoting

rate. These things ought to have been inspected by the

Contractor. The learned Arbitrator in the present

matter has not considered this aspect of the matter.

The Board of Arbitrators had considered this aspect.

(ii) Extra quarrying and transport charges for stone

and metals for concrete work and also for work of

filling. It is the case of Contractor that useful stones

were not available along with canal line and he was

required to bring that material from the other place,

k.m. 91. The work was to be done from k.m. 72 to 87

and 88 to 99. Here only it needs to be observed that

the learned Arbitrator has not touched the record of

sites already informed by the Employer. The learned

Arbitrator has decided this point only on the basis of

quantities used in the work and it is presumed that

these quantities were brought from distant place when

Arb.Appeal Nos.6 & 5/16

no material whatsoever was produced by the

Contractor to show that this material was in fact

brought from distant place.

40) The discussion already made and the material show

that the work of controlled blasting was executed in the year

1994-95. It is already observed that it was necessary for the

Contractor to presume that the department was not accepting

this claim as extra item and so, it was necessary for the

Contractor to refer this claim to arbitration. This opportunity was

there to the Contractor when the Board of Arbitrators was

constituted, but he preferred to virtually withdrawn the claim.

Same can be said in respect of the other claim, extra item of

stone and metals.

41) Before the learned Arbitrator from the present

matter, the Contractor had made in all 7 claims which included

the aforesaid two claims. The department took the defence that

already revised rate was given to the Contractor by the Board of

Arbitrators in the past and the new claims were not raised

before the Arbitrator. It was submitted for the Employer that the

agreement did not provide for separate or additional charges

Arb.Appeal Nos.6 & 5/16

even in respect of the controlled blasting. The defence was

taken that there was no prior approval of incharge Engineer with

regard to controlled blasting. As already observed, like point of

res-judicata, the point of limitation was also there.

42) So far as the item of controlled blasting is

concerned, the attention of the learned Arbitrator was drawn to

the Clause 2.16 of second volume of agreement. This clause

provides for execution of hard rock chiseling/control blasting. It

is the case of Employer that the tender rates were fixed after

preparing estimates on the basis of survey done by the

department and the contractor had accepted the rate and so, it

was not open to him to claim additional rate or as extra item.

The attention of the learned Arbitrator was drawn to clause No.

2.16.2 of the second volume showing that when the control

blasting was not permissible in the zone of 100 meters directly

below transmission line, the Contractor ought to have resorted

to pneumatic rock breakers or chiseling. In view of this clause, it

was necessary for the Contractor to first take permission of the

Employer if he wanted to do the control blasting under

transmission lines. It is not the case of Contractor that such

permission was granted by the Employer to him. For this reason

Arb.Appeal Nos.6 & 5/16

also, nothing could have been given by the learned Arbitrator

under this head to the Contractor. It can be said that it was not

agreed item. Even when Arbitral Tribunal has held that

permission was not granted by the Employer, the claim is

allowed by the Arbitrator.

43) So far as the claim No. 2 which was withdrawn by

the Contractor in the past when the Board of Arbitrators was

constituted is concerned viz. the claim of extra quarrying and

transport of stones/metals, the attention of the learned

Arbitrator was drawn to Clause No. 20 of G.C.C. and Clause No.

5.6 of the special terms and conditions of the contract. The sites

where quarries could have been taken were already informed

and it was made clear that if the material available at those

quarries was not sufficient, the Contractor was to make his own

arrangement at own cost of such material. The clauses show

that the Contractor was expected to spend for construction of

road also for transport of such material. Even if the case of

Contractor that he was required to Collect the material at k.m.

91 could have been considered by ignoring the aforesaid clauses

of agreement, then also it was necessary for the Contractor to

substantiate that claim. The award delivered by the Arbitrator

Arb.Appeal Nos.6 & 5/16

shows that he did not refer to the drawings and maps annexed

with the tender record showing the quarries. The learned

Arbitrator did not ask the Contractor to produce the record

which is ordinarily created like payment of royalty in respect of

such material to the revenue department. Surprisingly, the

learned Arbitrator has granted the claim by presuming that the

quantities actually used was required for work and so, the

Contractor must have transported this quantity from the place

which he has contended. The Contractor himself has admitted

that some material was available at the other quarries which

were not that away from the site of work, but the Contractor has

not given the exact quantity of the material recovered from

those sites by producing record of royalty and other record.

These circumstances show that most casual approach was

shown by the learned Arbitrator and even when there was no

material to substantiate the claim, the learned Arbitrator has

granted the claim and so award on such claim cannot sustain in

law. The Arbitral Tribunal has not referred Clause No. 5.7 of the

special terms and conditions. Thus, there was no material with

the Contractor to substantiate the claim under this head and the

Contractor had virtually failed to substantiate this claim and the

Court has rightly set aside the claim under this head.

Arb.Appeal Nos.6 & 5/16

44) The decision of the learned Arbitrator of granting

claims under issue No. 3A, 3B, 4A and 4B viz. revised rates for

entire quantities of work executed after 20.1.1993 and for

quantities which were less than 70% of the tender quantity

show that there was virtually non application of mind. It is

already mentioned that the Board of Arbitrators had given

revised rates to the Contractor by presuming that delay was

caused to the employer, but the learned Arbitrator has again

given compensation under this head. Even if, the Board of

Arbitrators had not given such compensation, in that case also,

the decision of the Board of Arbitrators had become final on that

point as this point was raised before the Board of Arbitrators and

so, there was bar of principle of res-judicata for granting these

claims. From this angle, the learned Arbitrator has not

considered these claims. Thus, the award on such claims cannot

sustain in law.

45) The claim in respect of excess price allegedly paid by

the Contractor for sand mentioned in issue Nos. 5A and 5B is

similar to the claim in respect of other material like rubble,

Arb.Appeal Nos.6 & 5/16

metal etc. It was the responsibility of the Contractor as per the

Clause 20 of G.C.C. and Clause 5.6 of special terms and

conditions of the contract to procure the sand. This aspect of the

agreement is not at all considered by the learned Arbitrator and

compensation is granted under this head. Such award cannot

sustain in law.

46) The claim in respect of interest under issue No. 6A

viz. interest on bank guarantee could not have been awarded by

the Arbitrator. Clause No. 10.3 of the special terms and

conditions of the contract shows that it was necessary for the

Contractor to keep such bank guarantee with the employer

during the period of execution of work. As per this clause, bank

guarantee was to remain with the Employer and it was to be

released only after completion of the work and settlement of the

account. Thus, the learned Arbitrator has committed grave error

in awarding interest on the bank guarantee in the present

matter. If issue Nos. 6A, 6B and 7 are read, which were framed

by the learned Arbitrator, it can be said that the learned

Arbitrator had not applied mind even for framing the issues. For

these reasons, the award on claims under this head needs to be

set aside.

Arb.Appeal Nos.6 & 5/16

47) Issue No. 12 framed by the learned Arbitrator was

about entitlement of the Contractor to get compensation,

revision of rates and specific relief at the same time. As already

observed, claims were considered by the Board of Arbitrators

and decision was given by the Board of Arbitrators on this point.

This point appears to be separately considered by the learned

Arbitrator and it can be said that it was not necessary for the

learned Arbitrator to decide this issue in view of the decision

given by the Board of Arbitrators. This issue could not have been

considered separately as it had connection with other claims.

48) The decision given under section 34 of the Act by the

learned P.D.J., Parbhani shows that the award in respect of claim

Nos. 2 to 5 is set aside and for the reasons given by the 'Court'

and by this Court, it is not possible to interfere in the said

decision of the P.D.J. The P.D.J. has however confirmed the

award given on claim Nos. 1 and 6. But the award given in

respect of those claims also cannot sustain in law in view of the

discussion already made.

49) The learned counsel for Employer placed reliance on

Arb.Appeal Nos.6 & 5/16

the observations made by the Apex Court in the case reported

as 2016 (8) SCALE 779 [Union of India and Anr. Vs.

Indusind Bank Ltd. and Anr.]. This case is on the

interpretation of provision of section 28 of the Contract Act as

amended in the year 1997. The Apex Court has laid down that

the provision has prospective effect. This Court has quoted the

relevant terms and conditions of the agreement and the best

possible case for Contractor is considered. In spite of such

consideration, this Court has come to the conclusion that it is

not possible to hold that the Contractor took action for

enforcement of his so called right within prescribed period of

three years from the date of cause of action. Thus, even if the

observations made in this case are ignored in view of the terms

and conditions of the Contract, the Contractor cannot succeed in

the matter. However, there cannot be dispute over the

proposition made by the Hon'ble Apex Court in this matter.

50) On the point of interest claimed on the bank

guarantee amount, the learned counsel for Employer placed

reliance on the observations made by the Apex Court in the case

reported as 2016 (3) Mh.L.J. 1 [Union of India Vs. Bright

Power Projects (India) Pvt. Ltd. In the case decided by three

Arb.Appeal Nos.6 & 5/16

Hon'ble Judges of the Apex Court, it is made clear that when

there is agreement that no interest would be awarded to the

Contractor, the Arbitral Tribunal cannot award interest. The Apex

Court has referred the provision of section 31 (7)(a) of the Act,

which runs as under :-

"31(7)(a) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the Arbitral Tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made."

51) The facts of the reported case show that there was

the claim in respect of interest on security deposit, earnest

money and also on other amount, but in view of the agreement

that no interest would be payable, the Apex Court held that

Arbitral Tribunal could not have awarded interest. On the other

hand, the learned counsel for respondent placed reliance on the

observations made by the Apex Court in the case reported as

AIR 1985 SC 607 [Hyderabad Municipal Corporation Vs.

M. Krishnaswami Mudaliar]. In this case decided by two

Hon'ble Judges of the Apex Court, the work was abandoned and

Arb.Appeal Nos.6 & 5/16

in view of the claim made by the Contractor under the Interest

Act, in that case, the Apex Court held that granting of interest

was possible. The facts were different and further, there is the

case cited supra viz. 2016 (3) Mh.L.J. 1 [Union of India Vs.

Bright Power Projects (India) Pvt. Ltd. decided by the three

Judges of the Honble Apex Court showing that Arbitrator is not

expected to give award which will be against the terms and

conditions of the agreement. In the present matter, relevant

facts are considered by this Court and relevant portion of the

agreement is already quoted and so, the finding is given that the

Contractor is not entitled to get interest on the bank guarantee.

52) The learned counsel for respondent placed reliance

on the observations made by the Apex Court in the cases

reported as 2014 (4) Arb.LR 307 (SC) [Associate Builders

Vs. Delhi Development Authority] and 2014 (4) Arb.LR 1

(SC) [Swan Gold Mining Ltd. Vs. Hindustan Copper Ltd.].

The Apex Court has laid down that ordinarily when view

expressed by the Arbitrator on facts is possible view, the

decision of the Arbitrator given on factual aspect cannot be

disturbed by the Court. However, the observations show that

such award needs to be based on evidence given to substantiate

Arb.Appeal Nos.6 & 5/16

the claim and it should be in accordance with the terms and

conditions of the Contract and it should not be against the law.

There cannot be dispute over the proposition. Only to that

extent, this Court has considered the challenge against the

award.

53) In view of the aforesaid discussion made by this

Court, this Court holds that point Nos. (iii), (iv), (v), (vi) and

(vii) need to be answered against the Contractor and they are

answered accordingly.

54) So, this Court holds that the proceeding filed by the

department, Employer needs to be allowed and entire award of

the learned Arbitrator needs to be set aside. Similarly, the

decision given by the learned P.D.J. of conforming the award in

respect of claim Nos. 1 and 6 needs to be set aside. In the

result, following order :-

ORDER

(I) Arbitration Appeal No. 6/2016 of the Employer is

allowed. The entire award delivered by the learned Arbitrator is

hereby set aside and the claims stand rejected. The decision

given by the learned P.D.J., Parbhani in proceeding filed under

Arb.Appeal Nos.6 & 5/16

section 34 of the Act, by which award in respect of claim No. 1

and 6 is confirmed, is also set aside and the entire proceeding

filed under section 34 of the Act by the Employer stands

allowed.

(II) Arbitration Appeal No. 5/2016 of the Contractor

stands dismissed.

(III) Civil Applications filed in both the matters are

disposed of.

(IV) Parties to bear their own cost throughout.

[ T.V. NALAWADE, J. ]

ssc/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter