Citation : 2017 Latest Caselaw 1550 Bom
Judgement Date : 10 April, 2017
Cri.W.P.No. 790/16
1
IN THE HIGH COURT AT BOMBAY
APPELLATE SIDE, BENCH AT AURANGABAD
CRIMINAL WRIT PETITION NO. 790 OF 2016
1. Sau. Sunita w/o. Gangadhar
Suryawanshi (Babhalikar),
Age 50 years, Occu. Social Work,
R/o. Deshmukh Galli, Bhokar,
Tal. Bhokar, District Nanded. ....Petitioner.
(Ori. Complainant)
Versus
1. The State of Maharashtra,
Through Police Station,
Bhokar, Tal. Bhokar,
District Nanded.
2. Girish s/o. Vinayakrao Joshi,
Age 42 years, Occu. Service i.e.
Executive Engineer, P.W.D.
Bhokar, Tal. Bhokar, Dist. Nanded,
R/o. Plot No. 40, Flat No. 1,
Siddhi Residency, Shrey Nagar,
Aurangabad, Dist. Aurangabad,
Serving Superintendent Engineer,
P.W.D., Circle - Akola, Tq. & Dist.
Akola. ....Respondents.
Mr. P.R. Katneshwarkar, Advocate for petitioner.
Mr. S.W. Munde, APP for respondent No.1/State.
Mr. N.B. Khandare, Advocate for respondent No. 2.
CORAM : T.V. NALAWADE, J.
DATED : April 10, 2017.
JUDGMENT :
1) Rule. Rule made returnable forthwith. By consent,
heard both the sides for final disposal.
Cri.W.P.No. 790/16
2) The proceeding is filed under Articles 226 and 227 of
the Constitution of India to challenge the decision of Criminal
Revision No. 14/2015, which was pending in the Court of
Additional Sessions Judge, Bhokar. The revision filed by the
present respondent No. 2 - Shri. Joshi , who is presently serving
as Superintending Engineer is allowed by the Sessions Court and
the order of taking cognizance of one offence as against
respondent No. 2 on police report is set aside by the Sessions
Court. The report was filed by police under section 169 of
Criminal Procedure Code (Cr.P.C.) along with the chargehseet.
The learned Judicial Magistrate, First Class (J.M.F.C.), Bhokar did
not accept the report filed under section 169 of Cr.P.C., 'C'
Summary Report which is given as per the Maharashtra Police
Manual, 1999 and on the basis of the material collected, took
cognizance of the offence punishable under sections 420, 467,
468, 471, 409, 34 etc. of Indian Penal Code (I.P.C.).
3) Regular Criminal Case No. 76/2014 was filed as a
private complaint by the present petitioner for aforesaid
offences and in that matter, order under section 156 (3) of
Cr.P.C. was made by the learned J.M.F.C., Bhokar. After
completion of the investigation, police had filed aforesaid 'C'
Summary Report under section 169 of Cr.P.C. along with the
Cri.W.P.No. 790/16
chargehseet.
4) It is the case of original complainant that present
respondent No. 2 - Shri. Joshi was working as Executive Engineer
of Public Works Department (P.W.D.) of the State Government
Department and one Shri. Dange was working as Junior Engineer
for Bhokar. One Shri. Deshpande was working as Sub Divisional
Engineer at the relevant time. The complainant is resident of
Bhokar, District Jalna.
5) In the private complaint, allegations were made by
the present petitioner that false record of execution of work was
created in connection with Dhavari - Therban - Somthana - Kini -
Palaj road and by creating false record of measurement and
Government money was misappropriated by these Engineer staff
of P.W.D. Department. It was the duty of Shjri. Dange and Shri.
Deshpande to take measurement and prepare the bills and
Executive Engineer, respondent No. 2 - Shri. Joshi was to
sanction the bills and disburse the amount on the basis of bills.
He was also responsible for allotment of work. There is allegation
that amount of Rs.39,55,106/- of Government was
misappropriated by these persons by creating false record. It is
the case of complainant that she had made an attempt to collect
the record of measurement, but the record was not supplied and
Cri.W.P.No. 790/16
she had tried to collect the record of report of joint measurement
made by other Executive Engineer, but the department has
avoided to supply that record also. Ultimately, she got some
information and on that basis, she filed the complaint. The
complainant was sure that present respondent No. 2 and other
two Engineers were responsible for the creation of false record
and misappropriation and they were made accused in the
private complaint. The concerned police station filed report that
the complaint was made due to some misconception and such
report was filed under 'C' Summary category created by
Maharashtra Police Manual, 1999. The submissions made, the
report of police and the argument advanced show that not a
single person was arrested by police during investigation even
when anticipatory bail was refused by this Court to accused
Shri. Joshi.
6) In 'C' Summary Report, it was informed by police to
the learned J.M.F.C. that Report of the first Committee of expert
was confronted to accused by the police and respondent Shri.
Joshi had denied that Report by contending that he was not
present at the time when joint measurement was taken by the
Committee. Due to such defence taken by Shri. Joshi, police had
written to the Chief Engineer of the Department that the Report
cannot be accepted. It appears that in the Legislative Assembly
Cri.W.P.No. 790/16
and Council of the State, this subject was raised and the State
Government then gave directions to the Vigilance Committee
created for Aurangabad division to make inquiry and submit
report. Then other Executive Engineer made inquiry and
submitted report dated 14.2.2014. The previous report was
submitted on 13.7.2012. The subsequent Committee, Vigilance
Committee reported that the report of the year 2012 was not
correct and there was no substance in the allegations made
against these Engineers. The Superintending Engineer Shri.
Kulkarni considered the two reports and he gave his own report
to the Chief Engineer that subsequent report needs to be
accepted. He also reported that there was no necessity of joint
measurement again in view of the report of Vigilance
Committee. The papers of investigation and the police report
show that police had recorded statements of the persons, who
were involved in making the inquiry and police accepted the
final report and informed to the Magistrate that as the
subsequent report was of the Committee of higher grade, it was
necessary to accept it and so, the investigating agency was filing
'C' Summary Report.
7) The aforesaid record and the report of investigating
agency was considered by the learned J.M.F.C. Hearing was given
to the counsel of complainant. The learned J.M.F.C. refused to
Cri.W.P.No. 790/16
accept 'C' Summary Report and on the basis of aforesaid record
which included the report of first joint measurement and the
statements of the members of that Committee took cognizance
of the offences.
8) The learned Additional Sessions Judge has set aside
the aforesaid order of J.M.F.C. on following three grounds :-
"(A) There is no sanction under section 197 of Cr.P.c.
to initiate prosecution against accused.
(B) The lower court totally ignored the subsequent
report and there is no whisper of third and fourth
report.
(C) The contractors who prepared forged bill are not
implicated as an accused in absence of main accused
who are the author and mastermind of the forged bill.
There act can not fastened on the petitioner."
9) There are peculiar circumstances in the matter and
such circumstances are also with regard to the record of two
revisions and the matter which was filed in this Court. The record
produced shows that initially all the three Engineers had filed
Criminal Revision No. 8/2014 on 14.4.2014. This revision was not
pressed by them and so, it was shown to be disposed of as not
pressed on 25.7.2014. Prior to that, a proceeding was filed under
Cri.W.P.No. 790/16
section 482 of Cr.P.C. by present respondent No. 2 - Joshi to
challenge the order of investigation made by J.M.F.C. in this
Court. Thus, the order of J.M.F.C. was challenged by filing two
proceedings like revision and proceeding filed under section 482
of Cr.P.C. Joshi and other two accused also attempted to get
anticipatory bail by filing applications in Sessions Court and in
this Court. This Court had refused anticipatory bail to all these
three accused by order dated 25.8.2014 made in Criminal
Application No. 2664/2014. The record shows that the first
Criminal Revision No. 8/2014 was pending on 25.7.2014, but the
proceeding was filed under section 482 of Cr.P.C. The first
revision which was not pressed was filed through one Advocate
Shri. Sharma and the second revision was filed through another
advocate Shri. P.H. Deshmukh. Though some reasons are given
by the Sessions Court for deciding the second revision in favour
of accused, the fact remains that the accused had failed to get
order under section 482 of Cr.P.C. and also order of anticipatory
bail from this Court.
10) The aforesaid circumstances and particularly, the
creation of one more Committee for making inquiry and the
circumstance of acceptance of the the said report by the Chief
Engineer and the circumstance that police acted on the basis of
second report are sufficient to show that somebody from
Cri.W.P.No. 790/16
Government was helping these accused. While deciding the
anticipatory bail application, this Court had considered those
circumstances and it was observed that it was an attempt to
cover up the things. When the Court is expected act
independently and even police were expected to make
investigation independently and fairly, the learned Judge of the
Sessions Court ignored all these circumstances and presumed
that the report of the subsequent Committee ought to have been
accepted by the learned J.M.F.C. It cannot be said that the
learned Judge of the Sessions Court was not aware of the
aforesaid circumstances because the learned J.M.F.C. had
considered those circumstances. As the report submitted by
police under section 169 of Cr.P.C. and the papers collected by
police were available before the J.M.F.C., the learned Judge of the
Sessions Court ought to have presumed that the learned J.M.F.C.
had considered all this material and after that had taken
cognizance of the matter. The Sessions Court ought to have kept
in mind the scope of revisional jurisdiction and also the powers
of the learned J.M.F.C. The power exercised by the learned
J.M.F.C. is well withing his jurisdiction and that was on the basis
of some record, but the learned Sessions Judge did not consider
that aspect of the matter. It can be safely said that the learned
Sessions Court has exceeded the powers by accepting the other
probability which was suggested to him by the side of accused.
Cri.W.P.No. 790/16
11) On merits also, it can be said that the investigating
agency did not act fairly and did not make investigation
competently. When there were such serious allegations and
when there was the report of first Committee constituted for
joint measurement, investigation ought to have been made
independently. The investigating agency did not take help of any
independent agency to find out the truth in to the allegations.
The investigating agency did not record the statements of
persons living in the vicinity of the road. It did not record
statements of persons who were regularly using the said road
and the investigating agency did not approach some witnesses
who could have been supplied information as to whether the
material like Murum, metal etc. was supplied by them and it was
taken to the site for repair and construction of the road. When
such work is executed, some minor mineral like Murum, metal is
required to be excavated and for that, there is always revenue
record. The report of the Investigating Officer does not show that
such an attempt was made. The report even does not show that
the Investigating Officer went in to the details of the bills when
the first Committee had given finding that most of the work was
not actually executed and false measurements were recorded.
Thus, the things were not verified independently by the
investigating agency. There was atleast the material before the
Cri.W.P.No. 790/16
investigating agency like the statements of members of the first
Committee showing that they had visited the spot and they had
noticed that most of the work was not executed and false record
of measurement was prepared.
12) There is copy of Government Resolution (G.R.) dated
30.10.2003 of P.W.D. of Government in which guidelines are
given for making inquiry when there are allegations of present
nature. As per these guidelines, the first Committee for joint
measurement was constituted and one Shri. Khaja Masioddin
was presiding over this Committee and he was incharge
Executive Engineer at the relevant time. This Court has no
hesitation to observe that the first Committee was constituted as
per the G.R. dated 30.10.2003. The G.R. does not show that the
incharge Executive Engineer cannot do such inquiry. Clause No.
4 of the G.R. shows that such Committee consist of atleast five
members as follows :-
(i) Executive Engineer, Deputy Executive Engineer
and atleast one officer of rank of Branch
Engineer/Junior Engineer (Total number of members -
three), and
(ii) One Deputy Engineer and one Branch
Engineer/Junior Engineer of the office against which
there are allegations (Total number of members - two).
Cri.W.P.No. 790/16
If felt necessary, the Executive Engineer/Superintending
Engineer, Quality Control Committee, Vigilance Committee had
also right to remain present during such inquiry. Thus, the main
inquiry was to be conducted as per the aforesaid G.R. and that
was through joint measurement.
13) Clauses Nos. 3 and 5 of the aforesaid G.R. show that
in advance intimation of joint measurement needs to be given
and 20 days notice needs to be given to the officer against
whom there are allegations. However, it further shows that if the
officer does not remain present, his absence is to be marked and
the inquiry is to be completed. The G.R. also shows that if the
officer against whom there are allegations remains present and
he expresses some grievance with regard to any matter, the
Committee is expected to see that his grievance is redressed by
taking some steps. The procedure which is required to be
followed for taking joint measurement is also given in clause No.
7 of the G.R. and that includes the taking of the holes.
14) Copy of the report submitted by the first Committee
of joint measurement dated 13.3.2012 is on the record and it
shows that it was done on the basis of directions given to make
inquiry in respect of the allegations made against the Junior
Cri.W.P.No. 790/16
Engineer Shri. M.N. Dange. It shows that people of that area had
started agitation and they were asking for making inquiry.
15) The report of the first Committee shows that in all six
officers mentioned in the aforesaid G.R., who are required to be
included in the committed were present for joint measurement.
Shri. M.N. Dange, against whom there were allegations, was also
present. It appears that notice was given to one Shri. P.P.
Deshpande also. But, he remained absent. Thus, notices were
given against two officers. These two officers were working in
the field and they were expected to prepare the bills etc. after
taking the measurement and they were involved in day to day
supervision. The main points of the report prepared by the first
Committee after joint measurement are as follows :-
(i) Inquiry was made between 22.5.2012 and
19.6.2012.
(ii) The work in respect of the allegations was shown
to be completed in financial year 2010-11.
(iii) In all the items, the pieces of work, where
irregularities were found and misappropriation was
noticed, there is clear mention that the Committee had
visited the concerned site for measurement.
(iv) In respect of Dhavri - Therban - Somthana - Kini -
Palaj road, for repairs k.m. 38/700 to 39/100, in
Cri.W.P.No. 790/16
addition to other irregularities, it was noticed that no
work was actually executed as per the work order of
repairs and as per the measurements. The Committee
noticed that for about 800 mtrs. from the two side
road, some earth material was collected after digging
and that earth material was shown to be spread on side
pattis. By using this modus operandi, the amount of Rs.
7.06 lakh was misappropriated.
(v) In respect of the aforesaid road for
k.m.39/100 to 41/00 and k.m. 42/00 to 42/00 for
repairs, additional work was executed like 20 mm
premix carpet when there was no such tender and
estimate. Similarly, like done in aforesaid matter, earth
material from both the sides of the road was collected
to prepare the side pattis of the road and by using that
modus operandi, the amount of Rs.82,690/- was
misappropriated. There was one more irregularity in
respect of this work like giving of technical sanction of
Rs.7.95 lakh to the work when the administrative
sanction was of Rs.5 lakh. This Court is not going into
the details of that count and this Court is trying to deal
with the particular allegations made in respect of false
record and misappropriation.
(vi) For aforesaid road for the piece k.m. 41/200
Cri.W.P.No. 790/16
to 41/600, false record of measurement was prepared
and no work was actually executed on that place. Some
ditches were filled, but when the contractor was
expected to reconstruct the road of the width of 3.75
mtrs., such work was not executed and the amount of
Rs. 9.87 lakh was misappropriated.
(vii) to (x) These items are in respect of the same road
of k.m. 52/00 to 52/200, k.m. 54/400 to 54/600, k.m.
55/700 to 55/900 and k.m. 55/00 to 58/00. In respect of
these items also, it was noticed that record of false
measurement was created and loss was caused and
thereby Government amount was misappropriated.
Some other circumstances leading to suspicion like
creation of entire record of measurement and bills on
the same day are also noted. The notings made by the
Committee in these items show that they had visited
the spot and the material used for filling the ditches
was also seen and it is noted.
16) The first Committee had given report that loss of
Rs.39.55 lakh was caused and this amount was grabbed by
preparing false record of measurement and false bills. The blame
was put on divisional accountant also as the bills prepared were
found to be highly suspicious in nature. It is already observed
Cri.W.P.No. 790/16
that ultimately, the bills come to Executive Engineer for sanction
and releasing the amount.
17) From the aforesaid report prepared by the first
Committee and the procedure given in the G.R. already quoted,
it could have been presumed by the Magistrate at the stage of
cognizance that necessary procedure was followed by this
Committee and even holes were taken at various places by this
Committee for verification. As the measurement was taken by
this Committee immediately after the work was shown to be
completed, more importance could have been given by the
Magistrate to this report and so, the Magistrate gave due
importance to this report. There is one more circumstance that
Shri. Dange who was present on the spot at the time of
measurement taken by the first Committee, did not raise
grievance and this circumstance is not considered by the learned
Judge of the Sessions Court. Fortunately, police had recorded
statements of all the members of this Committee and they are
on record.
18) The second Committee is called as Vigilance
Committee and the report is signed by only one officer whose
designation is Executive Engineer. His report shows that he
visited the spot between 3.12.2013 and 5.12.2013 and again
Cri.W.P.No. 790/16
between 21.1.2014 and 23.1.2014. Here only it needs to be kept
in mind that the work was completed in the financial year 2010-
11. There is always wear and tear due to rain, wind, use etc.
There is also other circumstance like every year or after some
time repairs are again carried out of the same piece.
19) In the complaint itself, the complainant has
contended that he was required to run from pillor to post to
collect the information and every time, the officers of the
department had avoided to supply information, much less the
copies of report. In view of these circumstances, if there was the
direction to the second Committee, the second Committee ought
to have collected the record and ought to have done verification
by visiting the spot, but that was not done and vague excuse is
given by the Committee in respect of the most of the works by
saying that allegations are vague. If one goes through the
second report carefully, it is not difficult to form opinion that this
report was given to cover up the things. many loop holes are
kept in the second report by the Committee and it can be said
that this is done to save it's own skin. On one hand, this
Committee has observed for item No. (iv) that due to passing of
period of three years since the execution of the work, it was not
possible to give specific and clear report/opinion and on other
hand, it is again mentioned that sample holes were taken for
Cri.W.P.No. 790/16
verification and it was found that approximately work which was
to be executed was executed. In first Committee, as many as six
officers of the department were involved. In the second
Committee, only one Officer has signed the report and the
Superintending Engineer has given report that there is no need
to go for second joint measurement. It can be said that second
joint measurement could not have helped to find out the truth as
much time had expired and the possibility of again executing the
same work on same site was not at all considered in the second
report.
20) The Superintending Engineer, who accepted the
second report has given strange reason that post of Shri. Khaja
was of Sub Divisional Engineer and he was only holding the
charge of Executive Engineer and so, he was not competent to
take the joint measurement. The relevant portion of G.R. is
already quoted and it shows that to discard the report given by
the first Committee which was constituted as per the G.R., this
reasoning is not at all acceptable. Other reason is given that
short notice of four days was given to the officers against whom
there were allegations when 20 days notice is required and so,
the report is not binding even on Shri. Dange. Considering the
purpose behind the creation of Committee, this reason also
could not have been accepted by anybody. Shri. Dange had
Cri.W.P.No. 790/16
remained present when the first Committee took the joint
measurement. The other circumstance that when there was the
allegation of the complainant that at the same site,
subsequently more work was executed, attempt was not made
to ascertain on the basis of record as to whether such work was
executed subsequently. These circumstances are sufficient to
create probability that the second Committee tried to cover up
the things.
21) When there are aforesaid circumstances against the
officers of P.W.D., atleast investigating agency ought to have
acted fairly and ought to have made the investigation
independently. It was not open to the investigating agency to
give opinion only on the basis of rank or grade of the two
Committees. The investigating agency was expected to find out
the truth. The report of police does not show that police tried to
find out the truth. In ordinary course, Investigating Officer ought
to have recorded the statements of the persons of that locality,
the persons who were regularly using that road and also the
witnesses whose names were appearing in the record like bills of
the work. That exercise was not done. The investigating agency
could have appointed independent expert and the other expert
could have also ascertained as to whether the work was really
executed in the year 2010-11. But the investigating agency
Cri.W.P.No. 790/16
wrote to department to obtain one more report and that was
done only because respondent Shri. Joshi had objection to the
report prepared by Shri. Khaja. Thus, the investigation was not
made fairly, competently and independently.
22) The Sessions Court has committed serious error in
holding that the learned J.M.F.C. did not consider the entire
material. The Sessions Court ought to have presumed that the
entire material was before the J.M.F.C. as the aforesaid things
were mentioned by police in the report and the papers were
collected by police during investigation. The learned Judge of the
Sessions Court did not consider the circumstance that no
investigation was made by police and only on the basis of report
of the second Committee, which was accepted by
Superintending Engineer and Chief Engineer, opinion was formed
by Investigating Officer that it was a case in which 'C' Summary
Report needs be to be filed.
23) The learned Judge of the Sessions Court has
committed one more error in observing that the prosecution
cannot be allowed against the officers as the contractor, who
allegedly executed the work is not made accused. This
proposition is not correct in law. The main allegations are against
the officers and only due to these officers offence could have
Cri.W.P.No. 790/16
been committed. It is always open to the Court trying the
offence to include other persons who were also responsible for
the offence as provided in section 319 of Cr.P.C.
24) The learned Judge of the Sessions Court has
committed one more error in holding that there is necessity of
sanction under section 197 of Cr.P.C. for taking cognizance of
the matter as against the respondent and other Engineers. On
this point, one case is referred by the learned Judge of the
Sessions Court and reliance is placed on two cases reported as
(2013) 10 SCC 705 [Anilkumar and Ors. Vs. M.K. Aiyappa
and Anr.] and (2016) 9 SCC 598 [L. Narayan Swamy Vs.
State of Karnataka and Ors.]. The facts of the first case show
that it was a matter under Prevention of Corruption Act, 1988
and in view of section 19 (1) (3), the Apex Court had held that
for ordering investigation against the public servant sanction
needs to be obtained and if the matter is referred for
investigation without sanction, reference is bad in law. In the
second matter also, the provision of section 19 of the Prevention
of Corruption Act, 1988 was considered and it was also involving
directions given under section 156 (3) of Cr.P.C. Thus, the main
offence involved was different and the Apex Court was
considering the provision of section 19 of the Prevention of
Corruption Act.
Cri.W.P.No. 790/16
25) On the aforesaid point, the learned counsel for
petitioner placed reliance on the observations made by the Apex
Court in the case reported as AIR 2015 SC 2403 [Inspector of
Police and Ors. Vs. Battenapatla Venkata Ratnam and
Ors.]. In this case, the Apex Court has laid down that if the
public servants get indulged in criminal conduct constituting the
offences punishable under sections 420, 120-B, 468, 471 etc. of
I.P.C., the protection of section 197 of Cr.P.C. cannot be given to
them. This Court has no hesitation to observe that observations
made in this case need to be used in the present matter. There
was no necessity of sanction in the present matter in view of the
nature of allegations made against the Executive Engineer and
other Engineers.
26) The aforesaid discussion, the material and the law
show that the Sessions Court has committed error in interfering
in the order made by the learned J.M.F.C. Such decision cannot
sustain in law.
27) In the result, the petition is allowed. The decision
given by the learned Additional Sessions Judge, Bhokar in
Criminal Revision No. 14/2015 is hereby set aside. The order
made by the learned J.M.F.C., Bhokar in Final Report No. 1/2015
Cri.W.P.No. 790/16
dated 25.5.2015 is hereby restored.
Rule is made absolute in aforesaid terms.
[ T.V. NALAWADE, J. ] ssc/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!