Citation : 2017 Latest Caselaw 1442 Bom
Judgement Date : 4 April, 2017
apeal.128.00.jud.doc 1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
NAGPUR BENCH, NAGPUR
CRIMINAL APPEAL NO.128 OF 2000
State of Maharashtra,
through Anti Corruption Bureau,
P.S. Sitabuldi, Nagpur. .... Appellant
-- Versus -
Bhagwat s/o Dattuji Dongare,
Aged 39 years, Occu. Junior Clerk,
Command Area Development Authority,
Nagpur,
R/o Ravi Nagar Quarter, No.D-21/B, Nagpur. .... Respondent
-------------
Shri I.J. Damle, Additional Public Prosecutor for the Appellant/State.
Shri J.M. Gandhi, Advocate for the Respondent.
-------------
CORAM : KUM. INDIRA JAIN, J.
DATE : 4th APRIL, 2017. ORAL JUDGMENT :-
This appeal takes an exception to the judgment and
order dated 24/12/1999 passed by the learned Special Judge,
Nagpur in Special Case No.22/1991. By the said judgment and
order, respondent-accused came to be acquitted of the offence
punishable under Section 161 of the Indian Penal Code and
Sections 7, 13(i)(d) read with Section 13(2) of the Prevention of
Corruption Act (hereinafter referred to as 'the Act' for short).
02] Prosecution case, in brief, is as under :
i. Complainant Pramod Yashwant Ramteke was serving
as driver in the Office of Command Area Development
Authority, Nagpur. Accused was working as Junior
Clerk in the same office. Complainant was prosecuted
in a criminal case and was placed under suspension
from 12/04/1984 to 30/03/1989. After acquittal in
criminal case, he was reinstated. On reinstatement,
arrears of his pay were to be drawn.
ii. According to complainant, he requested the accused
to draw arrears of his pay. Accused did not prepare
pay bill. Before 15 days of incident, complainant met
accused in the office and asked to prepare his bill for
arrears. It is alleged that accused demanded Rs.
6,000/- for preparation of pay bill. Complainant
showed his inability to pay Rs.6,000/-.
iii. On 31/12/1990, complainant again met the accused.
That time, accused told the complainant to bring
Rs.2,000/- on the next day and thereafter he would
prepare his bill and the remaining amount should be
paid by him after getting the arrears. Complainant
was reluctant to pay money and so he went to the
Office of Anti Corruption Bureau and lodged report.
iv. PW-9 Police Inspector Rizvi reduced report of
complainant into writing. Panchas were called from
R.T.O. Office. PW-2 Bhaurao Zade and PW-3
Krishnarao Bhongade acted as panch. Verification of
demand was made in the presence of panch-
witnesses. ASI Lambe gave demonstration of
phenolphthalein powder and its effect with solution of
sodium carbonate. After the demonstration,
complainant produced currency notes of Rs.2,000/-.
Pre-trap panchnama was then drawn.
v. Trap was arranged on the same day. It was successful.
Detailed panchnama was drawn. Statement of
witnesses came to be recorded. On completing
investigation, charge-sheet was submitted to the
Special Court.
03] Charge of the alleged offence came to be framed vide
Exh.10. Accused pleaded not guilty and claimed to be tried. His
defence was of total denial and false implication. In his
statement under Section 313 of the Code of Criminal Procedure,
accused raised specific defence and submitted that after office
hours, he had taken his vehicle from the stand. Complainant
came in front of his vehicle, shook hand with him and asked for
lift till M.L.A. Hostel Square. He left him on the square and as
usual went to a pan-shop for cigar. The vehicle was parked 15
feet away from pan-shop. The bag, in which currency notes were
found, was in the vehicle. He returned after taking cigar.
Complainant was behind him. Thereafter, 10-15 persons came,
caught him and brought him to the Office of Anti Corruption
Bureau. According to the accused, those people have taken his
8 to 10 signatures on blank papers. He submits that his service
record was good. He was given advance increment. He denied
the allegations of demand and acceptance of money as alleged
by the complainant.
04] To substantiate the guilt of accused, prosecution
examined in all nine witnesses. Considering the evidence of
complainant, panch-witnesses, staff working in the office of
accused and Investigating Officer, trial Court came to the
conclusion that prosecution could not prove the guilt of accused
beyond reasonable doubt and in consequence thereof, acquitted
the accused. Being aggrieved with the judgment and order of
acquittal, this appeal has been preferred by the State.
05] Learned Additional Public Prosecutor assailed the
impugned judgment and order on many fold grounds. They are -
(i) Evidence of the prosecution witnesses, particularly
complainant and panch-witnesses, was not properly
appreciated.
(ii) Accused made a demand of Rs.6,000/-. It was
settled to pay Rs.2,000/- and Rs.1,000/- before
passing of bill and remaining Rs.3,000/- after
encashment of bill. Though demand and acceptance
of money is proved, trial Court wrongly held the
same as not proved.
(iii) Evidence of complainant is fully corroborated by
panch-witnesses and Investigating Officer. Still their
evidence has been discarded and disbelieved.
(iv) The approach of the trial Court is perverse and
wrong in holding that it was not possible for the
accused to draw bill of arrears of pay of
complainant.
(v) Though sanction was legally accorded under Section
19 of the Act, trial Court arrived at incorrect finding
that sanction was defective and mechanically
granted.
06] Per contra, learned Counsel for respondent strongly
supports the judgment and order of acquittal and submits that
evidence of complainant and panch-witnesses has been properly
and legally appreciated by the trial Court and no interference is
warranted in this appeal. Learned Counsel submits that accused
was not assigned with duty of preparing bill of arrears of pay and
when he was not dealing with such work, there was no question
of demand and acceptance of money for doing the work with
which accused had no concern. In this connection, reliance is
placed on the decision of the Hon'ble Supreme Court in Raghbir
Singh vs. State of Punjab - [(1976) 1 SCC 145, in which it
has been held by the Hon'ble Supreme Court in paragraphs 5
and 6 as under -
"5. In the first place, it appears clearly from the evidence that the appellant had nothing to do with the grant of exemption from payment of passenger or goods tax. The appellant was, at the material time, Passenger and Goods Tax Clerk II and, according to the evidence of Harmohan Singh, who was Passenger and Goods Tax Clerk I, the order of allocation of work made by the Excise and Taxation Officer assigned various duties to Passenger and Goods Tax Clerk II, but these did not include processing of application for exemption from payment of passenger or goods tax. The detection and recovery of passenger and goods tax was undoubtedly one of the duties entrusted to Passenger and Goods Tax Clerk II, but not the handling of applications for exemption. This was also made clear by Kashmir Singh who was an establishment clerk in the Excise and Taxation Office. Kashmir Singh stated that "the Passenger and Goods Tax Clerk has no concern with the exemption cases
and the same are dealt with by the Taxation Inspector" and he added that the release of attached property is also effected on the basis of the report of the Taxation Inspector and "the Passenger and Goods Tax Clerk has nothing to do with it". It would, therefore, be seen that the appellant was not in charge of applications for exemption which were dealt with by the Taxation Inspector. It is true that so far as the detection and recovery of goods tax was concerned, it was within the charge of the appellant, but nothing remained to be done on that count at the material time when the bribe was demanded and paid, since the truck was already attached by Taxation Inspector Brar on July 12, 1968. The only issue which was then being pressed by Jagdish Raj was that relating to exemption from payment of goods tax and so far as that issue was concerned, the appellant had nothing to do with it. There was, therefore, clearly no motivation for Jagdish Raj to give bribe to the appellant for obtaining grant of exemption. This circumstance weakens the foundation on which the edifice of the prosecution story rests and introduces an element of infirmity in it.
6. But more than anything else, the evidence of Taxation Inspector Sharma makes a serious inroad in the prosecution case. The evidence of Sharma shows that it was only on August 1, 1968 that Jagdish Raj
made an application for exemption from payment of goods tax supported by an affidavit and a certificate of exemption of token tax granted by the Licensing Officer. Now, obviously no exemption from payment of goods tax could be granted to Jagdish Raj until he made an application supported by a certificate of exemption of token tax obtained from the Licensing Officer. The certificate of exemption of token tax issued by the Licensing Officer would show that the truck was not plied during the period for which the certificate was granted and the registration certificate of the truck was lying deposited in the office of the Registration Authority."
07] The next contention raised on behalf of respondent is
that complainant was aware that bill for arrears of pay was not
to be prepared by accused. Sanction of the Government and
approval of the higher authority was necessary for preparing the
bill and in such contingency, complainant's allegations of
meeting the accused and the accused demanding and accepting
alleged illegal gratification need to be disbelieved. In support of
his submission, learned Counsel relied upon the decision of the
Hon'ble Supreme Court in G.V. Nanjundiah vs. State (Delhi
Administration) - [1987 (Supp) SCC 266] and particularly
paragraph 18, which reads thus :
"18. The High Court was not able to place reliance upon the statement of the appellant that he was at the site up to 2.00 p.m. As, according to the contractor, he had left the site about 11.00 a.m., the High Court assumed that the firm message cancelling the visit of the Prime Minister had been received before 11.00 a.m. It has been observed by the High Court that the appellant could have examined any one of the officers in support of his claim that he had left the site after 1.30 p.m., but, he had failed to do so. It may be pointed out that there is also no evidence corroborating the evidence of the contractor that he had left the site at 11.00 a.m. Without any such evidence and having regard to the fact that the learned Special Judge, who had seen the demeanour of the contractor, was disinclined to place any reliance upon the testimony of the contractor, the High Court was not justified in not giving any importance to the statement of the appellant. In our opinion also, it is difficult to accept the evidence of the contractor that he came back from the site at 11.00 a.m. and saw the appellant at his office in the DDA building at 1.00 p.m. when the appellant had demanded the bribe from the contractor. The contractor was very much aware that the appellant was not standing in the way of releasing his security amount and other amounts for extra work and, accordingly, it was not necessary for him to see the
appellant at his office. In the circumstances, we are not inclined to accept the case of the contractor that he accompanied by his son had met the appellant at his office at 1.00 p.m. on October 30, 1973. The learned Special Judge has also not placed any reliance on the testimony of the contractor's son. We also do not see any reason to place reliance upon his evidence in this regard."
08] Another contention raised on behalf of the respondent
is that his service record was excellent throughout. He received
an advanced increment for his outstanding work. Though he was
not concerned with the work of preparing bill of arrears of pay,
he was falsely implicated by the complainant.
09] On going through the material and evidence on record
and hearing the submissions advanced on behalf of the parties,
following points arise for determination of this Court -
(I) Whether prosecution could prove that on 01/11/1997,
respondent being a public servant, demanded Rs.
2,000/- other than legal remuneration as a motive for
preparing the bill towards arrears of pay of the
complainant?
(II) Whether sanction to prosecute the respondent
granted by the sanctioning authority is legal and
valid?
10] Findings to both the above points (I) and (II) are in the
negative for the reasons to follow :
It is not in serious dispute that at the relevant time,
accused was serving as Junior Clerk in the Office of Command
Area Development Authority, Nagpur. There is no serious
dispute that complainant PW-1 Pramod Ramteke was a Driver in
the said office and he was placed under suspension up to 1989.
It is stated by complainant that after his acquittal in criminal
case, as the bill towards arrears for his pay was to be prepared,
he approached the accused and accused demanded Rs.6,000/-
for the same. He states that after negotiations, it was agreed by
the accused that an amount of Rs.3,000/- should be paid before
preparation of bill and remaining Rs.3,000/- after encashment of
bill. The evidence of complainant shows that on 31/12/1990,
when he met the accused, accused told him to bring Rs.2,000/-
on 01/01/1991 and as he was not willing to pay Rs.2,000/-, he
reported the incident to Anti Corruption Office. PW-9 Police
Inspector Rizvi recorded the report [Exh.24] and then pre-trap
and post-trap panchnamas came to be drawn before and after
the raid.
11] The principal question in the case on hand is, whether
accused was responsible for preparation of bill towards arrears of
pay of the complainant. In this connection, evidence of PW-7
Executive Engineer (Technical Cell), C.A.D.A., Nagpur is relevant
and important. It is stated by PW-7 Mr. Vrujlal Gohil that accused
was attached to establishment section and the work of drawing
arrears of complainant was with the accused. PW-7 used to
countersign the bills and then it was submitted to the
Superintendent Engineer. He states that the matter of Ramteke
was put up before the Superintending Engineer for his approval.
As per service rules, sanction of the Government was necessary
to draw arrears of pay. He states that till 1993, he was in that
office and till that time, sanction of the Government was not
received in case of Ramteke. According to witness Gohil, on
02/03/1991, Ramteke made a complaint to Superintending
Engineer Mr. Santani. Departmental inquiry was going on
against the complainant. Complainant made a complaint to Mr.
Santani that on 15/07/1992, Inquiry Officer demanded Rs.2,000/-
to decide the matter in his favour. This fact elicited in the cross-
examination of PW-7 Gohil would clearly indicate that
complainant was a person of complaining nature. Sanction was
necessary for clearance of the arrears of complainant. The said
sanction was not received. Accused was not responsible for
clearing the bill. Even duty list placed on record shows that
clearance of bill of arrears of pay was not included in the duty
list of the accused. In such a situation, propositions of law laid
down by the Hon'ble Supreme Court in the case referred by the
learned Counsel for respondent would be applicable and whole
case of the complainant that he met the accused, accused
demanded and attempted to accept amount of Rs.2,000/-
becomes doubtful.
12] Even on merits, if evidence of complainant, panch-
witnesses and Investigating Officer is closely scrutinized, it can
be seen that there is no consistency in their evidence. On pre-
trap and post-trap panchnamas, evidence is conflicting and
itnesses do not corroborate each others in material particulars.
The trial Court has elaborately discussed the evidence of
complainant, panch-witnesses, office staff and the Investigating
Officer indicating as to how their evidence is not trustworthy and
believable. There is no reason for this Court to take a view
different than taken by the trial Court.
13] So far as sanction to prosecute the accused is
concerned, it would be necessary to look at the evidence of PW-5
Prabhakar Kulkarni, Sanctioning Authority. It is stated by Mr.
Kulkarni that in May, 1992, he was Superintending Engineer and
Administrator, Command Area Development Authority, Nagpur.
He received draft sanction order from Anti Corruption
Department along with the papers of investigation. He had gone
through those papers and accorded sanction (Exh.42).
14] Before considering the evidence of sanctioning
authority it is necessary to see the object of Section 19 of the
Act. Under section 19, grant of sanction is a weapon to
discourage vexatious prosecution and it is a safeguard for the
innocent, though not a shield for the guilty. The essentials of a
valid prosecution can be stated as under -
i. The prosecution must send the entire relevant record
to the sanctioning authority including the FIR,
disclosure statements, statements of witnesses,
recovery memos, draft charge-sheet and all other
relevant material. The record so sent should also
contain the material/document, if any, which may tilt
the balance in favour of the accused and on the basis
of which, the competent authority may refuse
sanction;
ii. The authority itself has to do complete and conscious
scrutiny of the whole record so produced by the
prosecution independently applying its mind and
taking into consideration all the relevant facts before
grant of sanction;
iii. The power to grant sanction is to be exercised strictly
keeping in mind the public interest and the protection
available to the accused against whom the sanction
is sought;
iv. The order of sanction should make it evident that the
authority had been aware of all relevant facts/
materials and had applied its mind to all the relevant
material.
v. In every individual case, the prosecution has to
establish and satisfy the court by leading evidence
that the entire relevant facts had been placed before
the sanctioning authority and the authority had
applied its mind on the same and that the sanction
had been granted in accordance with law.
15] In the above legal background, evidence of PW-5
Sanctioning Authority Mr. Kulkarni is to be scrutinized. It is
admitted by Mr. Kulkarni in the cross-examination that it may be
possible that draft sanction order and sanction accorded by him
vide Exh.42 are exactly identical. Even prosecution does not
dispute that draft sanction order and sanction accorded vide
Exh.42 are identical in verbatim. Sanctioning authority no where
states in the evidence details of investigation papers scrutinized
by the authority before according sanction. In such a situation,
possibility of Sanctioning Authority simply signing the sanction
order without application of mind is not ruled out.
16] In the above background, no fault can be found with
the reasonings recorded by the trial Court. The view taken by
trial Court is a possible view. Hence, no interference is called for
in this appeal. Hence, the following order :
ORDER
i. Criminal Appeal No.128/2000 stands dismissed.
ii. No costs.
(Kum. Indira Jain, J.) *sdw
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!