Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hindustan Petroleum Corporation ... vs Larson And Tourbo Limited
2016 Latest Caselaw 5297 Bom

Citation : 2016 Latest Caselaw 5297 Bom
Judgement Date : 16 September, 2016

Bombay High Court
Hindustan Petroleum Corporation ... vs Larson And Tourbo Limited on 16 September, 2016
Bench: Anoop V. Mohta
    ssm                                                               1           app14.06gp-16.9.16.sxw

                   IN THE  HIGH COURT OF JUDICATURE AT BOMBAY

                           ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                                  
                                   APPEAL NO. 26 OF 2006




                                                                          
                                             IN
                            ARBITRATION PETITION NO. 449 OF 2003




                                                                         
    Larsen and Toubro Limited,
    A Company registered under 
    the Companies Act and having 
    their ECC Division,




                                                                         
    At Mount Poonamallee Road,
    Manapakkam, P. O. Box. No. 979,          
    Chennai-600 089.                                                               ....Appellant

                         Vs.
                                            
    1         Hindustan Petroleum Corporation Ltd.
              A Govt. of India Undertaking
              registered Under the Companies Act,
          


              1956 and having office 
              At: 17, Jamshedji Tata Road, Churchgate,
       



              Mumbai-400 020.





    2         Shri S.K. Biswas (Sole Arbitrator),
              in his office at Hindustan Bhavan,
              Ballard Estate, 8 Shoorji Vallabhdas Marg,
              Mumbai-400 001.                                                      ....Respondents. 





                                                                 WITH

                                   APPEAL NO. 14 OF 2006
                                             IN
                            ARBITRATION PETITION NO. 449 OF 2003

    Hindustan Petroleum Corporation Ltd.
    a Government of India Undertaking

                                                                                                          1/56



            ::: Uploaded on - 21/09/2016                                  ::: Downloaded on - 22/09/2016 00:18:31 :::
     ssm                                                               2           app14.06gp-16.9.16.sxw

    registered under the Companies Act,
    1956 and having its registered office at
    17, Jamshedji Tata Road, Churchgate,




                                                                                                  
    Mumbai-400 020.                                                                ....Appellant.




                                                                          
                         Vs.

    1         Larsen and Toubro Limited,
              ECC Division, a company 




                                                                         
              registered under the Companies Act
              and having their ECC division
              at Mount Poonamalla Road,
              Manepakham, Po. Box. No. 979,




                                                                         
              Chennai-600 089.

    2         Shri S.K. Biswas,
              Sole Arbitrator in his office at
                                             
              Ballard Estate,
                                            
              Mumbai-400 001.                                                      ....Respondents. 


    Mr.   Atul   Rajadhyaksha,   Senior   Advocate   i/by   Kedar   Wagle   for   the 
          


    Appellant in APP No. 26 of 2006 and for Respondent No.1 in APP No. 
    14 of 2006.
       



    Mr. Minoo Siodia a/w Ms. Raksha Thakkar i/by Rustomji & Ginwala 
    for the Appellant in APP No. 14 of 2006 and for Respondent No.1 in 
    APP No. 26 of 2006. 





    None for Respondent No.2.


                           CORAM  :   ANOOP V. MOHTA AND
                                      G.S. KULKARNI, JJ.

RESERVED ON : 23 JUNE 2016.

PRONOUNCED ON : 16 SEPTEMBER 2016.

JUDGMENT (PER-ANOOP V. MOHTA, J.):-

ssm 3 app14.06gp-16.9.16.sxw

Both these Appeals, under Section 37 of the Arbitration

and Conciliation Act, 1996 (for short, "the Arbitration Act") (Appeal

and Counter-Appeal), filed by both the contesting parties (Claimant

and Respondent No.1), against Judgment and order dated 16

November 2005, passed by the learned Single Judge on a Petition

under Section 34 of the Arbitration Act in Arbitration Petition No. 449

of 2003 whereby, the award passed by the learned Arbitrator ("the

Arbitrator") dated 4 July 2003, has been substantially set aside and

partly maintained.

2 The Appellant-(Original Claimant)-Larsen and Toubro

Limited ("L&T") in Appeal No. 26 of 2006, which is a company

registered under the provisions of the Companies Act, has preferred

the Appeal, as the learned Single Judge has set aside the award qua

Claim Nos. 1, 2, 4, 9, 15, 16, 21 (i), 21(iii) and 21(iv) awarded by the

Arbitrator.

In the other Appeal, the Appellant is Respondent No.1-

Hindustan Petroleum Corporation Ltd. ("HPCL"), which is a

Government undertaking has challenged the order passed by the

learned Single Judge only with regard to Claim No. 19 and supported

ssm 4 app14.06gp-16.9.16.sxw

the Judgment on other claims.

Both the parties are the Appellant and Respondent No.1 in their

respective Appeals.

3 Following are the basic events, which lead to the

Arbitration proceedings.

On 23 April 1996, L&T submitted its tender for work relating to

"the laying, testing, pre-commissioning and commissioning of 18"

diameter 350 Kms. pipeline from Vishakhapatnam to Vijaywada,

including temporary cathode protection and optical fiber cable work."

On 25 November 1996, HPCL issued its Letter of Intent ("LOI"), which

was followed by a Letter of Allotment ("LOA"). Engineers India

Limited ("EIL") was the Engineer-in-Charge ("the consultant"). The

total contract price was Rs.53,64,39,858/-. The rate for the laying of

the pipeline and other works was all inclusive of rate all across the

terrains. The contractual date of commencement of work was 10

December 1996 and the completion date was 25 November 1997. On

29 August 1997, L&T submitted Bill No. 1 for extra work in the

amount of Rs.27,71,146/-. On 23 September 1997, L&T applied for

an extension for completion of contract upto 31 March 1998. On 10

ssm 5 app14.06gp-16.9.16.sxw

December 1997, L&T sought further extension upto 30 April 1998.

On 11 March 1998, L&T submitted Bill No. 2(A) for extra work in the

amount of Rs.12,39,57,262/-. The EIL reviewed these claims and

concluded that Bill No. 2A was not tenable. On 13 April 1998, EIL

extended the period till 30 April 1998 with the consent of HPCL. On

18 April 1998, L&T could not complete the work , hence applied for

further extension till 30 June 1998. On 23 April 1998, the consultant

declined to grant extension beyond 30 April 1998 for reasons stated in

the letter. On 20 August 1998, L&T completed a major portion of the

work and HPCL issued a completion certificate, except a submission of

no balance documents and the liquidation of checklist points. L&T

raised their Final Bill for Rs.53,66,77,790/- reserving their rights to

claim extra amount for the additional work.

4 Disputes arose between HPCL and L&T. On 22 August

2000, L&T invoked Arbitration as per Clause 14 and called upon the

Marketing Director of HPCL to nominate an Arbitrator. On 21

September 2000, HPCL appointed the General Manager, who was a

technically expert qualified engineer, as the arbitrator.

     ssm                                                               6           app14.06gp-16.9.16.sxw

    5                    Strikingly,  both the parties had agreed not to lead any oral 

    evidence,   but   to   submit   their   written   arguments   only.       Both   the 




                                                                                                  

parties further agreed that they would not be represented by the

advocates to argue the case and they would be represented by their

functional departmental officers and or law officers.

6 The Arbitrator prepared his Award. The total amount

claimed in 30 Claims was Rs.27,82,74,107/-. 16 Claims out of 30

Claims, were allowed, the aggregate amount was

Rs.7,43,66,44/-. On 30 September 2003, HPCL filed Arbitration

Petition No.449 of 2003 under Section 34 of the Arbitration Act.

HPCL challenged the Award in respect of 8 Claims allowed by the

Arbitrator. Insofar as Claim No. 21 is concerned, Claim Nos. 21(i), (iii)

and (iv), were amongst others allowed by the Arbitrator, there

challenged. On 16 November 2005, the impugned Judgment was

passed by the learned Single Judge, in Arbitration Petition .

7 Both the learned counsel appearing for the respective

parties, read and referred the reasons set by the learned Expert

Arbitrator and the learned Single Judge, including the terms and

ssm 7 app14.06gp-16.9.16.sxw

conditions of the contract, apart from the Judgments of the Supreme

Court and the High Courts in support of their particular claims and

counter-claims, including their written submissions.

8 In view of the specific Arbitration clause between the

parties, and as the significant power of appointment of Arbitrator was

exclusively with HPCL, the Arbitrator was preferred unilaterally.

There was no consent obtained from L&T for the same Both the

parties proceeded before the Arbitrator, keeping in mind the clauses,

where the technical terms and the facets of such construction contract

becomes relevant to resolve the disputes. Both the parties agreed to

proceed before the Expert Arbitrator, without leading any oral

evidence. Even the assistance of the advocates was not sought for.

The respective representatives of the parties appeared and

participated facing the Arbitrator. However, there is no serious issue

that the respective claims and counter-claims were submitted along

with supporting documents, with all the requisite, actual and technical

financial details. All representatives, officers, apart from the Expert

Arbitrator, were fully aware of the importance of such documents and

its technical details, and the nature of disputes which were required to

ssm 8 app14.06gp-16.9.16.sxw

be determined.

9 The learned Senior Counsel appearing for L&T made

submissions, in above background relying upon the law to reconsider

and decide rejected claims again by the Appellate Court, as the expert

Arbitrator had awarded the same, after hearing the parties, but the

Court has set aside. The learned Arbitrator was the General Manager-

ENG & Procurement in the HPCL organization. The appointment was

made by the Respondent-(HPCL). The parties raised specific issues.

Both the parties agreed and left the issues for the expert Arbitrator to

decide, based upon the documents, charts, statement and material

placed on record by the parties towards its claims and counter-claims,

apart from the knowledge and the experience in the filed of such

contract. The parties did not lead any oral evidence. The agreed

Arbitration procedure, as permissible in law, binds all the parties.

Legal proposition when the expert Arbitrator is appointed-

    a)        Mediterranean and Eastern Export Co. Ltd. Vs. Fortress Fabrics 

    (Manchester) Ltd.1

    i)        In   appointing   an   expert   arbitrator,   it   must   be   taken   that   the 
    1         1948 (2) AER 186 @ 187-189






     ssm                                                               9           app14.06gp-16.9.16.sxw

parties are content and intend to accept the judgment of a man in

their own trade on whose judgment they know they can rely (Page

188).

ii) An award of a technical arbitrator must be taken to mean that

he has acted on his own knowledge and experience (Page 189).

This judgment has been approved by the Supreme Court of

India and the Delhi High Court.

b)

Municipal Corporation of Delhi Vs. M/s Jagan Nath Ashok

Kumar & Anr.2

i) This is a case of construction contract and the arbitrator was the

Superintending Engineer.

ii) This judgment re-affirms the position in law held in

Mediterranean case (supra) and describes the approach in the earlier

case as an appropriate attitude.

10 The Award given by the Expert Arbitrator, need not be

lightly interfered with, was the another submission-

    a)        Jagdish Chander Vs. Hindustan Vegetable Oils Corpn.3


    2         AIR 1987 SC 2316 
    3         AIR 1990 Del 204 






     ssm                                                               10           app14.06gp-16.9.16.sxw

This case refers to the Mediterranean case with approval citing a different part of that judgment.

11 It is thus made clear that, in the case of an Expert

Arbitrator, who is a technical person and in the case a nominee of

contractor in the Arbitration, it is not necessary to articulate views

and findings with precision, as expected from a judicially trained

person.

a) EM & EM Associate Vs. Delhi Development Authority & Anr.4

i) This is a case where the Division Bench described the approach

of the Single Judge as that of a Court of Appeal and disapproved the

same (Page 235).

ii) This is also a case where the Division Bench held that a court

should be hesitant to interfere with an award made by an arbitrator

appointed by the Respondent (Page 233).

12 It is also contended on behalf of L & T that in the case of

an expert Arbitrator, there must be some reason for the decision and it

is not deficient because every process is not set out. Subject matter

needs to be looked at. The agreed Arbitration procedure, not to lead

evidence, is fundamental basis for the Court to proceed with the 4 2002 (2) Arb. LR 222.

ssm 11 app14.06gp-16.9.16.sxw

contentions, to interfere with such experts Arbitral award.

a) Rajesh Khanna Vs. Govt. of NCT of Delhi & Ors.5

i) Every process is not set out : subject-matter needs to be looked

at and it cannot be overlooked that the arbitrator cannot function like

a judge in a court.

ii) Parties in choosing experts from the field display an implied

faith in the personal judgment of the expert arbitrator and in such

circumstances meticulous reasons are not to be looked into.

    b)        M.L. Mahajan Vs. DDA6

    i.        This judgment reiterates the same principles as set out the in the 
           


    previous case. 
        



    13                   Having   considered   the   above   legal   position,   we   now 





examine the submissions as made on behalf of the parties in regard to

the claims which are the subject matter of these Appeals.

The Claims and the reasons-

Claim No.1- Claim for Additional work for canal at Chainage 205 km (introduced by irrigation dept.) 5 2005 (1) Arb. LR 247 (Delhi) 6 2005 (1) Arb. LR 561 (Delhi)

ssm 12 app14.06gp-16.9.16.sxw

14 We have considered the above position of law and the

scope and purpose of the appointment of Expert Arbitrator in a

dispute of this nature, where technical details are relevant for proper

adjudication of the claims and the counter-claims. We have also noted

the chart submitted by the learned counsel appearing for the parties,

covering the nature of claims and submission of L&T and also of

HPCL, referring to respective claims. The convenience charts with the

respective contentions and references, apart from the reasons given by

the learned Arbitrator and the learned Single Judge, have been read

and distinguished. We are dealing separately each claim and

counter-claims. For all the claims and particularly for Claim No.1, we

have to note the agreement clauses.

15 The following are the relevant clauses of agreement with

regard to the Arbitration, alterations and additions to the

specifications, designs and works:-

14 ARBITRATION-

14.1. Disputes or differences arising out of or in relation to agreement/contract shall be referred to the Director Marketing of the owner who may

ssm 13 app14.06gp-16.9.16.sxw

either act himself as Sole Arbitrator or nominate some Officer of the owner to act as an Arbitrator to adjudicate the disputes and differences

between the parties (except those in respect of which the decision of any person is by the

Contract expressed to be final and binding.

ALTERATIONS AND ADDITIONS TO SPECIFICATIONS,. DESIGNS AND WORKS-

The Engineer-in-Charge/Site-in-Charge shall have powers to make any alterations, additions and/or substitutions to the schedule of quantities, the original specifications,

drawings, designs and instructions that may become necessary or advisable during the progress of the work and

the Contractor shall be bound to carry out such altered/ extra/ new items of work in accordance with instructions which may be given to him in writing signed by the

Engineer-in-Charge/Site-in-Charge".......

"5.j.4. If the rates for the altered, additional or substituted work cannot be determined in the

manner specified above, then the Contractor shall,

within seven days of the date of receipt of order to carry out the work, inform the Engineer-in-

Charge/ Site-in-Charge of the rate at which he intends to charge for such class of work,

supported by analysis of the rate or rates claimed and the Engineer-in-Charge/ Site-in-Charge shall determine the rates on the basis of the prevailing market rates for both material and labour plus 10% to cover overhead and profit of labour rates

and pay the Contractor accordingly. The opinion of the Engineer-in-Charge/ Site-in-Charge as to current market rates of materials and the quantum of labour involved per unit of measurement will be final and binding on the contractor.

     ssm                                                               14           app14.06gp-16.9.16.sxw



    16                   The reliance was placed on the following contract clauses 




                                                                                                   

by the learned counsel appearing for HPCL-

Arbitration clause "...... to adjudicate the disputes and differences

between the parties (except those in respect of which the decision of any

person is by contract expressed to be final and binding)".

Clause 5.j.4 - specifically states "The opinion of the Engineer-in-

charge/Site-in-Charge as to current market rates of materials and the

quantum of labour involved per unit of measurement will be final and

binding on the contractor".

It is submitted, as per the above clauses, the rates for altered,

additional and substituted work is to be determined by Engineer-in-

Charge. For determining the rate, current market rate of the materials

and quantum of labour for unit measurement has to be considered.

These are only two components for determining the correct rate.

After determining the same rate, which is arrived at by Engineer-in-

Charge is final and binding on the contractor and hence, the same is

not arbitrable i.e. the Arbitrator has no jurisdiction to adjudicate on

the issue. On 15 April 1998, the Engineer-in-charge determined the

rate by giving detail analyses as per the clause of contract and the rate

arrived at by Engineer-in-charge was Rs.4,86,280/-, which was final

ssm 15 app14.06gp-16.9.16.sxw

and binding on the contractor and not arbitrable.

17 We have noted the Arbitrator's following reasons-

Original claim amount was Rs.27,71,146/- and revised claim

amount was Rs.16,26,160/-.

(a) "The valuation of the Consultants appears to be correct when

compared to the value claimed by the Claimants for similar

canal work ........."

(b) "Compared to similar work and cost thereof, the cost of

Rs.4,86,280/- as worked out by the Consultants is fair and

reasonable. It may be noted that the Bill of the Claimants was

not correct and not based on actual work performed by them as

can be seen from the conduct of the Claimants in reducing the

bill amount about Rs.16 lakhs.

(c) "I have carefully considered the respective cases of the parties,

their Written Submissions and authorities cited and hold that

while the evaluation of Claim No.1 at Rs.4,86,280/- is in

accordance with the Clause 5.j. of the GCC to the contract, that

the Claimants raised their bill on estimated basis and not on

actual work done by them. The Claimants declined to accept

ssm 16 app14.06gp-16.9.16.sxw

the valuation of the Consultants on vague and unsustainable

grounds vide Exhibits C-8 and C-9 of Volume -5."

(d) After holding as above, the Learned Arbitrator stated that

"Irrespective of the fact that the opinion of the Engineer-in-

Charge in this behalf is final and binding on the Claimants

under Clause 5-j of GCC of the Contract, being a technical

person myself, I have looked into the actual amount of work

involved in this extra claim. I find that the revised Claim of the

claimant is still exaggerated and high. The work is not equal to

Rs.16 lakhs or so which has been the revised claim, claimed by

the Claimant. The estimate of the Engineer in charge M/s.EIL is

a little to conservative and the work cannot be completed in

Rs.4.86 lakhs, which has been estimated by them. Accordingly,

I have gone through in detail and I find that a sum of

Rs.10,00,000/- will represent a true and proper valuation of

the work done by the Claimant and I award this amount of

money."

(e) After holding that Engineer-in-charge decision is final and

binding under clause 5-j of GCC of the Contract, the Learned

Arbitrator without any rate analysis or detail calculation, has

ssm 17 app14.06gp-16.9.16.sxw

awarded Rs.10 lakhs.

18 The Learned Judge stated that "It is, thus, clear that once

the Engineer-in-charge had made his decision, the Learned Arbitrator

had no jurisdiction to interfere and direct the Petitioner to pay higher

amount. It is clear from the award itself that the learned arbitrator has

directed the Petitioner to pay an amount of Rs.10 lakhs without

disclosing any reason and without disclosing the decision making

process, according to which the learned Arbitrator reached the

conclusion that the Respondent is entitled to receive Rs.10 lakh."

19 Under Section 31(3) of the Arbitration Act "The Arbitral

Award shall state the reasons upon which it is based". Under section

28(3) of the Arbitration Act, "In all cases, the Arbitral Tribunal shall

decide in accordance with the terms of the contract." We have already

distinguished the specific agreement between the parties, not to lead

any oral evidence and left the Arbitrator to draw the conclusion. The

Tribunal's decision so taken, therefore, binds all, unless there is any

perversity or misconduct.

     ssm                                                               18           app14.06gp-16.9.16.sxw

    20                   Both   the   learned   counsel   read   and   referred   the   various 

clauses of the contract between the parties, including the clauses so

reproduced above. The Arbitration clauses and specifically, clause

5.j.4 needs to be read in totality. The power of Engineer-in-Charge/

Site-in-charge to make the alterations, additions and/or substitutions

to the specification, to the designs and the work, during the progress

of the work is required to be followed by the contractor. The rates, as

per clause 5.j.4, for any altered, additional or substituted work, if not

agreed, the contractor required to submit within seven days the rate at

which he intends to charge for such class of work, supported by the

analysis so rate or rates claimed. The concerned officer, should

determine the rates on the basis of the prevailing market rates for the

material, as well as, the labour plus 10% overhead and profit and pay

the contractor, accordingly. The rates so fixed, including the opinion

given by these officers would be final and binding on the contractor.

L&T, never agreed for the rates, so fixed for such works. The

correspondences were exchanged accordingly, with reference to the

additional canal at Chain age 205 km. By communication dated 15

April 1998, after analyzing the subject work, it is communicated to

L&T by HPCL that, "You may kindly negotiate with the contractor and

ssm 19 app14.06gp-16.9.16.sxw

settle the claim suitably". The same is supported by the chart of claim

also. HPCL, by communication, as noted, forwarded a cheque of

Rs.4,86,280/- with clear rider to treat it as "full and final settlement of

above claims." This was based upon the detailed workings and revised

statement of account dated 1 May 2006, submitted by HPCL to L&T.

This was admittedly, after the impugned award and the Judgment

passed by the learned Single Judge in the Arbitration Petition of

HPCL. This amount so arrived at by the Engineer-in-Charge/Site-in-

Charge on 15 April 1998,, was final and binding on the contractor and

so not arbitrable, is the case of HPCL. Merely because HPCL

forwarded the cheque of Rs.4,86,280/- after deriving the figure as

noted above on 1 March 2006, that itself shows that this amount was

due and payable to L&T by HPCL for the additional work done, so

recorded above. L&T never accepted this amount. The learned

Arbitrator, after considering the clauses of the agreement between the

parties, apart from the statement and the record so placed, directed

HPCL to pay a lump sum amount of Rs.10 lakhs.

     ssm                                                               20           app14.06gp-16.9.16.sxw

    21                   There is no issue that the Arbitral Award should state the 

reasons above, which is based upon Section 31(3) of the Arbitration

Act, and further that the Arbitral Tribunal should decide in accordance

with the terms of contract under Section 28(3) of the Arbitration Act.

Having once adopted and specifically, agreed to proceed before the

expert Arbitrator without producing any oral evidence and even

without assistance of the advocates, and as the parties have

accordingly proceeded, are bound by the procedure. This, in our

view, is sufficient for the Arbitral Tribunal to decide the Arbitration

disputes, based upon the available documents on record. The decision

taken by the Arbitral Tribunal, was in accordance with the terms of

the contract and specifically agreed terms. The Arbitrator and/or

the Court has always power to decide the claim even in cases where

the decision of Executive Engineer, in such case is final. This was in

view of the Correspondences so referred above, as it was never

agreed or accepted by L&T.

22 Therefore, the assessment and analysis of the expert

Arbitrator, in the present facts and circumstances, ought to have been

accepted. The grant of Rs.10 Lakhs, ought not to have been interfered

ssm 21 app14.06gp-16.9.16.sxw

with by the learned Single Judge on the stated ground of no reason

and/or without disclosing the decision making process to arrive at the

conclusion. The final and binding decision of the officers, of which,

L&T sought inspection, had opposed the rate and the amount so fixed

for the additional work. The clauses so read and referred above,

basically for the running/agreed work, the agreed working situation,

the additional work so ordered and directed and proceeded by L&T

under their supervision, though after raising the contract, in no

way are sufficient to accept the submission of HPCL that the Arbitrator

has no jurisdiction to decide the claim so raised by L&T in this regard.

The dispute was arbitrable by the Arbitrator and rightly decided

accordingly.

23 The correspondence shows that the parties were directed

to negotiate and settle the claims. As the amount could not be settled,

therefore, the dispute for the additional work, as admittedly carried

out, supported by material and resolved by the learned Arbitrator, in

our view, was arbitrable.

     ssm                                                               22           app14.06gp-16.9.16.sxw

    24                   This is not the case, where the objections were raised that 

there were no documents whatsoever in support of the claims filed by

the Appellant. The grounds for challenge so raised, are about the

non-availability of reasons and the decision making process. We have

to consider here, also the fact of not leading oral evidence by the

parties, as agreed and permitted by the Arbitrator, to decide the

disputes, based upon the material so referred above. The experts in

the field, therefore, had decided the issue and awarded the amount of

Rs.10 Lakhs. This, in our view, cannot be stated to be a case of

"award of amount without disclosing the decision making process". This

aspect has been fortified by conduct of HPCL, where the concerned

officers of HPCL, based upon the material and/or documents so placed

on record, without assigning or giving any reasons, fixed the amount

of Rs.4,86,280/-. There was no specific reason provided therein. L&T

refused to accept the said amount. Having once agreed for

payment, based upon the material so referred, the expert's opinion,

as the dispute was arbitrable, overruled the decision of the

officers and awarded Rs.10 Lakhs, therefore, ought not to have

been interfered with by the learned Single Judge. The fact of not

granting even Rs.4,86,280/- by the learned Arbitrator, this itself, is

ssm 23 app14.06gp-16.9.16.sxw

a reason to interfere with the order so passed by the learned Single

Judge, as at least, this amount could have been or should have been

awarded by modifying the award, which admittedly not done in the

present case. The impugned Judgment, therefore, itself required to be

interfered with, at least to this extent. Therefore, the submission so

raised by HPCL is unacceptable.

Claim No.2. Claim towards Additional Liability for repair of coal tar

enamel (CTE) coating by heat shrink sleeves-

25 This claim No.2 towards additional liability for repair of

Coal Tar Enamel (CTE) coating by Heat Shrink Sleeves. The learned

Arbitrator, while awarding the restricted amount of Rs.4,13,00,000/-

i.e. 1/3rd (33%) of the total amount so claimed of Rs.12,39,57,262/-

observed as under:-

a) Most importantly, I find and hold that the very design

criteria/decision to use Coal Tar Enamel for a cross

country pipeline of this size is questionable.

b) It is well known that CTE coated pipes have a tendency

to go "soggy" in open terrain heat conditions while

laying cross country pipelines.

            c)       By the time of this contract, the usage of PERP coated 






     ssm                                                               24           app14.06gp-16.9.16.sxw

pipes was well recognized to be having superior

benefits. However PERP was not eh chosen material.

d) Yet the huge amount of damages leaves me with no

alternative but to hold that part of it is due to the

account of the Respondent due to poor design choice.

e) After careful consideration of the full facts, I am

inclined to award one third of the claim amount to the

Claimant....rounded off sum of Rs.4,13,00,000/- ....the

balance claim is rejected.

26 The learned Single Judge, however, referring to Section 28

of the Arbitration Act and further for the reasons that L&T failed to

lead evidence for the expenses incurred has set aside the award for

this claim. The important aspect in this matter is that there is no

specific challenge to the findings given by the learned Arbitrator

referred above, so also the fact that L&T has done the work under the

supervision, as per the agreement and HPCL has got the benefits of

the same. There is no contra material and/or averments, that no such

work was done by L&T. The submission so made by HPCL, referring

to clause 5.1 and other clauses that it was obligation on the contractor

ssm 25 app14.06gp-16.9.16.sxw

to complete the work without any extra compensation for repair

and/or rectification of defects recorded at the time of "taking over".

There is no specific challenge to the findings given by the learned

Arbitrator about the design criteria/decision to use the CTE for cross

country pipeline of the questionable size. The observation of the

learned Arbitrator that CTE coated pipes have tendency to go "soggy"

in open terrain heat conditions while laying the cross country pipeline.

Admittedly, L&T completed the additional work under the

supervision of HPCL, the rejection of total claim by the learned Judge,

in our view, would untenable. We are not inclined to accept the

submission of HPCL and the reasons so given by the learned Judge of

rejecting claim No.2, as awarded by the Arbitrator in Toto. The party,

one who has incurred the expenses for the additional work and as the

work was admittedly done, is entitled for the expenses so incurred

from the party one who got the benefit out of it. HPCL, having

obtained the benefit, in our view, ought not to have denied the claim.

The learned Judge, ought not to have therefore, rejected the claim , as

done in the present case.

     ssm                                                               26           app14.06gp-16.9.16.sxw

    28                   In view of above, there is no substance in the submission 

of HPCL that the learned Arbitrator was not the General Manager Pipe

Line and the Arbitrator's assignment in the office had nothing to do

with laying and/or design with the Pipe Line. Having once appointed

the expert Arbitrator, who was General Manager (Engineer and

Projects), his expertise assessment ought not to have been discarded

in such fashion.

The observation referred and relied upon by HPCL,

made by the Arbitrator, that the damages occurred due to wrong

handling of the pipes by the claimants and the other companies like

BPCL and IOCL were also using such CTE pipes. The learned Judge

while setting aside the award has not dealt with the subject precisely

as sought to be submitted by the learned counsel appearing for HPCL.

The reasons cannot be added first time in the written submission

before the Appellate Court. The reasons, if not recorded by the

learned Single Judge while setting aside the award on this claim,

which itself, is a factor to interfere with the award. The non-

consideration and/or not providing the reasons to set aside the

expert's opinion/reasons of the Arbitrator and the submission so

ssm 27 app14.06gp-16.9.16.sxw

made, this itself is an additional factor to interfere with the award.

There should have been clear reasoning, as sought to be contended by

HPCL in Appeal, before setting aside the award for want of reasons.

The rejection of claim by the learned Single Judge, so awarded by the

Arbitrator, therefore, requires an interference. The amount awarded

by the Arbitrator, in the facts and circumstances, should have been

retained as HPCL has gained out from the said work done by L&T.

Claim No.4. Claim for additional work for tree cutting and sizing of stem in Vizag port area-

30 So far as Claim No.4, the learned Arbitrator had awarded a

lump sum amount of Rs.2 Lacs for additional work for tree cutting and

sizing of stem in Vizag Port area, though the claim was of

Rs.2,40,724/-.

31 The learned Arbitrator, while awarding this claim by

keeping in mind Clause 5.2 whereby, it was obligatory on the part of

claimant (L&T) to comply with all the requirements of the authorities

at no extra costs to HPCL. It was held that -

ssm 28 app14.06gp-16.9.16.sxw

"it is to be understood that a contractor can only do work

which is reasonably expected out of him. Since the requirement of grubbing the trees, sizing them in

accordance with a particular pattern and then having them transported to a particular place resulted in some extra work and efforts, I am inclined to award this amount".

32 The learned Single Judge, however, has rejected this claim

of amount of Rs.2 lacs for want of no evidence in support of such

claim by L&T. HPCL has also supported the order passed by the

learned Single Judge, even on this part. The L & T's submission is that

such work was part of the contract terms 4.4 (ROW clearing and

grading) for specification of pipe line construction. The extra work so

done was at the behest of the competent Authorities. The reasoning,

therefore, so given by the learned Arbitrator, by considering the nature

and requirements of the contract and as such by interpreting the

clauses, ought not to have been rejected. The findings, therefore,

given by the learned Judge of setting aside the claim, is required to be

reconsidered in the background of the litigation and the procedure,

which the parties have followed to proceed with the Arbitration.

Claim No.9.Claim for additional work involved due to issue of Optical Fiber Cable of shorter length-

     ssm                                                               29           app14.06gp-16.9.16.sxw



    33                   So far as claim No.9 is concerned, the learned Arbitrator 




                                                                                                   

had considered the claim of L&T whereby, the amount of

Rs.28,78,713/- was claimed for additional work involved due to issue

of Optical Fiber Cable of shorter length. It is clear from the record

that HPCL had given OFC of 2 kilometer length, but a small number of

1 kilometer length of OFC was given as the repeat station, are not

exactly at 2 kilometer distance. It is recorded even by HPCL that

actual cable required was found to be around 360 kilometers, hence,

about 180 number of joints should have been required. However, only

174 number of joints have been carried out by L&T. Having noted the

above facts and that resulted into additional costs, the learned

Arbitrator, being expert in field, keeping in mind the actual work,

additional work/expenses required to be incurred by L&T, had granted

Rs.15,10,000/-, though claimed more. Therefore, once the issue of

OFC shorter length is not in dispute, that resulted into increase in

joints and therefore awarded the amount, though not as per the

contract terms as observed, but for the fact of an additional costs, so

incurred and for the extra work done, this was also not the claim

which ought to have been rejected by the learned Single Judge on the

same foundation of no evidence and/or any evidence. The additional

ssm 30 app14.06gp-16.9.16.sxw

expenses incurred, so referred above, because of supply of shorter

length of OFC, which the Arbitrator, being an expert person in the

field, realizing the actual additional expenses incurred, had restricted

the amount that, also ought not to have been interfered with by the

learned Single Judge. Merely because, HPCL on 15 July 1998,

rejected the claim of additional work, that itself, should not have

been the reason to deny the claim so awarded by the learned

Arbitrator in the background so referred above, specifically in the

recorded fact of number of joints, required to be carried out by L&T.

34 The Supreme Court, reiterated the principle of Section 34

of the Arbitration Act and the scope of Court to interfere with the

findings given by the Arbitrator. In the present case, as recorded

above, the expert Arbitrator in the field appointed by HPCL

themselves. The parties, as recorded, proceeded with the Arbitration

without leading any oral evidence and proceeded through their

respective representatives. The scope of Section 34 of the Arbitration

Act, in the present case, in view of the interference ought not to have

been made. ( Associate Builders Vs. Delhi Development Authority 7). It

is also settled that, another view even if possible, that should not have 7 AIR 2015 SC 620

ssm 31 app14.06gp-16.9.16.sxw

been the reason to interfere with the award. ( Union of India Vs. Moti

Enterprises & Anr.8).

Claim No.15- Claim for additional work executed in connection with civil works for isolation valve near the station outside the battery limits-

35 In claim No. 15, the Arbitrator has granted Rs.10,17,361/-

for additional work executed in connection with civil works for

isolation valve near the station outside the battery limits, as claimed

by L&T, based upon the material placed on record by them and

supporting facts and circumstances, so recorded by the Arbitrator.

36 Clause 10 of schedule of rates was read and referred by

the learned counsel appearing for HPCL and also submitted that the

entire scope of work, as shown in the diagram, is within the scope of

contract of L&T. The learned counsel read and referred even the

ground showing the scope of pipe line laying contract and pointed out

from their respective points of view, the issue about battery limits as

defined. The drawing shows, as contended by the learned counsel for

HPCL that the scrapper launcher from Vishakhapattnam dispatch

station to scrapper receiver station at Vijaywada receiving terminal.

    8         2003 Arb.LR 229 (Bom)






     ssm                                                               32           app14.06gp-16.9.16.sxw

The Arbitrator's findings, after rejected the contention of the HPCL

that the civil work pertaining to isolation valve near the station would

be within the scope of work of the claimant and also within the

battery limits, it is observed that since the drawing shows that it is

outside the battery limits, they had to pay for this extra work. The

observation, which is relevant here, that there is no argument made

regarding the amount to be paid as claimed by L&T and therefore,

awarded the total amount as claimed.

37 The amount was awarded by the learned Arbitrator again

for the extra work done by L&T. There is no denial to the fact that the

extra work was done. The submission of HPCL is that the work in

question, was well within the contract as awarded to L&T within the

scope of work and therefore, there is no question of claiming extra

amount, was not accepted. The observation relied upon by HPCL and

as recorded by the learned Judge that, "the work was outside the

battery limits according to the drawing", is correct statement, but in

which context the statement so made was not considered. The

learned Judge, ought not to have re-appreciated the findings,

including the scope of contract and the payment so awarded by the

ssm 33 app14.06gp-16.9.16.sxw

learned Arbitrator for the extra work. (Associated Builders (Supra)

and Venkatesh Construction Company Vs. Karnataka Vidyuth

Karkhane Limited (Kavika)9.

Claim No.16-Claim for additional work for laying of pipeline for Pullivagu Canal and Claim No.1-Claim for Additional work for canal at

Chainage 205 km (introduced by irrigation dept.)-

38 In claim No.16, L&T has also claimed for additional work

for laying of pipe line for Pullivagu Canal for Rs.4,67,425/-. This

claim is in any way, connected with claim No.1.

39 There is no serious issue that the claimant had to de-

mobilize, as instruction for anti-buoyancy measure was not given,

though, asked by letter dated 6 April 1997. HPCL could not deny this

de-mobilization of these resources. The claim was, therefore, for

incurring additional expenses. L&T had received the payment for laying

anti-buoyancy measure. The issue, therefore, is of laying and anti-

buoyancy measure, which have been paid in relevant items of SOR

specifically, when L&T denied the same and claimed for extra work. The

learned Arbitrator, after considering the rival contentions and the work

actually done for laying of pipe line, had opined that the Pullivagu is

9 2016(1) SCALE 409

ssm 34 app14.06gp-16.9.16.sxw

a canal crossing. This was also on the foundation that the permission

was required to be obtained from the Competent Authority for the

same and was the part of record. The issue, therefore, is canal

crossing or not, so raised by HPCL, also untenable. It was also

observed by the learned Arbitrator, that HPCL, while dealing with

Claim No.1, admitted indirectly that the claim amount of

Rs.4,67,245/- was reasonable. The learned Single Judge, ought not

to have interfered with the award so passed in favour of L&T. The

submission of prompt reply, in view of the findings given by the

learned Arbitrator, is of no assistance to interfere with the award so

passed. Here also, the additional work actually done was not in

dispute and so also the amount so incurred.

Claim No. 19 and Counter-Claim- Claim for release of Liquidated

Damages-

40 This claim No.19 is revolving around the contract clauses

of penalty and liquidated damages (LD). The relevant clause 10 of

penalty and other relevant clauses 2.18, 5.1, 7.1 are as under:-

"Clause 10: Penalty-

In case of delay in completing the work beyond the period of contract the contractor shall be liable to pay penalty at the rate of 0.5% of the total contract value for every week

ssm 35 app14.06gp-16.9.16.sxw

or part thereof of the delay subject to a maximum of 5% of the total contract value. The penalty shall be recovered by the Owner out of the amounts payable to the Contractor or

from the Guarantees or Deposits furnished by the Contractor or the Retention Money retained from the Bills

of the Contractor, should the amount of penalty is not recoverable or recovered in any manner in part or in full, the same shall be payable by the Contractor on demand by the owner with 24% p.a. interest till the date of payment."

"Clause 2.18:

The "Work" shall mean the works to be executed in

accordance with the Contract or part thereof as the case may be and shall include extra, additional, altered or

substituted works as may be required for the purposes completion of the work contemplated under the Contract."

"Clause 5.1: COMPLETION OF WORK AND COMPLETION CERTIFICATE.

"As soon as the work is completed in all respects, the

contractor shall give notice of such completion to the site-

in-charge or the Owner and within thirty days of receipt of such notice the site in charge shall inspect the work and shall furnish the contractor with a certificate of completion indicating:

a) defects, if any, to be rectified by the contractor

b) items, if any, for which payment shall be made in reduced rates.

                 c)        the date of completion.........."

                 "7.1 General:-

Commissioning of pipeline shall be considered completed when the line is charged with the product at operating

ssm 36 app14.06gp-16.9.16.sxw

pressure after precommissioning is completed and the total system operated at normal operating parameters for a minimum period of 72 hours.

Contractor shall submit a detailed commissioning

procedure for company's approval."

41 The relevant findings of the Arbitrator to Claim No.19 are

as under:-

a) A deeper look at the entire facts reveals that though the

work was completed as per the contract only on 20

August 1998 (and there is no dispute on this), the

pipeline had been laid and given for charging of

water/product on 10 May 1998 and so charged with

water and then product on 11 May 1998.

b) However the Respondent's main requirement of

petroleum transportation, through pipe line was

commenced/achieved on 11 May 1998 itself. The

Respondent could not suffered loss beyond that date.

c) I find that the delay committed by the Claimant is only

11 days.

42 Both the learned counsel read and referred their respective

ssm 37 app14.06gp-16.9.16.sxw

submissions from their perceptive. There is no issue that the time was

extended for various reasons, including the defaults of HPCL. There is

no issue that the penalty clause comes into the operation when there

is a delay in completing the work beyond the period of contract. The

learned Arbitrator while awarding the claim had given various

reasons. The basic reasons are -

a) I accept the case of the Respondent that the Claimant was

responsible for the delay in completion of the work even

by the extended date of completion.

b) Decision of the Consultant in regard to the extension is

final and binding and therefore, not arbitral.

c) The claimant accepted the completion certificate without

any demur or protest.

d) The actual work got completed on 20 August 1998 hence,

prima facie, the application of full liquidated damages by

the Respondent, at first glance looks correct.

e) The levy of penalty is as per Clause 10 of GTC and letters

dated 6 December 1997 and 23 April 1998, fully

supported the action of Respondent in levying penalty.

            f)      The   Respondent   also   demonstrated   the   losses   that   are 






     ssm                                                               38           app14.06gp-16.9.16.sxw

suffered by them on account of delay hence, there is

losses to the Respondent by various means including

ideal investment etc.

g) The contention of the claimant regarding waiver of

penalty, are not correct.

h) It may be technically correct that actual work was

completed in all respects as per the contract only on 20

August 1998, but the pipe line had been laid and given

for charging of water on 10 May 1998 and then product

on 11 May 1998. The Respondent could not have

suffered loss beyond that date.

i) The Respondent have shown that even if we assume the

delay of 10/11 days, they had suffered loss in excess of

the entire liquidated damages amount.

j) After holding at above, the learned Arbitrator states

"Thus I find and hold that delay committed by the

Claimant is only 11 days and I also find that the damages

are proved by the Respondent far in excess of the liquidated

damage amount and hence, I hold and award that the

Respondent is entitled to levy only 1% of the contract value

ssm 39 app14.06gp-16.9.16.sxw

as liquidated damages and balance 4% of the contract

value must be returned to the Claimant".

k) The Respondent is directed to pay back to the claimant a

sum of Rs.2,01,60,000/-.

43 The learned Single Judge, so far as this claim is concerned

as there was no proper ground raised by HPCL in the Petition and as it

unable to challenge the findings of facts, except by making allegations,

has maintained the award passed by the learned Arbitrator. The

learned counsel appearing for L&T, therefore, supported this part of

the award by relying on Hudson's on Building and Engineering

Contracts-Eleventh Edition and ONGC Vs. Saw Pipes.10 The learned

counsel appearing for HPCL however, challenged this part of the order.

44 HPCL submitted that LD clause is applicable only if there is

a delay in completing the work beyond the period of contract. The

work was completed on 20 August 1998, as pre-contract the pre-

commissioning was done on 11 May 1998, by charging water on 10

May 1998, and for product on 11 May 1998. HPCL has submitted

their evidence before the learned Arbitrator that there was only 10/11 10 2003(51)-ARBLR-5-SC

ssm 40 app14.06gp-16.9.16.sxw

days delay and they had incurred losses to the extent of Rs.2.52

crores. Therefore, the learned Single Judge, as well as, the Arbitrator

could not have awarded this claim for liquidated damages. This is in

the background that the Engineer-in-Charge has given a detail analysis

and assessed the quantum and hence his decision ought to have been

treated as final and binding. The Arbitrator had no jurisdiction to

decide and reassess the issue. We are not inclined to accept the

submission of HPCL, as the learned Single Judge has upheld the

reasons and the award so granted by the learned Arbitrator, by

accepting the findings given by the learned Arbitrator about the

pipe line so charged with the product on 11 May 1998, was

factually incorrect.

45 The learned counsel appearing for HPCL tried to

distinguish the Judgments cited by the learned counsel appearing for

L&T, mainly on the ground of clause 5.j.4 - the contract terms

whereby, the decision being final and binding and therefore, not

arbitrable. For the reasons already noted that such disputes are

arbitrable and therefore, rightly considered by the learned Arbitrator

and the learned Single Judge. We see there is no reason to interfere

ssm 41 app14.06gp-16.9.16.sxw

with the same, as this part of award is well within the framework of

law and the record.

Claim No.21- Claim for release of disputed rebates under the Contract. (3 Items):-

46 Claim No.21 consists of 3 items for release of disputed

rebates under the contract. The Arbitrator's findings in this regard of

Item Nos. (i), (iii) and (iv) are as under:-

Claim No.21, item No.(i)-

a) What has been found missing by the

Respondent/consultant is that they have not taken into

account the special nature of the E-7010 electrodes,

which were substituted for E-8010 electrodes.

b) These Electrodes, namely the E-7010 were not the

normal E-7010 electrodes but, having 77,000 psi UTS.

Thus, this UTS was far above the normal base metal

UTS of 70,000 psi. Hence this aspect not having taken

into account, there really cannot be any price

differential between this E-7010 electrodes used in the

pipe line and E-8010 originally contemplated under the

ssm 42 app14.06gp-16.9.16.sxw

contract.

c) Hence the Respondent cannot maintain this rebate.

Claim Allowed Rs.6,48,013/-

Claim No.21, item No.(iii)-

a) I find that while it may be contractually correct to seek

a rebate, it can be seen that the deletion of this item

was by the Respondent to expedite the commissioning.

b)

The Claimant had mobilized and got ready.

c) They would certainly have incurred expenses in

mobilizing and readiness for swabbing.

d) Even though the work was deleted, the Claimant has

incurred some expenditure.

Claim Allowed Rs.3,60,280/-

Claim No.21, item No.(iv)-

Having considered the above documents and the stand

taken by the parties, I find that such a deduction is not

in the proper spirit of the contract.

Claim Allowed Rs.60,71,920/-

     ssm                                                               43           app14.06gp-16.9.16.sxw




    47                   The learned Single Judge accepted HPCL's submission that 




                                                                                                   

the decision of the Engineer-in-Charge is final and therefore, the

Arbitrator has no jurisdiction to interfere with the calculation made by

the Engineer-in-Charge. The Arbitrator was duty bound to make the

award in accordance with the contract. There was no question of

making an equitable consideration. The learned Judge, therefore,

rejected the award granted in favour of L&T, solely on the ground that

it is not arbitrable.

48 The submission made by the learned counsel appearing for

L&T with regard to item No.(iii) is made in support of the award of

claim of all these items by the Arbitrator. The same arguments and

the Judgments so cited read and referred, with submission to retain

the order passed by the learned Arbitrator. This is again on the

foundation that L&T had incurred extra expenses in mobilization. The

deletion of item, at the instance of Respondent HPCL to accept the

commission was not in dispute, therefore, the claim so made cannot

be stated to be beyond the contract.

     ssm                                                               44           app14.06gp-16.9.16.sxw




    49                   We  are  inclined  to  observe  that  the  Arbitrator   had 




                                                                                                   
    not   gone   beyond   the   contract   and   he     had   to adjudicate this 




                                                                           
    claim   as   consultant.   The   Arbitrator   had   taken   note   of     the  

special nature of E-7010 electrodes, which was substituted for E-

8010 electrodes. The price difference, so recorded by the learned

Arbitrator, is required to be maintained. There was no reason

to interfere with the expert's decision on the same. The

decision of the learned Single Judge, therefore, in this claim is

unsustainable.

Scope and Power of Court under Section 34 of the Arbitration Act-

50 The Judgments cited by the learned counsel appearing for

L&T in support of their submissions revolving around Section 34 of

the Arbitration Act and some of them are recent Supreme Court

Judgments, reiterating the law on the subjects are also distinguished.

51 As the issue is settled and re-iterated by the Apex Court

and, therefore, being principle of law, we are inclined to reproduce the

ssm 45 app14.06gp-16.9.16.sxw

same for deciding the present Appeals.

52 In Navodaya Mass Entertainment Ltd vs. I. M. Combines 11,

it is observed as under:-

"8 In our opinion, the scope of interference of the

court is very limited. Court would not be justified in reappraising the material on record and substituting its own view in place of the arbitrator's view. Where there is an error apparent on the face of the record or the

arbitrator has not followed the statutory legal position, then and then only it would be justified in interfering

with the award published by the arbitrator. Once the arbitrator has applied his mind to the matter before him, the court cannot reappraise the matter as if it were an

appeal and even if two views are possible, the view taken by the arbitrator would prevail - see Bharat Coking Coal Ltd. v. L.K. Ahuja, [2004] 5 SCC 109; Ravindra & Associates v. Union of India, [2010] 1 SCC 80; Madnani

Construction Corporation (P.) Ltd. v. Union of India ,

[2010] 1 SCC 549; Associated Construction v. Pavanhans Helicopters Ltd., [2008] 16 SCC 128 and Satna Stone & Lime Company Ltd. v. Union of India, [2008] 14 SCC 785."

53 Recently, in Associate Builders (Supra), the Apex Court has

elaborated those principles in following words:-

"15. This Section in conjunction with Section 5 makes it clear that an arbitration award that is governed by part I of the Arbitration and Conciliation Act, 1996 can be set aside only on grounds mentioned Under Section 34(2) and (3), and not otherwise. Section 5 reads as follows:-

    11        (2015) 5 SCC 698






     ssm                                                               46           app14.06gp-16.9.16.sxw



                            "5.   Extent   of   judicial   intervention.-

Notwithstanding anything contained in any other

law for the time being in force, in matters governed by this Part, no judicial authority shall intervene

except where so provided in this Part."

16 It is important to note that the 1996 Act was enacted to replace the 1940 Arbitration Act in order to

provide for an arbitral procedure which is fair, efficient and capable of meeting the needs of arbitration; also to provide that the tribunal gives reasons for an arbitral award; to ensure that the tribunal remains within the limits of its

jurisdiction; and to minimise the supervisory roles of courts in the arbitral process.

17 It will be seen that none of the grounds contained in Sub-clause 2(a) of Section 34 deal with the

merits of the decision rendered by an arbitral award. It is only when we come to the award being in conflict with the public policy of India that the merits of an arbitral award are to be looked into under certain specified

circumstances."

"24 In DDA v. R.S. Sharma and Co., (2008) 13 SCC 80, the Court summarised the law thus:

21. From the above decisions, the following principles emerge:

(a) An award, which is

(i) contrary to substantive provisions of law; or

(ii) the provisions of the Arbitration and Conciliation Act, 1996; or

(iii) against the terms of the respective

ssm 47 app14.06gp-16.9.16.sxw

contract; or

(iv) patently illegal; or

(v) prejudicial to the rights of the parties;

is open to interference by the court under Section 34(2) of the Act.

(b) The award could be set aside if it is contrary to:

(a) fundamental policy of Indian law; or

(b) the interest of India; or

(c) justice or morality.

(c) The award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court.

(d) It is open to the court to consider whether the award is against the specific terms of

contract and if so, interfere with it on the ground that it is patently illegal and opposed to the public policy of India."

"29. It is clear that the juristic principle of a "judicial approach" demands that a decision be fair, reasonable and objective. On the obverse side, anything arbitrary and whimsical would obviously not be a determination which would either be fair, reasonable or objective."

"30. The audi alteram partem principle which undoubtedly is a fundamental juristic principle in Indian law is also contained in Sections 18 and 34 (2)(a)(iii) of the Arbitration and Conciliation Act. ......"

"31. The third juristic principle is that a decision

ssm 48 app14.06gp-16.9.16.sxw

which is perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where:

(i) a finding is based on no evidence, or

(ii) an Arbitral Tribunal takes into account something irrelevant to the decision which it arrives at; or

(iii) ignores vital evidence in arriving at its decision,

such decision would necessarily be perverse."

"32. A good working test of perversity is contained in two

judgments. In Excise and Taxation Officer-cum-Assessing Authority v. Gopi Nath & Sons (1992 Supp. (2) 312, it was held (SCC p.317, para 7):

7. ...It is, no doubt, true that if a finding of fact is arrived at by ignoring or excluding relevant material or by taking into consideration irrelevant

material or if the finding so outrageously defies

logic as to suffer from the vice of irrationality incurring the blame of being perverse, then, the finding is rendered infirm in law."

In Kuldeep Singh v. Commr. of Police (1999) 2 SCC 10 : 1999 SCC ( L & S) 429, it was held: (SCC p.14 para 10)

"10. A broad distinction has, therefore, to be maintained between the decisions which are

perverse and those which are not. If a decision is arrived at on no evidence or evidence which is thoroughly unreliable and no reasonable person would act upon it, the order would be perverse. But if there is some evidence on record which is acceptable and which could be relied upon, howsoever compendious it may be, the conclusions

ssm 49 app14.06gp-16.9.16.sxw

would not be treated as perverse and the findings would not be interfered with."

"34 It is with this very important caveat that the two fundamental principles which form part of the fundamental

policy of Indian law (that the arbitrator must have a judicial approach and that he must not act perversely) are to be understood.

Interest of India

35. The next ground on which an award may be set aside is that it is contrary to the interest of India. Obviously, this

concerns itself with India as a member of the world community in its relations with foreign powers. As at

present advised, we need not dilate on this aspect as this ground may need to evolve on a case-by-case basis.

Justice

36. The third ground of public policy is, if an award is against justice or morality. These are two different concepts

in law. An award can be said to be against justice only

when it shocks the conscience of the court. An illustration of this can be given. A claimant is content with restricting his claim, let us say to Rs. 30 lakhs in a statement of claim before the arbitrator and at no point does he seek to claim

anything more. The arbitral award ultimately awards him Rs. 45 lakhs without any acceptable reason or justification. Obviously, this would shock the conscience of the court and the arbitral award would be liable to be set aside on the ground that it is contrary to "justice".

"42.3 (c) Equally, the third subhead of patent illegality is really a contravention of Section 28(3) of the Arbitration Act, which reads as under:

"28. Rules applicable to substance of dispute.-(1)-

ssm 50 app14.06gp-16.9.16.sxw

(3) In all cases, the Arbitral Tribunal shall decide

in accordance with the terms of the contract and shall take into account the usages of the trade applicable to

the transaction."

This last contravention must be understood with a caveat. An Arbitral Tribunal must decide in accordance with the

terms of the contract, but if an arbitrator construes a term of the contract in a reasonable manner, it will not mean that the award can be set aside on this ground. Construction of the terms of a contract is primarily for an

arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something

that no fair minded or reasonable person could do."

"59. The Arbitrator has dealt with this clause in detail

and has construed and applied the same correctly while dealing with Claims 2, 3 and 4 and has obviously not applied the said clause to Claims 9, 10, 11 and 15 as no occasion for applying the same arose. The award cannot be

faulted on this ground."

"63. The appeal is, therefore, allowed and the judgment of the Division Bench (DDA V. Associate Builders, 2012 SCC OnLine Del 769) is set aside. The judgment of the Single

Judge [DDA V. Associate Builders, OMP No. 304 of 2005, Order dated 3-4-2006 (Del)] is upheld and consequently, the arbitral award dated 23-5-2005 is as a whole upheld. There will be no order as to costs."

The Award can be modified by applying even doctrine of severability:-

The issue about the Power of Court to modify the award by

applying the doctrine of severability is settled. The learned Judge in

this case itself maintained the Award, in reference to claim No.19 but

ssm 51 app14.06gp-16.9.16.sxw

rejected the other claims and accordingly modified the award.

54 A Full Bench of this Court in R. S. Jiwani (M/s.) v. Ircon

International Ltd, Mumbai12 after considering the judgments of the

Supreme Court settled the issue that the award can be modified in

para 38 which reads thus:

"38 For the reasons afore recorded, we are of the

considered view that the dictum of law stated by the Division Bench in the case of Ms. Pushpa Mulchandani

(supra) is not the correct exposition of law. We would predicate the contrary view expressed by different Benches of this Court for the reasons stated in those

judgments in addition to what we have held herein- above. It is difficult to prescribe legal panacea which, with regard to the applicability of the principle of severability can be applied uniformally to all cases. We

find that the principle of law enunciated by us herein- above is more in comity to object of the Act, legislative

intent, UNCITRAL Model Law and will serve the ends of justice better. Thus, we proceed to record our answers to the questions framed as follows:-

1. The judicial discretion vested in the court in terms of the provisions of Section 34 of the Arbitration and Conciliation Act, 1996 takes within its ambit power to

set aside an award partly or wholly depending on the facts and circumstances of the given case. In our view, the provisions of Section 34 read as a whole and in particular Section 34(2) do not admit of interpretation which will divest the court of competent jurisdiction to apply the principle of severability to the award of the Arbitral Tribunal, legality of which is questioned before 12 2010 (1) Mh. L. J. 547

ssm 52 app14.06gp-16.9.16.sxw

the court. The Legislature has vested wide discretion in the court to set aside an award wholly or partly, of course, within the strict limitations stated in the said

provisions. The scheme of the Act, the language of the provisions and the legislative intent does not support the

view that judicial discretion of the court is intended to be whittled down by these provisions.

2. The proviso to Section 34(2)(a)(iv) has to be read

ejusdem generis to the main section, as in cases falling in that category, there would be an absolute duty on the court to invoke the principle of severability where the matter submitted to arbitration can clearly be

separated from the matters not referred to arbitration and decision thereupon by the Arbitral Tribunal."

Admittedly, additional work done- entitlement for extra amount:-

55 Most of the claims of L&T, in the present case in hand, are

for the extra/additional work, than the work awarded. The amount so

claimed by L&T is for the costs of additional work so completed, under

the supervision of HPCL. The additional work as done is not in

dispute. The Arbitrator, therefore, based upon his experience and

knowledge of the nature of the work, awarded the lump sum amount

for such extra work. The main contention of HPCL throughout was, as

recorded by the learned Arbitral Tribunal and the learned Judge, and

even as per the submission made before this Division Bench, that

though extra/additional works was done, but same was within the

ssm 53 app14.06gp-16.9.16.sxw

scope and conditions of the main contract and therefore, there was no

question of extra payment, L&T was under obligation to perform these

additional part even if any, to complete the project in time. The

finding given by the learned Arbitrator with regard to the

additional/extra work based upon the material and the documents

placed on record, though no oral evidence was lead by the parties, as

agreed, the same ought not to have been interfered with by the

learned Judge, HPCL was aware of the fact of additional/extra work,

but to deny the payment for the same, in our view, was wrong.

56 It is held by the Supreme Court in Venkatesh construction

Company (Supra) that:-

"14 ..................When the evidence and material clearly depict the change of nature of work involved and when the extra work to be done was also admitted by DW-1,

parties cannot be expected to go for a revised agreement/contract. Moreover, having regard to the fact that the work was to be completed within a specified time-frame, the parties cannot be expected to go for a second round of negotiation and re-frame the

terms and conditions of the work. While so, the High Court was not right in placing reliance upon Clause 11 of the contract to reverse the findings of fact recorded by the trial court."

"16 The Appellate Court may not interfere with the finding of the trial court unless the finding recorded by the trial court is erroneous or the trial court ignored the

ssm 54 app14.06gp-16.9.16.sxw

evidence on record. The High Court reversed the decree passed by the trial court without discussing oral and documentary evidence and several grounds raised

before the trial court. The High Court veered away from the main issue and went on to elaborate on the

law of arbitration and the mode of setting aside the arbitral award under Section 34 of the Arbitration Act, which in our view, was not warranted. Without considering the oral and documentary evidence, the

High Court erred in interfering with the factual findings recorded by the trial court and the impugned judgment is liable to be set aside."

Conclusion:-

57 We are of the view that, therefore, in the present case, the

learned Judge ought not to have interfered with arbitration decision

on the findings of facts by interpreting the provisions of the contract

in the background of his special knowledge/expertise in the field. The

learned Judge's total rejection of the claim of additional work done, as

awarded by the learned Arbitrator is unjust and contrary to the

record. This is in the background, when HPCL is not in position to

content that no extra work was done by L&T. There is an error in the

impugned judgment to this extent of reversing the award for all the

extra works by stating it to be within the scope of the contract.

Considering the scope and purpose of Section 34 of the Arbitration Act

read with the power of learned Judge to interfere with the finding of

ssm 55 app14.06gp-16.9.16.sxw

facts, arrived at by the learned Arbitrator based upon the possible

agreed method to deal with the claims and by taking the reasonable view

by keeping in mind the nature of the work, based upon the contract,

ought not to have been quash and set aside. The learned Judge has

maintained the award of liquidated damages in the background itself.

Remand and Power of Appellate Court under Section 37 of the

Arbitration Act-

We have to keep in mind the scope and object of the

Arbitration while deciding the Appeal arising out of Judgment on

Section 34 Petition of the learned Single Judge, where the award

passed by the Arbitral Tribunal may be confirmed or reversed or

modified. The scope of Section 34has been elaborated. The Court, if

not to interfere with the decision given by the Arbitrator, unless there

is perversity and illegality, then the Appellate Court needs to test the

decision of the learned Judge if it is against the law (supra). We find

no perversity and illegality in the Award. There was no case to

interfere with the Award. We, therefore, inclined to remand the

matter to the learned Single Judge, as this will give an opportunity to

all to deal with the claims again, except the LD claim. There will be

fresh reasons on these remaining claims/decisions, so that the

ssm 56 app14.06gp-16.9.16.sxw

Appellate Court may re-consider it in accordance with law, if

necessary.

    59                   Resultantly, the following order:-

                                                              ORDER




                                                                              
            a)           Judgment   and   order   dated   16   November   2005, 

passed by the learned Single Judge is quashed and

set aside, except claim No.19. The order on Claim

No.19 is maintained.

b) The Arbitration Petition No. 449 of 2003 is restored

and remanded back to the learned Single Judge for

reconsideration. The learned Single to reconsider

the same within three months from today, in view

of above order/observation.

            c)           There shall be no order as to costs.                              





              (G.S. KULKARNI, J.)                                           (ANOOP V. MOHTA, J.)









 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter