Citation : 2016 Latest Caselaw 6346 Bom
Judgement Date : 25 October, 2016
913.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 4703 OF 2016
1. Nandkumar s/o Kundlik Wagh
Age 59 years, Occu: Agri
R/o Adul (Kh), Tq. Paithan
Dist. Aurangabad.
2. Satish s/o Nandkumar Wagh ... Petitioners
Age 30 years, Occu: Agri
R/o Adul (Kh), Tq. Paithan
Dist. Aurangabad.
VERSUS
1. Union of India
Through Its Secretary,
Ministry of Road Transport and
Highways, New Delhi
2. Project Director,
Project Implementation Unit,
B-23, Kamgar Chowk,
CIDCO, N-4, aurangabad 431 003
3. The Competent Authority (Land
Acquisition)
Indian National Highway No.211
Deputy Colelctor, Land
Acquisition, Krushna Khore Vikas
Mahamandal, Aurangabad.
4. The State of Maharashtra, ... Respondents.
Through its Principal Secretary,
Public Works Department,
Mantralaya, Mumbai 400 032
Mr. S. S. Tope, Advocate for the petitioner,
Mr. S. B. Talekar, Advocate for respondent NO.2,
Mr. B. V.Virdhe, AGP for respondent No.4,
CORAM : S. V. GANGAPURWALA &
K. L. WADANE, JJ.
DATE : 25th October, 2016
1/4
::: Uploaded on - 27/10/2016 ::: Downloaded on - 28/10/2016 00:49:07 :::
913.odt
JUDGMENT (Per S.V. Gangapurwala, J):
1. Rule. Rule made returnable forthwith. With
consent of parties, the petition is taken up for final
disposal
2. Mr. Tope, the learned counsel for the
petitioners submits that the land of the petitioners
was acquired under the award dated 01.09.2014.
Compensation is awarded, however, not in accordance
with the provisions of the Right to Fair Compensation
and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013. The said Act of 2013 has
been made applicable to the acquisition under the
National Highways Act pursuant to Circular dated
03.02.2016 from 01.01.2015 and if compensation is not
paid prior to 31.12.2014, though the award is passed
prior to the said date, compensation is required to be
paid as per the new Act of 2013.
3. According to the learned counsel for the
petitioners, compensation was paid to the petitioners
on 28.01.2015 by R.T.G.S. in the accounts of the
petitioners. The learned counsel submits that even the
Highways Authority has taken a decision on 28.09.2016
to award compensation as per the Act of 2013.
913.odt
4. Mr. Talekar, the learned counsel for the
respondent National Highways Authority submits that on
01.11.2014, the Competent Authority (Acquisition) had
directed to the petitioners to submit account
particulars and the documents for depositing the
amount. The same was much prior to 31.12.2014. It was
delay on the part of the petitioners in forwarding the
documents and information as solicited by letter dated
1.11.2014. As such, the compensation is rightly paid.
5.
We have heard the learned AGP also.
6. We have gone through the affidavit in reply
filed by the Special Land Acquisition Officer. The
Special Land Acquisition Officer has categorically
admitted in his affidavit in reply that the petitioners
are entitled for the compensation as per the Act of
2013 and the same is required to be done.
7. We need not go into other aspects of the matter
in view of the letter dated 28.09.2016 issued by the
National Highways Authority, whereby, it has taken a
decision to grant escalation in the amount of
compensation awarded. The award pursuant to which the
land of the petitioners is acquired is also included
in the same. The said letter is placed on record by the
913.odt petitioners. As the National Highways Authority has
taken a decision to grant escalation in compensation as
per the Right to Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act,
2013, we need not debate into the merits of the
contentions.
8. The amount has been deposited as per the award
dated 01.09.2014 in the accounts of the petitioners on
28.01.2015.
9. Considering the aforesaid conspectus of the
matter, the respondents shall calculate the
compensation as per the Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013 in respect of the award dated
01.09.2014 with regard to the land of the petitioners.
The said exercise shall be done expeditiously,
preferably within six months from today and the amount
be paid to the petitioners.
10. Rule is made absolute accordingly. No costs.
(K. L. WADANE, J.) (S. V. GANGAPURWALA, J. ) JPC
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!