Citation : 2016 Latest Caselaw 5992 Bom
Judgement Date : 14 October, 2016
dgm 1 Judgment-app260.06.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 260 OF 2006
IN
ARBITRATION PETITION NO. 29 OF 2005
WITH
NOTICE OF MOTION (L) NO. 1368 OF 2013
IN
APPEAL NO. 260 OF 2006
1 Maharashtra State Electricity Board
through its Chairman, having office at
Prakashgad, Bandra (E), Mumbai - 400 051
2
Maharashtra State Distribution Company Ltd.
A Public Limited Company incorporated and
registered under the provisions of the
Companies Act, 1956, (I of 1956) having its
Office at Prakashgad, Bandra (E), Mumbai-51. .... Appellants
Vs
Maharashtra Conductor Association (SSI)
having its office at 45, Ratan Jyoti Industrial
Estate, Irla Lane, Vile Parle (W), Mumbai - 56
through its President, Shri Jitendra Dalal
having address at Kamal Kunj, First Floor,
Block No. 8, Vithalbhai Patel Road,
Andheri (West), Mumbai. .... Respondent
Mr. Prashant Chavan, Mr. Nirav Shah, Ms. Reshma Nathani i/b Little &
Co., for the Appellants.
Mr. S.S. Voditel, for the Respondent.
CORAM: ANOOP V. MOHTA AND
G. S. KULKARNI, JJ.
RESERVED ON : 12 July 2016 PRONOUNCED ON : 14 October 2016
dgm 2 Judgment-app260.06.odt
JUDGMENT (PER - ANOOP V. MOHTA, J.):-
The Appellants being aggrieved by the judgment/order
passed by the learned Single Judge, dated 27 September 2005
whereby the Award passed by the learned Arbitrator dated 30 April
2004 is set aside only restricted to Point Nos. 4, 8 and 11, as
challenged.
The important part of the learned Single Judge order is as
under :
In my opinion, therefore, it cannot be said that the Award is satisfied and therefore, the petition is not maintainable.
In the result therefore, the present petition succeeds and is allowed. The findings recorded and the Award made by the
learned Arbitrator in the impugned Award against point no. 8 is set aside. The Award made by the learned Arbitrator in so far as interest at the rate of 10% per
annum for the period subsequent to 26.04.2001, is set aside. Similarly, the Award made against point no. 11 by the learned Arbitrator is set aside. The respondent is directed to pay cost of this petition to the petitioner as incurred by the petitioner.
It is also observed in para 5 as under :
"5 .....The fixation of rate of interest at 10% per annum without disclosing any reason in the aforesaid circumstances, is totally unjustified and therefore, the Award in this regard is liable to be set aside. Section 31
dgm 3 Judgment-app260.06.odt
(7)(b) of the Arbitration & Conciliation Act, 1996 lays down that if no interest is awarded by the Arbitrator then for the period from the date of the award till the
date of payment, interest at the rate of 18% per annum can be recovered. Therefore, it is for the petitioner to
decide what course of action they want to adopt."
3 The background of this litigation, is as under:
The appellants floated two tenders being Tender No. T-
0901 and Tender No. T-0805 for supply of conductors. The tenders
submitted by the members of the Respondent were accepted by the
Appellants for various quantities. In the month of March 2001, the
four members of Respondent namely, (i) Patrik Conductors Pvt. Ltd.
(ii) Galaxy Cables Industries (iii) Dattatraya Cables Pvt. Ltd. (iv)
Reliance Cables and Conductors Private Ltd., who were not in position
to complete the orders requested for a termination of contract with no
liability on either side. In April/September the Appellant considered
the request/offer of the aforesaid four (4) Members of the Respondent
and cancel the contract for balance quantity, without any financial
liability on either side.
4 On 27 April 2001, the Respondent filed Writ Petition No.
1347 of 2001 claiming an interest on delayed payment against the
dgm 4 Judgment-app260.06.odt
Appellants under the Interest on Delayed Payments to Small Scale and
Ancillary Industrial Undertakings Act, 1993 ("the Act"). On 10
December 2002, consent terms were filed in the Writ Petition
referring the claims of the respective Members of the Respondent only
on interest issues under the Act, to Arbitration. Between January
2003 to April 2004, the statement of claims - reply were filed by the
parties. The impugned award was dated 30.04.2004 passed after
the conclusion of arguments. The Award challenged in Arbitration
Petition was as set aside by the learned Judge to the extent as set out
above - hence this Appeal.
5 The Respondents had also challenged part of the Award
on some other issues by filing Arbitration Petition No.328/2004 prior
to August 2004, through the same Advocate. The same was dismissed
on 30 August 2004 after hearing the parties. The Appellants came to
know about Arbitration Petition No.328/2004 only on 20 January
2005. The Appellants filed affidavit dated 5/2/2005 in Arbitration
Petition No.29/2005 and opposed the same. The Respondents in
rejoinder affidavit admitted the receipt of the amount of the Award
without any reservation.
dgm 5 Judgment-app260.06.odt
6 The written submission are filed on behalf of the
Appellants along with judgments and by the Respondent. The
judgments relied by the learned counsel appearing for the Respondent
are - (i) Snehadeep Structures Private Limited Vs. Maharashtra Small-
Scale Industries Development Corporation Limited 1 (ii) Modern
Industries Vs. Steel Authority of India Limited 2 and (iii) R.S. Jiwani
(M/s.), Mumbai Vs. Ircon International Ltd., Mumbai 3. The judgments
relied by the learned counsel appearing for the appellant are - (i)
Commissioner of Customs, Mumbai Vs. Virgo Steels, Bombay and
Another 4 (ii) Babulal Badriprasad Varma Vs. Surat Municipal
Corporation & Ors.5
7 Both the parties have read and referred Section 4 of the
Act.
"4. Date from which and rate at which interest is payable -
Where any buyer fails to make payment of the amount
to the supplier, as required under section 3, the buyer shall notwithstanding anything contained in any
1 (2010) 3 SCC 34 2 (2010) 5 SCC 44 3 2010 (1) Mh.L.J. 547 4 (2002) 4 SCC 316 5 AIR 2008 SC 2919
dgm 6 Judgment-app260.06.odt
agreement between the buyer and the supplier or in any law for the time being in force, be liable to pay interest to the supplier on that amount from the appointed day
or, as the case may be, from the date immediately following the date agreed upon, at one-and-a-half time
of Prime Lending Rate charged by the State Bank of India."
8 The relevant points determined by the learned Arbitrator
and dealt with by the learned Single Judge are as under :
"4 Whether the claimants establish the claim for payment
of interest in accordance with the provisions of the Act, if so, the quantum?"
"8 Whether four members of the Claimants, namely,
(i) Patrik Conductors Pvt. Ltd.
(ii) Galaxy Cables Industries,
(iii) Dattatraya Cable Pvt. Ltd.
(iv) Reliance Cables and Conductors Private Ltd.
are entitled to raise the claim for interest in respect of the Contract No. T-0901?"
"11 Whether the claimant is entitled to interest lite and future interest on the amount found due and if so at what rate?"
9 From the reading of Section 4 so reproduced above, the
Act and in view of the mandate of the specific wording of the
provisions namely, "Notwithstanding anything contained in any
dgm 7 Judgment-app260.06.odt
agreement between the buyer and the supplier or in any law for the
time being in force". The buyer, if fails to make payment of the
amount to the supplier as required under Section 3, he is liable to pay
interest, as per law from the appointed day, at one-and-a-half time of
Prime Lending Rate charged by the State Bank of India.
10 With reference to issue no. 4, the learned judge has set
aside the award of interest at the rate of 10% per annum from 26
April 2001. We are not in agreement with the view taken by the
Arbitrator, in so far as non grant of interest as per Section 4 of the Act
merely because of filing of Petition by the Respondent Association.
There was no interim relief in favour of the Appellant. Ultimately, in
view of the arbitration clause in agreement, the matter was referred to
the Arbitral Tribunal through the consent terms. The interest rate
should have been as per the provisions of law. The learned judge has
not granted and/or passed order in this regard. It is left to the parties
to ascertain the prime lending rate charged by the State Bank of India,
at the relevant time. The delay in claiming the rate of interest was an
important aspect, which the learned Arbitrator has considered. But
the rate cannot be less than the Section 4 requirement.
dgm 8 Judgment-app260.06.odt
11 The Apex Court in "SRI Paravathi Parmeshwar Cables
and Others Vs. Andhra Pradesh Transmission Corporation Limited
and Another 6 has maintained, affirmed and applied the Supreme
Court judgment in Snehadeep Structures Private Limited Vs.
Maharashtra Small-Scale Industries Development Corporation Limited
(Supra) and Modern Industries Vs. Steel Authority of India Limited
(Supra) with regard to the mandate of the Act in question. The Apex
Court in, M/s. Purbanchal Cables & Conductors Pvt. Ltd. Vs. Assam
State Electricity Board & Anr. 7 held that the Act is applicable to the
transaction enter into after coming in force the amended provision of
right of supplier to pay interest at higher rate. The cause of action of
this matter arose on 24.11.2005.
12 Therefore, though there exists the agreement between 4
members of the Petitioners and as they agreed to cancel the contract
for supply of balance quantity, these members waived their right to
receive interest under Section 4 of the Act is unacceptable. There was
no question of waiver of any rights to receive interest specifically
6 (2013) 10 SCC 693 7 AIR 2012 SC 3167
dgm 9 Judgment-app260.06.odt
when admittedly there was no payment made in time so fixed. That
itself should result into entitlement of interest as per provision of
Section 4. The decision so arrived at by the parties and agreed to
cancel the contract for supply of balance quantity, that itself, in our
view, should not be read to mean that the supplier who admittedly
did not receive payment in time and lost their rights or entitlement of
statutory interest on the delayed payment. The seller, having once
supplied the goods, are entitled for the amount in time and if payment
is delayed by the buyer, the interest as per the Act/provisions should
follow. The view taken by the learned Single Judge is correct on this
point and need no interference.
13 In so far as point nos. 8 and 11 with regard to entitlement
of claim of interest rate and future interest on the amount due and if
so, at what rate, whereby the learned Arbitrator has directed the
payment of interest @ of 10% per annum for the period subsequent to
26 April 2001 from the date of Award till the date of realization is also
got set aside. This resulted into setting aside of the Award passed by
the learned Arbitrator on interest on all counts i.e. issue no. 8 and 11.
dgm 10 Judgment-app260.06.odt
However, the remaining part of the Award on other points remain
undisturbed.
14 Taking overall view of the matter, we would have
remanded the matter back for reconsideration on limited issue.
However, when inquired and as noted, inspite of the order passed by
this Court permitting the parties to approach afresh for the interest
part, as observed, no steps whatsoever have been taken by the
Appellants and as no course they have adopted till this date on the
aspect of interest as per the provisions of the Act. Therefore, in these
circumstances, we see no reason to interfere with the order so passed,
to avoid further delay to the proceedings. Let the parties, as already
ordered, decide the course of action in this regard.
15 The Appeal and Notice of Motion are accordingly
dismissed. No costs.
(G. S. KULKARNI, J.) (ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!