Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Indiabulls Power Limited, New ... vs The State Of Maharashtra Through ...
2016 Latest Caselaw 2292 Bom

Citation : 2016 Latest Caselaw 2292 Bom
Judgement Date : 5 May, 2016

Bombay High Court
Indiabulls Power Limited, New ... vs The State Of Maharashtra Through ... on 5 May, 2016
Bench: B.P. Dharmadhikari
        wp4968.15                                                              1



             IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                      
                           NAGPUR BENCH

                       WRIT PETITION  NO.  4968  OF  2015




                                              
      RATTAN INDIA POWER LIMITED
      having its registered office at 




                                             
      12th Floor, Tower A, Building No.5,
      DLF Phase 3, DLF Cyber City,
      Gurgaon, Haryana 122 092.                         ...   PETITIONER




                                           
                                   Versus
                             
      1. The State of Maharashtra
         through the Chief Secretary,
         Mantralaya, Mumbai 400 032.
                            
      2. The Secretary (WRD),
         Water Resources Department,
         Government of Maharashtra,
         2nd Floor, Main Building,
      


         Mantralaya, Mumbai 400 032.
   



      3. The Secretary (CADA),
         Water Resources Department,
         Government of Maharashtra,





         2nd Floor, Main Building,
         Mantralaya, Mumbai 400 032.

      4. The Chief Engineer,
         Water Resources Department,





         Sinchan Bhavan, Shivaji Nagar,
         Upper Wardha Vasahat Camp,
         Amravati 444 603.

      5. Executive Engineer,
         Upper Wardha Dam Division,
         Shivaji Nagar, Uppar Wardha
         Vasahat Camp, Amravati 444 603.

      6. Executive Engineer,
         Vidarbha Irrigation Development


    ::: Uploaded on - 06/05/2016              ::: Downloaded on - 07/05/2016 00:00:59 :::
         wp4968.15                                                                     2



          Corporation, Sinchan Sewa




                                                                             
          Bhawan, Civil Lines, Nagpur.

      7. The High Power Committee




                                                     
         through the Principal Secretary
         (WRD), 2nd Floor, Main Building,
         Mantralaya, Mumbai 400 032.                  ...   RESPONDENTS




                                                    
      Shri M.G. Bhangde, Senior Advocate with Shri S.D. Dewani,




                                        
      Advocate for the petitioner.
      Shri Rohit Deo, Associate General with Mrs. Bharti H. Dangre,
                             
      GP for respondent Nos. 1 to 3 & 7.
      Shri   S.G.   Jagtap   with   Shri   S.S.   Godbole,   Advocates   for
      respondent Nos. 4 to 6.
                            
                         .....

                                           CORAM :  B.P. DHARMADHIKARI &
                                                           V.M. DESHPANDE, JJ.

DATE OF RESERVING JUDGMENT: FEBRUARY 10, 2016.

DATE OF PRONOUNCEMENT : MAY 05, 2016.

JUDGMENT : (PER B.P. DHARMADHIKARI, J.)

By this writ petition filed under Article 226 of the

Constitution of India, the petitioner seeks a writ in the nature

of certiorari and after setting aside adverse orders, a direction

to the respondents to apply Irrigation Potential Restoration

Charges (hereinafter referred to as IRC), as per Government

Resolution dated 21.02.2004 with respect to the water

allocated to the petitioner, based on deficit in water for

irrigation as per the latest report. The prayers have been

amended and a prayer to restrain the respondents from

recovering interest as per demand letters dated 17.01.2013

and 04.02.2013 has been added. Hiwever, no arguments are

advanced on this interest aspect.

2. It appears that the petition was presented at

Bombay as Writ Petition No. 1487 of 2013 and there, on

05.05.2014, this Court noted that ad interim order /

arrangement was operating as per statement of respondents

made before it on 26.02.2013. On 17.06.2014, the Court

noticed that the petitioner had already paid an amount of

Rs.116.57 crores to the Government towards IRC including an

amount of Rs.10 crores deposited on 21.05.2013 and granted

ad interim stay of coercive recovery of balance amount. On

03.08.2015, the Bench at Bombay felt that the matter should

have been presented at Nagpur and it was accordingly

returned to the Advocate for the petitioner. This matter has

then been presented at Nagpur.

3. The petitioner is a Public Limited Company

registered under the Companies Act, 1956, and it produces

electricity. For that production, it requires assured supply of

water constantly. It is not in dispute that because of deficit of

electricity in Maharashtra, Respondent No. 1 - State

introduced a policy viz., "Mega Power Policy" to promote

private investment in power generation sector. As per that

policy and guidelines thereunder, the petitioner offered to

make investment and set up Thermal Power Project (T.P.C.).

According to the petitioner, it agreed to invest about

Rs.15,000/- crores in setting up of a 2700 MW Thermal Power

Project at Amravati and Respondent No. 1 - State gave

necessary permission. Circular dated 21.02.2004 isssued by

the State regulate allocation of water for non-irrigational

purposes. The petitioner sought water allocation in December

2007 and High Power Committee accepted it in its meeting

dated 13.05.2007. Water agreement was then executed on

22.09.2008.

4. Respondent No. 5 - Executive Engineer submitted

a report on 11.01.2008 and quantified expenditure on IRC at

Rs.50,000/- per Hectare for notional area of 23218 Hectares,

totaling to Rs.116 crores. As per decision dated 21.02.2008,

the petitioner was required to pay its share towards capital

contribution and IRC at prevailing charges. The prevailing IRC

charges at that time was Rs.50,000/- per Hectare.

Accordingly, on 16.08.2008, Respondent No. 4 - Chief

Engineer of Water Resources Department conveyed the

decision of allocation of 87.60 MM3 water to the petitioner.

However, Respondent No. 5 - Executive Engineer demanded

IRC at the rate of Rs. One lakh per Hectare for 23218 Hectare.

The total demand was of Rs.549.98 crores out of which 232.18

crores represented IRC while balance Rs.317.80 crores were

demanded towards capital contribution. The petitioners also

claim that Respondent No. 6 - Executive Director had on

17.01.2012 sent a letter to Respondent No. 3 - Secretary of

Command Area Development Authority, pointing out that IRC

should have been demanded @ Rs.50,000/- per Hectare only.

5. The petitioner thereafter addressed various

representations and Respondent No. 1 - State and Respondent

No. 2 - Secretary of Water Resources department passed a

resolution on 06.03.2009 fixing maximum rate of IRC at Rs.

One lakh per Hectare prospectively from 01.04.2009. The

petitioner sent a letter to the Minister for Water Resources

Department on 25.01.2011 and pointed out discriminatory

and exorbitant demand. The petitioner then sent another

representation on 01.06.2011 and then a detailed

representation dated 30.06.2011 to the said Minister.

6. Respondent No. 5 on 23.04.2012 informed the

petitioner that last date for executing Water Agreement was

31.05.2012 and failure to execute it would result in

cancellation of water allocation. On 07.05.2012, the

petitioners replied to it and reiterated its grievance. The

petitioner stated that the Minister, Water Resources

Department was considering the demand of the petitioner,

however, power project being of national importance and due

to the fact that the respondent was in a position to exercise

economic duress on the petitioner, the petitioner agreed to

execute agreement by paying IRC of Rs.50,000/- per Hectare

with an undertaking on an affidavit to pay balance, if any,

subject to final decision of State on representation of the

petitioner. On 10.05.2012, the petitioner sent a letter to the

Superintending Engineer, Uppar Wardha Dam Project,

pointing out its readiness and willingness to execute

agreement without prejudice to its demand of calculating IRC

at Rs.50,000/- per Hectare. The respondents insisted upon

executing that agreement with IRC of Rs. One lakh per Hectare

and suggested that that amount be paid in installments. The

petitioner then submitted two demand drafts both dated

18.05.2012 and each in the sum of Rs.23,21,90,000/- towards

first installment of IRC. The petitioners were given draft of

agreement on 23.05.2012. The petitioner was forced to

execute that agreement in the form as supplied. The

agreement has been entered into for non-irrigation water

supply with effect from 22.05.2012 and as stipulated therein,

the amount paid by the petitioner towards IRC was made

subject to decision of the government on representation of the

petitioner.

7. The next installment of Rs.60.13 crores towards

IRC computed @ Rs. One lakh per Hectare was due on

21.11.2012 and the representation of the petitioner was not

decided, hence the petitioner approached this Court at

Bombay in Writ Petition No. 2714 of 2012. On 22.11.2012,

this Court directed the State Government to decide the

petitioner's representation within eight weeks. The petitioner

vide letter dated 18.12.2012 informed Respondent Nos. 3 & 5

about amounts deposited and grant of personal hearing.

Separate communication was sent to Respondent No. 5

disputing the bill raised towards water charges pointing out

that water charges could be levied only two years after

company started drawing water and also disputing its right to

levy interest. On 27.12.2012, Respondent No. 5 - informed

that Respondent No. 4 was seized of the matter and refuted

petitioner's charges that no water charges or interest was

payable. The petitioner's claim that on 03.01.2013 it clarified

that payments made towards IRC were without prejudice to

the petitioner's rights and submissions under law and the

representations filed by it. It further stated that interest could

be determined once the representations were conclusively

decided. On 21.01.2013, the petitioner informed Respondent

No. 3 about pending representation. This was repeated on

28.01.2013.

8. The Water Resources Department vide letter dated

29.01.2013, summarily disposed of the petitioner's objections.

This disposal has been questioned in present writ petition.

9. We have heard Shri M.G. Bhangde, learned Senior

Advocate with Shri S.D. Dewani, learned counsel for the

petitioner, Shri Rohit Deo, Associate General with Mrs. Bharti

H. Dangre, learned Government Pleader for respondent Nos. 1

to 3 & 7 and Shri S.G. Jagtap with S.S. Godbole, learned

counsel for respondent Nos. 4 to 6.

10. After narrating the facts, Shri Bhangde, learned

Senior Advocate has submitted that the dispute in this writ

petition is about the area qua whicu & rate at which Irrigation

Restoration Charges (IRC) is to be calculated. According to

him, it should be Rs.50,000/- per Hectare while the

respondents claim to be Rs. One lakh per Hectare. On second

contention about the area with reference to which this IRC is

to be calculated, he points out that according to the petitioner,

there is absolutely no loss of irrigation potential and,

therefore, as not an inch of land has been deprived of

irrigation, the petitioner is not required to pay anything on

that count. He further contends that in the alternative, the

said area is eithrt 4600 Hectare or then, 13140 Hectare. Thus,

the calculation considering that area to be 23218 Hectare by

the respondents is not correct.

11. Insofar as contribution towards capital expenditure

is concerned, it does not form part of this petition as the

petitioner has instead of capital contribution agreed to pay

higher charges for water supplied to it & Respondents have

consented to it.

12. Shri Bhangde, learned Senior Advocate submits

that IRC is to be worked out on a date when the water

allocation is finalized i.e. on 12.12.2007 and any subsequent

modification therein cannot be made applicable to such

allocation. He has invited attention to the fact that on

16.08.2008 sanction is granted for permanent water allocation

of 87.60 MCM from completed Uppar Wardha Project and it

was to be operational only after agreement is made. The

water charges at the rate as decided by the State Government

from time to time are to be paid. The said document,

however, demands Rs.232.18 crores towards IRC and this

calculation is @ Rs. One lakh per Hectare. For 232.18

Hectares. He states that as per clause 13, though action was to

be taken within three years, said period was extended up to

31.05.2012. He has invited attention to demand letter dated

26.09.2008 whereby the amount of Rs.549.98 crores has been

demanded and it includes IRC of Rs. 232.18 crores. He has

then taken us through various representations made by the

petitioner from time to time. The representation dated

25.01.2011 makes reference to IRC rates applied to other

similar units. It points out treatment extended to those units &

complains of discrimination. Instances are of total waiver for

NTPC, rate of Rs. 50,000/-per hectare to units like Adani

Power Maharashtra, Adani GR Power and Reliance Energy

Limited. He submits that State Government does not have any

uniform policy and IRC has been calculated by using varying

norms. Norm of 64 Hectare per cubic meter is applied in case

of Tata Power, while norm of 265 Hectare per cubic meter is

used in case of IPL. Therefore, the actual rate varies from NIL

to 265 crores which is the highest one. In that representation,

it has been pointed out that in case of the petitioner, the Chief

Engineer, Water Resources Department, on 11.01.2008, has

pointed out IRC of Rs.116.09 crores omly as per rate

prevailing on th date of water allocation.

13. Our attention has also been drawn to agreement

entered into between the petitioner and the respondents on

22.05.2012 to show that the petitioner - company agreed to

pay Rs.232.18 crores as IRC in five installments over a period

of two years with applicable interest but it was subject to

decision on representation of company dated 25.01.2011.

That decision was to be binding on parties. Petitioners

contend that the company was already permitted to draw

water for the specified purposes and thus agreement does not

reserve or allocate water for the first time for it. It only

facilitate use of water already allocated or reserved. An

undertaking furnished by the petitioner on 22.05.2012 to

support its request for five installments is also relied upon

to show that it is subject to the decision of representation.

14. Our attention has been drawn to the orders passed

at Bombay in Writ Petition No. 2714 of 2012 to demonstrate

that this representation was directed to be decided within

eight weeks and it was kept pending for quite some time

thereafter. The impugned order which decides representation

on 29.01.2013 is also relied upon to contend that it ignores

the vital aspect of the objection on "area" qua which the IRC

needed to be charged. The guidelines or norms prevailing on

the date of entering into an agreement have been erroneously

referred to and rate of Rs. One lakh per Hectare prevailing at

the time of agreement has been found proper.

15. To point out how illustration of other units given

by the petitioner have been perfunctorily dealt with, he has

placed reliance upon the discussion in paras 6(a) and 6(b) of

the impugned order. He submits that water allocation in case

of Aparna Infra Energy was on 01.07.2007. The company

executed an agreement on 24.01.2011 and still IRC was

calculated @ Rs.50,000/- per Hectare. The case of the

petitioner stands on same footing. Para 7 is also pressed into

service to show how favourable treatment has been extended

to Reliance Energy, Shahapur, Ispat Power Project, Pen and

Tata Power, Pen. He submits that rate of Rs. One lakh per

Hectare is introduced on 06.03.2009 with effect from

01.04.2009 and as it has not been made applicable in case of

Aparna, the same should not have been applied to the

petitioner also.

16. Water Policy providing for non irrigational user of

water formulated on 21.01.2003 has been relied upon by him

to submit that the petitioner has been given water allocation in

terms of said policy. Rate of Rs.50,000/- per Hectare

stipulated in clause 13 thereof is heavily relied upon by him.

The Circular issued on 21.02.2004 about payment of

contribution towards capital cost and about irrigation

restoration charges is also pressed into service to show that in

present facts, there is no question of exceeding rate of

Rs.50,000/- per Hectare. He adds that the rate prevailing,

when the water is reserved for the petitioner, is decisive and

date of entering agreement has got no bearing. Hence, the

later revisionor enhancement on 06.03.2009 with effect from

01.04.2009 cannot be applied retrospectively.

17. Our attention is invited to communication dated

11.01.2008 by which the proposal of the petitioner was

submitted for scrutiny to the State Government where rate of

Rs.50,000/- per Hectare has been applied to 23218 Hectare of

land. It is contended that in present matter, the reservation

was vide memorandum dated 16.08.2008 and even at that

time prevailing rate was Rs.50,000/- per Hectare. Hence,

stipulation in clause 12 thereof about amount of Rs.232.18

crores as IRC is bad. This error was pointed out on

17.08.2008 but it was not corrected. Had mistake been

corrected, the petitioner could have paid the amount or had

there been refusal, the petitioner could have come to this

Court. The learned Senior Advocate submits that delay in

taking decision is an error on the part of the State Government

and it cannot be allowed to take advantage of its own wrong.

18. Our attention is drawn to an affidavit tendered at

Bombay in Writ Petition No. 1487 of 2013 to urge that effort

made therein to explain different treatment extended to NTPC

is unsustainable. He points out that as NTPC was allotted land

otherwise to be used for irrigation project, rate of Rs. One lakh

has been applied to it. He further points out that on

25.07.2008, the Water Reservation rate has been sanctioned

by the Executive Director of VIDC. According to him,

documents on record show that said rate is not fixed by the

State Government. He draws support from communication

dated 22.12.2011 sent by the State Government to the

Executive Director of VIDC which mentions this fact.

19.

Strong reliance is placed upon the response thereto

by VIDC on 17.01.2012. This communication sent by the

Executive Director of VIDC to the Secretary of Water Resources

Department point out IRC of Rs.50,000/- per Hectare only.

The extent of area to be calculated for that is also taken as

150 Hectare per cubic meter of water as per this

communication. Manner in which said Executive Director has

explained distinguishing feature in the matter of NTPC is also

pressed into service by the petitioner.

20. Mega Policy dated 28.03.2005 is produced before

us by the petitioner during hearing. The respective counsel

appearing for the respondents were asked whether they have

any objection to that production and they gave their no

objection. Shri Bhangde, learned Senior Advocate submits

that clause 3(iii)(c) of this policy is assurance of water and

relying upon this policy and circular dated 21.02.2004, the

petitioner made huge investment. Our attention is invited to

grounds (hh)(ii) in memo of writ petition to substantiate the

same.

21.

Coming back to the impugned order, in this

background, Shri Bhangde, learned Senior Advocate submits

that it shows total non application of mind and the relevant

material has been overlooked. He adds that case of Aparna

looked into is identical to the case of the petitioner. Reference

to clause 27 of the Agreement dated 22.05.2012 is irrelevant

as it does not enable them to apply circular dated 06.03.2009.

He submits that legal relationship does not start from

22.05.2012 but it has started when water allocation was done.

He points out that express stand of VIDC in this respect has

been ignored.

22. Pointing out the judgment delivered by this Court

at Bombay in Writ Petition No. 757 of 2011 on 1 st & 2nd March

2013, the learned counsel states that there, after considering

the rival contentions, the Division Bench has looked into State

Water Policy and then in para 27 notices that 202.203 MCM of

water is sufficient for irrigating 75000 Hectare of land. He

contends that in the light of this observation, when water

being supplied is only 87 MCM, there is no reduction in

irrigation potential at all. Our attention is also drawn to an

affidavit filed by the Executive Director, VIDC in Writ Petition

No. 1038 of 2010 which was decided along with a Public

Interest Litigation to urge that as disclosed in para 8 thereof by

VIDC, the Power Project of the present petitioner does not in

any manner hamper the irrigation potential of the region. He,

therefore, submits that no IRC can be recovered from the

petitioner.

23. Using same equation (proportion), he points out

that at the most water lost is 17.60 MCM which could have

catered 4600 Hectare. Hence, IRC @ Rs.50,000/- per Hectare

could have been calculated only for 4600 Hectare of land. Our

attention is drawn to a report on Water Planning of Uppar

Wardha Project to submit that as mentioned therein, after

simulation study, with added requirement of 87.60 MCM

water for the petitioner, the total water available for the

irrigation purposes is 182.7 MCM. He, therefore, states that

the shortfall is at the most of 17.60 MCM as is apparent from

the stand of irrigation department looked into in paragraph

27 of the judgment dated 1.2 March, 2013 in W.P. 758 of

2011 , 757 of 2011 delivered at Bombay.

24. Without prejudice, he adds that as per letter of

VIDC dated 17.01.2012, the standard area which can be

catered per MCM of water is 150 Hectare. If this area is

applied, then loss of irrigation capacity is 13140 Hectare.

25. In this background, he again invites attention to

absence of uniformity in this respect as highlighted in

representation dated 25.01.2011 and accompanying chart by

the petitioner.

26. He concludes by pointing out that actual water

came to be released to the petitioner for the first time on

18.11.2013.

27. Shri Deo, learned Associate Advocate General

submits that on 21.02.2008, only a meeting took place and

89.72 MCM of water in principle was agreed to be reserved for

the petitioner. He states that as per said consideration, because

of this reservation, 232.19 Hectare of land was being deprived

of irrigation. He further submits that as per Government

Circular dated 21.02.2004, there are clear instructions which

put any controversy beyond doubt. The rate of IRC has to be

as prevailing on the date on which the agreement is reached

and supply of water without agreement has been specified to

be a grave misconduct. He also adds that the petitioner does

not seek quashing of agreement dated 22.05.2012. He invites

our attention to Government Resolution dated 21.01.2003 to

show how clause 13 again reiterates that water for non

irrigational purposes should not be supplied without

agreement. A High Power Committee has been constituted for

said purposes and, in this situation, only reservation of water

in favour of the petitioner cannot, therefore, result in fixing a

date for rate determination. A communication dated

16.08.2008 sent by the Assistant Chief Engineer containing

terms and conditions is heavily relied upon by learned AAG to

show that water reservation takes place only after agreement

is entered into. He points out that rate of capital expenditure

and IRC is mentioned in it and three years of time limit is also

prescribed. He further states that the petitioner exercised

option in relation to not paying capital contribution and

agreed to pay water royalty at a higher rate on 25.02.2011.

The petitioner never raised any objection from August 2008 till

17.10.2008 and thereafter till 21.05.2011. Shri Deo, learned

counsel adds that objection is only about rate and not about

area of land in relation to which the calculation needs to be

made. He invites our attention to representation dated

01.06.2011 sent by the petitioners where they sought

additional time of one year for executing agreement & during

said period time, government should take decision on the

proposal. The proposal was to set aside demand of Rs.232.18

crores. On 08.06.2011, Government extended that time. On

10.05.2012, the petitioner agreed to a conditional agreement

and to pay an amount of Rs.232.18 crores in five installments

subject to decision on its representation. On 18.05.2012, the

petitioner gave two Demand Drafts and then on 25.05.2012,

agreement under Article 299 of Constitution of India has been

entered. He contends that, therefore, it is not a statutory

contract.

28. Separate undertaking given by the petitioner on

the very same day is also relied upon by him with submission

that second installment was due on 21.11.2012 with interest

and at that juncture, the petitioner filed writ petition at

Bombay on 27.04.2012 which came to be decided on

22.11.2012. He submits that this court was reluctant to

intervene due to undertaking and other factors. Adv. Deo

urges that adjudication therein operates as res judicata. He

heavily relies upon said judgment dated 22.11.2012. to state

that all contentions being raised now were looked into and

High Court has refused to intervene. This being a contract

matter, writ jurisdiction is not available and only remedy is to

assail the impugned order in Civil Court. He states that there

is no scope to substitute siad order dated 25.02.2012 passed

by this Court in its writ jurisdiction.

29. According to him, pleadings in instant writ petition

are very narrow and mostly about rate of IRC. He invites

attention to pleadings in para 9 of writ petition about area

affected and to an affidavit in reply filed by the respondents in

reply to it. Formula applicable to determine said area & need

to work it out accordingly, is pressed into service by him to

urge that the irrigation potential affected by reservation has

been rightly calculated to be 23218 Hectare. He further points

out that as disclosed therein the irrigation potential ihas later

ncreased and with that increase, because of improvements in

infrastructure, 87.60 MCM water reserved for the petitioner is

enough cater to more than 23218 Hectare of land. He,

therefore, states that actual demand on account of IRC has to

be much more than Rs. 232.18 Crs. He, however, adds that as

all these are technical facets, this Court should not intervene in

writ jurisdiction.

30. On unequal treatment extended to the petitioner,

he has taken us through the very same reply affidavit to point

out how comparision done is either defective or legally

unsustainable. According to him, there is a distinguishing

feature in case of NTPC because NTPC project itself affects the

area of 560.68 Hectare and cause actual loss in irrigation

potential of 820.56 Hectare. He further submits that NTPC

paid amount to Water Resources Department in March 2012

@ Rs. One lakh per Hectare. He further adds that while

allocating water for non-irrigation purpose to NTPC, High

Power Committee agreed to waive Rs.95 crore as it is Central

Government Undertaking. He has submitted that insofar as

project Aparna Infra Energy, Chandrapur, is concerned,

Chandrapur is not a Water deficit area and proposal was

submitted to levy IRC at Rs.50,000/- per Hectare in the light of

Government Circular dated 21.02.2004. The High Power

Committee in its meeting dated 02.07.2008 decided to obtain

restoration charges of Rs.309 lakh. The reservation in favour

of Aparna Infra Energy is of 6 MCM from Nand-reservoir. The

allocation of reservation for the petitioner is much more ie

87.60 MCM, that too in water deficit area. The other technical

details are also pressed into service by him to urge that the

project of the petitioner cannot be compared with the project

of Aparna. The prevailing rate of IRC at Rs.50,000/- per

Hectare has been offered to M/s. Ideal Energy Private Limited

when agreement was entered into on 22.09.2008. The

projects of Reliance Energy, Shahpur; Ispat Power Project, Pen

and Tata Power, Pen (all in Raigarh district) were required to

be cancelled as non-irrigation agreement was not executed

within the prescribed time. He has relied heavily upon facts

disclosed in paras 16 and 17 of said affidavit to point out the

impact of reservation of water in favour of the petitioner.

Various technical details are given in para 17 to urge that the

petitioner is not entitled to any reduction in IRC charges.

31. In this background, the learned counsel submits

that reliance upon internal communication dated 17.01.2012

sent by the Executive Director, VIDC to the Secretary, Water

Resources Department, is misconceived. It is not a "decision"

of Government at all. The specific stand in reply in this

respect in para 23 is pressed into service by him.

32. Shri Deo, learned Associate Advocate General

urges that this Court has been approached belatedly and the

approach itself is barred as the petitioner has already

acquiesced in everything, therefore, the petitioner is estopped

from raising any grievance. He further contends that there is

no scope for remanding this issue or matter back as its

representation has been considered & rejected by the State

Government in accordance with law.

33. He has relied upon the judgment in the case of

State of Haryana vs. Lal Chand, reported at AIR 1984 SC 1326,

to urge that the present contract is not a statutory contract.

The judgment in the case of Pimpri Chinchwad Municipal

Corporation & Ors. vs. Gayatri Construction Company & Anr.,

reported at (2008) 8 SCC 172 is relied upon to submit that a

contract in relation to public utility service is not a statutory

contract. The judgment in the case of Orissa State Financial

Corporation vs. Narsingh Nayak, reported at (2003) 10 SCC

261, is relied upon by him to submit that rewriting of contract

in writ jurisdiction is not permissible. The judgment in the

case of Rajasthan State Industrial Development vs. Diamond &

Gem Development Corporation Ltd., reported at (2013) 5 SCC

470, is relied upon to contend that the petitioner cannot be

permitted to approbate and reprobate and contract between

the parties cannot be rewritten. The judgment in the case of

Shyam Telelink Ltd. Now Sistema Shyam Teleservices Ltd. vs.

Union of India, reported at (2010) 10 SCC 165, is the

judgment relied upon by him again on approbation and

reprobation. On enforcement of non statutory contract in writ

jurisdiction, he draws support from the judgment in the case of

State of U.P. & Ors. vs. Bridge & Roof Company (India) Ltd.,

reported at (1996) 6 SCC 22 and in the case of M/s.

Radhakrishna Agarwal & Ors. vs. State of Bihar & Ors., reported

at (1997) 3 SCC 457.

34. The judgment in the case of M/s. Mahabir Jute

Mills Ltd., Gorakhpore vs. Shri Shibban Lal Saxena & Ors.,

reported at (1975) 2 SCC 818, is pressed into service to urge

that while considering the representation of present nature, it

is not necessary to record the reasons. The adjudication of

petitioner's representation does not give any fresh cause of

action as representation is not statutory in nature. To buttress

this submission, he relies upon the judgment in the case of

Union of India & Ors. vs. M.K. Sarkar, reported at (2010) 2

SCC 59. The judgment in the case of Union of India & Ors. vs.

E.G. Nambudiri, reported at (1991) 3 SCC 38, is relied upon

by him to urge that in such matters, the petitioner cannot

insist for reasons.

35. Shri Deo, learned Associate Advocate General,

submits that, at worst, only one instance to support alleged

unequal treatment has been pointed out by the petitioner. He

relies upon the judgment in the case of Gurucharan Singh vs.

New Delhi Municipal Committee, reported at AIR 1996 SC

1175; Chandigarh Administration vs. Jagjit Singh, reported at

AIR 1995 SC 705; Shanti Sports vs. Union of India, (2009) 15

SCC 705 and in the case of Jayant Vegoils and Chemicals vs.

The City and Industrial Development Corporation, reported at

(1997) 2 BCR 600, to submit that any irregularity or illegality

cannot be perpetuated by taking recourse to Article 14 of the

Constitution of India.

36. He further submits that on IRC, the case of the

petitioner falls under clause B(1) of Government Resolution

dated 21.02.2004 and rate prevailing on the date of agreement

has been correctly relied upon. He invites attention to

representations made by the petitioner on 25.01.2011,

25.02.2011, 01.06.2011 and 30.06.2011, to contend that the

extent of area which is deprived of irrigation potential was

never in dispute. He, therefore, prays for dismissal of writ

petition.

37. Shri Bhangde, learned Senior Advocate, in his reply

points out that NTPC did not pay IRC and that amount has

been waived by High Power Committee (HPC). The reasons

given in the matter of Aparna in para 12 of affidavit are legally

unsustainable. The placement of an industry in water deficit

area or water surplus area is not disclosed as a relevant norm

in the water policy. He adds that otherwise, the petitioner

establishment would have gone to Chandrapur area. He

submits that even the quantum of water allotted, does not

appear to be relevant. The petitioner had submitted

representations on various occasions but the same were not

decided. He states that date of agreement in case of Aparna is

much after 1.4.2009, but as allocation was prior thereto, old

rate has been applied. Analogy and rate in the case of Aparna

ought to have been applied even in the case of the petitioner.

He further adds that rate applied even in the case of Ideal

Energy Limited ought to have been extended to the case of the

petitioner. The cancellation of permission to other projects is a

subsequent event which has got no relevance on a challenge

raised by the petitioner. He relies upon a communication

dated 17.01.2012 to urge that it has to clinch the issue.

38. On nature of contract and need of filing a Civil

Suit, he invites attention to the provisions of Section 58(6) of

the Maharashtra Irrigation Act, 1976, (XXXVIII of 1976) and

submits that water is made available to the petitioner under

that provision. The water policy has been elevated to a status

of statue by 2011 Amendment i.e. Section 31-B of the

Maharashtra Water Resources Regulatory Authority Act, 2005.

The water policy of State Government and grant of water to

the petitioner is deemed to be under Section 31B. He further

points out that dispute about IRC is at threshold of contract i.e.

before entering into contract and not a subject matter or

aspect of contract, hence, different principles apply. He draws

support from the judgment in the case of Radhakrishna

Agarwal v. State of Bihar, reported at (1977) 3 SCC 457, (para

10) for said purpose. He adds that imposition of a condition

contrary to Water Policy while entering into contract itself is

bad. While explaining absence of pleading on "area" dispute ,

he points out that the representation has not been looked into

and, therefore, it was not necessary to raise any plea in that

respect. He further states that in representation dated

21.01.2013, after High Court judgment, this point has been

raised and it has been replied to by the respondents in their

reply before this Court vide paras 12, 13 and 14. He also

submits that no prejudice is caused to the petitioner in absence

of such a plea because extent of area affected is a matter of

record and all material relevant thereto is undisputed. He also

relies upon the Division Bench judgment at Bombay between

the parties which mandated adjudication of representation to

show that that Division Bench expected decision on area

dispute also.

39. Taking us through said judgment, he points out

that it cannot operate as res judicata or constructive res

judicata because at that time representation was pending and

subsequently, it has been decided obeying the directions

issued therein. If tat all he petitioner had approached writ

court belatedly, the question needed to be raised in that matter

when the Division Bench decided said Writ Petition No. 2714

of 2012 on 22.11.2012. After that adjudication and directions,

such contentions cannot be raised by the respondents in this

matter. That Division Bench has kept everything open and

hence arguments of finality or propriety cannot be raised in

this matter.

40. He further points out that if prayer (A) in present

writ petition is allowed, prayer (B) therein becomes

redundant. The dispute is only in relation to correct rate and

proper area. The agreement between the parties dated

22.05.2012 is provisional on IRC rate as it depends on decision

of the representation. The said decision on representation

prevails over the arrangement in agreement. Communication

dated 17.11.2012 though internal, brings on record facts and

the petitioner has placed reliance upon it to invite attention to

those facts. The petitioner is not relying upon any

recommendation contained therein. He further submits that

doctrines like estoppal or approbate or reprobate are not

attracted here as the petitioner does not assail the agreement

and IRC rate is expressly agrred to be contingent upon the

decision on its representation by the parties thereto.

41. In respect of rate of IRC and relevant date, he

invites attention to clause (B) of Government Circular dated

21.02.2004. He contends that stipulation of rate in the letter

dated 16.08.2008 by the Assistant Chief Engineer (2), Water

Resources Department, Amravati, is contrary to this clause and

demand could not have been raised on its basis. He invites

attention to agreement dated 22.05.2012 to urge that

reservation of water was already done and agreement only

stipulates conditions subject to which right to it is to be

exercised. He further states that vide its page 6, the agreement

specifically refers to Maharashtra Irrigation Act, 1976.

42. He relies upon the judgment in the case of State of

Orissa v. Bhagyadhar Dash, reported at (2011) 7 SCC 406, to

urge that in such facts and circumstances, Article 226 of the

Constitution of India, is always open.

43. The affidavit in reply particularly para 16 is relied

upon to show the impact of payment made by the petitioner.

He contends that when project was over in 2005 itself,

subsequent developments or improvements made in services

thereafter cannot have any bearing in the matter. He argues

that the respondents have travelled outside the report of

experts and water policy. He further submits that the effort of

the respondents is to change the norm for calculating IRC.

44. The judgment in the case of State of Karnataka vs.

All India Manufacturers Organisation, reported at (2006) 4 SCC

683, para 60 is relied upon by him to urge that State has to act

reasonably in contractual matters. The judgment in the case

of Reliance Energy Ltd. vs. Maharashtra State Road Development

Corporation Ltd., reported at (2007) 8 SCC 1, is relied upon

by him to para 36 along with judgment in the case of Meerut

Development Authority vs. Association of Management Studies,

reported at (2009) 6 SCC 171, paras 35 to 39, to buttress the

said contention. To explain what constitute promissory

estoppel, he draws support from the observation of the Hon'ble

Apex Court in para 10 of its judgment in the case of Devi

Multiplex & Anr. vs. State of Gujarat & Ors., reported at (2015)

9 SCC 132.

45. The judgment in the case of South India

Corporation (P) Ltd. vs. Secretary, Board of Revenue,

Trivendrum & Anr., reported at AIR 1964 SC 207 (1), para 19

is relied upon by him to explain the meaning of phrase "subject

to". He contends that agreement between the parties is "subject

to" the decision of representation of the petitioner, and hence,

all objections raised by the respondents are misconceived. He,

therefore, prays for allowing the petition.

46. After considering these arguments and the

material on record, we find it appropriate to first look into the

facts and then proceed to appreciate the precedents cited by

the respective learned Counsel.

47. We find that the order of Water allocation to

petitioner is issued on 16.08.2008. It considers reservation of

100 MLD water for petitioners. Approval is accorded to this

allocation or reservation in 13th Meeting of Ministers High

Power Committee (HPC) held on 21.02.2008 and sanction has

been granted for permanent water allocation of 87.60 MCM on

that day. The terms and conditions regulating the

reservation, vide clause 12, apply rate of Rs. One lakh per

Hectare and demand Rs. 232.18 Crores towards irrigation

restoration charges on account of loss of irrigation. Material

on record shows that (on 06.03.2009) with reference to

Government resolution dated 21.01.2003, Government

Circular dated 21.02.2004 and Government resolution dated

26.02.2004; the Government circular dated 06.03.2009 has

been issued. However, it is mentioned as a government

resolution issued by the order and in the name of Governor of

Maharashtra. It further stipulates that in the government

circulars indicated in its reference part, in order to compensate

for irrigation loss on account of water reservation for non

irrigation use, the IRC be levied in future (henceforth) at Rs.

One lakh per Hectare. It expressly stipulates that new rate

becomes effective from 01.04.2009.

48. To understand what is irrigation restoration

charge, it is essential to look into the Government Resolution

dated 21.01.2003. In clause No.1, it gives preference number

to be accorded to demands for water, dependency upon its

user. Domestic user, has been placed at Sr.No. 1, Industrial

user has been placed at Sr.No. 2, while irrigation has been

placed at Sr.No. 3. This government resolution at its page No.

19, vide clause No. 13 mentions that the expenditure to

restore the land irrigation capacity should be computed at Rs.

50,000/- per Hectare. Vide Clause 10, it takes into

consideration total irrigation potential or capacity of the

project, loss in that capacity because of diversion of water for

non irrigational purposes and accordingly computation in

clause 13 is required to be worked out to compensate for that

loss. A circular no. BWS-1003 dated 21.02.2004 has been

issued thereafter, by order and in the name of Governor of

Maharashtra. Reason for its issuance is confusion over

recovery of capital contribution and irrigation restoration

charges at regional level which was causing delays in

executing the agreements with non-irrigation water user

bodies. Clause A therein deals with contribution towards

capital costs and enables the user body like the petitioner to

pay water levy at a higher rate, instead of said contribution.

Present petitioner has opted for this higher rate. Clause B is

relevant here. It is on the subject of irrigation restoration

charge. It reads as under -

About Irrigation Restoration Charges : As "B).

per prevailing directives, cost @ Rs. 50,000/- per Hectare is calculated towards loss in irrigation capacity due to water reservation for non-irrigation

purpose. Following directives are being issued in this regard

1) If the construction of canal network for

distribution for the area under irrigation of the

project is complete then the cost of irrigation restoration for the loss in irrigation area should be

recovered from the body for whom the water is reserved.

2) The work of under construction of distribution network should be curtailed keeping in

view the loss of area under irrigation on account of reservation for non-irrigation in the command area

of the project and further work of redundant distribution system should be immediately stopped. In such cases, there will not be any issue of recovery

of irrigation restoration charges as there will be no further expenditure.

3) If the distribution system in the command area where there is likely loss of irrigation on account of reservation for non irrigation is partially built, then further construction work of distribution system should be immediately stopped and the costs incurred

should be recovered from the entity for whom water

has been reserved for non-irrigation use. This cost

will be less than the stipulated area of Rs. 50,000/- per hectare."

(Emphasis added by Court)

Clause C thereafter is about requirement of

agreement to be made with such bodies. It warns that supply

of water without agreement would be viewed as grave

misconduct.

49. Scheme of Clause B supra shows that when such a

demand for non-irrigational purpose is made, and it is likely to

result in loss of irrigation, further construction work of

distribution channels etc. Of that irrigation project needs to

be immediately stopped. Costs ialready ncurred are to be

recovered from the body for whom water is to be reserved for

non-irrigational use. In that case, State Government has stated

that such costs would be less then the stipulated rate of Rs.

50,000/- per hectare. Thus, sub-clause [3] above of Clause B

shows that actual expenditure incurred till then for facilitating

use of quantity of water reserved for petitioner is to be

recovered from it. It also states that further expenditure for

facilitating the distribution of said quantity of water for

irrigation purposes ought not be incurred. Sub-clause [2] also

requires that in such an eventuality, construction of

distribution net-work should be curtailed and for that purpose,

proportionate reduction in area of land to be irrigated as water

is diverted for non-irrigational purposes is to be borne in mind.

Thus, because of proportionate reduction in command area of

project, the State Government has directed that the

construction of project or distribution net-work rendered

redundant due to water allocation should be

discontinued/stopped. It has further added that in that case

there would not be any issue of recovery of irrigation

restoration charge, as there would not be any further

expenditure. This therefore shows that IRC may not be due

and payable in all cases where the water is allocated for non-

irrigational purposes at the beginning of construction work of

an irrigation project. Proportionate water quantity already

allocated for non-irrigational purpose is deleted from

consideration for the purpose of completion of such project

and expenditure to utilize it for irrigation is avoided. Hence,

in that event, as no expenditure is incurred for providing that

water for irrigation purposes, the IRC is not payable by bodies

like petitioner. Even in sub-clause [1] when work of canal or

network for distribution of such reserved quantity of water is

complete, its actual costs as required to be recovered from the

body like petitioner. This arrangement & stipulation of norm

to determine IRC is already inbuilt in the scheme &, hence, not

negotiable between the parties. It flows into every contract

automaticaly & the State Governemnt can not deviate from it.

It is the basis on which bodies like Petitioner are induced to

take steps, finalize their power generation project and invest

on it.

50. This scheme of clause "B" supra, therefore, shows

that the extent of land to which irrigation facility could have

been provided by using the quantity of water which is diverted

for non-irrigational purpose is relevant only initially to

determine the amount spend to appropriate it for irrigation.

Once that amount is ascertained, change in said potential due

to improved infrastructure or technology is irrelevant and is

not the norm to be looked into. Only if any expenditure is

incurred for actually distributing (appropriating) the allocated

quantity of water or any part of it for irrigational purpose, then

only that much expenditure which otherwise represents the

part of project costs, is to be recovered from the body for

whom that water is reserved. This exercise therefore, is to be

undertaken only once and that is on the date on which water

is allocated or reserved. The government resolutions and

circulars prohibit further expenditure in any irrigation project,

on or for this reserved/ allocated quantity of water. It is this

amount actually spent till date of reservation of said water

which is recoverable from any industry as IRC. Hence,

considering this scheme, it appears that date on which the

allocation is made or water is reserved for petitioner is

significant and relevant. The date of agreement between

Petitioner & the Respondent has got no bearing on this issue.

The petitioner sought water allocation in December 2007 and

High Power Committee accepted it in its meeting dated

13.05.2007. Water agreement was then executed on

22.09.2008. It granted time of three years to Petitioner to

enter into an elaborate agreement & that time was extended

by one more year. Ultimately, within the tipulated time i.e. on

22.05.2012, the later agreement has been entered into. Later

agreement is essentially due to watrer reservation or allocation

on 22.09.2008. Later agreement dated 22.05.2012 does not

reserve or allocate water but specifies how that water is to be

used.

51. Mega Power Policy of Maharashtra State for

investment in power generation sector for capacity addition of

500 MW and above, issued on 28.03.2005 shows a decision to

promote the investment in power generation sector by giving

adequate support and single window clearance. State

Government has assured the availability of water for such

project. Certain other exemptions or incentives have been

granted while extending initial support. We need not delve

into the nicites thereof, but, it is in consonance with the

circular dated 21.02.2004 supra.

52. Agreement entered into between the parties on

22.05.2012, needs to be perused in this background. In this

agreement, petitioner - Company has instead of capital

expenditure, agreed to pay for water supplied at a higher rate

as per government resolution dated 21.02.2004. According to

it, petitioner company has to pay IRC (irrigation restoration

charge) calculated at Rs. 1,00,000/- her hectare, and

accordingly total Rs. 232.18 crores is to be paid in 5

installments over a period of two years with applicable

interest, for which it has to give Bank Guarantee equivalent to

10% i.e. of Rs. 23.218 crores. It has been also agreed

between them that decision on representation of petitioner

company dated 25.01.2011, addressed to Government shall be

binding on the parties. Petitioner Company has accordingly

submitted an undertaking on same date and in that

undertaking, it has reiterated its commitment to pay IRC of Rs.

232.18 Crores with interest and in installments, as stated

therein. Clause 8 of the undertaking mentions that

undertaking is without prejudice to rights of the petitioner,

made in the representation. The respondents have accepted

this undertaking. The Respondents before this Court accept

that readiness and willingness expressed by the petitioner to

pay IRC of Rs. 232.18 crores is subject to decision on its

representation dated 25.01.2011.

53. This representation dated 25.01.2011, points out

rate of IRC to NTPC, Adani Power Maharashtra, Adani GR

Power and Reliance Energy Limited. It then complains that

there is no uniformity in criteria for determining the loss of

irrigation potential. It states that calculation of area which

could have been brought under irrigation varies from 65

hectares MM3 to 265 hectares MM3. It is pointed out that

highest rate of 6.28 Crores has been applied to Petitioner. It

also points out that as per the original proposal dated

11.01.2008, only an amount of Rs. 147.84 Crores was

proposed to be recovered & out of it, sum of Rs. 116.09 Crores

was towards restoration of irrigation potential, while Rs. 31.75

Crores was towards capital investment. This demand is

obviously as per the government circular dated 21.02.2004 at

Rs. 50,000/- per Hectare . Along with this representation, the

petitioner also supplied a chart showing projects where water

allocation was approved by HPC (High Power Committee),

with details thereof. Again we need not delve into details

thereof. This representation does not dispute the area of land

to be considered to be 23,218 hectares, but, requests for

applying rate of Rs.50,000/- per hectare in relation thereto so

that total demand towards IRC works out to Rs. 116.09 Crores.

The respondents demand Rs. One lakh per hectares and hence,

total amount of Rs. 232.18 Crores. It is therefore, obvious

that in this representation, which is prior to the agreement,

there is no dispute about the extent of area with respect to

which IRC needs to be worked out. It is this representation,

subject to which an agreement has been entered into between

the parties, and subject to which an undertaking has been

furnished by the petitioner and accepted by the respondents.

In view of this position, the arguments of Shri M.G. Bhangde,

learned Senior Counsel that area with relation to which IRC

needs to be computed need not be and cannot be gone into.

He has advanced three different arguments and Shri R. Deo,

learned Associate Advocate General has in reply pointed out

that because of later improvements and modifications,extent

of area deprived of irrigation is much more. In the light of

our findings on water allocation policy and resolution dated

21.02.2004, changes in project potential after reservation of

water in favour of any body like petitioner cannot result in

adding to the burden of petitioner. State Government does

not permit any expenditure to be incurred to facilitate

distribution of that quantity of water which is reserved for

petitioner, and therefore, is no more available for irrigation

purpose. This is also in consonance with the decision of the

State Government to promote such power generation in State

of Maharashtra. Orders of this Court in Writ Petition No.

2174/2012, passed at Bombay on 22.11.2012 are in

appreciation of these documents. The Division Bench has

directed the State Government to decide the representation of

petitioner dated 25.01.2011, and also subsequent

representations within a period of eight weeks. It has also

directed that if as an outcome thereof, IRC are scaled down,

it would be open to the petitioner to pursue an appropriate

remedy available in law, either for refund or as the case may

be, to adjust the amount found in excess towards future

charges to be paid to the Respondents. It needs to be noted

that the said Division Bench has kept all rights and contentions

of parties open in case it became necessary for the petitioner to

challenge any adverse decision taken on said representations.

Division Bench, therefore, has entertained the Writ Petition

No. 2174/2012 and has also issued certain directions. It has

not held that the petition before it was not maintainable. This

discussion is sufficient to negate the arguments of res-judicata

or constructive res-judicata advanced by the learned Associate

Advocate General.

54. Here, it is necessary for us to briefly mention what the

Division Bench has said in its order dated 22.11.2012 in Writ

Petition No. 2174 of 2012 . In paragraph no.1, history has

been taken note of, it has then found that before entering into

an agreement dated 22.05.2012, petitioners paid first

installment of Rs. 46.43 Crores and Second installment of Rs.

60.53 Crores was due on 21.11.2012. After representation

dated 25.01.2011, petitioners submitted later representation in

the month of February and June, 2011 claiming levy of IRC at

Rs.50,000/- per hectare. Their complaint about discrimination

is then taken note of by the Bench. The Division Bench has

also noted that the petitioner claimed allocation approval in

2008 when rate of Rs. 50,000/- per hectare was in vogue as

per Circular dated 21.02.2004, and it was before revision of

the rate which took place on 26.03.2009. In paragraph No.3

of the order, the statement made by the Government Pleader

that representation submitted by the petitioner is pending

consideration and decision thereon would be arrived at within

reasonable period has been taken note of. The said Division

Bench also then looks into communication of petitioner dated

10.05.2012, whereby the petitioner did agree to pay Rs.

232.18 Crores in 5 installments over a period of 2 years with

interest but subject to decision on their representations as also

to consequential reduction or modification of installments and

adjustments of amount found paid in excess. Argument that

matter pertains to contractual obligation and hence, the Court

should not intervene, has also been taken note of. The

Government Pleader there had submitted that the second

installment was due on 21.11.2012, memo of Writ Petition No.

2174 of 2012 was affirmed on 05.11.2012 and was moved

only on 21.11.2012. The petitioners in reply, had pointed out

to that Division Bench that first and second installments by

them cover amount of Rs. 106 Crores, leaving balance amount

of Rs. 10 Crores and it would have become payable only in

May, 2014.

55. In paragraph No.5 of the order, the letter dated

10.05.2012 whereby the petitioner accepted the liability to pay

an amount of Rs. 232.18 Crores in 5 installments has been

considered and its material part has been reproduced. Then in

paragraph No.6 agreement entered into between the parties,

during the pendency of representations on 22.05.2012 and

approaching the Bench at fag end when second installment

was due has been considered. Undertaking furnished on

22.05.2012 has then been looked into. The Division Bench

expressed that taking over all view of the matter, it would not

be possible for it to obviate compliance with the agreement. In

the light of this finding, directions as mentioned supra has

been issued.

56. The present Writ Petition was tendered at Bombay

and registered as Writ Petition No. 1487 of 2013. While

passing orders in Writ Petition No.1487 of 2013 on

17.06.2014, the Division Bench at Bombay in paragraph no.10

observed that both the parties needed to consider whether

amount of Rs. 116.57 Crores already paid by the petitioner can

be considered as adequate IRC with a view to giving a

quietus to the entire controversy. The Division Bench in this

interlocutory order has also considered the contingency in

which the petitioner's challenge to computation of IRC at Rs.

One lakh per hectare was rejected, but, then State Government

was required to consider in the light of its subsequent report,

as to whether loss of irrigation facility would be only to the

extent of 4600 hectares, as against 23219 hectares, as

originally estimated. It held that the amount payable qua said

area would work out approximately to Rs. 46 Crores thereby

needing a refund. The Division Bench therefore, by way of ad-

interim order observed that it would be appropriate if both the

parties consider whether amount of Rs. 116.57 Crores already

paid by the petitioner, should be considered as adequate

irrigation restoration charges. In paragraph No.11, the said

Division Bench also takes note of the fact that the petitioner is

paying Block Water Tariff at a higher rate of Rs. 32 per 10000

liters. Paragraph No. 14 of the said order shows that amount

of Rs. 10 Crores was deposited on 21.05.2013, by petitioners.

In the light of these findings, the Division Bench granted ad-

interim stay of coercive recovery of balance amount of

irrigation restoration charges. This interim order continues to

operate even today.

57. The water is a natural and scarce commodity.

Similarly, "electricity" cannot be viewed differently. The

power generation plants are therefore, categorized as Public

Utility Industries. To make up the deficit in need of electricity

in State of Maharashtra, the State Government formulated a

scheme and allowed water, which was till then being used

primarily for irrigation purposes, to be withdrawn and used for

generation plants. Domestic users were given first preference,

while industrial use was placed at second number. Irrigation

purpose was placed at last as third one. In consonance with

this policy, a Mega Policy has come on 28.03.2005. Various

government resolutions and circulars needs to be viewed in

this background. Circular dated 21.02.2004 is issued to avoid

any confusion & hence, the State itself has declared itself to be

bound by it. No negotiations are possible on the factors

stipulated & regulated therein. IRC rate is expressly agreed to

be contingent upon the decision on Petitioner's representation

by the parties thereto. Rate of IRC is not seen left to be a

negotiable term of contract by the State but it has been

determined by GR or circular which may operate against the

wish of parties to Contract. The scheme for working out IRC

looked into above by us show that the rate of IRC may be less

than Rs. 50,000/- per hectare, minimum demand may be of

actual amount spent by the State while the maximum may be

Rs. 50,000/ per hectare. In a given case, there may be no

demand on account of IRC at all. We find that parties before

us are not litigating with any ulterior motive. Respondents

have not pointed out any mala fides on the part of the

petitioners. or vice versa. Though Writ Petition at Bombay

was filed at eleventh hour, it cannot be forgotten that the

representations made by the petitioners long back prior

thereto were pending and not decided by the State

Government. The Division Bench which has disposed of the

Writ Petition No. 2714 of 2012 on 22.11.2012, has looked into

all these and moulded the relief. That Division Bench finds it

necessary to direct the government to decide those

representations and also declares that the rights of petitioner

be altered and modified accordingly.

58. It is in this background that we have to appreciate the

precedents of the parties. To urge that there is no scope for

intervention available to this High Court in contractual

matters, the Respondent State has relied upon Orissa State

Financial Corpn. v. Narsingh Ch. Nayak, (2003) 10 SCC 261.

Hon'ble Apex Court in said judgment at page 263, takes note

of the fact that the High Court while considering the writ

petition filed by the owner of the vehicle for quashing of the

notice of auction-sale and for other consequential reliefs,

passed an order drawing up a fresh contract between the

parties and issued certain further directions in the matter i.e.

the Corporation had been directed to advance a fresh loan to

the writ petitioner to enable him to purchase a new truck; to

enter into agreement for realization of the balance loan

amount in accordance with law; to write off the remaining

amount of Rs.16,500 and to order waiving of the interest

liability etc. This type of order is declared beyond the scope

of the writ petition which was being considered by the High

Court and beyond the jurisdiction of the Court in a contractual

matter. Here, the issue is whether formula for computing IRC

in circular dated 21.02.2004 could have been overlooked by

the Petitioner power generation unit or the Respondents who

assured water to it.

59. In Pimpri Chinchwad Municipal Corpn. v. Gayatri

Construction Co., (2008) 8 SCC 172, the respondent Contractor

filed a writ petition in High Court challenging the termination

of his contract and publication of fresh tender invitation for

construction of road. Appellant Corporation pointed out the

disputed questions involved as also the provision for resolution

thereof in agreement. Hon'ble Apex Court, in para 6 takes

note of the disputed questions of facts arising between the

parties in said background, finds recourse to in house remedy

necessary. This aspect is also clear from State of U.P. v. Bridge

& Roof Co. (India) Ltd., (1996) 6 SCC 22, at page 29 : where

Hon'ble Apex Court, in para 16 observes that the contract

between the parties was a private and not a statutory contract.

Any dispute relating to interpretation of the terms and

conditions of such a contract cannot be agitated, and could not

have been agitated, in a writ petition. That was a matter

either for arbitration as provided by the contract or for the civil

court. All disputed questions arose under said contract which

could not be r adjudicated upon in a writ petition.

60. The effect of arbitration clause or in house remedy is

also clear from State of Orissa v. Bhagyadhar Dash, (2011) 7

SCC 406 : in para 22 observes that the clause in agreement can

not be construed to be an arbitration agreement. It operated

where in regard to a non-tendered additional work executed

by the contractor, if the contractor was not satisfied with the

unilateral determination of the rate therefor by the Engineer-

in-Charge, the rate for such work was to be finally determined

by the Superintending Engineer. It holds that a provision was

made with the intention to avoid future disputes regarding

rates for non-tendered item. The decision of the

Superintending Engineer was not a judicial determination &

open to challenge by the other party in a court of law. In facts

before us, the Respondents themselves urge that the

representation of Petitioner is non-statutory one. Division

Bench of this Court at Bombay has expressly permitted

Petitioner to assail it.

61. Petitioner relies on on para 60 in judgment of Hon.

Apex Court, State of Karnataka v. All India Manufacturers

Organisation, (2006) 4 SCC 683, where it observes :---

              "60.   Shrilekha Vidyarthi    v.  State of U.P.
                                                               is another

authority for the proposition that the State Government has to act reasonably and without

arbitrariness even with regard to the exercise of its

contractual rights. In Dwarkadas Marfatia and Sons

v. Board of Trustees of the Port of Bombay the situation was one in which a lease between the Bombay Port Trust and certain parties was

terminated in exercise of contractual rights and the lease rent was abnormally increased. It was held that there was always an obligation on the part of

public authorities in their acts of omission and

commission to be reasonable. In Biman Krishna Bose v. United India Insurance Co. Ltd. the question

was whether an insurance company could arbitrarily and unreasonably refuse the renewal of a policy. Considering that the insurance company, as

a result of State monopoly in the insurance sector,

had become "State" under Article 12 of the Constitution, this Court held that:

"... it [the insurance company] requires (sic) to satisfy the requirement of reasonableness and fairness while dealing with the customers. Even in

an area of contractual relations, the State and its instrumentalities are enjoined with the obligations to act with fairness and in doing so, can take into consideration only the relevant materials. They must not take any irrelevant and extraneous consideration while arriving at a decision. Arbitrariness should not appear in their actions or

decisions."

62. The petitioner also relies on judgment of Hon'ble

Apex Court, in Reliance Energy Ltd. v. Maharashtra State Road

Development Corpn. Ltd., (2007) 8 SCC 1. There it is observed--

"36. We find merit in this civil appeal. Standards

applied by courts in judicial review must be justified by constitutional principles which govern

the proper exercise of public power in a democracy.

Article 14 of the Constitution embodies the principle of "non-discrimination". However, it is not a free-standing provision. It has to be read in

conjunction with rights conferred by other articles

like Article 21 of the Constitution. The said Article 21 refers to "right to life". It includes "opportunity". In our view, as held in the latest judgment of the

Constitution Bench of nine Judges in I.R. Coelho v. State of T.N., Articles 21/14 are the heart of the chapter on fundamental rights. They cover various

aspects of life. "Level playing field" is an important concept while construing Article 19(1)(g) of the Constitution. It is this doctrine which is invoked by REL/HDEC in the present case. When Article 19(1) ( g ) confers fundamental right to carry on business to a company, it is entitled to invoke the said doctrine of "level playing field". We may clarify that

this doctrine is, however, subject to public interest.

In the world of globalisation, competition is an

important factor to be kept in mind. The doctrine of "level playing field" is an important doctrine which is embodied in Article 19(1)(g) of the Constitution.

This is because the said doctrine provides space within which equally placed competitors are allowed to bid so as to subserve the larger public

interest. "Globalisation", in essence, is liberalisation

of trade. Today India has dismantled license raj. The economic reforms introduced after 1992 have

brought in the concept of "globalisation". Decisions or acts which result in unequal and discriminatory treatment, would violate the doctrine of "level

playing field" embodied in Article 19(1)(g). Time

has come, therefore, to say that Article 14 which refers to the principle of "equality" should not be

read as a stand alone item but it should be read in conjunction with Article 21 which embodies several aspects of life. There is one more aspect which

needs to be mentioned in the matter of implementation of the afore-stated doctrine of "level playing field". According to Lord Goldsmith, commitment to the "rule of law" is the heart of parliamentary democracy. One of the important elements of the "rule of law" is legal certainty. Article 14 applies to government policies and if the

policy or act of the Government, even in

contractual matters, fails to satisfy the test of

"reasonableness", then such an act or decision would be unconstitutional."

It is obvious that the government policy emanating

from the circular dated 21.02.2004 aimed at avoiding

uncertainty must be adhered to by the parties before this

Court. Said condition relating to IRC is already prescribed &

parties can not escape from it.

63. To explain the reach of Article 14 in contractual

matters, the Respondent State states that Hon'ble Apex Court

in Radhakrishna Agarwal v. State of Bihar, (1977) 3 SCC 457,

at page 465 : such questions of fact attracting Article 14 to

establish that the State, acting in its executive capacity through

its officers, has discriminated between parties identically

situated. were not argued before the High Court. And, in any

event, they were of such a nature that they could not be

satisfactorily decided without a detailed adduction of evidence

possible in ordinary civil suits., Moreover, the Hon'ble Apex

Court held that it is the contract and not the executive power,

regulated by the Constitution, which governed the relations of

the parties on facts. Here we have already found that to avoid

any confusion, circular dated 21.02.2004 has been taken out &

it denudes the State of its power to bargain on IRC.

64. The Respondent State points out that while

considering the reach of writ court in contractual matters as

also non permissibility of approbation and reprobation,

Hon'ble Apex Court in Rajasthan State Industrial Development

& Investment Corpn. v. Diamond & Gem Development Corpn.

Ltd., (2013) 5 SCC 470, where in para 21, it states that

generally the Court should not exercise its writ jurisdiction to

enforce the contractual obligation. The primary purpose of a

writ of mandamus is to protect and establish rights and to

impose a corresponding imperative duty existing in law. It is

designed to promote justice (ex debito justitiae). The grant or

refusal of the writ is at the discretion of the court. The writ

cannot be granted unless it is established that there is an

existing legal right of the applicant, or an existing duty of the

respondent. Thus, the writ does not lie to create or to establish

a legal right, but to enforce one that is already established.

While dealing with a writ petition, the court must exercise

discretion, taking into consideration a wide variety of

circumstances, inter alia, the facts of the case, the exigency

that warrants such exercise of discretion, the consequences of

grant or refusal of the writ, and the nature and extent of injury

that is likely to ensue by such grant or refusal. Earlier in

paragraph 15 on approbation & reprobation, it observes that a

party cannot be permitted to "blow hot-blow cold", "fast and

loose" or "approbate and reprobate". Where one knowingly

accepts the benefits of a contract, or conveyance, or of an

order, he is estopped from denying the validity of, or the

binding effect of such contract, or conveyance, or order upon

himself. This rule is applied to ensure equity, however, it

must not be applied in such a manner so as to violate the

principles of what is right and of good conscience. In the wake

of discussion supra, we find that these observations of Hon'ble

Apex Court apply against the State. The State has to adhere to

the stipulation in circular dated 21.02.2004 on IRC and it can

not turn around to usher confusion back into the matter. It

also accepted that agreement and undertaking by the

petitioner, both dated 22.05.2012 are subservient to the

decision on the petitioner's representation dated 25.01.2011

and acquiesced in directions of this Court at Bombay in Writ

Petition No. 2714 of 2012 dated 22.11.2012. Respondent State

itself has pointed out that Hon'ble Apex Court in Shyam

Telelink Ltd. vs. UOI, (2010) 10 SCC 165 - in paragraph 23

held that a person can not accept or reject a document in part.

65. On factual dispute Hon'ble Apex Court in paragraph 10

of Kerala SEB v. Kurien E. Kalathil, (2000) 6 SCC 293 observes

that the interpretation and implementation of a clause in a

contract cannot be the subject-matter of a writ petition. If a

term of a contract is violated, ordinarily the remedy is not the

writ petition under Article 226. It appears that there the

contractor was seeking enforcement of a non-statutory

contract. Hon'ble Apex Court points out that a contract would

not become statutory simply because it is for construction of a

public utility and it has been awarded by a statutory body. It

did not agree with the observation of the High Court that since

the obligations imposed by the contract on the contracting

parties came within the purview of the Contract Act, that

would make the contract statutory. In facts before us, the

Petitioner Company points out that rate of IRC is predecided

on 21.02.2004 and Respondents are highhandedly trying to

change it. Petitioners have acted upon the representation

contained in said circular dated 21.02.2004 & the State,

though has enhanced the rate, has not revised it

retrospectively. Further, the observations of Apex Court in

paragraphs 12 & 13 of said judgment pressed into service by

the Respondent State show that after considering the nature of

dispute, Hon'ble Apex Court has refused to intervene in the

matter and allowed the High Court judgment to operate.

66. When State Government has its exclusive hold on

water, formulates a policy, diverts water and assures it to be

available for power generation in public good in terms

thereof, the contract can not be viewed as an ordinary private

contract and this court should, if no disputed issue crops up,

attempt to adjudicate it, both in the interest of general public

and the parties. State of Haryana & Ors. vs. Lal Chand & Ors.

(1984) 3 SCC 634 is relied upon to state the difference

between a statutory contract and contract entered into by the

State in exercise of its executive power. However, in present

facts, considering the previous litigation and circular

regulating IRC, we are not inclined to dwell upon said aspect.

An assurance made to all industrial establishments on

21.02.2004 openly to avoid any confusion can not be allowed

to be defeated to the prejudice of Units like that of Petitioners

who have altered their position relying on it. Judgments of

Apex Court in Gurusharan Singh & Ors. vs. New Delhi

Municipal Committee & Ors., AIR 1996 SC 1175; Chandigarh

Administration & Anr. vs. Jagjit Singh & Anr., AIR 1995 SC

705; Jayant Vegoils & Chemicals vs. City & Industrial

Development Corporation of Maharashtra Ltd., Division Bench

judgment of this High Court reported in 1997 (2) Bom. C.R.

600 - are relied upon by the Respondent - State to urge that

instances which show an illegality or irregularity can not be

used to invoke Article 14 or Article 226 as the illegality or

irregularity can not be perpetuated. We are not examining

here violation of Article 14 because of alleged discrimination

but we find Article 14 breached as the circular dated

21.02.2004 has been not adhered to & the representation of

Petitioner was not promptly decided. Hon'ble Apex Court in

P.H. Paul Manoj Pandian v. P. Veldurai, (2011) 5 SCC 214 :

(2011) 2 SCC (Civ) 681, at page 230 in para 45 lays down

that the departmental circulars are a common form of

administrative document by which instructions are

disseminated. Many such circulars are identified by serial

numbers and published, and many of them contain general

statement of policy. They are, therefore, of great importance

to the public, giving much guidance about governmental

organisation and the exercise of discretionary powers. In

themselves they have no legal effect whatever, having no

statutory authority. But they may be used as a vehicle in

conveying instructions to which some statute gives legal force.

It is now the practice to publish circulars which are of any

importance to the public and for a long time there has been no

judicial criticism of the use made of them. It shows that even

the executive instructions in circular dated 21.02.2004 are

binding in such circumstances.

67. To buttress the submission that notes in a file can

not be used by the Petitioner to claim a right or then an

illegality or irregularity can not be perpetuated by using such

remarks, support is being drawn by the State from Shanti

Sports Club vs. UOI, (2009) 15 SCC 705. The Petitioner is

only pointing out a letter dated 17.01.2011 sent by one office

to other. Only on the basis of such a letter, course of action or

treatment suggested therein, petitioner can not raise any

ground to attack or seek any relief. Different thought

processes or varying opinions may be put forth by different

officers for consideration via such notes in office files and

object is only to enable the competent superior authority to

reach an appropriate view after evaluating all pros & cons. Till

that is done, no decision binding on the State or any artificial

person, emerges. We are also not recording a finding on any

right or seeing any right in petitioner on the strength of advice

tendered in said letter.

68. To justify absence of elaborate reasoning in an

administrative order rejecting the representation passed on

29.01.2013, Respondent submits that as held in UOI vs. E.G.

Nambudri, (1991) 3 SCC 38, since no civil consequences ensue

and no vested right of Petitioners is being taken away,

insistence of Petitioner on reasons is ill founded. We find it

suitable to reproduce paragraphs 7 & 8 of this ruling where

the Hon'ble Apex Court observes--

"7. On behalf of the respondent it was contended

that principles of natural justice require the superior authority to record reasons in rejecting the government servant's representation made against

the adverse remarks as the order of rejection affected the respondent's right. It is true that the old

distinction between judicial act and administrative

act has withered away and the principles of natural justice are now applied even to administrative orders

which involve civil consequences, as held by this Court in State of Orissa v. Dr (Miss) Binapani Dei. What is a civil consequence has been answered by this

Court in Mohinder Singh Gill v. Chief Election

Commissioner. Krishna Iyer, J. speaking for the Constitution Bench observed: (SCC p. 440, para 66)

"But what is a civil consequence, let us ask ourselves, bypassing verbal booby-traps? 'Civil consequences' undoubtedly cover infraction of not merely property

or personal rights but of civil liberties, material deprivations and non-pecuniary damages. In its comprehensive connotation, everything that affects a citizen in his civil life inflicts a civil consequence."

The purpose of the rules of natural justice is to

prevent miscarriage of justice and it is no more in

doubt that the principles of natural justice are

applicable to administrative orders if such orders affect the right of a citizen. Arriving at the just decision is the aim of both quasi-judicial as well as

administrative enquiry, an unjust decision in an administrative enquiry may have more far-reaching effect than decision in a quasi-judicial enquiry. Now,

there is no doubt that the principles of natural justice

are applicable even to administrative enquiries. See: A.K. Kraipak v. Union of India.

8. The question is whether principles of natural

justice require an administrative authority to record

reasons. Generally, principles of natural justice require that opportunity of hearing should be given to the person against whom an administrative order

is passed. The application of principles of natural justice, and its sweep depend upon the nature of the rights involved, having regard to the setting and

context of the statutory provisions. Where a vested right is adversely affected by an administrative order, or where civil consequences ensue, principles of natural justice apply even if the statutory provisions do not make any express provision for the same, and the person concerned must be afforded opportunity of hearing before the order is passed. But principles

of natural justice do not require the administrative

authority to record reasons for the decision as there

is no general rule that reasons must be given for administrative decision. Order of an administrative authority which has no statutory or implied duty to

state reasons or the grounds of its decision is not rendered illegal merely on account of absence of reasons. It has never been a principle of natural

justice that reasons should be given for decisions.

See: Regina v. Gaming Board for Great Britain, ex p. Benaim and Khaida. Though the principles of

natural justice do not require reasons for decision, there is necessity for giving reasons in view of the

expanding law of judicial review to enable the citizens to discover the reasoning behind the decision.

Right to reasons is an indispensable part of a sound system of judicial review. Under our Constitution an

administrative decision is subject to judicial review if it affects the right of a citizen, it is therefore desirable that reasons should be stated."

In M/s Mahabir Jute Mills Ltd. vs. Shri Shibban Lal ,

(1975) 2 SCC 818 - cited by the Respondents Hon'ble Apex

Court considers act of appropriate government of refusing to

refer an industrial dispute u/s. 4-K of U.P. Industrial Disputes

Act, 1947. In present facts, in view of discussion already done,

We do not find it necessary to refer to it at length.

69. Respondents also submit that as held in Union of

India v. M.K. Sarkar, (2010) 2 SCC 59 the High Court can not

issue direction to decide the representations made

unnecessarily by the Petitioners & in any case, no cause of

action accrues in favour of petitioner, because of the decision

thereon. Following paragraphs in above judgment are relied

upon :---

"14. The order of the Tribunal allowing the first

application of respondent without examining the merits, and directing the appellants to consider his representation has given rise to unnecessary litigation

and avoidable complications. The ill-effects of such directions have been considered by this Court in C. Jacob v. Director of Geology and Mining: (SCC pp.

122-23, para 9 "9. The courts/tribunals proceed on the assumption, that every citizen deserves a reply to his representation. Secondly, they assume that a mere direction to consider and dispose of the representation does not involve any 'decision' on rights and obligations of parties. Little do they realise

the consequences of such a direction to 'consider'. If

the representation is considered and accepted, the ex-

employee gets a relief, which he would not have got on account of the long delay, all by reason of the direction to 'consider'. If the representation is

considered and rejected, the ex-employee files an application/writ petition, not with reference to the original cause of action of 1982, but by treating the

rejection of the representation given in 2000, as the

cause of action. A prayer is made for quashing the rejection of representation and for grant of the relief

claimed in the representation. The tribunals/High Courts routinely entertain such applications/petitions

ignoring the huge delay preceding the representation, and proceed to examine the claim on merits and

grant relief. In this manner, the bar of limitation or the laches gets obliterated or ignored."

15. When a belated representation in regard to a "stale" or "dead" issue/ dispute is considered and decided, in compliance with a direction by the

court/tribunal to do so, the date of such decision cannot be considered as furnishing a fresh cause of action for reviving the "dead" issue or time-barred dispute. The issue of limitation or delay and laches should be considered with reference to the original cause of action and not with reference to the date on which an order is passed in compliance with a court's

direction. Neither a court's direction to consider a

representation issued without examining the merits,

nor a decision given in compliance with such direction, will extend the limitation, or erase the delay and laches."

70. The representation of the Petitioners here can not

be seen as uncalled for. It is pointing out the rate of IRC

stipulated in circular dated 21.02.2004 and impact thereof.

This representation finds mention in the agreement between

the parties & also in undertaking of the Petitioner accepted by

the Respondents. The rate of IRC is expressly contingent upon

the adjudication of said representation. The Division Bench at

Bombay has in Writ Petition No. 2714 of 2012 on 22.11.2012,

expressly directed the Respondent State to decide it & to give

effect to that decision. Petitioner is left free by it to assail the

adverse decision on it. Hence, here neither the said

representation nor decision thereon can be viewed in the light

of law expounded by Hon'ble Apex Court in this judgment.

Observations of Hon'ble Apex Court itself show that nature of

representation seen therein is all together different than

Petitioner's representation.

71. Petitioner submits that as held in Devi Multiplex v.

State of Gujarat, (2015) 9 SCC 132, the doctrine of promissory

estoppel must apply to the rate of IRC in these facts. There the

Hon'ble Apex Court states :---

"20. The law on the subject of promissory estoppel

------- .......... ---------- ............... ---------- Godfrey

Philips India Ltd. by a Bench of three Judges. We deem it appropriate to quote paras 27-29, 34, 35

and 36 from the decision in State of Punjab v. Nestle

India Ltd.: (SCC pp. 474-78)

"27. However, the superstructure of the doctrine with its

preconditions, strengths and limitations has been

outlined in the decision of Motilal Padampat Sugar Mills Co. Ltd. v. State of U.P. Briefly stated: --------- .................... --------------- ................. ------------ State

Government so as to inhibit it from formulating and implementing its policies in public interest.

28. This Court rejected all the three pleas of the Government. It reiterated the well-known preconditions for the operation of the doctrine:

(1) a clear and unequivocal promise knowing and intending that it would be acted upon by the promisee;

(2) such acting upon the promise by the promisee so that it would be inequitable to allow the promisor to go

back on the promise.

29. As for its strengths it was said: that the doctrine was not limited only to cases where there was some contractual relationship or other pre-existing legal

relationship between the parties. The principle would be applied even when the promise is intended to create legal relations or affect a legal relationship which would

arise in future. The Government was held to be equally

susceptible to the operation of the doctrine in whatever area or field the promise is made--contractual,

administrative or statutory. To put it in the words of the Court:

'The law may, therefore, -------- .............. ------------

................. ------------ ................ to carry out the promise made by it.' (SCC p. 453, para 33)

34. The discordant note struck by Jit Ram case was firmly disapproved by a Bench of three Judges in Union of India v. Godfrey Philips India Ltd. It was affirmed that:

(SCC p. 387, para 12)

'12. There can therefore be no doubt that the doctrine of promissory estoppel is applicable against the Government in the exercise of its governmental, public or executive functions and the doctrine of executive necessity or freedom of future executive action cannot

be invoked to defeat the applicability of the doctrine of

promissory estoppel.'

35. It was held that irrespective of the nature of power wielded the Government is bound to wield that power

provided it possessed such power and has promised to do so knowing and intending that the promisee would act on such promise and the promisee has done so:

(Godfrey Philips India Ltd. Case 9, SCC p. 389, para 14)

'14. ... We think that the Central Government had power under Rule 8 sub-rule (1) of the Rules to issue a

notification excluding the cost of corrugated fibreboard

--------- ................. ----------------- ................ ------------

bound by promissory estoppel to exclude the cost of

corrugated fibreboard containers from the value of the goods for the purpose of assessment of excise duty for the period 24-5-1976 to 2-11-1982.'

36. The limitations to the doctrine delineated in Motilal Padampat Sugar Mills however, were also reaffirmed

when it was said: (Godfrey Philips India Ltd. Case 9, SCC pp. 387-88, para 13) '13. ... [T]hat there can be no promissory estoppel against the legislature in the exercise of its legislative functions nor can the Government or public authority be debarred by promissory estoppel from enforcing a statutory prohibition . It is equally true that promissory

estoppel cannot be used to compel the Government or a

public authority to carry out a representation or promise

which is contrary to law or which was outside the authority or power of the officer of the Government or of the public authority to make. We may also point out

that the doctrine of promissory estoppel being an equitable doctrine, it must yield when the equity so requires; if it can be shown by the Government or public

authority that having regard to the facts as they have

transpired, it would be inequitable to hold the Government or public authority to the promise or

representation made by it, the Court would not raise an equity in favour of the person to whom the promise or representation is made and enforce the promise or

representation against the Government or public

authority.'"

(emphasis in original)

In present facts declaring mode and manner of

computing IRC by circular dated 21.02.2004, the Sate

Government has not breached any statutory provision or

public interest. The concession or incentive offered by the

State is in larger public interest and the Respondents do not

even whisper that said policy violates any legal provision. We

have also pointed out how these executive instructions need to

be perceived with the help of judgment of Hon'ble Apex Court

in P.H. Paul Manoj Pandian v. P. Veldurai, supra.

72. The petitioner submits that even in contractual

matters the State can not act unfairly. We find their reliance

on Meerut Development Authority v. Assn. of Management

Studies, (2009) 6 SCC 171, apt in this case. Hon'ble Apex

Court, there, observes :--

"35. In Tata Cellular this Court observed that: (SCC p. 675, para 71) Judicial quest in administrative matters is to strike the just balance between the

administrative discretion to decide matters as per

government policy, and the need of fairness. Any unfair action must be set right by judicial review.

36. In Chief Constable of the North Wales Police v. Evans Lord Hailsham stated: (WLR p. 1161 A-B) The

underlying object of judicial review is to ensure that the authority does not abuse its power and the individual receives just and fair treatment, and not to ensure that the authority reaches a conclusion which is correct in the eyes of the court."

73. To explain the import of phrase "subject to"

employed in the agreement as also in undertaking dated

22.5.2012, Petitioner has invited our attention to South India

Corporation (P) Ltd. vs. Secretary, Board of Revenue,

Trivandrum & Anr., AIR 1964 SC 247(1)--1964) 4 SCR 280

where in paragraph 19, Hon'ble Court states :--

"19. That apart, even if Article 372 continues the

pre-Constitution laws of taxation, that provision is

expressly made subject to the other provisions of the Constitution. The expression "subject to" conveys

the idea of a provision yielding place to another provision or other provisions to which it is made subject. Further Article 278 opens out with a non

obstante clause. The ------- ....... ------------- in respect

of "works contracts".

When facts at hand are scrutinized in the light of

these two precedents, the omission or avoidance to decide the

representation of the petitioner for quite some time and till

this Court directed the State Government to do it, all show

improper and unwarranted approach on the part of the

respondents.

74. We find the water allocation is finalized on

12.12.2007 after High Power Committee accepted it in its

meeting dated 13.05.2007. On 16.08.2008 sanction is granted

for permanent water allocation of 87.60 MCM from completed

Upper Wardha Project and it is to be operational only after

agreement is made. As per clause 13, though action was to be

taken within three years, period was extended up to

31.05.2012. The Petitioners have paid the amount in

installments and not when it was determined or water was

reserved for it. The petitioner has, in communication dated

10.05.2012, agreed to pay Rs. 232.18 Crores in five

installments over a period of two years with interest. Hence,

for this delayed payment of IRC, interest of justice demands

that it must pay the interest @ 10% per annum.

75. Accordingly we partly allow the petition and

declare that demand of IRC at revised rate i.e. as per decision

dated 06.03.2009 from the petitioners is illegal and

unsustainable. Said decision dated 06.03.2009 fixes maximum

rate of IRC at Rs. One lakh per Hectare prospectively from

01.04.2009 and is not applicable in case of petitioner to whom

water allocation is finalized on 12.12.2007. Hence the

Respondents shall accordingly receive the IRC at the rate of Rs.

50.000/- per Hectare with interest as mentioned supra.

76. The Petitioner shall accordingly calculate the entire

amount and balance amount after taking credit for payments

already made shall be deposited with the Respondents within

four weeks. In default, it will be open to the Respondents to

recover the same by invoking such coercive means as are open

to it in law.

77. Writ petition is thus partly allowed. Rule is made

absolute accordingly with no order as to costs.

             JUDGE                                                   JUDGE

                                        ******





      *GS/RGD/Dragon.





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter