Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Anand Singh W/O Rk Singh vs Executive Engineer, National ...
2016 Latest Caselaw 2165 Bom

Citation : 2016 Latest Caselaw 2165 Bom
Judgement Date : 3 May, 2016

Bombay High Court
Anand Singh W/O Rk Singh vs Executive Engineer, National ... on 3 May, 2016
Bench: B.P. Dharmadhikari
     wp2220.05                                                                        1

                IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                          NAGPUR BENCH, NAGPUR.




                                                                           
                      WRIT PETITION NO.  2220  OF  2005




                                                   
     Smt. Anand Singh w/o R.K. Singh,
     aged - Major, occupation - Business,
     resident of Maiher, Tah. - Satna,




                                                  
     Madhya Pradesh.                                ...  PETITIONER

                    Versus




                                       
     1. Executive Engineer,
        National Highway Division No. 14,
                             
        Nagpur.

     2. The Collector, Satna, M.P.
                            
     3. The Tahsildar, 
        Revenue Department, 
        Maiher, District - Satna, M.P.              ...   RESPONDENTS.
      


     Dr. Anjan De, Advocate for the petitioner.
   



     Shri M.M. Ekre, AGP for the respondents.
                          ..... 

                                          CORAM : B.P. DHARMADHIKARI





                                                  P.N. DESHMUKH, JJ.

MAY 03, 2016.

ORAL JUDGMENT ( Per B.P. DHARMADHIKARI, J.)

Heard Shri De, learned counsel for the petitioner and Shri

Ekre, learned AGP for the respondents.

2. By placing reliance upon the Agreement dated 09.06.1993

between the petitioner and the respondents, in relation to recovery of

toll on Borgaon Bridge, Shri De, learned counsel submits that as per

Clause 7, if the bridge remains closed for traffic on account of law and

order situation or act of God or other natural calamities, the petitioner

becomes entitled to rebate as stipulated therein. The bridge could not

be used and toll could not be collected between 31.07.1993 and

07.08.1993 and thereafter from 15.09.1993 and 29.09.1993. This was

on account of All India strike call of Transporters. The petitioner

accordingly claimed rebate for said period. It was also recommended

by the Sub-Divisional Engineer of National Highway, Sub-Division No.

55, Bhandara. In spite of this recommendation, on 08.09.1995, the

petitioner received a demand of Rs.5,61,596, (including interest @

18%) for the period from 01.03.1994 to 30.09.1995. He contends that

thereafter the petitioner submitted reply but without looking into it

and without extending an opportunity of hearing, the impugned order

has been passed on 21.11.1997 i.e. after more than two years.

3. Shri De, learned counsel submits that the period for which

recovery is demanded is not clear. However, if it is for the period of

strike, the claim of the petitioner for rebate ought to have been looked

into. He points out that by impugned order dated 21.11.1997, rebate

claim has been rejected on the ground that no substantial evidence is

submitted by the petitioner regarding temporary closure of bridge. He

invites attention to judgment dated 08.01.2015 delivered by this Court

in Writ Petition No. 3265 of 1999 where an identical notice of same

date was questioned by the Contractor collecting toll and this Court

has remanded the matter for extending appropriate opportunity to the

petitioner.

4. Shri Ekre, learned AGP is relying upon reply affidavit. He

submits that the impugned order clearly points out that the

respondents did not order closure of bridge and the transportation was

also not closed.

5. We find that Sub-Divisional Engineer has on 22.09.1993

submitted a proposal to the Executive Engineer pointing out no

collection of toll between 31.07.1993 and 07.08.1993 and resumption

thereafter from 09.08.1993. This is due to strike of Transport

Association of India.

6. In his later communication dated 19.01.1994 for a period

from 15.09.1993 to 29.09.1993, again he has given same certificate

and pointed out that toll recovery could be resumed on 30.09.1993.

These two letters sent by a responsible officer of Respondent No. 1

constitute evidence on record to show that there could not have been

toll recovery during this period.

7. The RRC sent to the Collector which shows recovery of

Rs.5,61,596/- is dated 08.09.1995. It mentions collection of toll tax at

Borgaon bridge as its subject. However, the period of demand has not

been specified. The notice requests the Collector to recover total

amount of Rs.5,61,596/- (including 18% interest) with effect from

01.03.1994 to 30.09.1995. The period for which the petitioner

could not collect tax, has been mentioned by us supra. Whether the

demand is for the same period or for different period is not very clear.

The period of 01.03.1994 to 30.09.1995 may be the period for which

interest has been calculated but that also is not very clear.

8. In this background, when the impugned order is perused, it

rejects rebate claim of the petitioner on the ground that the petitioner

did not produce substantial evidence regarding temporary closure of

bridge. It is further stated that other mode of transportation, such as

State Transport (S.T.) buses and light vehicles were plying on said

bridge and hence there was only change or variance in traffic pattern

and there was no total closure. It is further pointed out that there was

no order given by the Competent Authority to close down the toll

collection during the said period. As total closure was not established,

the case of the petitioner was treated as one under clause 8 and not

under clause 7.

9. We find this appreciation erroneous and perverse. Two

communications sent by the responsible officer like Sub-Divisional

Engineer are totally lost sight of. In any case, in view of apparent

vagueness in RRC dated 08.09.1995, it is clear that the petitioner

ought to have been given sufficient opportunity in the matter.

10. We, therefore, find it just to adopt the course in the

judgment dated 08.01.2015 in Writ Petition No. 3265 of 1999 supra.

Accordingly, we quash and set aside the impugned order dated

21.11.1997. Respondent No. 1 shall consider the case of the petitioner

in accordance with law and look into two communications sent by the

Sub-Divisional Engineer already noted supra. An opportunity of

personal hearing shall also be given to the petitioner before taking any

decision.

11. The petitioner to appear before Respondent No. 1 for said

purpose on 14.06.2016 and to abide by its further instructions in the

matter. Respondent no. 1 shall attempt to complete the verification

and pass suitable orders afresh within next three months.

12. Writ Petition is thus partly allowed and disposed of. Rule

accordingly. However, in the facts and circumstances of the case,

there shall be no order as to costs.

                    JUDGE                                                   JUDGE
     *GS.



 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter