Citation : 2016 Latest Caselaw 696 Bom
Judgement Date : 17 March, 2016
Judgment. wp5867.15
1
IN THE HIGH COURT OF JUDICATURE AT BOMBAY,
NAGPUR BENCH, NAGPUR.
WRIT PETITION NO. 5867 OF 2015.
Eagle Digital Scale, A Partnership
Firm registered under the
Indian Partnership Act, 1932
having its office at 3rd Floor,
NKY Towers, Ajni Square, Nagpur,
through its partner
Mr. Ashok Singh. ..... PETITIONER.
VERSUS
Chandrapur City Municipal
Corporation, Chandrapur,
through its Commissioner. ..... RESPONDENT.
--------------------------
Shri S.P. Dharmadhikari, Senior Advocate with Shri S.A. Dharmadhikari, Advocate for the Petitioner.
Shri M.I. Dhatrak, Advocate for Respondent.
--------------------------
CORAM : B.P. DHARMADHIKARI & P.N. DESHMUKH , J J.
DATE : MARCH 17, 2016.
Judgment. wp5867.15
ORAL JUDGMENT : (Per : B.P. Dharmadhikari, J.)
Heard Shri S.P. Dharmadhikari, learned Senior
Counsel along with Shri S.A. Dharmadhikari, learned Counsel
for the petitioner and Shri M.I. Dhatrak, learned Counsel for
the respondent. By their consent the Writ Petition is taken up
for final hearing, by issuing Rule, making the same returnable
forthwith.
2. Because of policy to curb entry of overloaded heavy
motor vehicles within the Corporation limits, the petitioner has
been awarded work of constructing/installing electronic weigh
bridges at 5 entry points of Chandrapur Town. Accordingly an
agreement was entered into between the parties. The
agreement specifically stipulates that the work is to be
completed within a period of 90 days, after the site is handed
over, and all permission for said work are given by the
competent Authority.
3. Case of petitioner is, in relation to three sites as yet
Judgment. wp5867.15
necessary permissions are not given. Erection of weigh bridges
at Mul road entry point and Nagpur road entry point is already
over and the weigh bridges could have been made functional,
and operated by it after formal inauguration in June, 2015
itself.
4.
Challenge in this background is to a communication
sent by the Deputy Municipal Commissioner on 12.06.2015,
alleging that the petitioner has not completed work within the
stipulated time and work was found going on during their visit.
Petitioner has, therefore, been called upon to stop the work.
This communication has been replied to by the petitioner. He
has pointed out the work of erection of weigh bridges at
Nagpur road and Mul road entry points was already over and
in relation to remaining three sites, necessary permission were
still awaited. This reply of the petitioner dated 15.06.2015,
has been further replied to by the Municipal Corporation on
18.6.2015. It is reiterated that actual work was not complete.
It is further mentioned that the work ought to have been
Judgment. wp5867.15
completed within 90 days or at least within 180 days. The
P.W.D. has given permission on 09.09.2014, and hence, the
work should have been completed within stipulated time from
09.09.2014.
5. The communication does not show as to how claim
of petitioner that weigh bridges at Mul Naka and Nagpur Road
Naka were fully erected is, incorrect. Similarly, the stand of
petitioner that in relation to other three sites, necessary
permission has not been received, has not been dealt with. The
averments may give rise to disputed questions of facts.
6. Contract between the parties contains a clause for
termination. Said Clause no.12 prescribes giving of 30 days
notice and an opportunity to the petitioner, before decision to
terminate is taken. This procedure has not been followed and
hence facts have not been crystalized.
7. Here the impugned communication at the most
Judgment. wp5867.15
suspends the work, but, does not terminate the contract. The
suspension of work continues from 12.06.2015, and as no outer
time limit has been mentioned it is to continue in future
indefinitely.
8. Respondent has pointed out that the agreement vide
Clause no.13, provides for a procedure of settlement of dispute
and vide clause no.14, an arrangement for arbitration. Clause
13 requires the petitioner to complete certain formalities, if he
wants to raise a dispute for consideration of the Corporation.
In that event, he has to give sufficient prior intimation and also
necessary details in writing within a period of one month of the
cause of such claim. Here according to the petitioner the
dispute is being raised by the Municipal Corporation.
Arrangement for arbitration can be taken recourse to when
such a dispute raised by the petitioner is not resolved under
Clause 13. The respondent has avoided to act and terminate
contract. It appears to to be satisfied with status-quo.
Judgment. wp5867.15
9. In present situation, when the agreement has been
entered into between the parties, in public interest and two of
the weigh bridges have already been made functional and are
lying idle since June 2015, we are not inclined to accept the
contention of Shri Dhatrak, learned counsel appearing on
behalf of the respondent, that this Court should not intervene
in writ jurisdiction, in view of contract. The respondent
Municipal Corporation has apart from suspending the work
from 12.06.2015, has not proceeded to protect interest of
public. The contract has not been put to an end or then no
action has been taken against the petitioner. Thus, investment
into two weigh bridges is going waste and what ever work
which could have been undertaken on other sites in terms of
the award of contract to curb entry of overloaded vehicles,
within the city limits, has not been done. Thus, public revenue
is made to suffer and public roads may also continue to be
damaged.
10. It needs to be noted that the Municipal Corporation
Judgment. wp5867.15
has not pointed out that the claim of petitioner on affidavit in
relation to other three sites, necessary permission has not been
received till date, is incorrect or false.
11. We therefore, in the interest of general public, quash
and set aside the communication dated 12.06.2015. The
Municipal Corporation shall immediately proceed to take
necessary steps to see that the two weigh bridges i.e. the
weight bridge on Mul Road and Nagpur Road naka, can be
made operational immediately.
12. Similarly, the respondent Municipal Corporation
shall attempt to assist the petitioner in procuring the
permission for other three sites. Writ Petition is thus, partly
allowed and disposed of.
13. Rule is made absolute in the aforesaid terms, with
no order as to costs.
JUDGE JUDGE
Rgd.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!