Citation : 2016 Latest Caselaw 433 Bom
Judgement Date : 8 March, 2016
WP 1675/16
- 1 -
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO.1675/2016
Shri Ramkishan s/o Namdeorao Adude,
aged 45 yrs., occu.service,
r/o Nanded Tq.Nanded Dist.Nanded.
...Petitioner..
Versus
1] Dnyanopasak Shikshan Mandal's,
Through its President
Adv. G.N. Dudhgaonkar,
r/o Jintur Tq.Jintur
Dist.Parbhani.
2] Dnyanopasak Shikshan Mandal's,
Through its Secretary
Dr.Sandhya Ganeshrao Dudhgaonkar,
r/o Jintur Tq.Jintur
Dist.Parbhani.
3] Dr.S.L. Sadawarte,
age major, occu.service,
r/o Jintur Tq.Jintur
Dist.Parbhani.
...Respondents...
.....
Shri T.K. Prabhakaran, Advocate for petitioner.
Shri R.N. Dhorde, Senior Advocate i/b Shri V.R. Dhorde,
Advocate for respondents.
.....
::: Uploaded on - 11/03/2016 ::: Downloaded on - 31/07/2016 08:13:51 :::
WP 1675/16
- 2 -
CORAM: RAVINDRA V. GHUGE, J.
DATE: 08.03.2016
ORAL JUDGMENT :
1] Rule. Rule made returnable forthwith and heard
finally by the consent of the parties.
2] The petitioner has challenged the order dated
9.12.2015 delivered by the University and College
Tribunal thereby rejecting Miscellaneous Application
No.8/2012 and refusing to condone the delay of 15 months
and 25 days in filing the appeal.
3] Shri T.K. Prabhakaran, learned Advocate for the
petitioner, submits that in all four reasons were put
forth by the petitioner for seeking condonation of delay.
Firstly, that his mother was unwell and she expired
after his termination on 15.4.2011.
Secondly, on account of the demise of his mother and
coupled with his termination from service on 15.4.2011,
he suffered neurological problems and himself had to take
medical assistance.
Thirdly, the learned Advocate informed him that the
Tribunal was vacant and even if an appeal is filed, the
WP 1675/16
- 3 -
same may not be entertained due to the absence of the
Presiding Officer of the Tribunal.
Fourthly, the delay caused is not deliberate and
intentional.
4] He further submits that the Tribunal has failed
to consider the application for condonation of delay and
has rejected the same on the ground that the delay is not
properly explained and that he has resumed his duty as a
Chemical Analyst with the University with whom he had
maintained a lien on the post, which he occupied prior to
joining respondent no.1 - college.
5] He, therefore, submits that the Tribunal is not
expected to look into those events, which are not germane
to the cause of action, but should consider those
factors, which have been put forth as reasons for the
delay caused in filing an appeal for challenging the
order of termination. He further submits that the delay
is not to be explained on day-to-day basis. He relies
upon the reported judgment of this Court in the matter of
Ware's Educational Trust & another v. Subhash Bhagwan
Khedkar & another (2015 (2) Mah.L.J., 870).
6] Shri Dhorde, the learned Senior Advocate
WP 1675/16
- 4 -
appearing on behalf of all the respondents strenuously
opposes this petition. While supporting the impugned
order, he relies upon the affidavit in reply filed on
behalf of respondents before this Court. He points out
the dates and events set out in the affidavit in reply to
support his contention that the petitioner, after being
terminated on 15.4.2011 (as his service period was not
satisfactory), has joined the post of Chemical Analyst in
the Chemistry Department of Nanded University on
19.4.2011. Though he submits that his mother passed
away, the said unfortunate incident has occurred on
9.7.2011, whereas the appeal has been filed in August,
2012.
7] Shri Dhorde, therefore, submits that even if the
said demise of his mother is considered, after 9.7.2011,
he continued to be on duty with Nanded University and
after almost a year, the appeal has been filed.
8] He further submits that though the delay of 15
months and 25 days may not appear to be inordinate, the
reason cited for seeking condonation of delay amounts to
taking up a false plea. He relies upon the judgment of
the Hon'ble Supreme Court in the case of Pundlik Jalam
WP 1675/16
- 5 -
Patil (D) by L.Rs. v. Executive Engineer, Jalgaon Medium
Project & another (2008 (6) ALL MR 954 (SC). He,
therefore, prays for the dismissal of this petition.
9] I have considered the submissions of the learned
Advocates.
10] It is trite law that in matters of delay, the
Courts are expected to take a pragmatic approach rather
than taking a pedantic approach. If the delay is not
deliberate or inordinate and if laches are not attributed
to the conduct of the applicant, condonation of delay
could be liberally considered. So also if an applicant
gains any undue advantage by causing the delay, the
application for condonation of delay filed by such an
applicant is not to be considered liberally.
11] In my view, what is required to be considered is
as to whether the doors of justice would be closed on a
litigant by rejecting an application for condonation of
delay, provided that the delay is not deliberate,
inordinate, laches are not attributed to the conduct of
the applicant and he does not gain any advantage by
causing delay.
12] The Apex Court in the case of Collector, Land
WP 1675/16
- 6 -
Acquisition, Anantnag v. Mst.Katiji (AIR 1987 SC 1353)
has laid down the law as follows :-
"1. Ordinarily a litigant does not stand to benefit by lodging an appeal late.
Refusing to condone delay can result in a
meritorious matter being thrown out at the very threshold and cause of justice being defeated.
As against this when delay is condoned the
highest that can happen is that a cause would be decided on merits after hearing the parties.
3. "Every day's delay must be explained" does not mean that a pedantic approach should be made. Why not every hour's delay, every second's
delay? The doctrine must be applied in a
rational common sense pragmatic manner.
4. When substantial justice and technical considerations are pitted against each other,
cause of substantial justice deserves to be preferred for the other side cannot claim to have vested right in injustice being done because of a non-deliberate delay.
5. There is no presumption that delay is occasioned deliberately, or on account of culpable negligence, or on account of mala fides. A litigant does not stand to benefit by resorting to delay. In fact he runs a serious risk.
6. It must be grasped that judiciary is
WP 1675/16
- 7 -
respected not on account of its power to
legalize injustice on technical grounds but because it is capable of removing injustice and
is expected to do so." (emphasis supplied)
13] It is, therefore, trite law that each and every
day's delay is not to be explained. There must be a
reasonable explanation for the delay caused and the delay
must not appear to be inordinate.
14] In the instant case, the delay is about 15
months and 25 days. If the same is not condoned, the
petitioner would not be able to challenge his purportedly
unlawful termination before any Court and he would be
deprived of a valuable right only on account of the
technicality of delay. From the point of view of doing
justice to the parties, I am of the view that by
condoning delay, the highest that can happen is that
there would be a decision on merits, which is better than
depriving a litigant from getting justice owing to
technicalities.
15] As has been observed by the Hon'ble Supreme
Court in the matter of Collector, Land Acquisition,
Anantnag, by condonation of delay, the matter would be
WP 1675/16
- 8 -
decided on its merits and ends of justice would be met.
16] The respondents have relied upon paragraph no.11
of the Pundlik Jalam Patil case (supra), which reads as
under:-
"11. Whether the respondent made incorrect statement in the application seeking condonation of delay?
There is no dispute whatsoever that the respondent being the beneficiary of the
acquisition has been duly impleaded as a party respondent in the reference cases as is required
in law. It not only appeared in the matter through a properly instructed counsel but also filed its written statement opposing the claim
for enhancement of compensation but did not
choose to lead any evidence whatsoever. In the application filed in the High Court the plea taken by the respondent is as under:
"The applicant submits that, although the applicant being Acquiring Body, was arrayed as opponent in the said reference,
the opponent no. 4 herein (Original Opponent No. 1) S.L.A.O. or his subordinate contested the said reference by filing written statement. Therefore, this applicant was unaware about the stand taken by S.L.A.O. as well as the impugned judgment and award."
WP 1675/16
- 9 -
This averment in the application on the face of
it is totally incorrect. The Law & Judiciary Department as early as on 13.4.2000 i.e. to say
within the period of 15 days from the date of the award of the Reference Court communicated its decision to acquiesce in the decision of the
Reference Court and communicated the same to all the concerned including the beneficiary of the acquisition. It is not the case that the
Executive Engineer did not receive the said
communication. Having received the said communication the respondent did not act in the
matter and initiated any steps for filing the appeals if it was really aggrieved by the decision of the Reference Court. There is no
doubt whatsoever in our mind that the respondent
made totally incorrect statement in the application filed in the High Court. We express our reservation as to the manner in which a
public authority conducted itself in its anxiety to somehow get the relief from the court. In our considered opinion incorrect statement made in the application seeking condonation of delay
itself is sufficient to reject the application without any further inquiry as to whether the averments made in the application reveal sufficient cause to condone the delay. That a party taking a false stand to get rid of the bar of limitation should not be encouraged to get any premium on the falsehood on his part by
WP 1675/16
- 10 -
condoning delay. [See: (1993)1SCC 572]. "
17] It is apparent from the Pundlik Jalam Patil case
(supra) that a Government entity had taken a false stand
that it was unaware about the stand taken by the Special
Land Acquisition Officer as well as the existence of the
impugned judgment, when, in fact, it had participated in
the said proceedings through an Advocate and had
contested the matter on its merits. I do not think that
the facts set out in the Pundlik Jalam Patil case (supra)
could be said to be similar to the facts with regard to
the case in hand.
18] In the light of the above, this petition is
partly allowed. The impugned order dated 9.12.2015 is
quashed and set aside and Miscellaneous Application
No.8/2012 stands allowed subject to the condition that in
the event the petitioner succeeds in his appeal before
the Tribunal, he shall be deprived of monetary benefits
for the entire period of delay.
19] Rule is made partly absolute in the above terms.
No order as to costs.
20] At this juncture, the respondents pray for a
stay to this judgment for a period of four weeks.
WP 1675/16
- 11 -
Learned Advocate for the petitioner opposes the same on
the ground that the Tribunal would now register the
appeal and issue notices to the other side, which will
take some time. As such, it is submitted that there is
no reason to stay the operation of this judgment.
21] Considering the fact that this petition has been
partly allowed in the light of the ratio laid down by the
Hon'ble Supreme Court in the case of Collector, Land
Acquisition, Anantnag (supra), I do not find that the
request of the respondents deserves to be entertained.
The same is, therefore, rejected.
(RAVINDRA V. GHUGE, J.)
ndk/c831613.doc
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!