Citation : 2016 Latest Caselaw 318 Bom
Judgement Date : 4 March, 2016
dgm 1 app-407-15.sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 407 OF 2015
IN
ARBITRATION PETITION NO.958 OF 2012
WITH
NOTICE OF MOTION (L) NO. 1796 OF 2015
Waverley Private Limited ig )
having its registered office at )
Showroom No.2, Girton School Lane, )
Nugegoda, Sri Lanka. ) .. Petitioner
Versus
Diversey India Private Limited )
having its registered office at )
501, 5th Floor, Ackruti Centre Point, )
MIDC Central Road, Andheri (E), )
Mumbai 400 093 ) .. Respondent
Mr.Vishal Talsania a/w Ms. Mansi Patel i/by M/s.Thakore Jariwala &
Associates for the Petitioner
Mr.M.P.S. Rao, Senior Advocate a/w Mr. Nilesh Khandray i/by
M/s.Mallar Law Consulting for the Respondent
1/21
::: Uploaded on - 05/03/2016 ::: Downloaded on - 06/03/2016 00:02:17 :::
dgm 2 app-407-15.sxw
CORAM: ANOOP V. MOHTA AND
G. S. KULKARNI, JJ.
CLOSED FOR JUDGMENT ON: February 9, 2016
PRONOUNCED ON : March 04, 2016
JUDGMENT (Per Anoop V. Mohta, J.)
Rule, returnable forthwith. Heard finally.
The Appellant (original Respondent) has challenged
judgment dated 9 June 2015 by invoking Section 37 of the Arbitration
and Conciliation Act, 1996 (for short "the said Arbitration Act").
3 The learned Judge, by impugned judgment/order, allowed
Section 34 Application filed by the original Claimant/Respondent and
passed the following order :
"The impugned award dated 4th May 2012 in so far as
the issue of jurisdiction rendered in paragraph 17.1 (i)
of the impugned award holding that the arbitral
tribunal has no jurisdiction to hear the claimant's
claim for the sum of USD 37,505.60 claimed in the
invoices listed in Annexure B of the request for
dgm 3 app-407-15.sxw
Arbitration dated 20th July 2010 is set aside. Rest of
the award is upheld. No order as to costs.
At the request of the learned counsel appearing
for the respondent, operation of the order passed
today is stayed for a period of two weeks from today."
4 The learned Judge has recorded the relevant facts for the
purposes of deciding the issue in paragraphs 2 to 9, 12, 13 to 15, 19
to 22, which read thus :
"2. Prior to June 2005, the respondent was acting
as a distributor for the petitioner in certain areas
earmarked in Sri Lanka. There was no written agreement
between the parties prior to June 2005. On 14 th June
2005, the parties entered into an agreement for sale of
products manufactured by the petitioner which were to be
distributed by the respondent in the earmarked territory
in Sri Lanka. On 13th June 2006, the first agreement
came to an end.
3. During the period from 14th June 2006 to 31st
dgm 4 app-407-15.sxw
March 2007, the products of the petitioner continued to be
distributed in the territory of Sri Lanka. No agreement
was signed for the said period of 14 th June 2006 to 31st
March 2007 between the parties.
4. On 1st April 2007, the petitioner and the
respondent entered into an agreement. The said agreement
was to be operated for a period of two years ending 31 st
March 2009.
Under the said agreement, the petitioner
appointed the respondent as its distributor in the
Institutional and Industrial Channels of Trade for the
purpose of selling or otherwise for the products of the
petitioner in the specified territory on the terms and
conditions set out therein. Under the said agreement, the
respondent was granted 75 days' credit from the date of
invoicing for the products purchased from the petitioner
and the respondent was to establish Letter of Credit or TT
to avail the said credit facility. Under clause 6.3 of the
agreement, either party could terminate the said agreement
without being required to assign any reason at any time
by giving the other party 90 days prior written notice.
dgm 5 app-407-15.sxw
5. Clause 6.1 of the said agreement is extracted
as under :-
"6.1 Term- The terms of this Agreement commences on the Effective Date and continues in force for a period of two years, unless earlier terminated as provide therein or where it is mutually agreed by both parties to terminate this Agreement if both parties to
agree in writing the term of this Agreement may be extended for another one year term on the same terms and conditions unless otherwise mutually agreed upon."
6. Clause 9.1 of the said agreement provided for
arbitration which is extracted as under :-
"9.1 Law and Legal Proceedings - This Agreement and the
relationship of the parties hereunder : will be governed by and interpreted in accordance with the laws of India without regard to its principles respecting the conflicts of laws. Application of the U N Convention on the International Sale of Goods is hereby rejected Any and all disputes, claims and controversies between the parties
arising out of or relating to this Agreement, the alleged breach of this Agreement and the rights and obligations of the parties hereunder
shall be resolved exclusively by binding arbitration. Arbitration shall be administered by the International Chamber of Commerce which shall apply its international commercial arbitration rules as modified by this Agreement. The decision of any such arbitrator(s) shall be final and judgment on the award rendered may be entered in
any Court having jurisdiction thereof. Such Arbitrator(s) shall have the authority to impose all manner of remedies.Arbitration proceedings shall be conducted in Mumbai, India in the English Language."
7. On 6th April 2008, the respondent by its email
addressed to the petitioner, terminated the agreement dated
1st April 2007 however made effective from 1st September
2008. In the said email, the respondent requested the
dgm 6 app-407-15.sxw
petitioner to make an arrangement to purchase the balance
stocks including the demonstration equipments and the
spare parts and informed that the respondent would settle
the dues of the petitioner as well. It is the case of the
petitioner that the petitioner was unable to appoint another
distributor/agent for sale of its products in the specified
territory in Sri Lanka.
8.
On 27th August 2008, a meeting was held
between Mr. Sukrit Ghosh, the then Sales & Marketing
Manager of the petitioner and Mr.Gnana Samaratunga,
Managing Director of the respondent. The said meeting
was also attended by Mr. Nikhil Sawant, Director -
Healthcare & Hospitality of the petitioner. It is the case of
the petitioner that in the said meeting, the parties agreed
that the respondent would continue as an agent and/or
distributor of the products of the petitioner at least until
20th September 2008. It is the case of the petitioner that the
said record of discussion what was transpired on 27th
August 2008 was spelt out in the three emails all dated
4th September 2008 that were exchanged between the
dgm 7 app-407-15.sxw
parties.
9. On 4th September 2008, the respondent sent
an email to the petitioner at 10.39 a.m. recording that it
was agreed that the respondent would distribute the
chemicals of the petitioner and act as a distributor for one
more month ending 20th September 2008. In the said
email, it was also recorded that it was further agreed that
the petitioner would find a new distributor during the
said period and would ensure that the stocks and
chemicals were taken over from the respondent after due
payments during the said period.
12. It is the case of the petitioner that under the
said extended agreement, the petitioner supplied the
goods to the respondent for the period from September
2008 upto 25th October 2008 under the cover of invoices
drawn in the name of the respondent. During that period,
the petitioner raised invoices in the name of the respondent
and all documents of title such as invoice, bills of lading
dgm 8 app-407-15.sxw
etc. were all duly accepted by the respondent as
agent/distributor and also further caused the goods to be
sold in the specified areas in Sri Lanka.
13. The present dispute was in respect of invoices
substantially drawn during the period September 2008
until October 2008. It is the case of the petitioner that
some time in the month of January 2009, reconciliation
of the accounts between the parties in respect of the goods
of the petitioner sold and delivered from the period June,
2005 to 25th October 2008 took place. The said statement
of account dated 31st January 2009 showed balance of
USD 19.96 which was admitted and acknowledged as
payable by the respondent to the petitioner and another
statement of account which disclosed that a sum of US$
41363.93 was agreed to be payable by the respondent to
the petitioner. The said statement of account was duly
signed and/or initialed by the parties. It was the case of the
petitioner that all statements of accounts were signed and/or
initialed by the Managing Director of the respondent.
dgm 9 app-407-15.sxw
14. On 17th March 2009, the respondent
addressed a letter to the petitioner and made a claim of
US$ 4899495.05 for the period July 2005 to October
2009 on the alleged ground that there was a delay of
delivery due to mismanagement of operation in the
transaction by the petitioner.
15. On 23rd July 2009, the petitioner addressed a
letter to the respondent informing that after considering
the liabilities of the petitioner, balance of US$ 40607.93
was found payable by the respondent to the petitioner.
19. Before the learned arbitrator, the petitioner
filed a statement of claim, inter alia, praying for a sum of
USD 41,332.94 with interest @21% p.a. or at such other
rate as the learned arbitrator would deem appropriate and
for costs.
20. The respondent filed their reply and counter-
claim. In the said reply, the respondent raised a plea of
jurisdiction of the learned arbitrator to adjudicate upon the
dgm 10 app-407-15.sxw
claim of the petitioner for USD 41,332.94 on the ground
that the said part of the claim was related to the period after
31st August 2008. The respondent also made a counter-
claim against the petitioner for the sum of Sri Lankan
Rupees Rs.5,224,588.97 (equivalent to USD 47,496.26)
towards alleged financial losses caused to the respondent by
the petitioner.
21.
The learned arbitrator framed four issues
including the issue whether the claim of the petitioner
would fall within the ambit of arbitration clause. The
petitioner had also made an application before the learned
arbitrator to adduce the additional affidavit of Mr.Sukrit
Ghose after closure of hearing.
22. On 4th May 2012, the learned arbitrator
made an award holding that the learned arbitrator had no
jurisdiction to hear the claim of the petitioner for the sum
of USD 37,505.60 claimed in the invoices listed in
Annexure B of the request for arbitration dated 20 th July
2010. The learned arbitrator allowed the claim of the
dgm 11 app-407-15.sxw
petitioner for USD 3,827.34 with simple interest @ 9% p.a.
from 14th October 2009 i.e. from the date of demand for
payment till the date of the award and simple interest
@18% p.a. from the date of the award till the date of
payment. The learned arbitrator also held that he had no
jurisdiction to hear the counter-claim of the respondent
for the sum of Sri Lankan Rupees 5,224,588.97. The
learned arbitrator directed both the parties to bear their
own costs and expenses of the said arbitration. The
respondent did not challenge any part of the award dated
4th May 2012. The petitioner, however, has challenged the
said award dated 4th May 2012 in so far as the claim of
the petitioner in respect of USD 41332.96 is concerned
which was rejected by the learned arbitrator on the ground
of jurisdiction in this petition."
5 By noting the rival contentions of the parties, including
referring to the judgments so cited, apart from the pleadings and the
respective evidence led by the parties recorded the reasons, to set
aside the arbitral award, which we are in agreement, after going
through the whole pleadings so read and referred by the parties.
dgm 12 app-407-15.sxw
Paras 51 to 53 of the judgment read thus:
"51. A perusal of the award clearly indicates
that the learned arbitrator though did not render
any finding that the said three emails all dated 4 th
September 2008 exchanged between the parties were
fabricated or did not exist and on the contrary
referred to the said emails in paragraph 13.10 of the
agreement, the learned arbitrator held that even if
there was an oral agreement as alleged by the
claimant, such an oral agreement was outside the
terms of the agreement dated 1 st April 2007. In my
view the award shows ex facie contradictions and
patent illegality on the face of the award. Once the
learned arbitrator had not rejected those three emails
all dated 4th September 2008 and had referred to the
said emails in the impugned award for rejecting the
claim of the petitioner, the learned arbitrator could
not have taken a view that even if there was an oral
agreement, such agreement was outside the terms of
the agreement dated 1st April 2007. Since the
dgm 13 app-407-15.sxw
agreement was arrived at by exchange of emails, in
my view, there could not have been any oral
agreement between the parties. In this case,
discussions arrived at between the parties in the
meeting held on 27 th August 2008 were recorded by
exchange of emails. A perusal of Section 6.1 of the
agreement also makes it clear that the parties in
writing could extend the said agreement dated 1 st
April 2007 for another one year on the same terms
and conditions unless and until mutually agreed
upon. In this case, the parties agreed that the said
agreement dated 1st April 2007 would be continued
till 20th September 2008 and even beyond. In my
view, the said three emails clearly extended the
agreement dated 1st April 2007 prior to the letter of
termination having come into effect.
52. I am not inclined to accept the submission of
the learned counsel for the respondent that even if those
three emails were exchanged, the same were not in
dgm 14 app-407-15.sxw
accordance with Section 6.1 of the agreement on the ground
that the extension if at all could only be for one year and
not for smaller period. A plain reading of Section 6.1
clearly indicates that the parties could mutually agree upon
the extension even for a period of less than one year.
53. In my view, the finding of the learned
arbitrator that in view of the respondent having given
90 days' prior written notice as per clause 6.3 of the
agreement, the agreement is validly terminated with
effect from 1st September 2008 is totally perverse
and discloses patent illegality. In my view, since the
parties had already agreed to extend the period of
the agreement dated 1st April 2007, the said letter of
termination did not come into effect and was given a
go-bye."
6 The learned Judge even read and referred the contents of
the emails including the supporting evidence led by the parties and
given the finding of facts in this regard in paragraph 55 which reads
dgm 15 app-407-15.sxw
thus:-
"55. A perusal of the record makes it clear that
the respondent never made any such allegations in any
of the correspondence exchanged between the parties.
Be that as it may, since the respondent admitted that
the consignments were sent by the petitioner and
bill of lading were issued in the name of the
respondent, the respondent had to accept those
documents, it is clear that both the parties had acted
upon all such transactions having taken place after
31st August 2008. The respondent did not examine
M/s. Jayes Investment (Pvt) Ltd. in support of their
case before the learned arbitrator. The respondent
also did not examine Ms.Rashmi from whose email
ID, the said two emails were sent to the petitioner.
Since the respondent had accepted the documents
issued by the petitioner post 31st August 2008 and
had acted upon such transactions, it is clear that the
agreement dated 1st April 2007 was duly extended
by the parties as recorded in the said emails. I am
dgm 16 app-407-15.sxw
thus not inclined to accept the submission of the
learned counsel for the respondent that any of such
emails were fabricated or were of no consequence."
7 The law revolving around Section 7(4)(b) of Arbitration
Act is very clear whereby exchange of letters, telex, telegrams or
other means of communication also amounts to an arbitration
agreement in writing. The parties, as recorded through the exchange
of emails, recorded the agreements thereby all the terms and
conditions of the agreement dated 1 April 2007 of the basic
arbitration agreement got extended. Therefore, the conclusion that
through these three emails, the parties have agreed and extended the
contractual obligation and in fact acted accordingly need no
interference. Having once extended the agreement in toto, any
dispute between the parties for the transaction based upon the same
required to be adjudicated on the basis of main agreement itself. The
finding, therefore, based upon the facts and the law of Bharat
Petroleum Corporation Ltd v. Great Eastern Shipping Co Ltd 1 and
further in Trimex International FZE Limited, Dubai v. Vedanta
1 AIR 2008 SC 357
dgm 17 app-407-15.sxw
Aluminium Limited, India2 support the reasons which we also find is
well within the frame work of law and the record.
8 The Supreme Court in Oil and Natural Gas Corporation
Limited v. Western Geco International Limited3 has observed as under:
"39 No less important is the principle now recognised
as a salutary juristic fundamental in administrative law
that a decision which is perverse or so irrational that no
reasonable person would have arrived at the same will
not be sustained in a court of law. Perversity or
irrationality of decisions is tested on the touchstone of
Wednesbury Principle in Associated Provincial Picture
Houses Ltd v. Wednesbury Corpn. (1948) 1 KB 223 :
(1947) 2 All ER 680 (CA)."
This Court in Sahyadri Earthmovers v. L and T Finance Ltd 4 has
recorded as under with regard to the basic parameters for the
Arbitrator to follow, apart from other the following clauses are
2 (2010) 3 SCC 1 3 (2014) 9 SCC 263 4 2011 (4) Mh. L. J. 200
dgm 18 app-407-15.sxw
relevant for this case :
"CPC & Evidence Act
(xviii) Though Code of Civil Procedure and the Evidence Act are not applicable strictly, (section 19), but the settled principles do apply. The power of Arbitral Tribunal to determine the admissibility,
relevance, materiality and weight of any evidence just cannot be overlooked.
Substantial laws-customs-commercial usages and
practice
(xx) The Arbitrator is bound by the substantive laws of the land as well as procedural laws and practice and principle apart from the custom and usage of the trade
referring the business and commerce between the parties, in all respects.
To Analyse the evidence and the record
(xxi) The Arbitrator is required to consider all the
material and evidence/documents placed by the parties on record read with the evidence led by the parties. The Arbitrator is, therefore, bound to analyse and appreciate the same by giving proper and correct
interpretation of terms of the contract subject to provisions of law, before passing reasoned interim or final award. The Arbitrator to pass reasoned interim and/or final award, unless agreed otherwise.
The Doctrines to be followed
(xxiii) The Arbitrator cannot disregard the substantive and procedural law. The Arbitrator is therefore bound to take note of law; of interpretation, precedent, obiter dicta, ratio decidendi, Estoppel, acquiescence, waiver and res judicata, public policy,
dgm 19 app-407-15.sxw
natural justice, fair play and equity."
9 We find no reason to disturb the finding so recorded that
the Petitioner had proved the existence and contents of the three
emails. The reconciliation statement duly signed by the parties
further confirm the same covering the transactions after 31 August
2008. Mere termination, through a notice, that itself cannot be the
reason to dislodge the claim so raised based upon the agreed clauses.
The agreement expired by efflux of time is also unacceptable, having
once extended the same, through the email which is permissible mode
of written arbitration agreement on same earlier terms and conditions.
The parties, as recorded, have in fact acted upon. The typing error
and/or any error in the email that itself, in the present facts and
circumstances, cannot be the reason to overlook the other contents of
the same. The learned Judge has, therefore, has taken note of the
totality of the facts and circumstances and provided the finding while
reversing the award passed by the Arbitral Tribunal to the extent so
recorded above.
10 In the present case and as recorded by the learned Judge
dgm 20 app-407-15.sxw
that the finding recorded by the learned Arbitrator are perverse, illegal
and as this is not a case of appreciation of evidence. On the contrary,
the finding is that the learned Arbitrator refused to exercise
jurisdiction by holding that the Petitioner was not entitled for claim by
overlooking the emails and the contents thereof supported by
evidence and, therefore, the Arbitrator's finding is apparent on the
face of the record was illegal and perverse. The judgments, therefore,
of Ravindra Kumar Gupta and Company v. Union of India 5; Ropa
Plastics Pvt Ltd v. IPN Pakcaging Pvt Ltd.,6 and in M/s. Bhavani Cotex v.
M/s. C.A. Galiakotwala & Co Pvt. Ltd7, rightly observed, are of no
assistance.
11 Therefore, taking overall view of the matter and
considering the power and scope of Appellate Court under Section 37 of Arbitration Act and we have also noted that the reason provided by
the learned Judge is well within the frame work of law and the record. Recently, the Supreme Court in M/s.Chebrolu Enterprises v. Andhra Pradesh Backward Class Coop.Finance Corpn Ltd in Civil Appeal No.8918/2015 on
28.10.2015 has reinforced thus "This Court or even the Appellate Court would not look into the finding of facts unless they are perverse.". No case is made out to interfere with the impugned judgment .
5 (2010) 1 SCC 409 6 2014 (3) Mh. L. J. 150 7 Unreported judgment dt. 21.01.2014 in Arb. Pet. No.314/2013 by Bombay High Court
dgm 21 app-407-15.sxw
12 In the result, the Appeal is accordingly dismissed. Rule
stands discharged. There shall be no order as to costs.
12 In view of dismissal of Appeal, Notice of Motion (L) No.
1796 of 2015 does not survive and stands disposed of accordingly.
(G. S. KULKARNI, J.)
ig (ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!