Citation : 2016 Latest Caselaw 3495 Bom
Judgement Date : 30 June, 2016
1 WP.2276/2015(S-903)
mnm
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO. 2276 OF 2015
Shree Dipty C.H.S. Ltd. ...Petitioner
Vs.
Municipal Corporation of
Gr. Mumbai & Ors. ...Respondents
Mr. J.N. Jayale, Advocate for the Petitioner
Ms. Geeta Joglekar, Advocate for BMC, Respondent Nos. 1 to 3
Mr. V.S. Upadhyaya, AGP for Respondent No.4
CORAM : SHANTANU S. KEMKAR &
M.S. KARNIK, JJ.
DATED : 30TH JUNE, 2016
ORDER (PER JUSTICE SHANTANU S. KEMKAR):
With the consent of the parties heard finally.
2. By filing this Petition under Article 226 of the
Constitution of India the Petitioner has challenged the notice
dated 13th May, 2014 Exhibit-P by which Brihanmumbai
Mahanagarpalika has directed the Petitioner to vacate the
building in question immediately as the same is required to be
2 WP.2276/2015(S-903)
pulled down being in ruinous and dilapidated condition.
3. The case of the Petitioner is that the Builder had
obtained a structural report from M/s. Conpro Consultant Pvt.
Ltd. to the effect that the building is in dilapidated condition
whereas the Petitioner had obtained and submitted before the
Corporation a report from the N.M. Consultants to show that
the building though is in a bad condition, but is repairable.
4. The grievance of the Petitioner is that in pursuance to
the directions issued by this Court on 31 st July, 2014 while
disposing of the earlier Writ Petition (L) No. 1933 of 2014 the
matter was referred to the Technical Advisory Committee
(TAC), but the TAC in its report dated 24th November, 2014
has not considered the report submitted by the Petitioner in is
correct perspective has taken a decision holding that the
Petitioner's building needs to be evacuated immediately and
requires to be demolished as it is not fit for human habitation.
5. On the other hand learned Counsel for the Corporation
3 WP.2276/2015(S-903)
submits that the TAC has taken into consideration both the
reports and as per the Summary Test results and the
conclusions of both the structural audit reports the TAC after
visual examination, photographs distress mapping plan of the
building and the test results submitted by both the
Consultants held that the building needs to be evacuated as
the same is not fit for human habitation and is in a
dilapidated condition.
6. Having considered the submissions made by learned
Counsel for the parties and having gone through the TAC
report dated 24th November, 2014 we find that the TAC has
elaborately dealt with both the reports, one submitted by the
Builder and the other submitted by the Petitioner. The TAC
found that in the report submitted by the Petitioner it was
mentioned that the test result shows the concrete is of
doubtful quality. Following is the cruxs of the report
submitted by the Petitioner:
"(B) From the Test results, M/s. N.M. Consultants appointed by Society has concluded that :
4 WP.2276/2015(S-903)
1) The column of Gr. Floor are found to be with major
damage and lost compressive strength of concrete with
steel corrosion inside.
2) The received test results indicates major structural
damage. The concrete quality found very poor which has affected the load carrying capacity of structural members.
The overall condition of the building shows severe and major damages all around the building.
3) In addition proper support to be placed on
immediate basis wherever necessary and to safeguard the
structure.
4) Partial demolition requiring major structural
repairs, which enhances 3-4 years life of structure".
7. Thus we find that even in the aforesaid report
submitted by the Petitioner it was specifically observed that
the overall condition of the building shows severe and major
damages all around the building. The concrete quality is
found very poor which has affected the load carrying capacity
of structural members, the column of ground floor to be with
major damage and lost compressive strength of concrete with
steel corrosion inside, proper support to be placed
immediately wherever necessary and to safeguard the
5 WP.2276/2015(S-903)
structure. It further reveals that the building requires partial
demolition requiring major structural repairs, and the repair
would enhance the life of the structure to merely 3 to 4 years.
8. Thus the TAC on the basis of the aforesaid report as also
the one which was recommending for demolition has
recorded the finding that the building is not repairable and it
requires to be demolished. In the circumstances no fault
could be found in TAC report. As a result in the absence of
any perversity in the TAC report we find the decision of the
Corporation to demolish the building to be perfectly justified.
Accordingly the Petition deserves to be and is hereby
dismissed.
9. As regards Petitioner's prayer to grant some time to
vacate the building, in view of the fact that this Court vide
order dated 24th December, 2014 granted interim protection
to the Petitioner on submitting undertaking and that
undertaking has been filed, we are inclined to grant 4 weeks
time to the Petitioner to vacate the premises. The undertaking
6 WP.2276/2015(S-903)
given by the Petitioner shall remain operative till the
Petitioner vacates the premises as aforesaid.
(M.S. KARNIK, J.) (SHANTANU S. KEMKAR, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!