Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bharat Sanchar Nigam Limited vs Siemens Financial Services Ltd. ...
2016 Latest Caselaw 2992 Bom

Citation : 2016 Latest Caselaw 2992 Bom
Judgement Date : 20 June, 2016

Bombay High Court
Bharat Sanchar Nigam Limited vs Siemens Financial Services Ltd. ... on 20 June, 2016
Bench: Anoop V. Mohta
    dgm                                          1           appl-545-15-judgment.sxw


                IN THE  HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                
                      ORDINARY ORIGINAL CIVIL JURISDICTION




                                                        
                     ARBITRATION APPEAL (L) No. 545  OF 2015
                                      IN
                     ARBITRATION PETITION NO. 1006 OF  2013




                                                       
    Bharat Sanchar Nigam Limited
    through Chief General Manager,
    B.S.N.L., Maharashtra Circle,




                                           
    Santacruz (W), Mumbai 400 054                     ....   Appellant
                                    ig     (Orig. Respondent No.2.)

           vs
                                  
    1      Siemens Financial Services Ltd.,
           A Company incorporated under the
           provisions of Companies Act, 1956
           having its registered office at
          


           4th floor, Siemens Ltd., 130,
           Pandurang Budhkar Marg,
       



           Worli, Mumbai 400 018                         (Orig. Petitioner)

    2      Sai Infosystem (India) Limited
           A Company incorporated under the





           provisions of Companies Act, 1956
           having its registered office at
           Sai care, super Plaza, Near Sandesh
           Press Road, Bodakdev, Vastrapur,





           Ahmedabad-380 054                             (Orig.Respondent No.1)
                                                         ....    Respondents

    Ms. Neeta Vinay Masurkar for the Appellant.

    Mr.   Shavez   Mukari   with   Mr.   Srinivas   Atreya   i/by   India   Law   for 
    respondents 


                                                                                         1/9



          ::: Uploaded on - 23/06/2016                  ::: Downloaded on - 23/06/2016 23:58:56 :::
     dgm                                              2            appl-545-15-judgment.sxw




                                                                                     
                                     CORAM:    ANOOP V. MOHTA AND 
                                               A. A. SAYED,  JJ. 




                                                             
    CLOSED FOR JUDGMENT ON:     May 03,   2016 

    PRONOUNCED ON                           :    June  20, 2016




                                                            
    JUDGMENT (Per Anoop V. Mohta, J.) 

Being aggrieved by the judgment of the learned Single

Judge of this Court, the Appellant/original Respondent No.2 (BSNL)

- a third party to the arbitration agreement, has filed this Appeal

under Section 37 of the Arbitration and Conciliation Act, 1996. The

impugned judgment and order dated 28 October 2014 is passed in

Arbitration Petition No. 1006 of 2013 whereby Respondent No.1's/

Original Petitioner (Siemens) section 9 Application has been

disposed of by passing the following order :

"i) That before or during arbitral proceedings or

at any time after the making of the Arbitral Award

but before it is enforced, Respondent No. 1 and

Respondent No.2 are jointly and severally ordered

and directed by this Court to forthwith handover

possession of the said equipment mentioned at

dgm 3 appl-545-15-judgment.sxw

Exhibit "E" to the Petition, to the Petitioner and/or

its servants, agents and/or assigns from the

premises at BSNL CACT Complex, Doorwani

Nagar, Opp ITI, KR Puram, Bangalore 560 016,

where the said equipment is known to be placed

or wheresoever the said equipment may be lying

and being."

2 Siemens - Original Petitioner (Respondent No.1 herein)

had entered into a Master Lease Agreement (The Master Agreement)

along with the Lease Schedule with Sai Infosystem (India) Ltd (SIS) -

(Original Respondent No.1)(Respondent No.2 herein). The

equipment have been given possession as recorded in the Master

Agreement on 5 January 2012. There exists an arbitration agreement

having agreed clause of Court's jurisdiction at Bombay. Siemens had

filed Section 9 Petition against Respondent No.2 and the Appellant

(BSNL) for getting the possession of the equipment. The Appellant,

specifically Maharashtra Circle, was not party to the arbitration

agreement between the Respondents. The Appellant's counsel

submitted that there was an independent agreement between SIS and

dgm 4 appl-545-15-judgment.sxw

BSNL on 7 October 2009. It is provided that ownership of the

equipment installed by SIS at BSNL's above premises would pass on

BSNL in case of default by SIS. The submission is that SIS left the

contract during the lock-in-period, therefore, the ownership has been

passed on to the Appellant-BSNL. SIS has prayed for possession of

these equipments in the Arbitration Petition as filed on 17 September

2013. The Appellant, therefore, resisted the Arbitration Petition also

on the ground of jurisdiction and on merits. The learned Judge, as

recorded, has passed the impugned order against the Appellant.

Hence, this Appeal on 10/07/2015.

3 The Appellant on 23 December 2013, itself terminated it's

contract with SIS even before filing of the Arbitration Petition. The

learned counsel appearing for the Appellant submitted that the

arbitration proceedings between the Appellant and SIS is pending.

4 After hearing the parties and after going through the

documents and the agreement, read and referred including award

dated 15.04.2015 in the arbitration between Siemens and SIS, the

learned Arbitrator has declared Siemens as the owner of the

dgm 5 appl-545-15-judgment.sxw

equipment and directed SIS to pay to Siemens an amount of

Rs.5,98,63,881.38 p with interest.

5 SIS failed to make the payment, and cheques were

dishonoured and as there was default in the Master Agreement.

Siemens terminated the Master Agreement on 29 July 2013. The

arbitration clause was invoked on 3 September 2013. Those

equipment have been lying in the premises of the Appellant, in view

of the agreement between SIS and BSNL. The Receiver has been

appointed by the Court with a direction to take symbolic possession of

the equipment. The Court Receiver took symbolic possession and

made the inventory of the equipment on 9/10 December 2013 itself.

The learned Judge ultimately passed final order on 28 October 2014.

In the meantime, the learned Arbitrator passed the order in favour of

Siemens on 15 April 2015, pending the Appeal. The filing of Appeal

and the submissions so made, even if any, by the Appellant, in the

background, after more than 135 days delay, which we have

condoned by separate order, is, in no way, sufficient to disturb the

order passed by the learned Single Judge specifically in view of above

facts and the following reasons :

     dgm                                              6            appl-545-15-judgment.sxw




                                                                                     
                                                             
                               JURISDICTION OF THIS COURT




                                                            
    (a)    There   is   no   substance   in   the   submission   with   regard   to   the 

jurisdiction specifically in view of the agreed clause of Court's

jurisdiction at Mumbai, between Siemens & SIS, apart from the

reason so given by the learned Judge in support of rejecting the issue

of jurisdiction against the Appellant. We are in agreement with the

said reasons. This Court has jurisdiction to entertain Section 9

Petition as filed by Siemens.

THE EQUIPMENT IN RECEIVER'S SYMBOLIC POSSESSION LYING IN APPELLANT'S PREMISES.

(b) There is no denial to the ownership of the equipment in question

which is, as stated, and found to be in possession of Appellant though

at Bangalore premises. This Court's appointed Receiver is in

possession of the same. The learned Arbitrator, as recored, concluded

the issue in favour of Siemens against SIS. The claim of Appellant,

even if any, for and against SIS and/or Siemens, even if adjudicated in

dgm 7 appl-545-15-judgment.sxw

it's arbitral pending proceedings, still, that itself is not sufficient

reason to interfere with the order passed by the learned Judge at this

stage.

(c ) The Appellant admittedly, though they have different

office/Circle, are in possession of the equipment which are subject

matter of the Master Agreement between the Respondents, apart from

agreements of Appellant with SIS.

PROTECTIVE RELIEFS AGAINST THE THIRD PERSON

(d) The issue of passing interim order and/or direction and/or

protective reliefs against the third person, in the present case, as

stated, the Appellant being not party to the agreement of Siemens and

the SIS is also of no assistance as the equipment involved in the

present case which, are subject matter of the Master Agreement

between the Respondents. The prior agreement, even if any, of

Appellant with SIS would be considered separately in the separate

arbitration proceedings, if any. In the present case, the Appellant's

grounds so raised in the Appeal and the objection so raised in Section

9 Petition of Siemens are not sufficient to interfere with the reasoned

dgm 8 appl-545-15-judgment.sxw

order.

ARBITRATION APPEAL BY THIRD PARTY IS MAINTAINABLE

6 The Apex Court has dealt with the rights of third person and/or

objection of third person, in arbitration proceedings in Taiyo

Membrane Corporation Pty. Ltd vs. Shapoorji Pallonji and Company Ltd

[ (2016) 1 SCC 736. ], by following [Chloro Controls (I) Pvt Ltd

v.Severn Trent Water Purification Inc and anr., (2013) 1 SCC 641. ]. In

the present matter, we have to consider the submission of Appellant

accordingly. At the instance of a party, though not party to the

Arbitration Agreement in Taiyo Membrane Corporation Pty. Ltd

(supra), based on the facts and the correspondences between the

parties, the Supreme Court has maintained the invocation of the

arbitration clause by the third person to appoint Arbitrator under

Section 11(6) of the Arbitration Act. Therefore, depending upon the

facts of the case, even the third party can be added or joined as party

for appropriate reliefs and for it's effective implementation, specially

in Section 9 Petition. There is no total bar, but subject to the

interconnected and interdependent facts and the contract conditions

between the parties. In the present case also, all the transactions are

dgm 9 appl-545-15-judgment.sxw

interdependent and interlinked. Hence, we have to hold that the

present Arbitration proceedings so initiated and the order so passed is

sustainable. There is no perversity or illegality in the order. Hence,

the order :

ORDER

(a) The Appeal is dismissed.

    (b)    There shall be no order as to costs. 
                                   
                                  
        (A. A. SAYED, J.)                             (ANOOP V. MOHTA, J.)
        
     











 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter