Citation : 2016 Latest Caselaw 3990 Bom
Judgement Date : 20 July, 2016
1 WP/ 326 /2015
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
WRIT PETITION NO. 326 OF 2015
1] Kamlakar Raosaheb Patil
Age : 48 years, Occu.: Agriculture,
R/o : Plot No. 314, N-3, CIDCO,
Aurangabad,
Dist. : Aurangabad
2] Suhas Annarao Mane,
Age : 43 years, Occu.: Agriculture,
R/o : Plot No. 314, N-3, CIDCO,
Aurangabad,
Dist. : Aurangabad
ig .. Petitioners
VERSUS
1] The State of Maharashtra,
Through its Secretary,
Urban Development Department,
Mantralaya, Mumbai - 32
2] City and Industrial Development
Corporation of Maharashtra Ltd.,
Through its Administrator,
Udyog Bhavan, CIDCO,
New Aurangabad
3] The Municipal Corporation
Aurangabad through its Commissioner .. Respondents
----
Mr. S.B. Talekar, Advocate and Mr. U.R. Awate, Advocate for
the petitioners
Mr. N.B. Patil, AGP for the respondent No.1/State
Mr. A.S. Bajaj, Advocate for respondent no.2
Mr. V.P. Latange, Advocate for respondent no.3
----
CORAM : S.V. GANGAPURWALA &
K.K. SONAWANE, JJ.
DATE : 20/07/2016
2 WP/ 326 /2015
ORAL JUDGMENT :
Rule. Rule made returnable forthwith. Heard
finally with consent of the parties.
2. Mr. Talekar, learned counsel for the
petitioners submits that as per the order passed by this
Court in earlier Writ Petition, the petitioners were
allowed to file application with CIDCO seeking no
objection certificate within four weeks from the order
dated 18/11/2009 in Writ Petition No. 6175 of 2009. The
petitioners applied within 15 days for No Objection
Certificate on 2/12/2009. The petitioners were granted
No Objection Certificate on 3/12/2009 and immediately on
17/12/2009, the petitioners applied for commencement
certificate. The respondent communicated some
deficiencies vide its letter dated 15/1/2010. According
to the learned counsel for the petitioners, the
petitioners, as per the letter, had submitted all the
documents and complied all the necessary aspects but
there was total inaction on the part of the Municipal
Corporation and the Municipal Corporation, eventually
3 WP/ 326 /2015
issued commencement certificate on 26/12/2014. The
petitioners have carried out 100% construction as per
the plan submitted to the Corporation and as per the
commencement certificate dated 26/12/2014. However,
abruptly, on 3/12/2014, CIDCO issued the notice to the
petitioners with regard to the cancellation of the
allotment and the agreement. Learned counsel for the
petitioners submits that the petitioners had complied
with the orders passed by this Court and each and every
step was taken, however, it was only because of the
delay on the part of the respondent-Corporation, the
commencement certificate was not granted in time.
Learned counsel for the petitioners submits that even
after filing of the present writ petition, the site is
visited by the Officers of the CIDCO for the purpose of
processing No Objection Certificate for occupancy
certificate. The letter to that effect is also issued
by the Assistant Engineer, N.O.C. cell on 11/3/2015.
According to learned counsel, 100% compliance as per the
commencement certificate has been made, therefore, the
impugned order/notice be quashed and set aside.
4 WP/ 326 /2015
3. Mr. Bajaj, learned counsel for the respondent -
CIDCO submits that the petitioners have not complied the
order passed by this Court in Writ Petition No. 6175 of
2009. The petitioners did not carry out the
construction as per the terms of the agreement. The
petitioners also did not carry out the construction as
per the notice issued pursuant to the directions issued
by this Court. There was total lethargy on the part of
the petitioners to develop the property. Though the
petitioners applied to the Municipal Corporation on
17/12/2009, the said application was devoid of necessary
particulars, as was required. The petitioners did not
comply the deficiencies and the deficiencies were
complied after a lapse of more than 4-1/2 years
after issuance of notice by CIDCO. This shows that only
farce of compliance was made by the petitioners.
According to the learned counsel for the respondent, the
petitioners are not entitled for any discretionary
orders passed of this Court.
4. Mr. Latange, learned counsel for the respondent
Municipal Corporation submits that there is no delay on
5 WP/ 326 /2015
the part of the Corporation. It is the petitioners, who
did not comply with the deficiencies, as were pointed
out to the petitioners from time to time. The
petitioners are themselves responsible for the delay.
5. We have considered the submissions. Petitioners
got the fresh lease of life pursuant to the orders of
this Court in Writ Petition No. 6175 of 2009. This Court
has laid down the schedule for the petitioners to take
steps. No doubt the petitioners applied for the NOC and
the commencement certificate within time stipulated by
this Court. The respondent Corporation pointed out some
deficiencies. Said deficiencies, as per the Corporation
are cured on 10/12/2014 and the commencement certificate
is issued on 26/12/2014. There is word against word
with regard to the compliances being made/not made by
the petitioners. We need not go into the said aspect.
The CIDCO, was well within its right to issue notice if
the construction is not carried or commencement
certificate is not obtained within the period as was
stipulated in the order passed by this Court dated
18/11/2009 in Writ Petition No. 6175 of 2009.
6 WP/ 326 /2015
6. It is submitted by learned counsel for the
petitioners that subsequently, the entire construction
as per the commencement certificate has been carried out
by the petitioners and even the respondent CIDCO,
through its officer has visited the site, as can be
viewed from the letter dated 11/3/2015 annexed to the
rejoinder at Exhibit A-4.
7.
CIDCO was only required to be satisfied about
the construction as per the commencement certificate for
issuance of no objection certificate for the occupancy
certificate.
8. Considering the aforesaid conspectus of the
matter that now the construction is carried out and part
of the construction was carried by the predecessor in
title of the petitioners, though there is delay for
completion of the construction, we invoke our
jurisdiction under Article 226 of the Constitution of
India in favour of the petitioners, however, the
petitioners also deserve to be mulct with penalty.
Considering the above, we pass the following order:-
7 WP/ 326 /2015
9. Impugned order/notice dated 3/12/2014 is
quashed and set aside. The respondent Corporation has
already inspected the site and if satisfied that the
construction is as per the commencement certificate, it
shall issue no objection certificate for grant of
occupancy certificate. The petitioners shall pay
penalty of Rs.1,00,000/- (Rs. One Lakh) to the
respondent - CIDCO within four (4) weeks.
10. Rule is accordingly made absolute in above
terms. No costs.
[K.K. SONAWANE] [S.V. GANGAPURWALA]
JUDGE JUDGE
arp/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!