Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.R.R.B Realtors Pvt Ltd vs M/S.Subhash Nagar Rajeshwari ...
2016 Latest Caselaw 7578 Bom

Citation : 2016 Latest Caselaw 7578 Bom
Judgement Date : 22 December, 2016

Bombay High Court
M/S.R.R.B Realtors Pvt Ltd vs M/S.Subhash Nagar Rajeshwari ... on 22 December, 2016
Bench: S.J. Kathawalla
    KPPNair                                  1                                           arbp-681  

               IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                              
                   ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                 
                     ARBITR ATION PETITION NO. 681 OF 2016

    M/s. R.R.B. Realtors Pvt. Ltd.                                            ... Petitioner




                                                                
         vs.

    M/s. Subhash Nagar Rajeshwari CHS Ltd. and others                         ...Respondents

                            ALONG WITH




                                              
                 NOTICE OF MOTION NO.      OF 2015
                                IN
          BOMBAY CITY CIVIL COURT L.C. SUIT NO. 2598 OF 2015
                                 
    Dr. Birendra Saraf, along with Mr. Kunal Banage and Mr. Vasin Siddiqui, instructed
    by Kunal Banage for the Petitioner.

    Mr. Raj Patel, along with Mr. G.D. Uttangale, instructed by M/s. Uttangale & Co.,
        


    for Respondent No.1.
     



    Mr. A.S. Kharatmol for Respondent Nos. 2 to 8.

                                         COR AM: S. J. KATHAWALLA, J.
                                       Judgment reser ved on : 4th July, 2016





                                   Judgment pronounced on : 22nd December, 2016

    JUDGMENT:

1. The above Petition is filed by the Petitioner -- R.R.B. Realtors Pvt. Ltd., under

Section 9 of the Arbitration and Conciliation Act, 1996 ("the Act") against the

Respondents -- M/s. Subhash Nagar Rajeshwari CHS Ltd. and 10 others i.e.

Respondent Nos. 2 to 11, who are the members of the Respondent No.1 Society but

KPPNair 2 arbp-681

are not vacating and handing over possession of the tenements to the Petitioner

and/or the Respondent No. 1 Society for the purpose of redevelopment. The

Petitioner has therefore prayed for appointment of Court Receiver in respect of the

tenements occupied by Respondent Nos. 2 to 8 mentioned in Schedule-A to the

Petition with the power to take physical possession of the same and hand over the

same to the Petitioner for the purpose of redevelopment of the Society building i.e.

Building No. 18, Subhash Nagar, Chembur, Mumbai-400 071 and also for

appointment of Court Receiver in respect of the ig tenements occupied by

Respondent Nos. 9 to 11 (whose whereabouts are not known) with power to take

physical possession after making inventory of the articles lying in their tenements and

handing over the same to the Petitioner for the purpose of redevelopment and upon

completion of redevelopment of the new building to hand over possession of three

tenements to be allotted in the name of Respondent Nos. 9 to 11 either to the Court

Receiver or MHADA or to the Respondent No. 1 Society as may be deemed fit and

proper by this Court. The Petitioner has also sought directions of this Court against

Respondent Nos. 2 to 8 to forthwith vacate and hand over the physical possession of

the respective tenements to the Petitioner for expeditious development of the Society

building by accepting agreed rent, shifting charges, brokerage and corpus amount,

within a time bound period.

2. The Petitioner is a Private Limited Company primarily engaged in the business

KPPNair 3 arbp-681

of real estate development. Respondent No.1 is a registered Co-operative Housing

Society of persons belonging to "Lower Income Group" (LIG). The said society

comprises of 36 residential flats each admeasuring about 180 sq.ft. of carpet area.

The building which is owned by the Society was constructed by Maharashtra

Housing and Area Development Authority (MHADA) i.e. building No. 18 on plot

at S. No. 67 to 71 and CTS 831 (PT.) admeasuring about 1203.42 sq/mtrs. at

Subhash Nagar, Chembur, Mumbai-400 071 (the said building). The flat purchasers

later formed the Respondent No. 1 Society and got the same registered under the

Societies Registration Act. By a Deed of Conveyance dated 19 th January, 1994,

MHADA sold, transferred and conveyed the said building to the Respondent No. 1

Society. MHADA also granted lease of the land underneath the building in favour of

the Society.

3. As stated hereinabove, Respondents Nos. 2 to 8 are the non-cooperating

members of Respondent No-1-society who are refusing to vacate and hand over

possession of the respective tenements for redevelopment contrary to their individual

agreements as well as the Development Agreement dated 15 th July, 2013 executed by

the society. Respondent Nos. 9 to 11 are persons in whose name 3 flats stand in the

records of the Society. It is the case of the Petitioner that the said flats have remained

locked for nearly a decade and the owners of the said flats are not traceable. Pursuant

to an order dated 21st March, 2016, a notice was issued by way of publication in the

KPPNair 4 arbp-681

newspapers. However, Respondent Nos.9 to 11 have not appeared before the Court.

4. Out of the said 36 members, 26 members in consonance with the terms of the

Redevelopment Agreement dated 15th July, 2013 vacated their individual flats in the

said building and have already shifted to alternate transit accommodation of their

own choice. Since Respondent Nos.2 to 8 have failed to vacate the premises and

Respondent Nos. 9 to 11 have abandoned the premises and are not traceable,

according to the Petitioner and Respondent No.1, the entire redevelopment of the

Society has been held up thereby causing serious irreparable loss and prejudice not

only to the Petitioner but to a majority of members of the said Society i.e. 26 out of

36 members. The Petitioner has therefore filed the above Petition seeking reliefs set

out in paragraph (1) above.

5. Briefly set out are the facts as narrated by the Petitioner and Respondent No.1

Society:

5.1 The said building which is owned by the Society was constructed in or around

the year 1954.

5.2 Since the construction of the said building, no major repairs have been carried

out thereby resulting in the said building being in highly dilapidated and dangerous

condition causing a threat to the occupants of the building and also to the people in

its vicinity.

    5.3       In view thereof, the members of the Society including Respondent Nos. 2 to 8





     KPPNair                                   5                                           arbp-681  

in the meeting held some time in 2004-2005 unanimously resolved and appointed a

developer to carry out the redevelopment of the said building.

5.4 After appointing the first Developer, no progress was made in the

redevelopment process thereby resulting in further dilapidation of the said building.

The Respondent No.1 Society thereafter was on a look out for some other developer

to carry out the redevelopment work. It was at that time that the Petitioner came

forth and offered to undertake the redevelopment project.

5.5 That after detailed negotiations, the Petitioner made an offer to the

Respondent No.1 Society.

5.6 That after scrutinising the proposal for redevelopment forwarded by the

Petitioner, in the meeting of the Defendant No.1 Society held on 9 th August, 2009,

it was unanimously resolved to appoint the Petitioner as the developer for the society.

The meeting was attended by Respondent No. 3 and the original members of the flats

occupied by Respondent Nos. 2, 4 and 8. The said Resolution dated 9th August, 2009

has been annexed at Exhibit "B" - Pg.28 of the Petition.

5.7 In furtherance of the said resolution, a Development Agreement dated 22 nd

April, 2010 was executed between the Petitioner and Respondent No.1-society. As

per the said development agreement, the following benefits were to be given to each

member of the said society. ( "Annexure 2" - Page - 26, in the compilation of

documents filed by the Respondent No.1 ) : -

    (i)       Permanent Alternate Accommodation admeasuring 400sq.ft. in view of





     KPPNair                                   6                                           arbp-681  

180sq.ft. currently occupied by the said Respondents. (Clause No.2, Pg. 31)

(ii) Transit Rent - Rs. 11,000/- per month for 24 months (Clause No.3, Pg. 31).

(iii) Corpus Fund - Total Rs.4,00,000/-

(Rs.2,00,000/- before handing over possession and Rs.2,00,000/- to be paid in the

name of society at the time of giving possession. ) (Clause No.4, Pg. 31)

5.8 Further to the unanimous support expressed by all the members of the said

society including Respondent Nos.2 to 9, all the 33 out of 36 members of the society

in June 2010 executed individual consent letters in favour of the Petitioner thereby

signifying their irrevocable individual consent to the redevelopment project. The

copies of the said individual consent letters of Respondent Nos. 2 to 8 are annexed at

pages 37, 40, 42, 45, 48, 51 and 54 of the Petition.

5.9 Alongwith the aforesaid consent letters, the members including the

Respondent Nos. 2 to 8 in June, 2010 also executed 'Agreement for Alternate

Accommodation'. Each of these agreements incorporated an arbitration clause

(Clause 20) for resolution of disputes. The copies of the Agreement for Alternate

Accommodation executed by Respondent Nos. 2 to 8 are at pages 57,71, 85, 108, 123,

137 and 151 of the Petition.

5.10 The Petitioner vide its application dated 20 th September, 2010 applied to

MHADA seeking their NOC for redevelopment of the society building. ( Annexure 4

- Pg. 43 in the compilation of documents filed by the Respondent No.1.).

    5.11       MHADA issued its "First Offer Letter" in respect of redevelopment of the





     KPPNair                                 7                                           arbp-681  

said society. (Annexure - 5 - Pg. 44 in the compilation of documents filed by the

Respondent No.1)

5.12 In view of change of certain policies by MHADA, all redevelopment

proposals were put on hold. The Petitioner had to revise its proposal to MHADA a

few times. Finally, vide its letter dated 15 th May, 2013 MHADA granted NOC for

redevelopment on a condition that the Petitioner deposits an amount of

Rs.3,26,38,010/- towards MHADA charges and an additional amount of

Rs.1,05,31,518/- towards off-site infrastructure charges payable to MCGM.

(Annexure 6 - Pg. 49 in the compilation of documents filed by the Respondent No.1)

5.13 Due to delays caused in receiving the initial NOC/ clearance from MHADA,

Respondent No.1-society held a meeting dated 14th June, 2013. At the said meeting,

the terms of the Development Agreement were re-negotiated and the benefits to be

given to the members of Respondent No.1-society were enhanced. The said meeting

of Respondent No.1-society was attended by all the 33 available members including

Respondent Nos. 2 to 8 who in fact had taken a leading role in re-negotiating the

terms of the Redevelopment. At the said meeting, it was decided to further enhance

the benefits to be given to the members including enhancement in the area of flats to

be given to each member, enhancement in corpus fund, enhancement in monthly

transit rent, and also enhancement in the shifting charges. It was in this meeting that

all the members of the society unanimously resolved to modify the terms of

development.

KPPNair 8 arbp-681

(Minutes of the meeting are at "Annexure - 7" - Page 54 - English translation - 68"

in the compilation of documents filed by the Respondent No.1).

5.14 As agreed in the General Body Meeting dated 14/06/2013 the Petitioner along

with Respondent No.1-society executed a fresh Agreement for Redevelopment

incorporating the revised terms set out in Clause 15 above, which agreement was

registered on 15th July, 2013. The enhanced benefits provided in this agreement are

as follows:

(i) Corpus Fund - Rs.5,40,000/-

(Rs.3,00,000/- before handing over possession and Rs.2,40,000/- to be paid in the

name of society at the time of giving possession.

(ii) Alternate Area 450 sq.ft. in place of 400 sq.ft as agreed earlier.

    (iii)     Monthly Transit Rent Rs.18,500/- .
      



    (iv)      One time shifting charge Rs.20,000/-

(Copy of the said Registered Development Agreement dated 15/07/2013 is annexed

at "Annexure 8" - Pg. 91 in the compilation of documents filed by the Respondent

No.1 )

5.15 Vide its letter dated 3rd February, 2014, MHADA gave its final approval to the

redevelopment proposal forwarded by the Petitioner. ("Annexure 9" - Pg.214 in the

compilation of documents filed by the Respondent No.1).

5.16 In pursuance of the final approval received from MHADA the Petitioner paid

an amount of Rs.3,71,80,310/- to MHADA for FSI/ TDR and further paid an

KPPNair 9 arbp-681

amount of Rs.1,21,19,727/- to MCGM towards infrastructure charges.

5.17 The members of Respondent No.1-society had even neglected to pay the basic

service charges to MHADA which had by now aggregated to Rs.31,80,806/-. The

Petitioner had to pay this amount on behalf of the Defendant No. 1 society in order to

receive the final consent from MHADA for redevelopment.

It was after making all the aforesaid requisite payments amounting to nearly Rs.

5.18

5,34,80,843/-, that the Petitioner finally secured NOC from MHADA for procuring

IOD in respect of the re-development project.

5.19 The Petitioner thereafter applied for IOD to MCGM for the said project and

made the requisite deposit of Rs.10,00,000/- towards IOD charges.

5.20 MCGM after scrutinizing the proposal forwarded by the Petitioner granted

IOD for Redevelopment dated 30th June, 2015. ("Annexure 16 - Pg.237" in the

compilation of documents filed by the Respondent No.1).

5.21 At the meeting held on 14th June 2013, the members of the Respondent No.1-

society had left to the Petitioner to grant certain additional areas to the members

beyond the area of 450 sq.ft. The Petitioner, to respect the sentiments of the

members, agreed to allot permanent alternate accommodation admeasuring 480 sq.ft.

carpet area and the said understanding was crystallized in the "Individual

Agreement" for alternate accommodation executed between the individual member

and the Petitioner herein. These agreements were executed at the time when the

KPPNair 10 arbp-681

individual members started vacating their flats and handing over the possession

thereof to the developer.

5.22 The process of entering into individual agreements for permanent alternate

accommodation with the members commenced on 11th August, 2015. The last such

agreement was executed on 25th March, 2016. In consonance with the understanding

arrived at between the parties the Petitioner paid to each member who had vacated

his existing premises the requisite amounts towards shifting charges, advance transit

rent and corpus fund as agreed between the parties collectively amounting to

Rs.2,42,74,600/-. With this payment, the funds invested by the Petitioner in this

project aggregated to Rs. 7,77,55,443/-.

5.23 In the meanwhile, instead of vacating the premises to enable the

commencement of redevelopment work, Respondent No. 3 along with the Associate

Members of Flats occupied by Respondent Nos. 4, 7 and 8, filed a regular Civil Suit

bearing L.C. Suit 9449 of 2015 against the Petitioner and Respondent No.1. The

prayers in the said Suit are as follows: -

(i) That this Hon'ble Court be pleased to declare by an order of this Hon'ble Court that the Development Agreements dated 22 nd April, 2010 and 15th July, 2013 stands cancelled in respect of the suit premises i.e. Building NO.18, Rajeshwari Co-Operative Housing Society, Subhash Nagar, Chembur, Mumbai - 400 071.

     KPPNair                                     11                                           arbp-681  

              (ii)    That this Hon'ble Court be pleased pass an Order by directing




                                                                                                

the Defendant No.4 to appoint New Developer by following due process of law in respect of suit premises i.e. Building No.18,

Rajeshwari Co-operative Housing Society, Subhash Nagar Chembur, Mumbai - 400 071.

(iii) That this Hon'ble Court be pleased to pass an order by directing the Defendant No.2 and Defendant No.3 not to grant permission for any construction activities carried out by Defendant No.1 in respect of

the suit premises i.e. Building No.18, Rajeshwari Co-operative Housing

Society, Subhash Nagar Chembur, Mumbai - 400 071.

(iv) That this Hon'ble Court be pleased to pass an order directing Defendant No.4 to declare balance Fund of Society and utilise said fund for repairs and maintenance of the society.

(v) That this Hon'ble Court be pleased to pass an order and permanent injunction of this Hon'ble Court restraining Defendant No.1 and Defendant No.4 from carrying out construction activities at

the suit premises i.e. Building No.18, Rajeshwari Co-operative Housing Society, Subhash Nagar Chembur, Mumbai - 400 071.

5.24 In the said Suit, the Plaintiffs filed a Notice of Motion seeking interim relief

restraining the Petitioner from carrying out any redevelopment activities and for

appointment of a new developer. Pursuant to an order dated 21/03/2016 passed by

this Court, the said Suit has been transferred to this Court and the Notice of Motion

has been heard alongwith the Arbitration Petition filed by the Petitioner.

KPPNair 12 arbp-681

6. The Learned Advocate appearing for the Petitioner has taken me through the

above facts and has made the following submissions:

6.1 That the Respondent No.1 Society pursuant to a unanimous resolution of all

its available members has entered into a development agreement with the Petitioner.

The Society and its members have extensively negotiated the terms of the

development agreement with the Petitioner which have been incorporated in the

development agreement and the individual agreements with the members. All the

members other than the Respondent Nos.2 to 8 have vacated their individual

premises and are in transit accommodations. Respondent Nos.9 to 11 in whose names

the remaining three premises stand in the records of the Respondent No.1-society are

not traceable and have not appeared before this Court despite public notice having

been issued. It is therefore, seven out of 36 members who are obstructing the

redevelopment process. The Petitioner has obtained all the necessary permissions to

commence the construction and it is only due to Respondent Nos. 2 to 8 not vacating

their respective premises that the entire process of redevelopment is at a stand still.

6.2 That the Respondent Nos. 2 to 8 are bound by the agreement executed by the

Respondent No.1-society and cannot be permitted to obstruct the development

project agreed to by the majority members of the society. In fact, the Respondent

Nos. 2 to 8 had also accepted the redevelopment and also executed individual

agreements. The stand now taken by Respondent Nos. 2 to 8 is clearly illegal and an

after thought.

     KPPNair                                    13                                           arbp-681  

    6.3       Pursuant to the development agreement, the Petitioner has spent 7,77,55,443/-




                                                                                               

of which more than 3.5 crores has been invested by the Petitioners out of their own

funds. The Petitioners are willing to deposit all the monetary benefits due to the

Respondent Nos. 2 to 11 in Court. The Petitioners have also appointed reputed

architect and interior designer to execute the project, details of which are set out in

the affidavit dated 04.06.2016 filed by the Petitioner.

6.4 That it is settled law as laid down by various judgments of this Hon'ble Court

in Girish vs. Mahesh1 , Bharat Infrastructure Engineering Pvt. Ltd. vs. Park Darshan

CHS Ltd.2 , Akash Pruthi Lifestyle vs. Akash Co-op. Hsg. Society Ltd. 3, Disha

Constructions vs. Jaysen Mastakar4 and Mayfair Housing Pvt. Ltd. vs. M/s. Meera

M. Bhagat5 that the dissenting members are bound by the decision of the majority in

a co-operative society and cannot defeat the rights of the Respondent No.1-society by

obstructing the redevelopment process. The obstructive attitude of Respondent

Nos. 2 to 8 is causing grave and irreparable harm, loss and prejudice not only to the

Petitioner but all the other members of the Respondent No.1-society who have

vacated their respective premises.

1 (2010 (2) Mh.L.J.657) [Paragraphs 18 to 20].

2 (Judgment dated 18.03.2013 in Arbitration Petition No.199 of 2013) [Paragraph 24, 32 & 33].

3 (Judgment dated 26.08.2013 in Notice of Motion (lodging) No.1518 of 2013 in Suit (lodging) No.662 of 2013 [Paragraphs 19 & 20].

4 (Judgment dated 16.09.2013 in Notice of Motion No.859 of 2009 in Suit No.397 of 2013 [Paragraphs 62 & 63].

5 (Judgement dated 18.02.2012 in Notice of Motion No.74 of 2012 in Suit No.40 of 2012 [Paragraphs 22]

KPPNair 14 arbp-681

7. The Learned Advocate appearing for the Respondent No. 1 Society has also

pointed out the aforestated facts and has submitted that since the said building has

been in a dilapidated and dangerous condition due to lack of maintenance and repairs,

the members of the Respondent No. 1 had been deliberating the issue of

redevelopment of the building since the year 2002, However, the Respondent No. 1

was unable to undertake the redevelopment of the building due to lack of sufficient

funds for the Society. The Society had in fact identified a developer in the year 2005-

2006. However, the said developer abandoned the project due to pressure from the

local leaders who were wanting to promote only one particular developer to

redevelop the cluster of buildings in the area. Thereafter, the Society approached the

Petitioner for the purpose of redevelopment of the Society building some time in

June, 2009. On 9th August, 2009, the Society held a Special General Body Meeting

where Respondent Nos. 3, 5 and 6 were personally present and Respondent Nos. 2,

4, 7 and 8 were being represented by the nominee members/family members. In the

said meeting, all the members present unanimously passed various Resolutions viz.

appointing the Petitioner as a developer, the rent for alternate accommodation,

corpus fund to be given to the Petitioner, Bank guarantee to be taken from the

developer, carpet area for the permanent accommodation, etc. These Resolutions

were in fact seconded by Respondent No.3. The Development Agreement was

thereafter executed on 22nd April, 2010 and all the members of the Society including

KPPNair 15 arbp-681

Respondent Nos. 2 to 8 executed consent letters in favour of the Petitioner on 8 th

June, 2010 and also executed individual agreements for alternate accommodation.

After the execution of the development agreement in 2010, the members of the

Society held further discussions with the Petitioner and bargained for higher amount

of corpus fund, rent for alternate accommodation, larger carpet area, shifting and

brokerage charges etc. The said meeting was personally attended by Respondent

Nos. 3 to 7 and Respondent Nos. 2, 4 to 6 and 8 were represented by their family

members/nominee members. All the members present at the meeting have passed

various resolutions unanimously. In view of the resolutions passed at the meeting

held on 14th June, 2013, a Development Agreement was executed between the

Petitioner and Respondent No. 1 Society on 15 th July, 2013. Since the Society and its

members bargained hard with the Petitioner, the Petitioner increased the area to be

allotted to the members of the Society from 400 sq.ft. (carpet) to 450 sq.ft. (carpet)

and later to 480 sq.ft. (carpet).

8. It is further submitted on behalf of the Respondent No. 1 Society that the

election of the Managing Committee was held in the Annual General Meeting on 23d

August, 2015 in the presence of the Co-operative Officer appointed by the Deputy

Registrar, Co-operative Societies, Bandra, Mumbai. The Respondent Nos. 2, 3, 4, 5

and 7 also contested the said elections. However, except for Respondent Nos. 4 to 7,

Respondent Nos. 2, 3 and 5 lost the elections. In view thereof, Respondent Nos. 2 to

KPPNair 16 arbp-681

8 started objecting to the decisions taken by the new Managing Committee thereby

acting against the benefit and interest of the majority of the members of the Society

and filed a Suit in the City Civil Court seeking reliefs against the Society and its

office-bearers. The Society has conducted AGMs/SGMs every year as per the

provisions of law. However, Respondent Nos. 2 to 8 have made incorrect allegations

against the Society that they have been kept in dark and were not informed about the

progress pertaining to the redevelopment. The Petitioner has already spent crores of

rupees on the redevelopment project.

ig 26 members have shifted to temporary

alternate accommodations long back and the Petitioner has paid to them the part

corpus fund, advance rent for 12 months, shifting and brokerage charges as agreed

under the Development Agreement dated 15th July, 2013. All of them are eagerly

waiting for the building to be demolished and the redevelopment to start and to

return back to the new flats having larger area of 480 sq.ft. in lieu of the present

tenements admeasuring 180 sq.ft. Respondent Nos. 2 to 8 are wrongly and

unreasonably obstructing the redevelopment project through the Petitioner. The

balance of convenience is in favour of the Petitioner and the members of the Society

and therefore the Petition be allowed as prayed.

9. The Learned Advocate appearing for Respondent Nos. 2 to 8 has submitted as

follows:

    9.1       That the present Petition is not maintainable in law since Respondent Nos. 2 to





     KPPNair                                   17                                           arbp-681  

8 have already filed a suit being No. 2598 of 2015 in the City Civil Court at Mumbai,

against the Petitioner and others pertaining to the same subject matter.

9.2 That the Petitioner and Respondent No. 1 are acting in collusion and are bent

upon evicting Respondent Nos. 2 to 8 in the guise of redevelopment, though there

are many triable issues raised in the Suit filed by them being Suit No. 2598 of 2015.

9.3 That on 15th July, 2013, the Respondent No. 1 Society entered into a

Development Agreement with the Petitioner without informing Respondent Nos. 2

to 8 and without taking them in confidence. Respondent Nos. 2 to 8 had to obtain the

Development Agreement under the Right to information Act.

9.4 The Respondent Nos. 2 to 8 were required to obtain a copy of the development

agreement under the Right to Information Act.

9.5 That the arbitration clause No. 57 of the Development Agreement dated 22 nd

April, 2010, became redundant in view of clauses 54, 59 and 60 of the said

Agreement.

9.5 That during the period between 2010 and 2013, the Petitioner had not made

any sort of correspondence and communication with Respondent Nos. 2 to 8.

Respondent Nos. 2 to 8 continuously approached Respondent No. 1 for enquiry

about the stage of development activities undertaken as per the development

agreement between the Petitioner and Respondent No.1. However, Respondent No. 1

did not respond at all. The tenure of the Committee of Respondent No. 1 expired in

the year 2013 and existing Committee of Respondent No. 1 did not take any steps

KPPNair 18 arbp-681

for holding election and has not held AGMs since 2013.

9.6 That Respondent No. 1 has not explained any factual position/progress of

redevelopment project and also not followed due process of law such as

appointment of Project Management Consultant, tender offer procedure , holding

of AGM/SGM in the presence of the Dy. Registrar of the Co-operative Societies.

9.7 That the PMC Structural Audit Report in Point No. ( E) -DURABILITY

has stated that "Building needs to be maintained for carrying out repairs from time to

time for durability. The above suit building is not maintained properly".

9.7 That Respondent No. 1 has not followed due process of law while verifying

credentials of the Petitioner.

9.8 That the Petitioner has not explained anything about the progress of the

building proposal i.e. what the Petitioner is proposing to offer such as area and size of

flat, corpus, rents, etc.

9.9 That the Petitioners have not replied to the letter addressed to them by the

Advocates for Respondent Nos. 2 to 8 through Subhash Chandra Pal.

9.10 That the Petitioner and Respondent No. 1 have in collusion prepared new flat

allotment list as per their convenience and mentioned wrong new flat numbers and

new floor numbers of Respondent Nos. 5 and 6.

9.11 That it is not proper to grant interim relief under Section 9 of the Act against

the persons who have no contractual relationship with the Petitioner. The contract is

only between the Petitioner and Respondent No. 1 Society.

     KPPNair                                    19                                           arbp-681  

    9.12        That the above Petition needs to be dismissed and the Notice of Motion be




                                                                                               
    allowed.




                                                                   
    9.13        That the decision of the Delhi High Court dated 25 th May, 2009 in the case

of KK Modi Investment and Financial Services Pvt. Ltd. vs. Apollo International

Inc. lends support to the submission of Respondent Nos. 2 to 8 that the Petitioner

has no privity with the Respondent Nos. 2 to 8.

10. The Learned Advocates appearing for the Petitioner as well as Respondent No.

1 have in rejoinder submitted that the submissions and contentions raised by

Respondent Nos. 2 to 8 are false, untenable and baseless and the above Petition be

therefore allowed as prayed.

11. I have gone through the petition filed by the Petitioner as well as the papers

and proceedings in the Suit filed by Respondent Nos. 2 to 8 being Suit No. 2598 of

2015 before the City Civil Court at Bombay which suit is transferred to this Court

and by consent of the parties the Notice of Motion taken out by Respondent Nos. 2

to 8 in the said Suit is taken up for hearing along with the above Petition.

12. Respondent Nos. 2 to 8 have submitted that the Development Agreement

dated 15th July, 2013 was executed without informing them and without taking into

confidence. Admittedly the said building was constructed in the year 1954 by

MHADA for persons belonging to Lower Income Groups (LIG).The 36 flat

purchasers who purchased the flats admeasuring 180 sq.ft. formed and registered a

KPPNair 20 arbp-681

Society in whose favour MHADA, executed a conveyance dated 19th January, 1994

and also granted lease in respect of the land beneath the said building As submitted

by the Society, over the years the members were not able to carry out any major

repairs resulting in the said building being in a dilapidated condition. In the year

2005-2006, the Society did identify a developer to redevelop the said building.

However, since the said developer abandoned the project, the Respondent No. 1

Society approached the Petitioner developer for the purpose of redevelopment of the

said building in June, 2009.

12.1. From the records it becomes clear that Respondent No. 1 Society held a

Special General Body meeting on 9th August, 2009, which was personally attended by

Respondent Nos. 3, 5 and 6 and by the family members/nominee members of

Respondent Nos. 2, 7 and 8. In the said meeting, all the members present

unanimously passed a Resolution appointing the Petitioner as the developer. In

furtherance of the said Resolution, a Development Agreement was executed on 22 nd

April, 2010, between the Petitioner and Respondent no. 1 Society wherein the

Petitioner agreed to provide permanent alternate accommodation admeasuring 400

sq.ft. in lieu of 180 sq.ft. occupied by the members of the Society. The Petitioner also

agreed to pay transit rent of Rs. 11,000/- per month for 24 months to the members

and further agreed to pay the total corpus fund of Rs. 4 lakhs to each of the members

i.e. Rs. 2 lakhs before handing over possession and Rs. 2 lakhs to be paid to the

Society at the time of giving possession.

KPPNair 21 arbp-681

12.2 In furtherance to the unanimous support expressed by all the members of the

Society including Respondent Nos. 2 to 9, all the 33 out of 36 members of the Society

executed individual consent letters in favour of the Petitioner thereby signifying their

irrevocable individual consent to the redevelopment project. The copies of the

individual consent letters of Respondent Nos. 2 to 8 dated 6 th June, 8th June and 22nd

June, are annexed to the Petition at pages 37, 40, 42, ,45, 48,51 and 54 respectively.

Respondent Nos. 2 to 8 have in the said letters, inter alia, categorically stated as

under:

"I/We are aware that the Society, vide Resolution passed in the Special

General Body Meeting dated 09-08-2009 has decided to redevelop the Society property by demolishing the existing building and construct a new building on the plot thereof.

That I/We are also aware that the Society has received offer for

development from various builders and developers and the Society have appointed as developers, M/s. RRB Realtors Pvt. Ltd., a Company incorporated under the Companies Act, 1956. The Society and its

constituent members have consented for the said proposed development and the same is binding on me.

!/We hereby given my/our consent to the Society and to the said

Developers, M/s. RRB Realtors Pvt. Ltd. to proceed with the proposed redevelopment, in accordance with the plans as approved by the Municipal Corporation of Greater Mumbai.

I/We also agree to sign and execute the Individual Agreement for the Permanent Alternate accommodation, as and when plans for revised area are ready and approved by BMC."

KPPNair 22 arbp-681

The Petitioner vide its application dated 20 th September, 2010 applied to

MHADA seeking their NOC for redevelopment of the society building to which

MHADA issued its "First Offer Letter" in respect of redevelopment of the

said society building. Due to change in certain policies by MHADA, the

redevelopment proposals were put on hold for some time. The Petitioner had to

revise its proposal to MHADA a few times. Finally, vide its letter dated 15 th

May, 2013 MHADA granted its NOC for redevelopment on a condition that the

Petitioner deposits an amount of Rs.3,26,38,010/- towards MHADA charges

and an additional amount of Rs.1,05,31,518/- towards off-site infrastructure

charges payable to MCGM.

12.3. In fact, due to delays caused in receiving the initial NOC/ clearance from

MHADA, Respondent No.1-society renegotiated the terms of the Development

Agreement with the Petitioner and in its meeting held on 14 th June, 2014, got the

benefits earlier agreed to be provided to the members, substantially enhanced. The

corpus fund was increased from Rs. 4,00,000/- to Rs.5,40,000/- (Rs.3,00,000/- to

be handed over to each member at the time of handing over possession of their

tenements for redevelopment and Rs.2,40,000/- to be paid in the name of society at

the time of giving possession). The area of permanent alternate accommodation was

increased from 400 sq.ft. to 450 sq.ft. The monthly transit rent was increased from

Rs. 11,000/- to Rs. 18,500/-. One time shifting charge of Rs. 20,000/- was also

KPPNair 23 arbp-681

charged to the Petitioner. This meeting was also attended by Respondent Nos. 3 to 7

personally and Respondent Nos. 2 and 8 through their family members/nominee

members. In furtherance of the revised terms of development as agreed in the

General Body meeting dated 14th June, 2013, the Petitioner along with Respondent

No. 1 Society executed a fresh agreement for redevelopment which was registered on

15th July, 2013.

12.4. MHADA has given its final approval to the redevelopment proposal

forwarded by the Petitioner vide its consent dated 03 rd February, 2014. In pursuance

thereto, the Petitioner paid an amount of Rs.3,71,80,310/- to MHADA for FSI/

TDR on behalf of the Respondent No.1- Society and Rs.1,21,19,727/- to MCGM

towards infrastructure charges on behalf of the Respondent No.1 society. Since the

members of Respondent No.1-society had even neglected to pay the basic service

charges to MHADA which had by now aggregated to Rs.31,80,806/-, the Petitioner

also had to pay this amount to MHADA on behalf of the said society. The Petitioner

thereafter applied for IOD to MCGM for the said project and made the requisite

deposit of Rs.10,00,000/- towards IOD charges. MCGM after scrutinizing the

proposal as was forwarded by the Petitioner granted IOD for Redevelopment dated

30th June, 2015.

12.5. The Society and its members did not stop at this. Since the Respondent No.1

Society and its members had left to the Petitioner to grant certain additional areas to

the members beyond the area of 450 sq.ft. in the meeting held on 14 th June, 2013, the

KPPNair 24 arbp-681

Petitioner now agreed to allot permanent alternate accommodation flats to the

members of the Society being permanent alternate accommodation admeasuring 480

sq.ft. carpet area in lieu of 180 sq.ft. tenements currently occupied by them. The

process of entering into individual agreements for permanent alternate

accommodation for the members commenced in or around 11 th August, 2015. The

last such agreement was executed on 25th March, 2016. In consonance with the

understanding arrived at between the parties the Petitioner paid to each member who

had vacated his existing premises the requisite amounts towards shifting charges,

advance transit rent and corpus fund as agreed between the parties collectively

amounting to Rs.2,42,74,600/. The Petitioner has therefore invested an aggregate

amount of Rs. 7,77,55,443/- in the said project.

13. The above facts clearly establishes that Respondent Nos. 2 to 8 were at all

relevant times kept informed about the progress pertaining to the redevelopment of

the said buildings and belies the submission made by Respondent Nos. 2 to 8 that the

Development Agreement dated 15th July, 2015 was executed without informing them

and without taking them in confidence.

14. Respondent Nos. 2 to 8 have contended that the Arbitration Clause 57 of the

Development Agreement dated 22.04.2010 does not survive in light of clauses 54, 59

or 60 is equally baseless. The Agreement dated 22nd April, 2010 stood substituted by

the Development Agreement dated 15th July, 2013. The Development Agreement

KPPNair 25 arbp-681

dated 15th July, 2013 incorporates an Arbitration Agreement in Clause 57. It is this

Arbitration Agreement which is applicable. In any event the arguments advanced on

behalf of Respondent Nos. 2 to 8 in this regard are now academic since 2010

Agreement stood substituted by the subsequent development agreement dated 15 th

July, 2010.

15. The contention of Respondent Nos. 2 to 8 that the Petitioner had not made

any correspondence and communication with Respondent Nos. 2 to 8 between 2010

and 2013 and despite them having continuously approached Respondent No.1, they

did not receive any response nor take their case any further. Once all the members

of the Society at a meeting held on 14 th June, 2013 renegotiated the terms and the

Society entered into a fresh development agreement, the period prior to this

agreement is completely irrelevant. As set out hereinabove, the Petitioner as well as

Respondent No. 1 Society has explained the cause why the Development could not

take place between 2010 and 2013. These reasons were known and placed before the

members who then renegotiated the terms regarding the development agreement of

2013.

16. As regards the contention of Respondent Nos. 2 to 8 that the tenure of the

Managing Committee expired in 2013, and steps were not taken for holding election,

it appears that the said contention is incorrect in view of what is explained on behalf

of the Society and recorded in paragraph 8 hereinabove. In any case, once all the

KPPNair 26 arbp-681

members of the Society had unanimously passed the resolution on 14 th June, 2013,

this issue is of no relevance whatsoever.

17. The contention of Respondent Nos.2 to 8 that Respondent No.1 has not

explained any financial position/progress of the Redevelopment Project, is also

incorrect since the Petitioner has filed an affidavit dated 04 th June 2016, setting out

the steps taken by the Petitioner qua the redevelopment till date and the manner in

which it would be completed.

18.

As regards the submission of Respondent Nos. 2 to 8, that the Respondent No.

1 has not followed due process of law such as appointment of Project Management

Consultant, tender offer procedure and holding AGM/SGM in the presence of the

Dy. Registrar of the Co-operative Societies, the Society has submitted that in fact a

Project Management Consultant has been appointed by the Society. Respondent

Nos. 2 to 8 have in Paragraph 6 of the Written Submission itself, referred to the

report of the Project Management Consultant.

19. As regards the contentions of Respondent Nos. 2 to 8, that the Project

Management Consultant prepared a structural audit report as per the convenience of

the Respondent Nos. 2 to 11 and both are playing a fraud on Respondent Nos. 2 to 11,

the said allegation is without any basis or particulars. The condition of the building

is apparent from the photographs itself. The report of Project Management

Consultant is annexed at Page 348 of the Petition. The conclusion given by the

KPPNair 27 arbp-681

Project Management Consultant is as under:

"To recapitulate, the structure as it stands bears the marks of major deterioration which can be seen in attached photographs. The Structure

has outlived its design life and may not sustain and withstand seismic forces in near future. Hence it is advisable to demolish and reconstruct

the building as per prevailing IS codes and norms"

In light of the same, the reliance placed by the Respondent Nos. 2 to 8 on only a

portion of the report is, as submitted by the Petitioner and Respondent No.1 Society,

not a fair reading of the entire report. In any case, whether to undertake a

redevelopment or not is a collective decision of the majority members of the Society

and the minority members cannot question the said decision, unless the same is

fraudulent, lacks bona fides and smacks of mala fides.

20. The contention of the Respondent Nos. 2 to 8 that the Petitioner and

Respondent No. 1 has not explained anything about the progress of the building

proposal and what the Petitioner is proposing to offer such as area and size of flats,

corpus, rents, etc. is belied by the minutes of the meetings dated 14 th June 2013, the

terms of the Development Agreement and the clear and categoric statements made

by the Petitioner in its Affidavit dated 04th June 2016.

21. Respondent Nos. 2 to 8 have submitted that no reliefs U/s. 9 of the Act be

granted against the said Respondents as they are not privy to any agreement

containing a clause for Arbitration whereby the relief sought in the present Petition

KPPNair 28 arbp-681

against them can be justified. The submission is devoid of any substance. Individual

agreements have been signed by Respondent Nos. 2 to 8 with the Petitioner. All the

Agreements contain Arbitration clause (clause 20). All the Agreements are marked

Exhibit-D Colly. to the Petition (Pages 51 to 151). Even if there were no such

individual agreements, in the proceeding under Section 9 of the Act, the Petitioner is

entitled to implead the dissenting members of a Co-operative Society with whom it

has a Development Agreement and seek relief against the dissenting members. This

is held by a Division Bench of this Court in the case of Girish vs. Mahesh (supra)

(Paragraphs 12 to 18) which has been followed in the case of Bharat Infrastructure &

Engineering Pvt. Ltd. vs. Park Darshan CHS Ltd. [Supra]. In light of the law laid

down by this Court, the reliance placed by the Petitioner on the judgment of the

Delhi High Court in the case of K.K. Modi Investment & Financial Services Pvt.

Ltd. vs. Apollo International Inc. is misplaced and not applicable to the facts of the

present case.

22. The mere filing of a suit by the dissenting members does not justify the

refusal of the relief and the Petition filed by the Petitioners. There was no ad-interim

relief in the said suit. In any case, to obviate any grievance, this Court with the

consent of the parties transferred and has heard the interim application in the said

suit along with the Arbitration Petition. The case made out by Respondent Nos. 2 to

8 in the said suit is the same as the defence set out in the above Arbitration Petition.

KPPNair 29 arbp-681

For the reasons set out herein, there is no prima facie case made out by Respondent

Nos. 2 to 8 in the Notice of Motion filed by them in that suit. In view thereof mere

pendency of the suit cannot be a bar to grant any relief as prayed for by the Petitioner

in the above Petition.

23. As set out hereinabove, Defendant Nos. 2 to 8 have failed to justify their

unreasonable and unfair conduct. 26 out of 36 members have already vacated their

tenements about a year back and are residing in temporary transit accommodation

which they have obtained on leave and license basis. The members are facing grave

inconvenience and are waiting for the redevelopment work to start at the earliest and

completed to enable them to shift in their new ownership flats admeasuring 480 sq.ft.

carpet area in lieu of their present tenaments admeasuring only 180 sq.ft. Respondent

Nos. 2 to 8 have by refusing to vacate the premises, for reasons best known to them,

obstructed the entire redevelopment process and put the majority members in grave

difficulty and inconvenience. The condition of the building is also deteriorating.

Further in case of any collapse of the building or part thereof, grave loss would be

caused to the life and property of persons who are occupying the said building and

also to the individuals who are around the vicinity of the building. The balance of

convenience is entirely in favour of the Petitioner, the members of the Respondent

No. 1 and their family members. The Respondent Nos. 9 to 11, have kept their

premises vacant and locked since the last one decade and have not come forward to

KPPNair 30 arbp-681

answer the above Petition.

24. In view thereof, I pass the following order:

(i) The Court Receiver, High Court, Bombay, is appointed Receiver in respect of

the tenements presently occupied by Respondent Nos. 2 to 8. The

Respondent Nos. 2 to 8 shall, on or before 13th January, 2017 hand over quite,

vacant and peaceful possession of premises presently occupied by them to the

Court Receiver who shall in turn hand over the same to the Petitioner and/or

the first Respondent Society for redevelopment. In the event of Respondent

Nos. 2 to 8 not handing over possession of the tenements to the Court

Receiver as directed herein, the Court Receiver shall be at liberty to take

forcible possession of the premises occupied by Defendant Nos. 2 to 8 with

police assistance and hand over the same to the Petitioner and/or Respondent

No. 1 Society for redevelopment.

(ii) The Court Receiver, High Court, Bombay is also appointed Receiver in

respect of the tenements of Respondent Nos. 9 to 11. The Court Receiver shall

forthwith do the following :

(a) Open the flats in front of the Officials from the local Police Station as well

as the Chairman and Secretary of the Society and take an inventory of the

belongings lying therein. The Society shall make arrangements to store the

items found in the flats.

(b) The Court Receiver shall arrange to have the entire process of taking

KPPNair 31 arbp-681

inventory i.e. right since the breaking open of the locks of the said flats video

recorded.

(c) The Court Receiver shall thereafter handover the flats owned by

Respondent Nos. 9 to 11, to the Petitioner for redevelopment.

(iii) The Petitioner shall simultaneously, with Respondent Nos. 2 to 8 handing

over possession of their tenements and/or the Court Receiver forcibly taking

possession of the tenements, pay all amounts due till date to Respondent Nos.

2 to 8 as agreed and provided under the Development Agreement 15 th July,

2013.

(iv) The Respondent Nos. 2 to 8 shall also sign agreements with the Petitioner for

permanent alternate accommodation as per the agreed terms in the

Development Agreement dated 15th July, 2013 with a modification to the

extent of allotting permanent alternate accommodation to each of them

admeasuring 480 sq.ft. carpet area.

(v) Upon the construction being completed and the occupation certificate

obtained by the Petitioner, the Petitioner and/or the Society shall forthwith

hand over the new flats allotted to Respondent Nos. 2 to 8 to them and the

flats allotted to Defendant Nos. 9 to 11 to the Court Receiver or MHADA or

Respondent No. 1 Society.

KPPNair 32 arbp-681

The Arbitration Petition is accordingly allowed and the Notice of Motion in

Bombay City Civil Court L. C. Suit No. 2598 of 2015 is dismissed. However, there

shall be no order as to costs.

(S. J. KATHAWALLA, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter