Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ultratech Cement Ltd. Formerly ... vs Sunfield Resources Pvt. Ltd
2016 Latest Caselaw 7519 Bom

Citation : 2016 Latest Caselaw 7519 Bom
Judgement Date : 21 December, 2016

Bombay High Court
Ultratech Cement Ltd. Formerly ... vs Sunfield Resources Pvt. Ltd on 21 December, 2016
Bench: Anoop V. Mohta
    PVR                                    1                                                   app881-05.doc


                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                         ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                                  
                                     APPEAL NO. 881 OF 2005




                                                                          
                                                   IN
                          ARBITRATION PETITION NO. 35 OF 2004




                                                                         
    Ultratech Cement Ltd. (formerly Known as                               )




                                                     
    Larsen And Toubro Ltd.) an existing company                            )
    under the Companies Act,1956 having its 
                                    ig                                     )
    registered office at Ahura Centre, 'B' Wing,                           )
    2nd Floor, Mahakali Caves Road, Andheri (East)                         )
                                  
    Mumbai-400093.                                                         )        ...Appellant


            Versus
       
    



    Sunfield Resources Pty. Ltd.                                           )
    Suite No.1003, 370 Pitt Street,                                        )
    Sydney 2000 NSW, Australia.                                            )        ...Respondent






    Mr.Pradip   Sancheti,   Senior   Advocate   with   Dr.Birendra   Saraf,   Mr.Darshet  
    Jain,     Mr.Sachin   Chandarana,   Mr.Vijeyandra   Purohit   i/b.   Manilal   Kher  
    Ambalal & Co., for the Appellant.


    Mr.Sanat Mukharjee i/b. Mr.A.M.Vernekar, for the Respondent.




          ::: Uploaded on - 21/12/2016                                    ::: Downloaded on - 22/12/2016 01:07:43 :::
     PVR                                    2                                                   app881-05.doc


                                             ---
                                          CORAM :  ANOOP V. MOHTA & 
                                                   G.S. KULKARNI, JJ.
                                  Pronounced  on   :              21st DECEMBER,2016

                                                  ----
    Judgment (Per G.S.Kulkarni,J.):




                                                                         

1. This appeal under Section 37 of the Arbitration and

Conciliation Act,1996 (for short "the Arbitration Act") arises from the

judgment and order dated 30 June 2005 passed by the learned Single

Judge whereby the Appellant's petition under Section 34 of the Arbitration

Act, challenging the Award of the Sole Arbitrator dated 4 July 2003 has

been rejected. The learned Arbitrator allowed the claim made by the

Respondent (original claimant) and rejected the counterclaim of the

Appellant (original Respondent). Thus there are concurrent findings of

two forums against the Appellants.

2. The factual antecedents in which the controversy arises may

be illustrated by the following facts:-

The Respondent-claimant is a company incorporated in

Australia having its principal place of business in Sydney. At the material

time, it was represented in India through its representative M/s.Ensource

Energy (India) Private Limited (for short "ENSOURCE"). The business of

the Respondent was interalia of supplying non-coking coal. The Appellant

PVR 3 app881-05.doc

(formerly known as Larsen & Turbo Ltd.) had entered into contract dated

18 September 1999, with the Respondent, for bulk purchase of 'Steaming

non-coking coal', from the Respondent, which set out the terms and

conditions of the said transaction. The coal to be supplied by the

Respondent was of South African origin.

3. There is no dispute that under clause 4 of the contract the

cargo size was agreed and that the cargo was to be discharged at the

Appellant's jetty at Pipavav Port. The contract also provided for the

discharge of the cargo at Chennai Port as also the cargo size for discharge

at the said location. Clause 8 of the contract provided for "Timing" for

five items of firm cargo and option cargo to be separately indicated at a

later date. Clause 8 of the contract provided as follows:-

"8. Timing:

            FIRM CARGO NO.               LOADING AT LOAD                       DISCHARGE PORT
                                         PORT





            aa)                          AROUND 25th to                        L & T JETTY-
                                         30th                                  PIPAVAV
                                         September,1999
            bb)                          DECEMBER,1999                         CHENNAI PORT





            cc)                          FEBRUARY,2000                         L & T JETTY-
                                                                               PIPAVAV
            dd)                          APRIL,2000                            L & T JETTY-
                                                                               PIPAVAV
            ee)                          JULY,2000                             CHENNAI PORT
            ff) Option                   OPTION CARGO TO BE SEPARATELY 
            Cargo                        INDICATED AT A LATER DATE



4. Clause 10 of the contract provided for issuance of an arrival

PVR 4 app881-05.doc

notice at the discharge port, tendering of notice of readiness,

commencement of laytime at discharge port, discharge rate, payment of

demurrage/ despatch, etc. The dispute between the parties arose under

clause 10(v) relating to demurrage. It would be thus appropriate to

reproduce clause 10(v) of the contract which reads as under:-

"10(v) Demurrage/Despatch:

At the discharging port, buyers shall pay demurrage to the Seller or Vessel owners through sellers if required, at the rate not

exceeding US $ 8000.00 per day or pro-rata for part of the day and sellers shall pay despatch to buyers if earned, at a rate of 50% of

demurrage rate, not exceeding US $ 4000.0 per day or pro-rata for part of the day.

All demurrage or despatch to be settled within 60 days after laytime statement submitted with supporting documents, like Notices of Readiness, Statement of Facts and Time Sheets.

Any disagreement over the laytime statement must be raised

by the other party within 30 days after such statement is transmitted

and received, otherwise, the statement is accepted as correct."

(emphasis supplied)

5. It is not in dispute that under the contract and in compliance

with the schedule of shipment of cargoes incorporated in the contract, the

Respondent shipped to the Appellant from the Port of Richards Bay, South

Africa, five firm cargoes as under:-

Vessel Bill of Lading Quantity M/T Discharge Port No. & Date

mv"Dakshineshwar 1 39206 Pipavav " 10.10.1999 mv "Rishikesh" 1 37306 Chennai

PVR 5 app881-05.doc

22.12.1999 mv 1 39123 Pipavav "Dakshineshwar" 05.02.2000

mv"Pataliputpra" 3 & 4 13981 Pipavav 06.04.2000

mv"Pataliputpra" 1 36617 Chennai 11.05.2000

6. The cargoes were discharged from the vessels by the

stevedores appointed by the Appellant and the 'statement of facts' were

signed by the Master, the vessel's agents and the agents of the Appellant

who were the receivers. The Respondent's case is that in each of the

aforesaid shipments, the vessels went on demurrage. The Respondent

accordingly prepared laytime calculations based on the 'statement of facts'

and submitted the same to the Appellant alongwith the other documents

and commercial invoices for demurrage claims, for settlement. According

to the Respondent as per clause 10(v) of the contract (supra), the

demurrage payable by the Appellant to the Respondent in US dollars was

as under:-

                         Vessel                   Invoice Date                      Amount 
                                                                                     US $





            mv"Dakshineshwar"                     29.06.2000                    41027.78
            mv "Rishikesh"                        29.06.2000                    94684.72
            mv "Dakshineshwar"                    29.06.2000                    16678.48
            mv"Pataliputpra"                      14.07.2000                    01159.44
            mv"Pataliputpra"                      14.07.2000                    91787.50
                                                                               245337.92
                                                                               ======



Respondent's case was that as per clause 10(v) of the contract, the

PVR 6 app881-05.doc

demurrage claim was required to be settled within sixty days after

submission of laytime statement with supporting documents like Notices

of Readiness, Statement of Facts and Time Sheet. Further clause 10(v) of

the contract also provided, that any disagreement over laytime statement

must be raised by the other party within thirty days after such statement is

transmitted and received, otherwise, the statement would be accepted as

correct. The Respondent's case is that though invoices alongwith the

supporting documents were submitted by the Respondent to the

Appellant, there was no disagreement on the part of the Appellant and

thus as per Clause 10(v) the Appellant was under an obligation to settle

the demurrage within sixty days of the submission of the invoices, which it

failed to do. The correspondence between the parties in that regard being

crucial, the parties have interalia referred to the letters dated 30 October

2000, 1 November 2000, 2 November 2000 and 22 November 2000 of the

Respondents and letters dated 1 November 2000 and 9 November 2000 of

the Appellant.

7. The case of the Respondent was that, the Appellant despite

assurance of making payment, which intention could be clearly seen from

the said correspondence, in a sudden volte-face, by its letter dated 24

November 2000 invoked the arbitration clause as contained in the

contract, alleging that certain disputes have arisen between the parties,

without specifying, as to what was the dispute and sought appointment of

PVR 7 app881-05.doc

an Arbitrator by giving names of the retired Hon'ble Judges, who can

arbitrate the dispute, and called upon the Respondent to give its consent,

failing which the Appellant would be constrained to make an application

under the Section 11 of the Arbitration Act. On receipt of this letter of the

Appellant, the Respondent replied the same by its letter dated 29

November 2000 and sought a clarification, to state as to what were the

disputes according to the appellants, had arisen between the parties. The

Respondent recorded that they were unaware about any dispute except

for the fact that there was an outstanding payment of US$ 247411.15,

payable by the Appellant to the Respondent, on account of demurrage

incurred at the discharging port and that the Appellant had informed the

Respondent that they are in the process of arranging payment.

8. On this background Mr. Justice M.N.Chandurkar, Former

Chief Justice of the Bombay High Court, was appointed as the Sole

Arbitrator to arbitrate the dispute between the parties in regard to the

demurrage claim of the Respondent, against the Appellant. Respondent's

claim for demurrage was for a sum of US $ 2,45,337.92 being the

demurrage payable on the vessels hired by the Respondent under the

contract with the Appellant, as also an interest claim payable by the

Appellant at 8% per annum on each of the demurrage claims, from the

respective due dates till payment or realisation.

PVR 8 app881-05.doc

9. Before the learned Arbitrator, the Appellant resisted the

Respondent's claim by filing a reply to the statement of claim and disputed

its liability to pay any demurrage to the Respondent interalia on the

ground that under Clause 10(v) of the contract, demurrage was payable

to the vessel owner. The Appellant, thus asserted that the right of the

Respondent to claim demurrage was only in the form of an indemnity and

there was no evidence to show that the Respondent had made payment of

any demurrage to the vessel owner, and unless the Respondent establishes

and/or proves that it had paid demurrage to the vessel owner, the

Appellant was not liable to pay any demurrage.

10. On behalf of the Appellant a counter claim was made of an

amount of US$ 4,78,619.62 relating to a alleged loss suffered by the

Appellant stated on account of the breach of contract by the Respondent

in failing and neglecting to supply option cargo as per the terms and

conditions of the contract.

11. The Respondent contested the counter claim of the Appellant

by filing its reply. The Respondent raised an objection that the

counterclaim made in the said proceedings was not maintainable and

could not form the subject matter of the arbitration proceedings, for the

reason that the Appellant had never, prior to the notice dated 24

November 2000, nor in the said notice made any claim or raised any

PVR 9 app881-05.doc

dispute regarding the amount as claimed in the said counterclaim.

12. The learned Arbitrator on all the issues (claim, counterclaim)

permitted the parties to file their respective pleadings, as also permitted

amendment to the pleadings and further replies and rejoinder thereto and

to place on record of the proceedings, the respective documents of the

parties.

13.

On the basis of the pleadings, the learned sole Arbitrator

framed the following issues on the Respondent's 'statement of claim' and

the Appellant's counterclaim:-

"Statement of Claim

1. Whether clause (v) of the Contract is in the nature of indemnity as alleged in paragraph 2 of the reply and, if so, whether

the Claimant has suffered any loss or damage which is required to be indemnified.

2. Whether clause (v) of the Contract only provides for a ceiling

on the amount payable as demurrage and whether the Claimant is entitled to receive only such amount which is actually found payable and paid as alleged in paragraph 2A of the Reply.

3. Whether the Respondent is entitled to exemption of certain

periods in the calculations of demurrage as alleged in paragraph 2B of the reply.

4. Whether the vessels in question went on demurrage as alleged in paragraph 6(a) of the Statement of Claim.

5. Whether demurrage in the amount of US $ 245,337.92 was incurred as alleged in paragraph 6(b) of the Statement of Claim.

6. Whether the Claimant is entitled to a sum of US $ 245,337.92 as alleged in paragraph 10 of the Statement of Claim.

PVR 10 app881-05.doc

7. Whether the Claimant is entitled to interest at the rate of 8% p.a. on the aforesaid amount as alleged in paragraph 11 of the

Statement of Claim

Counterclaim

1. Whether the Respondent had exercised their option for option cargo in accordance with the requirements of the said contract.

2. Whether the Claimant is estopped from pleading that

confirmation of option cargo beyond 15 th February,2000 is not valid and/or whether there was a waiver of the said requirement as alleged in paragraph 3A of the Counterclaim.

3. Whether the Respondent is entitled to recover from the Claimant a sum of US $ 478,619.62 as alleged in paragraphs 4 and 5

of the Counterclaim ?

4. Whether the Respondent is entitled to interest at the rate of

18% p.a. on the said amount as alleged in paragraph 10 of the Counterclaim."

14. The parties examined their respective witnesses. The

Appellant examined Mr.R.Venkateshwaran (R.W.1) and

Mr.D.S.Patwardhan Vice president (Shipping) (R.W.2) as their witnesses

and were cross examined by the Respondent. The learned Arbitrator

considering the documentary and the oral evidence and the submissions

of the parties delivered a reasoned Award dated 4 June 2003. The

operative award is as under:-

"(1) The Claimant is entitled to recover from the Respondent and the Respondent is liable to pay to the Claimant an amount of US $ 2,45,337.92.

(2) The Claimant is entitled to interest at 5% per annum in US Dollars from 15th September,2000 till the date of the Award and thereafter till payment.

     PVR                                            11                                                   app881-05.doc


                      (3)      The Counterclaim made by the Respondent is rejected.
                      (4)      The   Claimant   will   be   entitled   to   costs   of   these   proceedings  




                                                                                                           

from the Respondent, which are computed at Rs.3,00,000.00 (Rupees three lacs only)."

15. It would be profitable to note some of the material findings in

the Award of the learned Arbitrator:-

(As regards Issue No.4:- Whether the vessels in question went

on dumurrage.)

"(i) There is no dispute that the Statements of Facts, on the basis

of which the Invoices and lay time calculations have been made, have all been signed by the representative of L & T. It is also not in dispute that

the lay time calculations in the case of each of the five vessels are made on the basis of the Statements of Facts. The Statements of Facts and the corresponding Invoices in respect of the vessels, m.v.Dakshineshwar

Voyage 1, Rishikesh, Dakshineshwar Voyage 2, Pataliputra Voyage 1 and

Patliputra Voyage 2 are at pages 35,40, 52, 32 and 60, respectively of the pleadings compilation, and the corresponding Invoices are at pages 36, 46, 55, 64 and 73, respectively. These Statements of Facts are admittedly

signed by the Master of the vessel, the vessels' Agent and "the agents of the receivers" i.e. the Respondent. In the Reply to the Statement of Claim, in paragraph 9, L & T has specifically admitted as correct the contents of

paragraph 5 of the Statement of Claim, in which one of the statements made was that "the Statements of Facts were signed by the Master, vessels' agents and agents of the receivers", namely, the Respondent.

(ii) When a person signs a document, he is taken to have agreed to the correctness of the statements made in the document and since the Agent of L & T has signed the Statements of Facts, the statements made

PVR 12 app881-05.doc

therein must be held to be binding on L & T. It must, therefore, be held that the vessels in question had gone on demurrage as alleged in

paragraph 6(a) of the Statement of Claim.

(As regards Issue No.3 - The Appellant's entitlement to exemption of certain periods in the calculations of demurrage.)

(iii) "The witness was, however, unable to give any explanation

for the delay caused in berthing of the vessel. Consideration of all the material evidence would, therefore, indicate that L & T has failed to

establish that the anticipated strike or the strike had resulted in any delay in berthing of the vessel m.v. Rishikesh on the ground alleged by it,

namely, that all the four berths were allotted to TNESB. Consequently, the claim made for exclusion of the period of 17 days as stated for the first

time in evidence of Venkiteshwaran cannot be accepted.

In view of the fact that the averments made in paragraph 2B of the Reply of L & T are not established, the further legal question as to

whether the Respondent was entitled to avail of the force majeure clause

does not really arise."

(As regards Issue Nos.1 & 2 - Whether Clause 10(v) of the Contract is in the nature of indemnity and whether the Respondent is entitled to receive only such amount which is actually found payable and paid as alleged in paragraph 2A of the Reply.)

(iv) The question as to the nature of the liability created by the first part of Clause 10(v) must necessarily be considered on a reading of the Clause as a whole. The first part of Clause 10(v) creates an absolute obligation against the buyer to pay demurrage to the seller or vessel owner through the seller if required at a rate not exceeding US$ 8000.00 per day. At the same time a provision was also made that the seller shall pay despatch to buyers if earned, at a rate of 50% of demurrage rate, not

PVR 13 app881-05.doc

exceeding US $ 4000.00 per day or pro-rata for part of the day. The manner of working out the claim for demurrage or despatch is set out in

the second paragraph of Clause 10(v), the effect of which, plainly, is that the amount to be paid by way of demurrage or despatch has to be settled

within 60 days after lay time statement is submitted with supporting documents, like notices of readiness, statement of facts and time sheets. There is not a whisper in Clause 10(v) of the contract that the liability to

pay demurrage is dependent upon demurrage being paid by the seller to the vessel owner. The contract in question is between the seller, namely

the Claimant, and the buyer, L & T. When the first paragraph of Clause 10(v) provides that the demurrage shall be paid "to the seller or vessel

owners through the sellers if required", it obviously contemplated that the party which requires demurrage to be paid to the vessel owner is the seller

through whom the demurrage is to be paid. There is no privity of contract between L & T and the vessel owner and the obligation to pay directly to the vessel owner any amount of demurrage would arise only if the buyer

is so directed by the seller.

(v) That L & T also understood Clause 10(v) as not providing for an indemnity is also clear from the evidence of witness Patwardhan.

Patwardhan was asked in cross-examination with regard to the payment already made by L & T. Patwardhan was the person who, on his own admission, was concerned with the decision to pay demurrage and such

demurrage had been paid earlier. He unambiguously stated, as already pointed out, that the claim for demurrage paid to Glencore International was on the basis of three documents, namely, (1) statement of facts given by Glencore, (2) verification thereof and, if necessary, correction thereto, and (3) charter party agreement. With reference to these statements, he stated "the above documents are generally documents which I considered while determining whether demurrage is to be paid or not". These

PVR 14 app881-05.doc

statements of Patwardhan and the fact that demurrage was decided to be paid by L & T earlier on the basis of the documents referred to above

clearly indicate that even L & T had never understood the clause relating to payment of demurrage as being in the nature of an indemnity.

Admittedly, the amount of demurrage claimed by the Claimant is at the rate which is payable by the Claimant to the ship owner under the contract of affreightment. It is also important to point out that the

agreement between the parties that the claim for demurrage/despatch should be settled within 60 days after lay time statement was submitted

with supporting documents also militates against the contention that the contract is one in the nature of an indemnity.

(vi) In my opinion, if a similar clause like Clause 10(v) has been

construed by a High Court in India, propriety demands that in so far as arbitration proceedings are concerned, that construction of the Clause should be accepted, particularly in view of the fact that the two Clauses,

namely, the Clause which fell for consideration before the High Court and

the Clause in the instant case are more or less similar. I am, therefore, inclined to reject the argument advanced on behalf of L & T that demurrage has necessarily to be construed in all cases as providing for

liquidated damages and having regard to the settled position of law that a claim for liquidated damages cannot be granted without proof of actual loss.

(vii) It is also important to point out that so far as the amount of demurrage is concerned, it was L & T's representative who insisted upon the figure of demurrage being intimated to it. L & T wrote to Ensource Energy (India) Pvt.Ltd., agent of the Claimant, on 16 th September,1999 in reply to a Fax message dated 15 th September,1999 relating to nomination of the vessel m.v.Dakshineshwar. This nomination was made by Ensource

PVR 15 app881-05.doc

Energy by Exhibit C-24 on 15th September,1999 and L & T was asked to send acceptance before noon of 16th September,1999. By Exhibit C-25

dated 16th September,1999, among the various items, information was sought by L & T from Ensource Energy with regard to

demurrage/despatch amount and item No.6 of this letter refers to "demurrage/despatch rate to be indicated". It was in pursuance of this letter that the demurrage rate of US $ 7,000 was intimated. On the facts

of the present case, therefore, it is clear that the figure of demurrage did not and was never intended to present an amount of liquidated damages.

Consequently, the argument of the learned Counsel for L & T that the claim for demurrage must be rejected as no loss has been proved has to be

rejected."

16. On this background the Appellant challenged the award by

filing a petition under Section 34 of the Act. The Appellant's contention

before the learned Single Judge interalia was that Clause 10(v) of the

contract was in the nature of an indemnity and thus there would be a

liability to pay demurrage only if the Respondent had actually made

payment of the same to the vessel owner. It was further contended that

payment of demurrage was required to be considered as providing for

liquidated damages, for which the Respondents were required to prove

actual loss, as a claim for demurrage is a claim arising from a breach of

contract namely detention of the vessel beyond the agreed period of time.

An amount agreed to be paid for such breach would be governed by the

provisions of Section 73 and 74 of the Indian Contract Act, and thus the

Respondent would become entitled to a reasonable compensation for loss

PVR 16 app881-05.doc

suffered except in a case where the Respondent could satisfy that it is not

possible to prove the quantum of damages. It was contended that the

award was thus contrary to the universally accepted concept of demurrage

being in the nature of damages. The Appellant on the basis of the force

majeure clause defended the demurrage claim in respect of one of the

vessel m.v.Rishikesh on the ground that there was a strike at Chennai Port

from 6 a.m. on 18 January 2000 to 6 a.m. on 25 January 2000 as the said

vessel had berthed on 24 January 2000, was not in dispute.

17. The learned Single Judge repelled the contentions as urged

on behalf of the Appellant and rejected the Section 34 Petition of the

Appellant. The Appellant thus being aggrieved by the judgment of the

learned Single has preferred this Appeal under Section 37 of the Act.

Appellants Submissions

18. Learned Senior Counsel for the Appellant in assailing the

impugned order has made the following submissions:-

(i) The claim for demurrage is in the nature of liquidated damages. It is

submitted that the learned Arbitrator had committed an error in holding

that the demurrage did not represent liquidated damages but was in the

nature of a fixed charge. It is submitted that it is a universally accepted

concept that the demurrage is in the nature of liquidated damages which

is well recognized in the private international law. He supports this

PVR 17 app881-05.doc

submission by relying on the views , of the well-known authors namely

(a) John Schofield "Laytime & Demurrage", 3 rd Edition; (b) Payne and

Ivany's "Carriage of Goods by Sea", 12 th Edition; (c) McGregor on

Damages, 18th Edition. Reliance is also placed on the decisions in the

case of (i) President of India Vs. Lips Meritime Corporation1, (ii)

Nanhoomal Jyoti Prasad Vs. Commissioner of Income Tax 2 (iii)

Hindustan Fertilizer Corporation Vs. C.V.Jani & Co.3, (iv) Adithyaa,

rep. By Prop. N.Santhanam Vs. Food Corporation of India4, (v)

Narmada Cement Company Vs. Chowgule Steamship5.

(ii) It is next submitted that proof of damages was necessary as

the claim for damages is a claim arising in the event of breach of the

contract namely detention of the vessel beyond the agreed period of time.

It is submitted that as such, any amount agreed to be paid under the

contract for such a breach (whether such sum specified by way of

liquidated damages or an upper limit fixed) would be governed by the

provisions of Section 73 and 74 of the Indian Contract Act. It is submitted

that the Respondent being a seller, if had suffered any damages, the

Respondent could have easily proved the same by producing the claim or

on demand made by Glencore-the owners of the vessels and any payment

made thereunder. In support of this submission, reliance is placed on the 1 (1987)2 Lloyd's Law Reports 311(H.L) 2 123 ITR 269 (All) 3 2010 SCC Online Del 54 4 2014(1) MWN (Civil) 13 5 Judgment dt. 30.4.2003 in Arbitration Petition no.107 of 2003 by Bombay High Court

PVR 18 app881-05.doc

observations of the Supreme Court in paragraph 50 in the case of "Oil

and Natural Gas Corporation Ltd. Vs. SAW Pipes Ltd."6 . Then reliance

is placed on the observations of the Supreme Court in paragraph 43 of the

decision in the case "Kailash Nath Associates Vs. DDA"7.

(iii) It is next contended that the Respondent has not suffered any

loss. Admittedly the Respondent-seller was not the vessel owner and the

goods were shipped in a third party vessel under the Contract of

Affreighment (COA). Therefore, between two alternatives in clause 10(v)

of the contract, the relevant portion of the clause applicable is the portion

relating to payment of demurrage to the vessel owner. It is submitted that

the quantum of damage would be exclusively within the knowledge of the

Respondent and in order to claim the same from the Appellant, the

burden of proof under Section 106 of the Indian Evidence Act was heavily

on the Respondent to prove such loss/damage. It is submitted that thus it

is apparent that the Respondent has not incurred any loss or as such the

question of award of any damage did not arise. It is submitted that the

contention of the Respondent that it is difficult / impossible to prove

extent of damage suffered by him relying on the passage from 18th

Edition of McGregor on Damage is misconceived. It is submitted that the

following extract in the 18th Edition of McGregor on Damages in fact

supports the Appellant's contention that the demurrage is in the nature of

6 AIR 2003 SC 2629 7 (2015) 4 SCC 135

PVR 19 app881-05.doc

damages:-

"27-075. ....... the normal measure of such damages will be

constituted by the amount lost through loss of use of the ship. For this, one illustration - they are quite numerous - is provided by

Gatoil Anstlat V. Omenial, The Balder London (No.2) where the owners of a ship, wrongfully prevented by the charterers from withdrawing her from a charter, were awarded as damages the

difference between the charter rate and the market rate of hire for the period in question."

The submission is that the above extract deals with the scenario where the

shipowner is itself claiming demurrage which is distinct from the present

case where the Respondent is not the owner and has chartered another's

Vessel. In this situation, the Respondent could have proved damage

suffered by it by merely producing the amounts or demurrage paid by it to

the vessel owner. The above extract of 'McGregor on Damages' gives only

one of the illustrations of the manner in which the damage can be proved

and would not be applicable in the present case where the Respondent has

chartered the vessel of the vessel owner.

(iv) The next submission is that the Respondent cannot profiteer

or make windfall out of claim for damages. It is submitted that very word

"damages" is meant that the party suffering due to breach of contract is

compensated for the loss suffered by it. This submission is stated to be

supported by relying on paragraph 44 of the judgment of the Supreme

PVR 20 app881-05.doc

Court in the case "Kailash Nath Associates" (supra)

(v) It is next submitted that in any case under Clause 10(v) of the

contract the obligation of the Appellant to pay demurrage relates to the

demurrage payable by the Respondent-seller to the vessel-owner, as the

said clause of the contract specifically recognizes payment of demurrage

to the vessel owner, as the clause provides that "Buyer shall pay demurrage

to the seller or vessel-owner through the seller, if required". The clause is

required to be interpreted in such a manner that the word "if required"

are not rendered otiose. The use of words "if required" indicate that in a

case where the seller transports the goods by a ship belonging to a third

party (vessel owner), the demurrage, would be payable to the vessel

owner and, therefore, the words "if required" relate to the liability, if any,

of payment of demurrage to the vessel owner. In contrast, if the seller

himself is the vessel owner, then obviously, the demurrage is payable to

the seller as he would suffer loss by reason of vessel being detained

beyond the agreed period of time.

(vi) As regards the counterclaim as made by the Appellant, the

contention before the learned Arbitrator was the quantity of coal to be

supplied was set out in clause 4 of the agreement. In addition to the five

shipments agreed to be supplied, there was an option cargo (sixth

shipment), which was to be confirmed by communication of likely

shipment schedule confirming the same. That the Appellant confirmed

PVR 21 app881-05.doc

the option cargo. The correspondence would thus indicate that the

Appellant had exercised the option and opted for the option cargo.

However, the Respondent failed and neglected to deliver the same. A

letter dated 20 January 2000 of the Appellant cannot and does not in any

way derogate from the above opposition. Thus, learned Arbitrator

committed a patent error in not considering the undisputed position

emerging from the admitted documents.

Respondents Submissions

19. On the other hand, the learned Senior Counsel appearing for

Respondent submits that the present appeal raises the following four

broad matters:-

(i) The Appellant's original challenge (based on indemnity) to the

Respondent's claim for demurrage;

(ii) The Appellant's subsequent challenge (based on liquidated damages

and invoking Section 74 of the Indian Contract Act) to the Respondent's

claim for demurrage;

(iii) The Appellant's challenge (based on the strike at Chennai Port)

restricted to Respondent's claim for demurrage on the vessel m.v.Rishikesh

only; and

(iv) The Appellant's challenge to the dismissal of its counterclaim.

20. It is submitted that the Appellant in its submissions has not

PVR 22 app881-05.doc

touched item (i) above and the Appellant barely touched item (iii) and

(iv). It is submitted that the main thrust of the Appellant's argument was

devoted for seeking to show that demurrage is liquidated damages and

thus not allowable under Indian Law without proof of actual damage. It is

submitted that the essential matters in items (iii) and (iv) above were

clearly factual as item (iii) turned on whether or not the strike at Chennai

Port had in fact caused delay to the unloading of the vessel Rishikesh.

That item (iv) turned on whether the Appellant had exercised its option to

call for an additional shipment before the contractual due date for

exercising the option or, alternatively, whether notwithstanding failure to

exercise the option in due time, the parties had nevertheless, by mutual

consent, agreed on such additional shipment. It is submitted that the

Appellant did not make any attempt to rebut the extensive and detailed

reasons put forward by the learned Arbitrator in arriving at his decision

on both these issues and therefore, the Respondent did not deal with these

issues in making their submissions.

21. The learned Counsel for the Respondent in support of the

Respondent's case has drawn our attention to the correspondence ensued

between the parties in regard to the demurrage claim made by the

Respondent. It is submitted that the Appellant in fact never denied the

claim and the letters of the Appellant clearly go to show that there was no

denial to make payment and in fact the Respondents were assured for

PVR 23 app881-05.doc

payment towards demurrage. It is submitted that the Appellant never

disputed the statement of facts on the calculation of demurrage on each of

the shipment for which a specific maximum limit was provided in the

contract itself. On the basis of the correspondence, the Respondent

submits that at no time prior to its letter of 24 November 2000 demanding

Arbitration did the Appellant find anything in the laytime calculations to

dispute and that the Appellant never lacked any documents to carry out

its own check. It is submitted that that the Appellant's story that it lacked

any documentation is contradicted by its own letter of the 1 November

2000 that attributed the delay on its part to "certain organisation

changes". It is submitted that when on 9 November 2000 it sought to

provide some excuse for delay, all it could come out with was "certain

difficulties in documentation as per the requirement of Indian law for

remittance in foreign exchange". It is submitted that even the Contract of

Affreightment (COA) was supplied by the Respondent to the Appellant

after the Appellant complained that it was having difficulty with remitting

the demurrage in foreign exchange. It is submitted that the statement

made by the Appellant, in its letter of reference to Arbitration dated 24

November 2000, that the reference was made because there were "certain

disputes" between the parties was palpably false as no disputes existed

and the Appellant's further allegation in the said letter of reference that

attempts were made to settle the disputes amicably and these had failed,

was also palpably false, and this was so, because this false averment was

PVR 24 app881-05.doc

necessary in order to comply with the Arbitration Clause 25 in the

Contract (at Vol. VII at page 19) which required that a reference was to be

made only in the event of failure to settle the dispute amicably. It is

further submitted that this documentary evidence is to be coupled with

the conclusive admissions made by Mr.Patwardhan (Appellant's Vice

President in charge of shipping), in the course of his cross-examination.

When making its counterclaim, the Appellant stated that it had itself

entered into a separate contract of purchase of coal from Messrs Glencore

International AG (Vol VII page 167). It is submitted that the contract was,

as usual, on the Appellant's same standard contract form as in the present

case. It is submitted that the witness was specifically asked in the cross

examination (Vol IV at page 773 paragraph 39) as to what were the

documents on the basis of which he had allowed payment of demurrage

to Glencore International under that contract, to which he answered that

the documents were : Statement of Facts, verification thereof and

necessary corrections, and the Charter Party agreement. The witness

stated that "the above documents are generally documents which I consider

while determining whether demurrage is to be paid or not". It is further

submitted that paragraph 22 of the cross examination is to the same

effect. It is submitted that at paragraph 39 of his cross examination (Vol IV

at page 773) when confronted with the Appellant's letter dated 2

November 2000 (Vol VII page 260), the said witness stated that whatever

verification was to be done of the Respondent's demurrage claim, was

PVR 25 app881-05.doc

completed by the end of the year 2000 leaving only some disputed

amounts. It is submitted that the witness added as follows:- "It is correct

that by end of the year 2000 all documents necessary for verification were

available to us."

22. On the basis of the above, the Respondent would submit that

the following consequences are incontrovertible:-

(i) Not only did Clause 10(v) of the Contract, when it listed out

the documents on the basis of which demurrage would be payable, it also

makes no mention of proof of actual payment of demurrage;

(ii) At no stage in the correspondence that went on for months

after the last shipment was over did the Appellant call for proof of actual

payment;

(iii) That the Appellant in fact assured the Respondent that it

would be remitting the demurrage and that delay was (first version) on

account of organization changes or (second version) on account of

difficulty of remittance in foreign exchange;

(iv) That the Appellant's own Vice-President in charge of releasing

demurrage payments, Mr.Patwardhan, did not, even in other cases, call for

proof of actual payment before releasing payment of demurrage to its

sellers;

(v) That on Mr.Patwardhan's own admission, the Appellant was

able to and in fact did complete its verification of Respondent's demurrage

PVR 26 app881-05.doc

claim by end of the year 2000 (leaving only some disputed items) and

needed no further documents for that verification.

23. The Respondent would thus submit that the case as urged in

the appeal on behalf of the Appellant, whether grounded on indemnity or

on liquidated damages, flies in the face of express terms of the contract

and thus palpably contrary to the Appellant's own well established

commercial practice. It is submitted that significantly the said stand as

now being urged solemnly in the appeal are nothing but a cynical ploy to

avoid payment of a liability that the Appellant never at the relevant time

considered disputable.

24. The Respondent would urge that in any event whatever be

the Appellant's motive, the fact remains that the objection to demurrage

was to be taken more than thirty days from the dates on which the

laytime statements in each of the claim was submitted and received. It is

thus submitted that it must follow that by reason of clause 10(v) of the

Contract, the Appellant must be taken as having accepted that the

demurrage claim is correct and for this reason alone the Respondent's

claim should stand to be adjudged in its favour.

25. It is submitted that the original defence of the Appellant was

that the demurrage was in the nature of an indemnity and thus was not

PVR 27 app881-05.doc

payable without proof of actual payment by Respondent to the ship owner.

It is submitted that in fact this case is only lightly touched in the course of

arguments.

In this context it is submitted that the question of whether or

not in general law demurrage is based on indemnity or is a stand-alone

and independent provision was considered by the U.K. Court of Appeal in

the case of "FAL Oil Co.Ltd Vs. Petronas Trading Corporation"8 It is

submitted that the Appellant has not sought to argue that the law

expressed in "FAL Oil Co.Ltd" (supra) is not the same in India. It is

submitted that in the present case there is no cross reference of any kind

to the Contract of Affreightment (COA). On the contrary, the detailed

provisions as to the calculation of laytime and of demurrage contained in

Clause 10 clearly show that demurrage is an independent liability, for if

the liability was only a transferred liability of demurrage arising under the

Contract of Affreightment, all these provisions would be otiose. It is

submitted that the demurrage would be only that liability that had arisen

under the Contract of Affreightment, and only relevant provisions for

calculating laytime would be those found in the Contract of Affreightment

and not in the Sale Contract. That would mean giving a go-by to the

specific terms of the present contract.

26. As regards the contention of the Appellant's founded on the

8 (2004)2 Lloyds Rep.282=(2004) EWCA Civ 822

PVR 28 app881-05.doc

words in Clause 10(v) that "buyers shall pay demurrage to the seller or

vessel owners through sellers if required", the Respondent would urge

that these words do not avail to the benefit of the Appellant at all. It is

submitted that the learned Arbitrator dismissed the arguments while

holding that all that it means is that if the seller so requires, the buyer will

pay demurrage to the shipowner through the seller. For the reason that

there is no privity of contract between the buyer and the shipowner and

payment to the shipowner is only dependent on whether the seller so

directs it. The Respondent would submits that this is the natural and

plain reading of the clause and no reason is suggested to show that it is

wrong. It is submitted that on the contrary, a detailed laytime provisions

in Clause 10 and the fact that, out of the documents specified in Clause

10(v) to be submitted in proof of the demurrage claim, none relate to

proof of actual payment to the shipowner, clearly establish that demurrage

was intended as an independent and stand-alone liability.

27. The Respondent contends that the Appellant's second line of

defence is namely "demurrage is in the nature of liquidated damages"

cannot be accepted. It is submitted that the Respondent has preliminary

objection on this for the reason that this defence was never pleaded in the

Appellant's reply before the learned Arbitrator. It is submitted that it was

advanced for the first time by the Appellant's Counsel before the learned

Arbitrator only at the final stage of arguments, after the evidence of both

PVR 29 app881-05.doc

sides had been closed and Respondent's Counsel had completed his

arguments. It is submitted that this is clear from the issues framed by the

parties and adopted by the learned Arbitrator and it is confirmed that

until final stage of hearing the issue of "liquidated damages" was never

even in contemplation. It is further submitted that in the written

submissions before the learned Arbitrator, the Respondent had specifically

objected to and challenged the Appellant's right to take this defence. It is

submitted that however without considering this argument, the learned

Arbitrator proceeded to consider this point and however rejected it. The

Respondent would thus submit that the Respondent's preliminary

objection being not considered in the Award, does not prevent the

Respondent in this Appeal from defending the Award even on a point

taken (sub silentio) against it. It is submitted that such a course would be

entirely permissible in a civil appeal and it would be extraordinary if it

were not available in a petition under Section 34 of the Act. The

Respondent would submit that the argument on liquidated damages is not

a simple legal argument, for its determination also requires investigation

into the facts of which two are more significant. Firstly, was the

demurrage provision a genuine pre-estimate of damages and would, in its

absence, calculation of damages be a difficult task. The Respondent relies

on paragraph 2A of the Appellant's reply before the learned Arbitrator to

contend that the Appellant never put the Respondent to a notice that the

Appellant would be challenging the demurrage claim on the ground that it

PVR 30 app881-05.doc

amounts to liquidated damages. It is submitted that the submission on

pleadings, as made by the Appellant herein can be employed in the

manner now sought by the Appellant, then, pleadings will become a death

trap.

28. As regards the Appellant's submissions that the demurrage is

liquidated damages under the Indian Law, it is submitted that there is

conceptual difference between the compensatory debt/charge and

damages. It is submitted that two parts of a contract are the primary terms

and the secondary terms. The obligations that parties are required to

perform in the course of the execution of the contract such as payment of

price (in a sales contract), Freight (in a transportation contract), fees (in a

service contract) etc. are the primary terms of the contract. The

secondary terms, on the other hand, deal with obligations when the

contract has been broken, such as clauses regulating damages payable for

the breach, clauses providing for termination for the breach, arbitration

clauses etc. The monetary obligations falling in the Primary category are

in the nature of debt or charge. Monetary obligations falling in the

secondary category are in the nature of damages. When dealing with the

situation where one party has been unable to perform a primary

obligation fully, commercial contracts do not invariably treat it as a breach

of contract, for doing so would usually cause disruption of the working of

the contract. What is often done is to introduce a degree of flexibility into

PVR 31 app881-05.doc

the term imposing the primary obligation by providing for compensation

to the other party when the contract has been imperfectly performed.

Though liquidated damages provisions are part of the secondary terms of

the contract, the distinction between them and compensatory charge

provisions which fall among the primary terms, is of little practical

significance in jurisdictions where liquidated damages do not require

proof of actual loss. Both impose a liability for liquidated sums, and

neither of them require proof of actual loss.

29. It is submitted that if one looks at the contract in the present

case, the clear impression would be that the demurrage provision in

clause 10(v) is in the nature of compensatory charge. Nowhere does the

clause characterise the failure to discharge within the laytime as a breach

of the contract. It merely contents itself by saying that demurrage shall be

payable at a particular rate. Furthermore, the coupling of the demurrage

with the despatch (which is obviously not in the nature of damages) again

points to demurrage being no more than an adjustment provision, in the

same way that clause 12 is an adjustment provision to the "Total moisture'

term in clause 5.

30. The Respondent would then submit on the issue 'as to what

does Indian Law lay down on the nature of demurrage?' Referring to

clause 25 of the contract which reads that "The contract will be governed

PVR 32 app881-05.doc

and construed in accordance with Indian Law.", the Respondent would

submit that the issue thus revolves itself into whether or not demurrage,

in Indian Law, is liquidated damages or a compensatory charge or debt. It

is submitted that the contract does not state that the demurrage payable

under clause 10(v) is in the nature of liquidated damages and that no

Indian statute lays down such a proposition. It is submitted that the other

source of law consists of the decisions of Indian Courts, referring to the

decisions in (i)Hindustan Paper Corp. Vs. Wellbrines Chemicals P.Ltd. 9;

(ii)Nanhoomal Jyoti Prasad Vs. Commissioner of Income Tax (supra);

(iii)M/s.Raichand A. Shah vs. Union of India 10; (iv) Narmada Cement

Company Vs. Chowgule Steamship (supra); (v) Adithyaavs Vs. Food

Corporation of India (supra); (vi) Hindustan Fertilizer Corporation Vs.

C.V.Jani & Co (supra). Relying on these decisions, it is submitted that

there is no Indian Judicial Authority binding on this Court which deals

with the nature of demurrage, whether as liquidated damages or fixed

charge. In the absence of any binding pronouncement of Indian Courts on

whether or not demurrage partakes of the nature of liquidated damages or

of the nature of a debt, the Appellant has turned to judgments of the UK

Courts and the UK textbooks to establish what the India Law on the

subject is. These authorities of UK courts are only persuasive. As

authorities, statements in textbooks stand on a lower footing than Court

judgments. It is submitted that in assessing what law is right for India or 9 (2002)3 Cal LT 114 10 AIR 1964 SC 1268

PVR 33 app881-05.doc

Indian Court has but one guide and that is what would be the public

policy of India referring to the decision In "ONGC Vs. Saw Pipes" (supra)

and its discussion on the "Public Policy of India' as contained in paragraph

31.

31. The Respondent on the above backdrop submits that the

demurrage claims arise in the hundreds, day in and day out, whenever

ships take more time to load or discharge than contemplated by the

shipping contracts. Common business sense requires that they be dealt

between the parties expeditiously and without recourse to lengthy

procedures for proving actual damages. One does not have to go far for

proof of this. It is thus submitted that clause 10(v) of the present

contract which is in the Appellant's own standard form contract, clearly

depicts this position. The list of documents to be looked at is very limited.

The period of time within which the demurrage is to be settled is limited

to 60 days. The time given for submission of disagreement is only 30 days

from the date of receipt of the laytime statement. Most importantly of all

the Appellants own Vice President in charge of shipping has testified to

the extremely limited nature of the scope of inquiry that he conducts

before releasing demurrage payments to sellers.

32. The Respondent would then submit that it is required to be

borne in mind that proof of actual loss in international sales contracts

PVR 34 app881-05.doc

such as the present, where the seller has to engage a ship to carry the

cargo for delivery to the buyer cannot end merely by showing that the

seller has paid demurrage to the vessel-owner under his contract of

Affreightment (COA) or Charterparty. It is thus submitted that if the

Appellant is right in its assertion that demurrage requires proof of actual

loss, then a seller would have to lead evidence to show not only that he

has paid demurrage to the vessel-owner but he must further lead evidence

to prove whether and to what extent the vessel-owner had suffered

"actual loss" by detention of his vessel and where, as in the present case,

the person (Glencore International) from whom the seller has engaged the

vessel is not itself the vessel-owner but has chartered the vessels in

question from the actual vessel-owner (vessels belonging to Shipping

Corporation of India), the difficulty is even worse confounded. The seller

would then require to prove (i) not only its charterparty with its disponent

owner but also (ii) the charter party of its disponent owner with the

actual vessel-owner; (iii) the factum of his own payment; (iv) the factum

of payment by the disponent owner, and finally (v) proof of actual loss

(namely list of freight earnings) suffered by the actual vessel-owner. The

Respondent submits that in this context in the Appellant's written

submissions before the learned Arbitrator ( Volume V paragraph 2.5, page

917 to 919) the Appellant itself has contended that not only had Sunfield

to prove the actual amount paid and payable to Glencore but also the

actual amount paid and payable by Glencore to the vessel-owner. The

PVR 35 app881-05.doc

Respondent submits that the Appellant would be perfectly right if the

provisions of Section 74 of the India Contract Act are held to be applicable

to demurrage under a Sales contract and in that event every time the

seller claims demurrage, he will have to lead evidence not only of

shipping contract and payment, but his disponent owner's contract with

the vessel-owner and payment of demurrage to the vessel-owner under

the contract, for which evidence will have to be led about the loss suffered

by the vessel-owner himself by reason of his ship being detained. It is

submitted that none of these extraordinary difficulties arise under English

law wherein it is well established that in a case of liquidated damages, the

claimant need not have to prove actual loss.

33. The Respondent would then submit that it is very well for the

Appellant to argue that Indian Law must follow English Law, presumably

because everyone knows English Law, but the view that English law has

taken on demurrage is the product of the English Courts' anxiety to

implement the intention of the parties. It is submitted that nothing

describes this linkage, in the matter of demurrage, between English Law

and the public purpose that underlies that law than the following passage

from McGregor on 'Damages'(18th Edition (page 493):-

"(a) Sum held to be liquidated damages. The courts implement the intention of the parties in the case of liquidated damages by holding the claimant entitled to

PVR 36 app881-05.doc

recover the stipulated sum on breach, without requiring proof of the actual damages and irrespective of the

amount, if provable, of the actual damage."

Thus, in view of the above it is, submitted that in England the

classification of demurrage as liquidated damages fulfills and implements

the intention of the parties because under English Law the recovery of

liquidated damages does not require proof of actual damages.

34.

It is thus submitted that both the present contract and the

behaviour of commercial men (as exemplified by the Appellant's own Vice

President in charge of shipping) clearly bring out the Indian companies

and shipping people share which they must, the same anxiety as English

businessmen and shipping people to settle demurrage without recourse to

long drawn out proof of actual damages. It is submitted that it is

therefore imperative for the Court to have a legal policy which is

acceptable to the commercial practices which internationally prevail,

failing which it would be detrimental to the international business

interest.

35. The Respondent would then submit that the Appellant's case

that when Indian contracts incorporate demurrage terms, the parties have

in mind the special legal concepts of demurrage found in English

PVR 37 app881-05.doc

Judgments and English textbooks and thus Indian contracts must be

interpreted accordingly. The Respondent submits that Ensource's answer

would be "Nothing can be further from the truth. An Indian businessman

signing sales contracts is not animated by thoughts of "Aktieselskabet

Reidar V. Arcos Limited, (1926)2 KB 83" as relied upon by the Appellant".

It is submitted that but by the conception that he derives from and shares

with businessmen around the world, that demurrage claims are and

should be settled expeditiously ('60 days' in the present contract) on the

basis of Statement of Facts, Notice of Readiness and Time Sheets.

36. It is submitted that the argument of the Appellant to "allow"

demurrage to escape the rigours of Section 74 of the Indian Contract Act

will open floodgates, and every claimant whose claim would fall under

that section would escape it. It is submitted that the short answer is " if

(i) a claimant can show that his contract not only does neither describe

nor treat the payment in question as liquidated damages but treats it as a

compensatory charge; and (ii) that the charge is one that in the very

nature of things and by the necessities of international commerce calls out

for expeditious resolution; and (iii) that the only reason advanced as to

why it should be treated as liquidated damages is that, it is the law of a

foreign land with discrepant legal provisions, then why should his claim

not be treated as falling outside Section 74 ? What reasons compels the

application of Section 74 to such a claim? The above three conditions

PVR 38 app881-05.doc

open not a floodgate, but a rational door founded on sound policy and

justice.

37. It is thus submitted on behalf of the Respondents that the

Appellant submissions that this Court should treat demurrage as

liquidated damages, should be rejected. This is for the reason that

nothing in the contract, nothing in Indian law, nothing but undue

deference to UK cases stands in the way. It is submitted that once this

course is adopted, the Court will be seen to "implement the intention of

the parties" to quote the words of McGregor.

38. The Respondent has made an alternative submission that

even if demurrage be treated as liquidated damages, actual loss is difficult

to prove. The Respondent makes this submission on the footing that the

English law of demurrage as liquidated damages applies to India. It is

submitted that the recent authoritative exposition on the intent and scope

of Section 74 of the Indian Contract Act, is in the decision of the Supreme

Court in the case of "Kailash Nath Associates Vs. DDA, "(supra) and

commenting on the observations of the Supreme Court in its decision in

paragraphs 43.1 to 43.6 the Respondent submits that for a claim for

liquidated amount fixed by contract to be allowable without proof of

actual loss, two requirements need to be satisfied: firstly it must be shown

that the amount fixed is not in the nature of penalty but is a genuine pre-

PVR 39 app881-05.doc

estimate of damages (paragraph 43.1) and secondly, that actual loss be

difficult or impossible to prove (paragraph 43.6). As regards the first

requirement, it is submitted that law makes a distinction between two

kinds of damages fixed by contract-Liquidated Damages and Penalty, the

first being a genuine pre-estaimate of damages and the latter being a sum

named in terrorem. It is submitted that the demurrage whether is a

liquidated damage, should not be a question in these proceedings. In

making this submission the Respondent referred to the written

submissions of the Appellant before the Arbitral Tribunal wherein the

Appellant has stated to have admitted (Vol. V. page 912 para 2.2) that at

no point in his oral submissions before the Tribunal, the Appellant's

Counsel questioned this position. It is submitted that in fact the learned

Counsel for the Appellant repeatedly put his case on the footing that

demurrage in this case constituted liquidated damages. It is submitted

that the second requirement namely that proof of actual loss would be

difficult to establish. It is submitted that it was the case of the Appellant

before the learned Arbitrator that in a case of demurrage payable under a

sales contract such as the present, proof of actual loss would inevitably

require, proof not only of payment by the seller of demurrage to its

disponent owner but also of the payment and payability of demurrage by

the disponent owner to the vessel-owner. That would require proof that

the vessel-owner himself suffered loss as a consequence of the detention

of his vessel and the quantum of that loss, and that loss is to be quantified

PVR 40 app881-05.doc

on the basis of the "amount lost by the use of the vessel" over the period

of vessel's detention. A reference is made to McGregor on damages page

1040 (para 27-075) where, in discussing the normal measure of

unliquidated damages for detention of a vessel, the learned Author states

that "The normal measure for such damages will be constituted by the

amount lost through loss of use of the ship."

39. It is then submitted that the market freight rate that the ship

can earn is of course vitally dependent on a variety of factors namely on

the size of the ship, her age, the kind of cargo she is capable of carrying,

the cargo-loading equipment she has on board, the length of the intended

voyage, whether the voyage in contemplation is to be a coastal voyage or

a foreign-going voyage, etc. It is submitted that moreover the market

rates are regularly changing in response to market forces. It is stated that

apart from these serious difficulties in proving the market freight rate, one

basic difficulty would be : how could one even ascertain the the market

rate for voyages for as short a period as the periods of detention involved

in this case which are

"Dakshineshwar 5 days 2 hrs Rishikesh 11 days 19 hrs Pataliputra 11 days 11 hrs Dakshineswar 2 days 2 hrs Pataliputra 3 hrs."

PVR 41 app881-05.doc

It is the Respondent's question as to who would taking a vessel for such

short periods? Even for Rishikesh and Pataliputra the very period for

loading and discharging any cargo would take longer than the demurrage

days, leaving aside the time necessary in completing the voyage. It is

further submitted that even proving the going market freight rate is very

difficult. Unlike the markets for oil or steel, there are no published rates

for voyage fixtures. The only way to prove the going freight rate would be

to call an expert witness (a broker) to give evidence of the rates he had

managed to fix in or around that same period. Only sheer coincidence

would ensure that on the relevant dates he had managed to broker a deal

for that length of days, and for that class of ship and that port of loading.

All of this goes to show that proof of actual loss may not be completely

impossible, but it would be difficult in the extreme and how much more

so when it is not the vessel-owner who is proving his lost market earnings

but a seller whose connection to the vessel-owner is separated by one or

more intermediate charterers. There is no good reason why a vessel-owner

should lend his aid in proving loss of his earnings to aid a seller with

whom he does not have a contract. It is submitted that paragraph 68 of

the Judgment in "ONGC Vs. Saw Pipes"(supra) the Supreme Court has

given examples of cases where it would be difficult to prove actual loss. It

is thus submitted that the Appellant has not been able to adduce even

more detailed proof of the difficulties in proving actual loss. And that the

Appellant by failing to plead the liquidated damages point, has only itself

PVR 42 app881-05.doc

to blame. It is submitted that in any event, even on the basis of the plain

facts inherent in the hiring of ships, it is clear that proof of actual loss for

a vessel-owner (and many times more for a seller) would be difficult in

the extreme. This is just such a case that the Supreme Court had in

contemplation when it opened the door in Section 74 to claim

compensation without proof of actual loss.

40. The Respondent would then contend that in this case the

Appellant's case is rooted in malafides from the very outset. It is submitted

that the objection to the Appellant's demurrage claim was never disputed

at any time before the filing by the Appellant's of its reply in the

Arbitration. Not only that, the Appellant had repeatedly assured the

Respondent that its claims were being paid. It is submitted that during

the arbitration itself, the Appellant advanced arguments one after other to

cover the deficiencies of each succeeding argument inasmuch as firstly an

indemnity defence it had never hinted at before; secondly next by

amendment to its reply advancing an argument suggesting that the actual

demurrage rate was never agreed to and only a maximum provided, and

then, when that was seen to have no substance, by argument on

liquidated damages advanced at the final stage of oral arguments. It is

submitted that at the hearing of this appeal, the learned Counsel for the

appellant virtually abandoned the Appellant's original defence founded on

indemnity and non-fixation of the demurrage rate. It is submitted that

PVR 43 app881-05.doc

also virtually abandoned in this appeal was Appellant's counter claim. It

is thus submitted that the findings of the learned Arbitrator on the

falsehoods on which that counterclaim was based and then incorporated

in the evidence of Mr.Venkiteshwaran exposes the utter lack of common

honesty that characterised Appellant's conduct in the arbitration

proceedings.

41. It is finally submitted that the Appellant's attempt to thrust

English Judge-made law upon the Law of India even where the

compulsions that led to the former are so different from the legal context

in our country stands ought to be, rejected, and that such a finding on this

issue would lift a burden from our maritime commerce and alternative

approach to the same problem by way of giving effect to the judgment in

"Kailash Nath Associates" (supra) would be equally effective in allaying

fears that Indian Law is too hide-bound to address the necessities of

Indian commerce.

Questions for Consideration

42. Considering the rival submissions and the arguments as

advanced by the learned counsel, the following questions would fall for

our consideration in adjudication of this appeal:-

(i) Whether the claim for demurrage is in the nature of liquidated

damages or a fixed charge, and what would be its nature in the contract in

PVR 44 app881-05.doc

question?

(ii) Whether the Respondent was required to prove that it had suffered

any loss and/or it had actually paid the vessel owner, in making a claim

for demurrage ?

Discussion and Reasons

43. We may at the outset observe that the Appellant's plea that

the claim for demurrage is a claim in the nature of liquidated damages

was not a specific plea as raised by the Appellant in the reply to the

Respondent's statement of claim. The Appellant's case can also be seen

interalia from the issues framed by the learned Arbitrator relevant being

firstly: whether clause 10(v) of the contract is in the nature of indemnity,

and if so, whether the Respondent had suffered any loss or damage which

was required to be indemnified. Secondly, as to whether the amount

mentioned in clause 10(v) of the contract only provided for ceiling on the

amount payable as demurrage and whether the Respondent was entitled to

receive only such amount which is actually found payable and paid as

alleged in paragraph 2A of the reply by the Appellants. We have already

noted the details of the issues as framed by the learned Arbitrator. From a

perusal of the Award it is clear that the Appellant in the course of its final

submissions raised the issue that the claim for demurrage is in the nature

of liquidated damages. In the circumstance there being no specific

pleadings on facts, on this issue, before the learned Arbitrator, when no

PVR 45 app881-05.doc

doubt such an issue becomes a mixed issue of fact and law, on this

background, we find that this issue was thus considered by the learned

Arbitrator and the learned Single Judge only as a legal issue. We

therefore examine the issue accordingly.

44. As noted above there is a finding of fact as recorded by the

learned Arbitrator that the vessels, as claimed by the Respondent, went

on demurrage. These findings are recorded on the basis of statement of

fact, lay time calculation, which were submitted to the Appellant

alongwith other documents like the commercial invoices for demurrage,

claims for settlement etc. The learned Arbitrator has recorded a finding

that the 'statement of facts', on the basis of which the invoices and lay

time calculations have been made are all signed by the representative of

the Appellant. The Appellant also specifically admitted the Respondent's

case in paragraph 5 of the statement of claim in which one of the

statement was that "the statement of facts were singed by the Master, the

vessels' agents and the agents of the receivers namely the Respondent." The

learned Arbitrator has recorded that once it was admitted that the

representative of Appellant has signed the Statements of facts without any

reservation, the burden was clearly on the Appellant to show that any of

the statements made therein was incorrect. The learned Arbitrator thus

held that the vessels had gone on demurrage. Further the learned

Arbitrator also rejected the case of the Appellant as defended on the

PVR 46 app881-05.doc

ground of force majeure (Clause 20 of the Contract) in regard to the

Respondent's claim for demurrage in respect of m.v.Rishikesh . Thus it is

clearly established that the vessels went on a demurrage. These findings

of fact as recorded by the learned Arbitrator as reflecting the correct

factual position, were accepted by the learned Single Judge. We,

therefore, do not find that there is any material, to regard this factual

conclusion and the concurrent finding on this issue, as recorded by both

the forums, can be regarded as not acceptable and/or perverse on any

count.

45. In view of the clear position that the vessels went on a

demurrage, we examine the consequences as would fall in terms of clause

10(v) of the contract (supra). The contract is admittedly between the

Appellant as a buyer and the Respondent as a seller. As noted above, the

Appellant's contention before the learned Arbitrator was that the

Respondent's right, to claim and recover demurrage from the Appellant

(as pleaded in paragraph 2 of the reply filed before the learned

Arbitrator) was on the ground that it was only in the form of an

indemnity. The Appellant stated that as the Respondent did not show that

the Respondent paid the alleged demurrage to the vessel-owner, therefore

the Respondent cannot be said to have suffered any loss or damages. The

Appellant therefore contended that the Respondent cannot assert that the

claim be indemnified. In other words, the Appellant's stand was that

PVR 47 app881-05.doc

unless the Respondent proved, that the Respondent itself had incurred a

liability to pay the demurrage, to the owner of the vessel, and in fact paid

demurrage to the vessel-owner, the Respondent cannot have a cause of

action against the Appellant. Alebit not in the written statement the

Appellant in their final submissions before the learned Arbitrator,

contended that the amount of demurrage represents 'liquidated damages'

and thus unless the Respondent established that it had suffered any loss,

the Respondent was not entitled to claim any amount by way of

demurrage. Thus two fold submissions were canvassed firstly in the

written statement that the claim was in the nature of indemnity requiring

proof of payment to the vessel owner and secondly de hors any written

pleadings that the claim is in the nature of 'liquidated damages', interalia

requiring a proof of payment to the vessel-owner.

46. In the above context it is necessary to first consider the

purport of clause 10(v) of the contract (supra) under which the

Respondent claims its entitlement for demurrage. The rival contentions,

therefore, are required to be tested on what would be the correct meaning

and intention between the parties in agreeing to clause 10(v) of the

Contract coupled with the manner the parties commercially understood

the clause as reflected from the correspondence and as to how the parties

acted upon the same. In this context, our first endeavour would be to

consider Clause 10(v) of the contract (supra) in its entirety. From a

PVR 48 app881-05.doc

perusal of clause 10(v), it can be clearly seen that it can be bifurcated in

two parts. The wordings of the first part indicate that it creates an

obligation on the buyer to pay demurrage to the seller or vessel-owner

through the seller if required at a rate not exceeding US $ 8000 per day. It

also correspondingly creates a provision that the seller shall pay despatch

to the buyers if earned, at the rate of 50% of demurrage rate, not

exceeding US $ 4000 per day or pro-rata for part of the day. The

significant content of clause 10(v) is the requirement that all demurrage

or despatch is required to be settled within sixty days after laytime

statement is submitted with supporting documents like notices of

readiness, statement of facts and time sheets. This shows that the parties

agreed to the manner of working out the claim for demurrage or

despatch. This on the basis of laytime statement submitted with

supporting documents and statement of facts and time sheet, that the

parties would settle demurrage or despatch.

Further a vital requirement of clause 10(v) is that, if there is

any disagreement in the laytime statement, then the party which has so

disagreed must raise such a disagreement within thirty days after such

statement is transmitted and received, otherwise the effect is that it is

agreed that the statement is accepted as correct. It may thus be observed

from a plain reading of clause 10(v), that the contention of the Appellant

that the liability to pay demurrage would be depending upon the

demurrage being paid by the seller to the vessel-owner is not in any

PVR 49 app881-05.doc

manner reflected from clause 10(v). In our opinion the Appellant is trying

to create an unwarranted confusion of the wordings "to the seller or vessel-

owner through the seller". These wordings in the first part of Clause 10(v)

simply provide for an option that either the demurrage be paid to the

seller or if the seller so feels, he may require the buyer to pay to the

vessel-owner. It can therefore be clearly gathered that ultimately it is the

desire of the seller as to how it should be paid. It also cannot be

forgotten, that the contract in question is a contract between the

buyer(appellant) and the seller(respondent) and the vessel-owner has no

privity of contract with the buyer (the appellant), and therefore the

parties have explicitly agreed that it is only when the seller (respondent)

so desires the buyer would be required to make payment of demurrage to

the vessel-owner. There can be no other reading of these words of clause

10(v). The Appellant's interpretation on this count therefore cannot at all

be accepted.

47. As regards the first contention on the part of the Appellant

before the learned Arbitrator namely of indemnity, though this issue was

urged before the learned Arbitrator, it was not argued in this appeal on

behalf of the Appellant. However for the sake of completeness, we deal

with the same. In this regard we may observe that on a plain reading of

clause 10(v), it cannot be construed as a contract of indemnity as Section

124 of the Contract Act would envisage. The requirement of Section 124

PVR 50 app881-05.doc

of the Contract Act is that when a person contracts to indemnify another,

the latter may compel the indemnifier to place him in a position to meet

the liability that may be cast upon him without waiting until the

indemnity holder has actually discharged that liability. This surely is not

the position as clause 10(v) of the contract in question would

contemplate. From the documents as placed on record, it is clear that the

Appellant understood clause 10(v) as not providing for any indemnity,

and more particularly clear from the evidence of Mr.Patwardhan who was

asked in cross examination with regard to demurrage payments made by

the Appellant in some contracts. Mr.Patwardhan admitted that he was the

person who had taken the decision to pay demurrage and such demurrage

was paid in similar contracts. Mr.Patwardhan also stated that the claim for

demurrage paid to Glencore International in another contract was on the

basis of three documents namely (i) statement of facts given by Glencore,

(ii) verification thereof and if necessary, correction thereto, and (iii)

charter party agreement. Referring to these three documents,

Mr.Patwardhan stated that these documents are generally documents

which he considered while "determining whether demurrage is to be paid

or not." The learned Arbitrator taking into consideration the entire

correspondence between the parties which did not indicate any different

position than what the Appellant had in similar contracts, has recorded a

finding that the demurrage was decided to be paid by the Appellant

earlier on the basis of the said documents which clearly indicate that the

PVR 51 app881-05.doc

Appellant never understood the clause relating to payment of demurrage

as being in the nature of an indemnity. This is a finding of fact indicating

how the parties positioned themselves commercially. What cannot be lost

sight is that clause 10(v) provides for a complete code within which the

parties agree to settle a claim for demurrage. It provides for all the

safeguards as noted by us, so that any dispute on the payment of

demurrage can be avoided. This contemplates the following three

factors:- Firstly that the rate of demurrage was not to exceed US $ 8000

per day. Secondly, the demurrage is required to be settled within 60 days

after laytime statement is submitted with the supporting documents like

'Notices of Readiness', 'Statement of Facts' and 'Time Sheets'. Thirdly, any

disagreement over the laytime statement must be raised by the other party

within 30 days after such statement is transmitted and received, failing

which the statement would be considered to be accepted as correct. The

parties, therefore, cannot raise a contention which would fall outside this

agreement. Significantly, this is not the arrangement as agreed between

the parties only for 'demurrage' but also for 'despatch'. In view of this

clear position, the argument of the Appellant that clause 10(v) was in the

nature of indemnity cannot be accepted, as rightly rejected by the learned

Arbitrator and the learned Single Judge.

48. Now coming to the main bone of the contention that the

demurrage to be paid to the Respondent would be in the nature of

PVR 52 app881-05.doc

liquidated damages. On this proposition, on behalf of the Appellant,

reliance is placed on (a) John Schofield "Laytime & Demurrage", 3 rd

Edition; (b) Payne and Ivany's "Carriage of Goods by Sea", 12 th

Edition; (c) McGregor on Damages, 18th Edition, and the decisions in

that regard which we have noted above.

49. Before we analyse the legal position, it would be appropriate

to examine how the parties understood clause 10(v) in the working of the

contract, namely the test of commercial understanding of the clause. In

this regard, it would be profitable to take note of some correspondence

between the parties. As an illustration we refer to a letter dated 6 March

2000 of Ensource to the Appellant with a specific attention of

Shri.D.S.Patwardhan, Vice President. Ensource who are the agent of the

Respondent in India were authorised to deal with the Appellant in respect

of shipping arrangements of the contract cargo. We may note that similar

letters were addressed in respect of each of the shipment and what is to

be noted is the specific amount of demurrage/despatch on which

acceptance of the Appellant was sought to each of the shipment being

subject matter of such letters. Admittedly, the amount of demurrage

which has been quoted and for which acceptance was sought is within the

specified amount agreed between the parties under clause 10(v). We

illustratively reproduce this letter:-

                     "                                                              6th March,2000





     PVR                                         53                                                   app881-05.doc

                     M/s.Larsen & Toubro Limited
                     Metropolitan,
                     Bandra-Kurla Complex,
                     Mumbai-400050




                                                                                                        
                     Fax No.6541433

Kind Attn: Shri.D.S.Patwardhan, Vice-President

Ms.Punam Ingle

Dear Sirs,

Sub: Steaming (non-coking) coal in Bulk from South Africa

L & T Jetty Pipavav - Your P.O.No: IMP/990520 dd) cargo

Our Principals have please to nominate the following vessel for L&T Jetty- Pipavav.

M.V.PATALIPUTRA OR SUB

INDIAN FLG BLT 1986 47,175MT DWT ON 11.825M SSW

5HO/HA

LOA/BEAM 189/30.4M

4x25T CRANES + 4x8 CBM GRABS 55215 CBM GRN

ALL DTLS ABT LOADABLE QUANTITY : 40,000MT+10% LOADPORT LAYCAN : 21st MARCH- 4th APRIL 2000 DEM / DES RATE : US $ 7000/DHD FTA RBCT : 29th /30th March 2000 AGW WP

KINDLY SEND US YOUR ACCEPTANCE AT THE EARLIEST.

Best regards,

Yours faithfully, for ENSOURCE ENERGY (INDIA) PVT.LTD.

N.Dhanaraj

CC to : Shri.D.S.Patwardhan VP, Awarpur Cement Works."

(emphasis supplied)

This letter of Ensource was confirmed by the Appellant by letter dated 7

March 2000 in which the Appellant accepted all the conditions and most

importantly the condition of demurrage rate of US $ 7000. Some recitals

in the Appellant's said letter are as under:-

"This has reference to the fax message dated 06 th March 2000 received today as regards nomination of vessel "m.v.Pataliputra" for L&T Jetty Pipavav.

PVR 54 app881-05.doc

The vessels specifications are generally acceptable to us and we hereby convey our approval to the same. .... .... ...."

Thus the demurrage/despatch rate was specifically indicated and agreed

at US $ 7000. This was the method by which, in respect of each of the

shipment, the demurrage rate was indicated and accepted by the

Appellants. Further the parties also confirmed the shipment in respect of

each of the vessels as agreed. Ensource had also furnished lay-time

calculation in regard to each of these vessels. The lay-time calculations

were not disputed in any manner and the communication in that regard

from Ensource and Glencore were forwarded and accepted by the

Appellant. The Appellant never disputed the statements of facts which

were forwarded by the Respondent as per the requirement of clause 10(v)

of the contract. All this makes it clear, that as regards the demurrage was

concerned, the Appellants were intimated the figure of demurrage by the

Respondent as regards each of the shipment under the contract. The

Appellant by its various letters addressed to Ensource (agent of the

Respondent) accepted the rate. Further the conditions as contemplated in

the second part of clause 10(v) about settlement of any issues in that

regard, within the stipulated time, had also worked itself out as it is a

matter of record that there was no disagreement on any of the lay-time

statements, as none was raised on behalf of the Appellant which was to be

raised within 30 days after such statement was transmitted and received,

PVR 55 app881-05.doc

failing which the contract clause provided that the statement was

accepted as correct.

50. The learned Arbitrator has recorded a finding of fact that as

regards the amount of demurrage is concerned, it was the appellant's

representative who insisted upon the figure of demurrage being intimated

to it. The appellant wrote to Ensource Energy Pvt. Ltd., the agent of the

claimant, on 16 September 1999, in reply to a Fax message dated 16

September 1999 in relation to nomination of the vessel m.v.

Dakshineshwar. This nomination was so made by Ensource on 15

September 1999 (Exhibit "C-24") and the Appellant was asked to send

acceptance before noon of 16 September 1999. By letter dated 16

September 1999 (Exhibit "C-25") amongst various items, information was

sought by the appellant from Ensource with regard to demurrage/dispatch

amount and item no.6 of this letter refers to "demurrage/dispatch rate to

be indicated." It is observed that in pursuance of this letter the demurrage

rate at US $ 7000 was intimated. Thus, it was clear from this

correspondence that the figure of demurrage was mutually accepted to be

the amount to be paid by the Appellant if the vessels were to go on a

demurrage. These facts clearly show the real intention of the appellant

as to how the appellant commercially understood and accepted the

consequence of the demurrage clause. In this background and in the facts

and circumstances of the case the Respondents in our opinion would not

PVR 56 app881-05.doc

be so inaccurate to submit that the Appellant understood the payment as a

fixed charge amount to be paid under the contract. However, later on the

Appellant discovered the legal side of it namely the Appellant's contention

that the Respondent's claim is in the nature of liquidated damages for

which loss was required to be proved by the Respondent and as no loss

has been proved by the Respondent, the Respondent is not entitled to its

claim for demurrage.

51.

Apart from the above apparent commercial understanding of

the contractual terms and the position taken by the parties in the working

of the contract, we now test the legal side of the Appellant's argument,

whether demurrage is in the nature of liquidated damages or its a fixed

charge. The contention of the Appellant is on the basis of the extract in

(a) John Schofield "Laytime & Demurrage", 3 rd Edition; (b) Payne and

Ivany's "Carriage of Goods by Sea", 12 th Edition; (c) McGregor on

Damages, 18th Edition, and on the basis of the decisions as we have

noted above. We thus examine the concept of demurrage.

Concept of demurrage

52. As the entire issue in this appeal is in regard to the claim of

the Respondent on demurrage, it would be appropriate to consider the

concept of demurrage. A contract for carriage of goods in a ship is called

in law a Contract of Affreightment (COA) and is also called a charterparty

PVR 57 app881-05.doc

under which the entire vessel or some part of her may be used or

employed by the charterer for a voyage or series of voyages or for a period

of time. In Halsbury's laws of England, Fourth Edition (Vol. 43(2) in

Chapter 14 Heading (H) describes "Terms as to loading and discharge" and

(J) describes "Terms as to demurrage and damages for detention".

Paragraph 1506, 1508 and 1509 thereunder reads thus:-

"1506.Demurrage days and payment of dispatch money. At the expiration of the lay days, the charterer may be allowed, in

consideration of an additional payment called 'demurrage', a further number of days, known as 'demurrage days'. Sometimes no further time is expressly allowed, but it is simply provided that

the charterer is to pay demurrage at the rate of so much a day for every dayy that the ship is detained beyond the lay days. Conversely, it is often provided that the charterer is to be paid

'dispatch money' for days saved in loading or discharging. It is, therefore, important, for the purpose both of ascertaining when the lay days expire and the liability for demurrage begins and of calculating the amount of demurrage payable, to define what is meant by the word 'day' in a charterparty. In practice, its

meaning is usually made more or less clear by the insertion of qualifications. Once a ship is on demurrage, the charterers are in continuing breach of contract and may claim exemption from

liability to pay demurrage only under clearly worded exemption clauses to that effect.

1508. Charterer's right to demurrage days. The specification of

lay days and demurrage days in the charterpary is equivalent to a contract on the part of the charterer that he will not delay the ship for a further period, and also to a contract on the part of the shipowner that during those days the ship is to be at the charterer's disposal. The charterer has, therefore, the right to make use of both the lay days and the demurrage days for the

due performance of his obligation either to load or to discharge, and it would seem that he commits no breach of contract in detaining the ship until the expiration of the demurrage days. If the charterparty does not specify the number of lay days, demurrage, where provided for, will become payable at the expiration of a reasonable time, and will continue to be payable, if the charterparty does not specify the number of demurrage days, as long as the ship is detained by the charterer.

However, detention after the lay days or after the demurrage days, where either are specified, and, in other cases, detention after the expiration of a reasonable time for loading or discharging, constitutes a breach of contract on the part of the charterer. In respect of this breach of contract the charterer is

PVR 58 app881-05.doc

liable for any damage actually suffered by the shipowner in consequence of the delay and not merely for the agreed rate of demurrage, which will only be applicable to a claim for damages

for the actual detention of the ship.

The detention does not, however, entitle the shipowner to treat the contract as repudiated and sail away forthwith; it seems

that he may only do this if the charterer's conduct is such as to show that he does not intend to perform the charterparty, or if the detention lasts so long as to frustrate the commercial purpose of the adventure.

1509. When the demurrage is payable.

Demurrage in the strict sense of the word is payable only where there is an express term to that effect. In the absence of any such term the shipowner is not entitled to claim demurrage as such, nor is the charterer justified in detaining the ship beyond the

expiration of the time allowed by the charterparty for loading or discharging, as the case may be. If, therefore, he detains her for any further time, he is guilty of a breach of contract, and is liable

to pay damages for her detention as soon as the lay days expire.

The distinction between demurrage and damages for detention is that the first is liquidated and the second

unliquidated damages. Demurrage being liquidated damages, no damages are recoverable for delay in payment of demurrage as there is no cause of action for late payment of damages."

(emphasis supplied)

53. The extract from John Schofield "Laytime & Demurrage",

3rd Edition, Chapter 6 of the "Laytime and Demurrage" is as under:-

                     "                              CHAPTER 6
                                                   DEMURRAGE 

                     Meaning and Nature

The Charterparty Laytime Definitions 1980 define demurrage as

follows"

"DEMURRAGE" means the money payable to the owner for delay for which the owner is not responsible in loading and/or discharging after the laytime has expired.

However, this definition avoids what at one time was unclear, namely whether a failure to complete loading and discharging in the allowed laytime of itself constituted a breach of charter. The current view is that demurrage is liquidated damages for such a breach. In origin, however, demurrage did not mean a sum payable for breach of contract but a sum payable under and by reason of a contract for detaining a ship at the port of loading or discharge beyond the allowed time. In Lockhart V. Falk,(1875)LR

PVR 59 app881-05.doc

10 Ex.132, at page 135, Baron C Cleasby said:

The word demurrage no doubt properly signifies the agreed additional payment for an allowed detention beyond a

period either specified in or to be collected from the instrument; but it has also the popular or more general meaning of compensation for undue detention; and from the

whole of each charterparty containing the clause in question we must collect what is the proper meaning to be assigned to it."

... ... ... ...

More recently, in Union of India Vs. Compania Naviera

Aeolus SA (The Spalmatori) (1964) AC 868 at p.899, Lord Guest said:

Lay days are the days which parties have stipulated for the loading or discharge of the cargo, and if they are exceeded the charterers are in breach; demurrage is the agreed

damages to be paid for delay if the ship is delayed in loading or discharging beyond the agreed period.(Lord Reid also took the view that failure to complete loading/discharing

within the allowed laytime was a breach of contract.)"

(emphasis supplied)

54. Payne and Ivany's "Carriage of Goods by Sea" Twelfth

Edition in which Chapter 10 deals with "Demurrage and desptach

money" narrates the concept of demurrage:-

"Chapter 10 Demurrage and despatch money

(A) DEMURRAGE It is first necessary to define 'demurrage' and 'damages for detention' and to show the difference between them. A number of lay days are allowed to the charterer. It is important to notice when these commence, and to notice the effect of lay time being fixed. It is necessary to ascertain

when loading is complete, what the rate of demurrage is and the persons by whom demurrage is payable.

THE DIFFERENCE BETWEEN DEMURRAGE AND DAMAGES FOR DETENTION.

A charter-party generally fixes a number of days called 'lay days' in which the ship is to be loaded or discharged, as the case may be.

'Demurrage' is a sum named in the charter party to be paid by the charterer as liquidated damages for delay beyond such lay days.

PVR 60 app881-05.doc

The shipowner is entitled to sue for 'damages for detention' if

(i) the lay days have expired and demurrage has not

been provided for; or

(ii) the time for loading or discharge is not agreed, and a reasonable time for loading or discharge has expired; or

(iii) demurrage is only to be paid for an agreed number of days and a further delay takes place."

(emphasis supplied)

55. The Maritime Law by Christopher Hill, (Fifth Edition)

would describe 'Demurrage' as under:-

"What is demurrage/

Demurrage is liquidated damages. The rate of demurrage is fixed, agreed between owner and charterer at the time of the concluding of the charter party and the rate is stated in the charterparty. On the basis that it is fixed and unalterable

the author prefers to think of demurrage as a penalty imposed upon the charterer for exceeding the laytime period and delaying the ship beyond the agreed laytime in order to complete loading or discharging. The rate of demurrage is linked in with the rate of freight so that the shipowner

satisfies himself as far as he can that overall by the time the voyage is fully completed he will have balanced his books

and made a reasonable profit.

Demurrage should be contrasted with damages for detention the latter being unliquidated, assessable damages payable by a charterer for detaining the ship for whatever reason (there may be reasons other than exceeding laytime-

e.g. Repairs necessitated after the causing of damage to the ship by charterers' stevedores for whose negligence the charterers are vicariously liable).

Due to the 'penalty' nature of demurrage, it runs continuously from the point when laytime expires. Laytime exceptions do not interrupt the running of demurrage. This

is typified by the oft-used expression "once on demurrage, always on demurrage'.

If demurrage itself, as opposed to laytime, is to be interrupted by any excepted period, such an exception must be expressly provided for in the charterparty. This was made clear in The Dias (1978) 1 Lloyd's Rep.325. It cannot be assumed that laytime exceptions apply equally to demurrage as they do to laytime. They do not unless expressly stated as applying also to demurrage."

PVR 61 app881-05.doc

56. A cumulative reading of the above wealth of material would

clearly bring out the meaning and concept of 'demurrage' as under:-

(I) On expiration of lay days, the charterer may be allowed, in

consideration of additional payment called 'demurrage', a further number

of days known as 'demurrage days'.

(II) Demurrage is the agreed amount of damage which is required to be

paid for the delay of the ship caused by default of charterers.

(III) It would be payable principally for the acts which are not the

responsibility of the owner in loading and/or discharging after the laytime

has expired.

(IV) Demurrage thus is liquidated damages, the rate of which is fixed

agreed between the owner and the charterer.

(V) Once a ship is on demurrage, the charterers are in continuing

breach of contract and may claim exemption from liability to pay

demurrage only under clearly worded exemption clauses to that effect.

(VI) Detention after the expiration of a reasonable time for loading or

discharging, constitutes a breach of contract on the part of the charterer.

For such breach of contract the charterer is liable for any damage actually

suffered by the shipowner in consequence of the delay and not merely for

the agreed rate of demurrage, which will only be applicable to a claim for

damages for the actual detention of the ship.

(VII) Demurrage in the strict sense of the word is payable only where

there is an express term to that effect. In the absence of any such term

PVR 62 app881-05.doc

the shipowner is not entitled to claim demurrage as such, nor is the

charterer justified in detaining the ship beyond the expiration of the time

allowed by the charterparty for loading or discharging, as the case may

be. The distinction between demurrage and damages for detention is that

the first is liquidated and the second unliquidated damages.

(VIII) Demurrage being liquidated damages, no damages are recoverable

for delay in payment of demurrage as there is no cause of action for late

payment of damages.

57. Thus in a given case the parties may commercially

understand a demurrage clause as a fixed charge and accordingly consider

and discharge their obligation albeit the underlying legal position as

above. This certainly will depend on the facts and circumstances of each

of such case.

58. The Appellant's endeavour in insisting that the demurrage

necessarily is required to be accepted as liquidated damages is wholly to

bring the claim of the Respondent within the purview of Section 73 and

Section 74 of the Contract Act. This is for two fold purposes, as the

Appellant would urge, firstly that the claim for demurrage is a claim

arising out of breach of a contract, and secondly, a party would be entitled

for damages for breach of a contract, only on application of the test

underlying Section 73 and Section 74 of the Contract Act, that is 'the

PVR 63 app881-05.doc

proof of loss' and 'entitlement for a reasonable compensation/damages'. It

is only because in respect of a general claim for damages these

consequences would flow from Section 73 and Section 74 of the Contract

Act, the Appellant intends to categorize the claim for damages as any

other general claim and contend that such a claim cannot succeed unless

the claimant (Respondent) proves that it has suffered losses.

59. Thus even if the contention of the appellant that payment of

demurrage is liquidated damages is to be accepted and thus would attract

Section 74 of the Contract Act, we consider as to whether the test of proof

of damages would be a sine qua non, for the Respondent to sustain its

claim. We examine this, adverting to the factual position which has come

on record before the learned Arbitrator, that the vessels have gone on

demurrage and that the amount of demurrage as claimed by the

Respondent, is the amount as agreed between the parties and that the

respondents claim is not above the said agreed amounts. We may add here

that there is not an iota of material brought on record by the Appellant to

support this contention, that the Appellant at any time considered

payment of demurrage conditional either as a indemnity or conditional to

proof of loss to be furnished by the Respondent. On this conspectus we

examine the principal contention as urged on behalf of the Appellant that

the Respondent's claim for demurrage being in the nature of liquidated

damages. On behalf of the Appellant elaborate submissions are made as

PVR 64 app881-05.doc

noted above on the application of Sections 73 and 74 of the Indian

Contracts Act,1872 (for short 'the Contract Act'). We thus examine the

application of the provisions of Section 73 and 74 of the Contract Act and

the legal position as enunciated in the various decisions, and more

particularly in the context of liquidated damages in its application to a

demurrage claim, to the facts in hand.

60. Chapter VI of the Contract Act pertains to "Of the

consequences of breach of contract." Under this Chapter, Section 73

provides for 'Compensation of loss or damage caused by breach of contract'

and Section 74 provides for 'Compensation of breach of contract where

penalty stipulated for'. Section 74 was amended by Act VI of 1899 which

added certain words to the section and illustrations (d), (e), (f) and (g) as

also the Explanation. Previous to the amendment the first paragraph of

Section 74 read as under:-

"When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not

exceeding the amount so named."

It would be profitable to extract both Section 73 and Section 74 of the

Contract Act as they stand today, as the entire focus of the submissions of

the parties revolves around the application of these provisions and the law

as would emerge thereunder. Sections 73 and 74 read thus:-

PVR 65 app881-05.doc

73. Compensation of loss or damage caused by breach of contract When a contract has been broken, the party who suffers by such

breach is entitled to receive, form the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from such breach,

or which the parties knew, when they made the contract, to be likely to result from the breach of it.

Such compensation is not to be given for any remote and indirect loss of damage sustained by reason of the breach.

Compensation for failure to discharge obligation resembling those created by contract : When an obligation resembling those created by contract has been incurred and has not been discharged, any person injured by the failure to discharge it is entitled to receive the same compensation from the party in default, as if such person

had contracted to discharge it and had broken his contract. Explanation : In estimating the loss or damage arising from a breach

of contract, the means which existed of remedying the inconvenience caused by non-performance of the contract must be taken into account.

74. Compensation of breach of contract where penalty stipulated for [When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual

damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not

exceeding the amount so named or, as the case may be, the penalty stipulated for Explanation.-- A stipulation for increased interest from the date of default may be a stipulation by way of penalty.]

Exception.-- When any person enters into any bail-bond, recognizance or other instrument of the same nature or, under the

provisions of any law, or under the orders of the [Central

Government] or of any [State Government], gives any bond for the

performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to pay the whole sum mentioned therein. Explanation.-- A person who enters into a contract with Government does not necessarily thereby undertake any public duty, or promise to do an act in which the public are interested."

Thus, Section 73 provides that a party who suffers under a

breach of contract becomes entitled to receive from a party who has

PVR 66 app881-05.doc

broken the contract, compensation for any loss or damages caused to him.

Compensation can be recovered for loss or damage which naturally arose

in the usual course of things from such breach, or which the parties knew,

when they made the contract, it is likely to result from the breach of it,

and that, such compensation is not to be given for any remote and indirect

loss of damage sustained by reason of the breach. The third paragraph of

Section 73 applies the same principle where breach occurs of obligations

and resembling contracts. The fourth para of section 73 provides that

while assessing damage means which existed to the person claiming

damages of remedying inconveniences caused by non-performance must

be considered. It is well-settled that the illustration to the Section

represent the general rules that can be followed while interpreting a

Section. As regards Section 74, it provides for Compensation of breach of

contract where penalty is stipulated in the contract itself. Thus if a

contract is broken, and if a sum is named in a contract as amount to be

paid in case of breach or if any other stipulation by way of penalty, it

provides that the party complaining of the breach becomes entitled,

whether or not actual damage or loss is proved to have been caused, to

receive from the party who has broken the contract reasonable

compensation, not exceeding the amount so named or the penalty

stipulated for.

61. The intention of the legislature as embodied in Section 74

PVR 67 app881-05.doc

can be noted from the ineffable observations of Ameer Ali, J. in

"Mahadeoprasad Vs. Siemens (India) Limited"11 wherein His Lordship

considering the claim for liquidated damages of the plaintiff observed

thus:-

"That brings me to the question of damages for the breach of the guarantee, which, as I indicated at the outset, was

ultimately the only point argued on behalf of the defendatns. The question involves a point of law, namely, the effect of section 74 of the Contract Act. Speaking for myself, I have never understood section 74. I am always

convinced of the difficulty of a particular point when both sides say it is perfectly simple.

I will deal first with the point of law involved and then with the main question of fact which underlies every issue as to damages, including the question of mitigation.

What is the effect in Indian Law of "naming a "figure?"

I should perhaps say now that I have no doubt that these parties at the time of the compromise fully considered

their position. The figures named are undoubtedly large, but I have no doubt that they were arrived at after

consideration, and I think the harshness of the contract (if you can call it that) is not so much the fixing of these particular figures as the unconditional undertaking to fulfill a very stringent guarantee under what must have

been almost unknown circumstances.

However, the point is a point of law and has been argued as such on behalf of the defendant company, and quite rightly and very ably argued. What is the effect of naming a sum, having regard to section 74?

... ... ...

Before I state what I consider to be the law in the form of propositions, I desire to say something about the section itself. In the first place, by reason of the fact that there has been an amendment, it does not make sense at all. The second clause of the section contains the phrase "any other stipulation by "way of penalty" which has been added. In contradistinction to "other" is "a sum named in the "contract as the amount to be paid, etc." According to

11 ILR VOL. LX CALCUTTA 1379

PVR 68 app881-05.doc

English law and phraseology, such a sum would not be a penalty at all. For the purposes of this case I disregard the clause in question referring to a "penalty." It is then clear

that the Indian law professes simply to be oblivious to the fact that in England "sums named in the contract" have

been divided into distinct species: (a) liquidated damages,

(b) penalties. The Indian law has not heard of them.

In all cases, when a sum is named, certain consequences shall follow. What are those consequences ?

The plaintiff is entitled "whether or not actual damage or loss is proved to have been caused, to receive reasonable compensation not exceeding the "amount, etc." It should be noted here that, by reason of the last clause, we again get away from penalty, because in English law the sum

named, if a penalty, ceases to have any effect at all either as a lower or upper limit. In Indian Law it remains an

upper limit, or maximum.

The other point to be noticed as "whether or not "actual damage or loss is proved." Now, what is the sense

of that, if you have to disregard the figure named entirely? If it is simply a maximum,what is the sense of it ? It may have little sense upon any reading, but none at all if one has to disregard the sum named entirely, i.e., for all

purposes except as a maximum.

Now, there are cases in Calcutta which I have not

had time to look into, but there is one, The Brahmaputra Tea Co.Ltd. Vs. Scarth, (1985) I.L.R. 11 Calc.545,550, 551" where this Section is discussed:

It is clear that the court might have awarded the full

sum stipulated without any proof of damages or loss.

That you get from the section itself. Then :

No doubt the court has a discretion to fix what it

considers reasonable compensation; but when the parties have already agreed among themselves as to what the penalty should be, we think the court should not, in fixing the compensation, wholly ignore the amount agreed on, unless this is, on its face, wholly unreasonable with reference to the position of the parties and the breach provided against.

which does not get you very far.

PVR 69 app881-05.doc

To my mind, the following is the intention of the legislature:-

(1) The plaintiff must prove his damage in a general

sense;

(2) the contract made by the parties estimating their

damages is in itself evidence;

(3) if there is no other evidence of damage, I can conceive of certain cases where this evidence alone will be considered sufficient, nor do I think that the Judicial

Committee intended by anything said in Panna Singh V.

Firm Bhai Arjan Singh, (1920) 33 C.W.N.949" to exclude such a possibility;

(4) the sum named, however, is not conclusive evidence, that is to say, if there is other evidence or circumstances

showing that it was excessive, the court will not consider itself bound by it;

(5) if, on the other hand, the other evidence and circumstances indicate that the damage equals or may equal, or is likely to exceed the amount named, the Court

will abide by it, and lastly, (6) in case (4), that is to say, where the other evidence shows that it is unreasonable, the plaintiff will have to prove his damages irrespective of the figure."

(emphasis supplied)

We are in respectful agreement with the above interpretation of Ameer

Ali J. when it is held that for the purposes of Section 74, the plaintiff

must prove damage in a general sense as the contract made between the

parties estimating their damages is in itself evidence of damages. In the

facts of the present case admittedly there is a breach of the contract once

the vessels have gone on demurrage. The amount which is claimed by the

Respondent is the amount of demurrage as agreed between the parties.

There is no other evidence to show as to what was demanded by the

Respondent was unreasonable or there was no legal injury caused to the

PVR 70 app881-05.doc

Respondent. In fact that was never the case of the Appellant. The

appellant cannot be expected to go beyond the explicit terms of the

contract to which it was all throughout conscious as also on which it had

acted upon.

62. The observation of Ameer Ali, J. in Mahadeoprasad Vs.

Siemens (India) Limited (supra) in effect are also supported by the

observations of the Supreme Court in "Fateh Chand v. Balkishan Das12"

referring to Section 74 of the Contract Act, their Lordship of the

Constitution Bench in paragraph 8 observed thus:-

"(8) ... ... ...

The section is clearly an attempt to eliminate the somewhat elaborate refinements made under the English common law in distinguishing

between stipulations providing for payment of liquidated damages and stipulations in the nature of penalty. Under the common law a genuine pre-estimate of damages by mutual agreement is regarded as

a stipulation naming liquidated damages and binding between the parties: a stipulation in a contract in terrorem is a penalty and the Court refuses to enforce it, awarding to the aggrieved party only reasonable compensation. The Indian Legislature has sought to cut

across the web of rules and presumptions under the English common law, by enacting a uniform principle applicable to all stipulations naming amounts to be paid in case of breach, and stipulations by way of penalty. The second clause of the contract provides that if for any reason the vender fails to get the sale-deed registered by the date stipulated, the amount of Rs. 25,000/- (Rs. 1,000/- paid as earnest

money and Rs. 24,000/- paid out of the price on delivery of possession) shall stand forfeited and the agreement shall be deemed cancelled. The covenant for forfeiture of Rs. 24,000/- is manifestly a stipulation by way of penalty.

... ... ...

(10) ... ... ..... ...The measure of damages in the case of breach of a stipulation by way of penalty is by S. 74 reasonable compensation not exceeding the penalty stipulated for. In assessing damages the Court has, subject to the limit of the penalty stipulated, jurisdiction to award such compensation as it deems reasonable having regard to

12 AIR 1963 SC 1405

PVR 71 app881-05.doc

all the circumstances of the case. Jurisdiction of the Court to award compensation in case of breach of contract is unqualified except as to the maximum stipulated; but compensation has to be reasonable,

and that imposes upon the Court duty to award compensation according, to settled principles. The section undoubtedly says that the aggrieved party is entitled to receive compensation from the party

who has broken the contract, whether or not actual damage or loss is proved to have been caused by the breach. Thereby it merely dispenses with proof of "actual loss or damages"; it does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of

contract can be awarded to make good loss or damage which naturally arose in the usual course of things, or which the parties knew when they made the contract, to be likely to result from the breach. "

63.

The legal journey of section 74 and consistent to what has

been held by Ameer Ali J. in Mahadeoprasad Vs. Siemens (India)

Limited (supra) is well reflected in several other decisions between

period of Fateh Chand v. Balkishan Das, AIR 1963 SC 1405 up to

Kailash Nath Associates Vs. DDA, (2015)4 SCC 135. We discuss some

decisions in this context.

64. In "Shiva Jute Baling Limited. Vs. Hindley and Company

Limited"13, the case concerned the Appellant-Indian Company which had

entered into a contract with the Respondent company incorporated in

England for the supply of bales of jute. Clause 12 of the contract provided

that in the event of default of tender or delivery, the seller shall pay to the

buyer as and by way of liquidated damages 10 s. per ton plus the excess

(if any) of the market value over the contract price. There was also a

13 AIR 1959 SC 1357

PVR 72 app881-05.doc

provision for arbitration in London, and the appellant having failed to

supply the bales as contracted and disputes having arisen between the

parties, the respondent referred the matter to the arbitration of the

'London Jute Association'. The arbitrators awarded liquidated damages

provided under clause 12 of the contract i.e. not only the difference

between the contract price and the market price but also a further sum of

10 s per ton. The respondent had prayed that judgment be pronounced in

accordance with the award and decree be passed accordingly. The

appellant contended that extra amount of 10 s per ton included in the

sum of liquidated damages was against the provisions of Sections 73 and

74 of the Contract Act and therefore, the award being against law of India

was bad on the face of it and should not be enforced in India in view of

the provisions of Section 7(e) of the Arbitration (Protocol and

Convention) Act. In this context the Supreme Court held that there was

nothing in Sections 73 and 74 of the contract Act which made the award

of such liquidated damages illegal. Both these sections provide for

reasonable compensation and Section 74 contemplates that the maximum

reasonable compensation may be the amount which may be named in the

contract. The arbitrators having awarded the maximum amount so

named and nothing more, their award in the circumstances could not be

said to be bad on the face of it, nor could it be said to be against the law

of India as contained in these sections of the Contract Act. The

observations in that regard are contained in paragraph 14 of the Report

PVR 73 app881-05.doc

which reads thus:-

"The argument under this head is that the liquidated damages

provided under cl. (12) of the contract include not only the difference between the contract price and the market price on the date of default but also a further sum of 10s. per ton. Reference in

this connection is made to ss. 73 and 74 of the Indian Contract Act, 1872 (IX of 1872) and it is said that the extra amount of 10s. per ton included in the sum of liquidated damages is against the provision of these sections and therefore the award being against the law of India is bad on the face of it and should not be enforced in

India. Section 73 provides for compensation for loss or damage caused by breach of contract. It lays down that when a contract has been broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose

in the usual course of things from such breach, or which the parties knew, when they made the contract, to be likely to result from the

breach of it. Section 74 provides for breach of contract where penalty is stipulated for or a sum is named and lays down that when a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract

contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty

stipulated for. What cl. (12) of the contract provides in this case is the measure of liquidated damages and that consists of two things,

namely, (i) the difference between the contract price and the market price on the date of default, and (ii) an addition of 10s. per ton

above that. There is nothing in s. 73 or s. 74 of the Contract Act, which makes the award of such liquidated damages illegal. Assuming that the case is covered by s. 74 , it is provided therein

that reasonable compensation may be awarded for breach of contract subject to the maximum amount named in the contract.

What the arbitrators have done is to award the maximum amount named in the contract. If the appellant wanted to challenge the reasonableness of that provision in cl. (12) it should have appeared

before the arbitrators and represented its case. It cannot now be heard to say that simply because cl. (12) provided for a further sum of 10s. per ton over and above the difference between the contract price and the market price on the date of the default, this was per se unreasonable and was therefore bad according to the law of India as laid down in ss. 73 and 74, of the Contract Act. Both these sections provide for reasonable compensation and s. 74 contemplates that the maximum reasonable compensation may be the amount which may be named in the contract. In this case the arbitrators have awarded the maximum amount so named and nothing more. Their award in the circumstances cannot be said to be bad on the face of it, nor can it be said to be against the law of India as contained in these sections of the Contract Act. The second

PVR 74 app881-05.doc

contention must also fail." (emphasis supplied)

65. In the case Pandit Janki Nath Zutshi & Anr. Vs. Ghulam

Qadir Mir and Others14, His Lordship S.Murtaza Fazl Ali observed that it

is well settled that after the amendment of 1899 in Section 74 of the

Contract Act in India, the legislature abolished the distinction between

'penalty' and 'liquidated damages'. Section 74 would thus show that even

though the parties may by agreement settled a fixed sum as damages for

the breach of the contract, the Court is not powerless to grant relief to the

party committing default, if it is held that the amount of damages fixed by

the parties is unconscionable or penal. Once the Court comes to this

finding, it is open to it to grant such reasonable compensation as the court

may in the circumstances determine. The Court considering the decision

in "Bhai Panna Singh Vs. Arjun Singh"15 and the decision in "Badhava

Singh Vs. Charan Singh"16 has made the following observations in

paragraph 13 which read thus:-

"13. In a later case, Michel Habib V. Sulaiman El Taji AIR 1941 PC 101 the same principle was enunciated and it was held that the amount fixed by the parties in the

contract would not include a sum fixed in terrorem covering breaches of contract of varying degrees. Their Lordships further held that the agreed liquidated damages in order to be enforced must be the result of a genuine pre estimate of damages. In this connection, their Lordships observed as follows:-

"Agreed liquidated damages, if to be enforced must

14 AIR 1964 Jammu & Kashmir 26 15 AIR 1929 PC 1/9 16 AIR 1955 Raj 87

PVR 75 app881-05.doc

be the result of a "genuine pre-estimate of damages" to use the illuminating phrase of Lord Duneain. They do not include a sum fixed in terrorem covering breaches of

contract of many varying degrees of importance the possible damages from which bear no relation to the fixed

sum, and which obviously have at no time been estimated by the contracting parties. It seems right therefore, to conclude that now when the code is applied to contracts, "damages" will be taken to mean actual damages, and

the article will only apply to an agreement which represents "a genuine pre-estimate of damages". Where there is such an agreed sum "no more and no less" can be awarded. But if the court applying well known rules has to conclude that the sum agreed was a penalty, whatever

it may be called in the agreement, then the penal stipulation will not be enforced". It seems to me that

where the clause relating to the award of damages as consequence of the breach of the contract is an integral part of the contract and has been added as a guarantee

for the performance of the contract, and the sum fixed is pre-estimate of damages, agreed to by the parties, the courts should normally carry out the terms of the contract and grant damages as agreed to between the

parties. I am supported in this view by a decision of the Nagpur High Court reported in Champat Rao Mahadeo

V. Mahadeo Bajirao, AIR 1937 Nag 143, and also Vaithinatha Iyer V. Govindaswami Odayar, AIR 1922 Mad 67. The question as to whether or not the amount fixed in the contract is pre-estimate of damages or is a

penalty will have to be determined according to the facts of each case. In the instant case, we have to find out as to whether the clause relating to withholding of the balance of the consideration money of Rs.20,000/- was a penalty or was really a pre-estimate damage as agreed to between

the parties. (emphasis supplied)

66. The learned Single Judge of this Court in "Indian Drugs and

Pharmaceuticals Ltd., Hyderabad Vs. Industrial Oxygen Co.Ltd, Poona

PVR 76 app881-05.doc

& Anr."17, considering Section 74 of the Indian Contract Act has observed

thus:-

"If the very purpose of putting a genuine pre-estimate is to avoid

litigation and introduce certainty in computation of difficult question of assessment of damages, it seems to be in the highest degree unlikely that the intention would have been that the clause of liquidated damages will not come into operation till the entire contract has been broken."

67. In "K.P.Subbarama Sastri & Ors. Vs. K.S.Raghavan & Ors"18

the Supreme Court affirming the full Bench decision, held that Section 74

of the Contract Act in the context whether a particular stipulation in a

contractual agreement is in the nature of a penalty has to be determined

by the court against the background of various relevant factors, such as

the character of the transaction and its special nature, if any, the relative

situation of the parties, the rights and obligations accruing from such a

transaction under the general law and the intention of the parties in

incorporating in the contract the particular stipulation which is contended

to be penal in nature, it was observed that if on such a comprehensive

consideration, the court finds that the real purpose for which the

stipulation was incorporated in the contract was that by reason of its

burdensome or oppressive character it may operate in terrorem over the

promiser so as to drive him to fulfill the contract, then the provision will

be held to be one by way of penalty. The following are the observations of

the Full Bench of Kerala High Court which are affirmed in the decision:-

    17 AIR 1986 BOMBAY 186
    18 AIR 1987 SC 1257




     PVR                                         77                                                   app881-05.doc


".... .... .... We quote below the observations made by the full Bench in paragraphs 6 & 7:

"6. The question whether a particular stipulation in a

contractual agreement is in the nature of a penalty has to be determined by the court against the background of various

relevant factors, such as the character of the transaction and its special nature, if any, the relative situation of the parties, the rights and obligations accruing from such a transaction under the general law and the intention of the parties in incorporating in the contract the particular stipulation which

is contended to be penal in nature. If on such a comprehensive consideration, the court finds that the real purpose for which the stipulation was incorporated in the contract was that by reason of its burdensome or oppressive character it may

operate in terrorem over the promiser so as to drive him to fulfil the contract, then the provision will be held to be one by way of penalty."

"7. Where a contract provides for payment of money in instalments and contains also a stipulation that on default

being committed in paying any of the instalments the whole sum shall become payable at once, the true test for determining whether the said condition is in the nature of a penalty is to find out whether the amounts referred to in the agreement were debita in praesenti although solvenda in

futuro or whether they were to become due to the promisee only on the respective dates when the instalments were

payable. If on a proper construction of a contract it is found that the real agreement between the parties was to the effect that the whole amount was on the date of the bond a debt due but the creditor for the convenience of the debtor allowed it to

be paid by instalments intimating that if default should be made in the payment of any instalments he would withdraw the concession, then the stipulation as to the whole amount of the balance becoming payable would not be penal; if, on the other hand, on a proper consideration of the terms of the contract the court comes to the conclusion that the debt itself

arises or becomes due and payable by the debtor only on the respective dates fixed for the instalments the stipulation that on default being made in the payment of any instalment the whole of the balance should become due and payable would be in the nature of a penalty."

68. In "Oil and Natural Gas Corporation Ltd. Vs. SAW Pipes

PVR 78 app881-05.doc

Ltd."19 discussing Sections 73 and 74 of the Indian Contract Act,1872 and

considering the law in that regard as laid down in the decisions in the

cases Fateh Chand v. Balkishan Das20, Maula Bux v. Union of India21,

Union of India v. Rampur Distillery and Chemical Co. Ltd. 22 and Union

of India v. Raman Iron Foundry23, the Supreme Court held that genuine

pre-estimate of damages by mutual agreement was in effect a stipulation

naming liquidated damages and was binding on the parties. The

observations in paragraphs 40, 41, 46 and 69 read thus:-

"40

It cannot be disputed that for construction of the contract, it is settled law that the intention of the parties is to be gathered from the words used in the agreement. If words are unambiguous and are

used after full understanding of their meaning by experts, it would be difficult to gather their intention different from the language used in the agreement. If upon a reading of the document as a whole, it can fairly be deduced from the words actually used therein that the parties had agreed on a particular term, there is nothing in

law which prevents them from setting up that term. {Re: Modi & Co. v. Union of India [(1968) 2 SCR 565]}. Further, in construing a contract, the Court must look at the words used in the contract

unless they are such that one may suspect that they do not convey the intention correctly. If the words are clear, there is very little the court can do about it. {Re: Provash Chandra Dalui and another v. Biswanath Banerjee and another [1989 Supp (1) SCC 487]}.

41. Therefore, when parties have expressly agreed that recovery from the contractor for breach of the contract is pre- estimated genuine liquidated damages and is not by way of penalty duly agreed by the parties, there was no justifiable reason for the arbitral tribunal to arrive at a conclusion that

still the purchaser should prove loss suffered by it because of delay in supply of goods.

... ... ...

From the aforesaid Sections, it can be held that when a

contract has been broken, the party who suffers by such

19 AIR 2003 SC 2629 20(1964) 1 SCR 515 at 526 21(1969) 2 SCC 554 22(1973) 1 SCC 649 23(1974) 2 SCC 231

PVR 79 app881-05.doc

breach is entitled to receive compensation for any loss which naturally arise in the usual course of things from such breach. These sections further contemplate that if parties knew when

they made the contract that a particular loss is likely to result from such breach, they can agree for payment of such compensation. In such a case, there may not be any necessity

of leading evidence for proving damages, unless the Court arrives at the conclusion that no loss is likely to occur because of such breach. Further, in case where Court arrives at the conclusion that the term contemplating damages is by way of

penalty, the Court may grant reasonable compensation not exceeding the amount so named in the contract on proof of damages. However, when the terms of the contract are clear and unambiguous then its meaning is to be gathered only from the words used therein. In a case where agreement is

executed by experts in the field, it would be difficult to hold that the intention of the parties was different from the

language used therein. In such a case, it is for the party

who contends that stipulated amount is not reasonable compensation, to prove the same .

... ... ...

69. From the aforesaid discussions, it can be held that:- (1) Terms of the contract are required to be taken into consideration before arriving at the conclusion whether the

party claiming damages is entitled to the same;

(2) If the terms are clear and unambiguous stipulating the

liquidated damages in case of the breach of the contract unless it is held that such estimate of damages/compensation is unreasonable or is by way of penalty, party who has committed the breach is required to pay such compensation

and that is what is provided in Section 73 of the Contract Act. (3) Section 74 is to be read along with Section 73 and, therefore, in every case of breach of contract, the person aggrieved by the breach is not required to prove actual loss or damage suffered by him before he can claim a decree. The Court is competent to award reasonable compensation in case

of breach even if no actual damage is proved to have been suffered in consequences of the breach of a contract. (4) In some contracts, it would be impossible for the Court to assess the compensation arising from breach and if the compensation contemplated is not by way of penalty or unreasonable, Court can award the same if it is genuine pre- estimate by the parties as the measure of reasonable compensation."

PVR 80 app881-05.doc

69. In "Board of Trustees of Port Vs. Pioneer Engineer & Anr."24

again considering the decisions of the Supreme Court in the case "Fateh

Chand v. Balkishan Das, 1964 SCR (1) 515"; "Maula Bux v. Union of

India (UOI), 1970 (1) SCR 928"; "ONGC Ltd. v. Saw Pipes Ltd., (2003)

5 SCC 705" accepted the legal position that in every case of breach of

contract, the person aggrieved by the breach is not required to prove

breach or actual loss/damages suffered by him before he can claim a

decree and the Court is competent to award a reasonable compensation

even if no actual damages is proved in support in consequence of the

breach, when the contractual clause prescribes the liquidated damages in

genuine pre-estimate. The observations in paragraphs 23 read thus:-

"23. After indicating that reasonable compensation is the principle

underlying Section 74 of the Contract Act, the Supreme Court clarified that though Section 74 says that whether or not actual damage is proved, the aggrieved party is entitled to receive

compensation thereby it only dispenses with proof of actual loss or damage. This does not justify the award of compensation when in consequence of the breach no legal injury at all has resulted, because compensation for breach of contract can be awarded only to make

good loss or damage which naturally arose in the usual course of things or which the parties know when they made the contract to be likely to result from the breach. Extracts from the judgment in Fateh Chand's case have been quoted in later judgments of the Supreme Court with approval and there could be no dispute that Fateh Chand is still a good law and holds the field.

70. In Kailash Nath Associates Vs. DDA (supra) was a case

where the Court was dealing with a 'forfeiture clause' whereby the

earnest money was forfeited. The Appellant therein was a successful

24 2006(5) Bom.C.R. 628

PVR 81 app881-05.doc

bidder and on deposit of 25% of the bid amount being the earnest money

had requested for extension of time for payment of balance amount, time

was extended. The Appellant also had sought consent of the Respondent

for payment of balance amount with 18% interest. For payment of the

balance 75% of the amount the case was forwarded to the Ministry of

Urban Development since the land was nazul land which was also agreed

by the Respondent. The Central Government had informed that the land

was not nazul land. However, three years after such information from the

Central Government, the Respondent cancelled the bid allotment

forfeiting the earnest money as the Appellant failed to pay the balance

amount. Interalia in this context the suit which was filed by the

Appellant seeking specific performance of the agreement and damages,

which was dismissed by the learned Single Judge of the High Court.

However ordering refund of earnest money on the ground that the

Respondent did not suffer any loss since the said plot was sold to a third

party for about three and half times higher price and cancellation of

allotment and consequent forfeiture of earnest money was made without

notice to the Appellant. The Division Bench, however, set aside the order

of the learned Single Judge relying on Section 74 of the Contract Act

holding that the proof of loss is not required to recover the earnest money.

In this context the Supreme Court considering the law on the issue

("Fateh Chand v. Balkishan Das, 1964 SCR (1) 515"; "Maula Bux v.

Union of India (UOI), 1970 (1) SCR 928"; "ONGC Ltd. v. Saw Pipes

PVR 82 app881-05.doc

Ltd., (2003) 5 SCC 705") and other decisions and the scheme of Section

73, 74 and 75 of the Contract Act held that compensation can be

awarded for damages or loss suffered. If damage or loss is not suffered,

the law does not provide for a windfall. The respondent had sold the plot

for a price three and half times more than the price at which it had sold to

the appellant and thus it was held that in the facts of the case, the

Respondent was not put to any damage but profited in their auction. The

terms and conditions of the auction contract stipulated that the earnest

money can be forfeited only in case of default, breach or non compliance

of any of the terms and conditions of the auction or on misrepresentation.

It was held that having extended the time twice by setting up High Power

Committee and also granting consent to payment of balance amount, the

respondent never insisted on payment of balance bid amount. Hence, it

was held that there was no breach of the terms and conditions of the

auction and the Respondent therefore had arbitrarily forfeited the earnest

money. In this context it was observed that Section 74 of the Contract

Act is sandwiched between Section 73 and 75 of the Contract which deals

with compensation for loss or damages caused for breach of the contract

and compensation for damage which a party may sustain through non

fulfillment of a contract, after such party rightfully rescinds such contract.

In that context analysing various authorities, the their Lordships in

paragraphs 43 and 44 held thus:-

"43. On a conspectus of the above authorities, the law on compensation for

PVR 83 app881-05.doc

breach of contract under Section 74 can be stated to be as follows: 43.1. Where a sum is named in a contract as a liquidated amount payable by way of damages, the party complaining of a breach can

receive as reasonable compensation such liquidated amount only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the Court. In other cases, where a sum is named in a

contract as a liquidated amount payable by way of damages, only reasonable compensation can be awarded not exceeding the amount so stated. Similarly, in cases where the amount fixed is in the nature of penalty, only reasonable compensation can be awarded not exceeding the penalty so stated. In both cases, the liquidated amount or penalty is the

upper limit beyond which the Court cannot grant reasonable compensation. 43.2 Reasonable compensation will be fixed on well known principles that are applicable to the law of contract, which are to be found inter alia in Section 73 of the Contract Act.

43.3 Since Section 74 awards reasonable compensation for damage or loss caused by a breach of contract, damage or loss caused is a

sine qua non for the applicability of the Section. 43.4. The Section applies whether a person is a plaintiff or a defendant in a suit.

43.5 The sum spoken of may already be paid or be payable in future.

43.6 The expression "whether or not actual damage or loss is proved to have been caused thereby" means that where it is possible to prove actual damage or loss, such proof is not

dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount

named in the contract, if a genuine pre-estimate of damage or loss, can be awarded.

43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the

terms and conditions of a public auction before agreement is reached, Section 74 would have no application.

44. The Division Bench has gone wrong in principle. As has been pointed out above, there has been no breach of contract by the appellant. Further, we cannot accept the view of the Division Bench

that the fact that the DDA made a profit from re-auction is irrelevant, as that would fly in the face of the most basic principle on the award of damages - namely, that compensation can only be given for damage or loss suffered. If damage or loss is not suffered, the law does not provide for a windfall." (emphasis supplied)

71. The decision of the learned Single Judge (Ashok Kumar

Ganguly, J.) of the Calcutta High Court in "Hindustan Paper Corp. Vs.

PVR 84 app881-05.doc

Wellbrines Chemicals P.Ltd"(supra) concerned a claim for demurrage as

made on behalf of the disponent only, who had chartered a vessel from

M/s.Shipping Corporation of India Ltd. under a charterparty agreement.

There was a demurrage clause. There was inter alia a dispute under the

contract which was referred for arbitration. The Arbitrators had awarded

Rs.11,83,645.80 towards demurrage and interest to be paid thereon by

the petitioner. In assailing the award, the petitioner contended that the

Arbitrators have awarded demurrage as liquidated damages which was

contrary to the express provisions of the Contract Act. On this

background, the learned Judge applied the test of commercial practice

and referring to the decision of the Supreme Court in the case "Fateh

Chand v. Balkishan Das" (supra) and "Union of India v. Raman Iron

Foundry" (supra) and referring to the English law on 'demurrage'

observed that the concept of demurrage is capable of two shades of

meaning. Firstly the demurrage means a sum agreed by the charterer to

be paid as liquidated damages for the detention of the ship beyond its

stipulated or reasonable time for loading or unloading as described in

"Scrutton on Charterparty, 20th Edition, page 298". It was observed that

the other meaning which can be attributed to the concept of demurrage is

that demurrage means nothing more than a liquidated sum payable by the

charterer to the owner for the further time taken in loading or unloading

after the expiry of the lay time. It was observed that in view of this second

interpretation the demurrage is nothing but a liquidated price payable to

PVR 85 app881-05.doc

the owner for using the ship beyond the period of lay time and on this

interpretation, demurrage sounds more in debt than in damages. The

learned Judge referred to the observations of the Queen's Bench in the

case of "Clink v. Rod Ford", reported in "(1891)1 Queens' Bench, 625".

In this context the learned Judge has made the following observations:-

"103. From a perusal of the award, it appears that in the award, the Joint Arbitrators have noted submission of the petitioner that in English Law demurrage is a form of liquidated damage. But, the award does not say whether the said contention is correct also in the context of the Indian Law.

104. This Court is of the view that even under the English Law, the

concept of demurrage is capable of two shades of meaning. On a strict meaning, demurrage means a sum agreed by the charterer to be paid as liquidated damages for the detention of the ship beyond its stipulated or reasonable time for loading or unloading (see Scrutton

on Charterparty, 20th Edition, page 298}.

105. Another meaning is also attributed to the concept of demurrage. The second interpretation of this concept is that demurrage means nothing more than a liquidated sum payable by the charterer to the owner for the further time taken in loading or unloading after the

expiry of the lay time. In view of the second interpretation, demurrage is nothing but a liquidated price payable to the owner for

using the ship beyond the period of lay time. On this interpretation, demurrage sounds more in debt than in damages. The learned counsel for the respondent in developing this argument has placed reliance on a decision of the English Court of Appeal in the case of

Clink v. Rod Ford, reported in (1891)1 Queens' Bench, 625. At page 630 and 631 of the report, Lord Justice Brown held as follows :

"Now the word "demurrage" has a primary and a secondary sense and with regard to the construction of that word, I will take the language used by Cleasby J. in Lodchart v. Falk (Law Rep. 10 Ex. 132 at l35) -- a case which it is impossible I think

to distinguish from the present -- as expressing shortly that which no doubt is expressed in many other judgments, namely, the way in which we ought to deal with the question of interpretation. He says : The word "demurrage" no doubt properly signifies the agreed additional payment (generally per day) for an allowed detention beyond a period either specified in or to be collected from the instrument; but it has also a popular and more general meaning of compensation for undue detention, and from the whole of each charterparty containing the clause in question we must collect what is the proper meaning to be assigned to it", So far as to the meaning of the word "demurrage". It is an elastic word; it has a strict

PVR 86 app881-05.doc

sense, but it can be stretched beyond its strict sense.....The word "demurrage" having two meanings we must look at the Charterparty to see if it is used in the strict sense or in the

more popular and elastic sense."

106. Therefore, the principle, which is deducible from the above passage is that the question whether the stipulation relating to the

demurrage sounds more in damage than in debt is a question which falls within the domain of interpretation of the particular clause in the charterparty. In the instant case, the stipulation relating to the demurrage is contained in clause 25 of the Charterparty. The said clause is set out below :

"Clause 25. If the vessel is detained longer than the time allowed for loading/discharging, demurrage shall be paid by charterers to owners at the rate of Rs. 1,50,000/- (Rupees One Lakh Fifty thousand only) per running day or pro-rate

and despatch money for all working time saved at the loading/discharge Port will be paid to charterers at half the demurrage rate per running day or pro-rate."

ig (emphasis supplied)

The learned Judge also referred to the decision of the

Supreme Court in the case "M/s. Raichand Amulakh Shah v. Union of

India and Ors."(supra) which case pertained to a claim for demurrage

under section 46C of the Railways Act, 1890. The learned Judge also

referred to the decisions of the Supreme Court in the case "Consumer

Education and Research Centre Vs. Union of India"25, "United

Breweries Ltd. V. The State of Andhra Pradesh" 26 and "Chunilal Mehta

V. Century & Manufacturing Co.Ltd.27" has observed thus:-

"108. The statutory law in India also shows that the term demurrage has been employed more in the sense of liquidated charge or debt rather that as liquidated damages. Reference, in this connection, may be made the Constitution Bench decision of the Hon'ble Supreme Court in the case of M/s. Raichand Amulakh Shah v. Union of India and Ors., reported in AIR 1964 SC 1468. In that case, Section 46C of

25 AIR 1995 SC 922 26 AIR 1997 SC 1316 27 AIR 1962 SC 1314

PVR 87 app881-05.doc

the Railways Act, 1890 came up for consideration. In para 7 sub- para (ii) at page 1271 of the report, the Hon'ble Supreme Court inter alia, held as follows :-

"Demurrage is therefore a charge levied on the goods not unloaded from the wagons within the free time of six daylight hours and wharfage is the charge levied on goods not removed

from the railway premises after the expiry of the free time allowed for that purpose. Wharfage and demurrage are, therefore, charges levied in respect of goods retained in the wagons or in the railway premises beyond the free time allowed for clearance under the rules."

.....

112. This Court finds that in none of these decisions cited by the learned counsel for the petitioner, there is any observation or any suggestion by the learned Judges that the person who is receiving

liquidated damages is first required to give the detailed evidence of proof of damage in support of his case. In fact, cases of liquidated

damages of the kind which are stipulated in the charterparty between the parties, are those cases where proof of actual damage is practically not possible. But then this stipulation in the charterparty of liquidated damages cannot be called a penalty. Liquidated damages

is a genuine pre-estimated sum of damages where proof of damage is not possible or is very onerous. In such a situation, the liquidated damages is adopted as the reasonable compensation. The concept of penalty is a different thing and in essence is a payment of money stipulated as in terrorem of the offending party, but the essence of the

liquidated damages is a genuine and reasonable pre-estimated damages. In order to acquire the character of penalty, the sum

stipulated must be proved to be extravagant and unconscionable. But here, no such evidence has been laid by the petitioner before the Arbitrator that the stipulated amount mentioned in clause 25 is either extravagant or unconscionable. In fact, no such evidence could be led as the amount was a mutually agreed reasonable sum.

113. Reference, in this connection, may be made to the judgment of the Hon'ble Supreme Court in the case of Chunilal Mehta v. Century & Manufacturing Co. Ltd., . In that matter, questions came up on a contract between the Company and Chunilal appointing Chunilal as its Management Agent. It has provided in that contract that in the

event, the Managing Agency is terminated, the Managing Agent will be entitled to receive from the company as compensation by way of liquidated damages for the loss of appointment and the same amount is not less than Rs. 6,000/- per month for the unexpired portion of the agency. Considering the compensation for termination which was provided for payment to Chunilal, the learned Judges of the Hon'ble Supreme Court in par 11 at page 1319 of the report, after constructing Sections 73 and 74 of the Contract Act, held that where the parties have themselves provided for the precise amount of damages that would be payable that party must be 'deemed to exclude right to claim an unascertained sum of money as damages'. It was also held in the said para 11 that if the Court accepts that the

PVR 88 app881-05.doc

parties intended to confer on the Managing Agent merely a right under Section 73 of the Court Act, in that case, 'the entire clause would be rendered otiose'. Therefore, the requirement of proof under

Section 73 of Contract was held not applicable to such a situation. Therefore, there is no difference in the Indian Law either. And the Hon'ble Supreme Court upheld the award of a sum of Rs. 6,000/- to

the Agent for the unexpired period of the term of Agency and the interest thereon."

72. We may also usefully refer to the decision in the case of

"Suisse Atlantique Societe D'Armement Maritime S.A. Vs. N.V.Rotterdamsche

Kolen Centrale"28 by a charterparty dated December 1956, the respondents

agreed to charter a vessel from the appellants for the carriage of coal from

the United States to Europe. The charter was to remain in force for a total

of two years consecutive voyages. The vessel had with all possible

dispatch to sail and proceed to a port in the United States and, having

loaded a cargo of coal, proceed with all possible dispatch to a port in

Europe. She had to be loaded at a specified rate per running day and, if

she was detained beyond the loading time, the respondents were to pay

$1,000 a day demurrage. Similarly, if she were detained longer than was

required to unload her at the stipulated rate per day and that was not due

to strikes, etc., or other causes beyond the control of the respondents, the

respondents, who were to discharge the cargo, were to pay demurrage at

the rate of $1,000 a day. In September,1957, the appellants regarded

themselves as entitled to treat the charterparty as repudiated by reason of

the respondents' delays in loading and discharging the vessel. That was

28 1966(2) the All England Law Reports 61

PVR 89 app881-05.doc

not accepted by the respondents, and, in October,1957, the appellants and

respondents agreed, without prejudice to their dispute, that from

thenceforward the charterparty would be carried out. Between then and

the end of the charter the vessel made eight round voyages. The

appellants alleged that, due to delays in loading and unloading for which

the respondents were responsible, the vessel did not make as many

voyages as she should have done, with the result that they were deprived

of the freights they would have earned on the additional voyages and,

after giving credit for the demurrage payments received by them, claimed

damages from the respondents. The appellants contended that, if the

delays for which the respondents were responsible, were such as to entitle

the appellants to treat the charterparty as repudiated, the demurrage

provisions did not apply and they were entitled to recover the full loss that

they had suffered. On this conspectus their Lordships of House of Lord

held that the appellants, having elected in October,1957, to affirm the

charterparty, continued bound by its provisions, including the demurrage

provisions, and on the true construction of the charterparty the demurrage

provisions (Clause 3) were not to be regarded as limiting the respondents'

liability but were provisions for payment of agreed damages, and on proof

of breach by detention (within clause 3) the appellants were entitled only

to the agreed damages, and not to damages for loss of profit, i.e., loss of

freight, notwithstanding that the breach was deliberate and that the loss

of profit was willfully caused, if those were the facts. Lord Viscount

PVR 90 app881-05.doc

Dilhorne and Lord Upjohn observed that there is a difference between a

fundamental breach of contract and breach of a fundamental term; in the

case of a fundamental breach the question is whether, having regard to

the character of the breach, performance has become something totally

different from what the contract contemplated, but a breach of a

fundamental term goes to the root of the contract and, without regard

having to be had to other circumstances, entitles the party not in breach to

repudiate the contract.

73. In this context the learned Counsel for the Respondent has

appropriately placed reliance on the decision of the English Court in

"(1)Fal Oil Co.Ltd., (2) Credit Agricole Indosuez (Suisse). -and-.

Patronas Trading Corporation SDN BHD"(Neutral Citation Number:

((2004)EWCA Civ 822)"(supra) wherein after the exhaustive study of the

earlier case law on the subject, the Court summarised its findings in

paragraph 42 of the judgment. The Court held that the question of

whether or not demurrage in a sale contract was an indemnity or an

independent provision is a matter of construction of each such contract. If

the contract makes any reference to or incorporates the demurrage

provisions of the Charterparty or other third party contract (e.g.

"demurrage as per Charterpary") that would be an indication that

demurrage was only indemnificatory. On the other hand in the absence of

PVR 91 app881-05.doc

any such cross-reference the natural inference would be that demurrage

was independent. In the latter case there was nothing in law preventing a

seller from making a profit from the demurrage provision in its sale

contract. Lord Justice Mance considering the English decision in

paragraph 42 has observed as under:-

"42. This examination of the authorities leads to conclusions, which I can summarise as follows:

i) Provisions in a sale contract regarding laytime and demurrage should be approached without any pre-

conceptions or presumption as to their likely nature. That follows from general principle, as well as from the passage

quoted above from Houlder Bros.

ii) The scope and effect of such provisions is a question of construction. See Suzuki

iii) The underlying rationale of any sale contract demurrage provision is that the receiving party may suffer loss under a charter or other third party contract. However, this is consistent with the provision operating

either by way of indemnity or independently. An independent provision can, subject to the law on penalties,

be justified as a genuine pre-estimate of the receiving party's exposure.

iv) Although the authorities distinguish generally between (a) provisions operating as an indemnity and (b)

independent provisions, the precise nature and effect of any demurrage provision depends upon the context and wording of the particular provisions, including the scope of any reference to or incorporation of the demurrage provisions of any charterparty or other third party

contract.

v) In the absene of any cross reference in the said contract provisions to a charterparty or other contract under which demurrage liability may arise, the natural inference is that the sale contract fall within category (b); of Houlder Bros. And also the dicta in Ets. Soules. But it is of course conceptually possible to have an implied as well as an express cross-reference of this nature.

vi) In cases where there is some form of cross-reference to a charterparty or other third party contract under

PVR 92 app881-05.doc

which demurrage liability may arise, the nature, purpose and effect of the cross-reference become critical. There are two broad situations, corresponding with categories (a)

and (b) mentioned in conclusion (iv) above. In the first, the sale contract creates a liability for demurrage by way

of "indemnity", that is to pay only if and so far as such a liability exists under the charter or other third party contract (although Suzuki is the only clear reported example in the authorities). It would no doubt also be

conceptually possible for sale contract provisions to operate by way of "indemnity", but subject to the additional qualification or precondition that any liability for demurrage can and should only arise so far as consistent with other sale contract terms (e.g. as to the

length of permissible laytime). But such a construction is likely to lead to the practical problems identified in

Houlder Bros. And the authorities provide no positive example of The second situation (exemplified by a number of authorities) is one where the sale contract provisions

simply refer to or incorporate provisions of a charterparty or other third party contract (or at least one of such provisions e.g. as to the rate of demurrage) in an otherwise independent sale contract scheme. The extent of

any such reference or incorporation is then itself of course a matter of construction."

74. Thus adverting to the enunciation of law as laid down in the

above decisions it is clear that in the context of liquidated damages as

agreed between the parties, when the contract is broken, the party who

suffers by such breach would be entitled to receive compensation for any

loss which would naturally arise in the usual course of things from such

breach. The claimant would be required to prove his damage in general

sense as the contract made by the parties estimating their damages is in

itself evidence, unless there is some other evidence to show that the

subject claim was unreasonable. The parties when agree to an amount to

PVR 93 app881-05.doc

be paid in case of a breach, in such a case, there may not be any necessity

of leading evidence for proving damages, unless the Court arrives at a

conclusion that no loss is likely to occur because of such breach. More

particularly when an agreement is executed by the experts in the field and

when an agreement is so arrived in their commercial wisdom, it cannot be

construed that the intention of the parties was different from what they

have agreed in having such a stipulation in the contract. The burden in

such a case would be on the party who contends that the stipulated

amount in the agreement is not reasonable compensation, to prove the

same. (see para 46 "ONGC Vs. Saw Pipes" (supra)). The expression as

used in Section 74 "whether or not actual damage or loss is proved to

have been caused, thereby", means that where it is possible to prove

actual damage or loss, such proof is not dispensed with and that only in

cases where damage or loss is difficult or impossible to prove that the

liquidated amount named in the contract, if a genuine pre-estimate of

damage or loss, can be awarded. (see para 46.6 Kailash Nath Associates

Vs. DDA)

75. We may also note that the decision of His Lordship Ashok

Kumar Ganguly, J. in the case Hindustan Paper Corp. Vs. Wellbrines

Chemicals P.Ltd. (supra), in our opinion, does not deviate from the

accepted principle, that demurrage is in the nature of liquidated damages,

PVR 94 app881-05.doc

however additionally it only recognizes the manner in which it is

commercially understood in a charterparty agreement. In that context His

Lordship has made the observations relying on the English Law that as to

whether the stipulation relating to the demurrage sounds more in damage

than in debt, is a question which falls within the domain of interpretation

of the particular clause in the charterparty. His Lordship interpreting

Clause 25, which fell for consideration in the said decision, made the

observations that in the facts of the case it was not contended on behalf of

the petitioner that the demurrage clause sounds only in damage and not

in debt. His Lordship observed as to whether in a given case the

demurrage would be required to be considered as liquidated damages or a

fixed charge is required to be tested in the context of the agreement

between the parties in regard to the demurrage and such interpretation

would be required to be derived on the facts of each of such case. We are

in agreement with these observations of His Lordship. We are, therefore,

of the opinion that a straight jacket argument that the demurrage is in the

nature of fixed charge would not be acceptable and it would be required

to be tested in the context of the agreement between the parties. We may

so observe, also for the reason that in respect of certain enactments for

example under the Majour Port Trust Act or the Railways Act as their

Lordships were concerned, in the case of M/s.Raichand A. Shah vs.

Union of India (supra) the Court considered demurrage as fixed charge in

the context of Railways Act. Thus the position may differ from contract

PVR 95 app881-05.doc

to contract. However, this would not displace the well established concept

of demurrage being in the nature of liquidated damages as understood in

a commercial contract and as extensively discussed by us above.

76. We may therefore, answer the questions as framed by us in

para 42 as under.:

(i) The claim for demurrage is in the nature of liquidated

damages and in some contracts by virtue of statutory provisions as for

example in Railways Act as considered by the Supreme Court in

M/s.Raichand A. Shah vs. Union of India (Supra) can be in the nature of

a fixed charge. Thus, the test to be applied would vary and depend on the

nature of the agreement and how the parties have understood such a

clause under the contract. The endeavour of the Court would be to gather

the intention of the parties not only from the words of the agreement but

also the understanding of the same by the parties who are themselves

expert in the field and as reflected in the pleadings.

(ii) The contention of the Appellant that the respondent was

required to prove that he has suffered any loss and/or he has actually paid

the vessel-owner in making a claim for demurrage is misconceived and

cannot be accepted for the reason as we have extensively set out including

our observations on the applicability of the test laid down by Ameer Ali, J.

in Mahadeoprasad Vs. Siemens (India) Limited (supra), on the contract

itself being the evidence estimating the damages. In fact the appellant

PVR 96 app881-05.doc

never contended before the Arbitral Tribunal that the claim of the

Respondent was unreasonable and if the Appellant was to so contend, the

burden to prove that it was unreasonable, was on the appellant (see para

46 ONGC Vs. Saw Pipe (supra))

77. We are thus afraid that the contention of the appellant on the basis

of the decision in Kailash Nath (Supra), that the Respondent would be

required to prove the damage and only thereafter the respondent would

be entitled for a reasonable compensation, cannot be accepted. This is for

two fold reasons firstly in Kailash Nath their Lordships in para in

paragraph 43.1 have clearly held that where a sum is named in a contract

as a liquidated amount payable by way of damages, the party complaining

of a breach can receive as reasonable compensation such liquidated

amount only if it is a genuine pre-estimate of damages fixed by both

parties and found to be such by the Court. Once this is the test as laid

down by their Lordships and clearly applicable to the facts of the case

then the immediate question is whether or not the appellant had brought

any material before the Arbitral Tribunal to show that it is not a genuine

pre-estimate of the damages. (see para 46 "ONGC Vs. Saw Pipes"

(supra)). We may observe with certainty that as seen from the

correspondence and the succinct observations of the learned arbitrator,

that the Appellant never disputed the demurrage amount as fixed qua

each of the vessels, much less to place any material contrary to the claim

PVR 97 app881-05.doc

of the respondent and that the same was not a genuine pre estimate of the

damages. Further in the facts of the present case we do not see how the

observation of their Lordships in paragraph 43.6 would not help the

Respondents. As noted above the contract in question is between a foreign

party (respondent) and a Indian party (appellant). The terms of

demurrage and the amount thereof at the maximum pre-estimated and

fixed at US$ 8000 and as regards each of the individual shipments, the

same is confirmed by letters between the agents and the Appellant which

is within the amount so fixed in the demurrage clause 10(v). If that be the

case then to dislodge such an agreed figure, there ought to have been

some material brought on record by the Appellant that the same is not the

genuine pre-estimate. In any event the principles as laid down by Ameer

Ali J. in Mahadeoprasad Vs. Siemens (India) Limited are clearly

applicable in the fact situation, as the agreement between the Appellant

and the Respondent estimating their damages would itself be an evidence

in the absence of no other evidence as regards the claim amount to be

unreasonable.

It can also be very well be said in the facts of the present case

and considering peculiarity of the contract, the pre-estimate of the amount

of demurrage/damage, as agreed between the parties is also required to

be accepted, for the reason that such damage or loss was impossible to

prove. We are in complete agreement with the contention as urged on

behalf of the Respondent that considering the nature of the contract being

PVR 98 app881-05.doc

a shipping contract, having peculiar traits on a variety of aspects and the

parties in that context having agreed to the rate of demurrage,

considering several factors which also would have elements of

international commerce and trade, it would not only be unreasonable but

wholly unrealistic and impossible to call upon the respondent to prove the

loss suffered by it. In fact, in our opinion, Clause 10(v) of the Contract

reflects the certainty with which the parties expected to position

themselves on the issue of demurrage. The very purpose of agreeing to

the specified amount of demurrage was to avoid litigation and complexity

in assessing damages in that regard. The present case would completely

fall within the examples of cases as discussed in paragraph 69 of the

judgment in ONGC Vs. Saw Pipes (supra) being cases where it is very

difficult to prove actual loss. Thus the respondent had become entitled for

the demurrage as pre-estimated. In our opinion and with quite certainty

the appellants contentions in this context are completely an afterthought

and an attempt by hook or crook to avoid the liability under the contract.

We may also observe that to the misfortune of the Respondent despite a

crystal clear position on their entitlement for the demurrage claim, the

Appellant has made the Respondent suffer for last sixteen years to

deprive them of this legitimate entitlement.

78. Having considered the Award and the impugned Judgment of

the learned Single Judge and the rival contentions, we may thus

PVR 99 app881-05.doc

summarise our observation and conclude that the case of the Appellant

firstly that clause 10(v) of the Contract was in the nature of indemnity

cannot be accepted, as noted by us there is no whisper in the clause 10(v)

of the Contract that the liability to pay demurrage is depending upon the

demurrage being paid by the Respondent. In any case, there was no

privity of contract between the Appellant and the owner of the vessel.

Further the Appellant also understood clause 10(v) is not providing for

indemnity is also abundantly clear from the evidence of Mr.Patwardhan,

Vice President, who clearly admitted that as per the commercial practice

being followed by the Appellant, the claim for demurrage was on the basis

of three documents, firstly statement of facts, secondly verification thereof

and necessary corrections thereof and thirdly the charter party agreement.

According to his evidence, these are generally the documents which would

be considered while determining whether demurrage is to be paid or not.

It is significant that in the entire correspondence, there is no indication

whatsoever by the Appellant to even remotely suggest that they have

understood the clause 10(v) being in the nature of indemnity as at no

point of time and in the normal course by dealing such proof of payment

of demurrage to the vessel owner was sought for. There was no denial of

the fact that there was COA agreement between the Respondent and the

vessel owner. The fallacy in the argument is completely exposed from the

specific stipulation of the second part of clause 10(v) which requires that

demurrage or despatch should be settled within 60 days after lay time

PVR 100 app881-05.doc

statement is submitted with supporting documents. There is no material

which would support the contention of the Appellant that the clause

10(v) being in the nature of indemnity. We may observe that the

Appellant being quite sure that they would fail on their contention that

payment of demurrage would be in the nature of indemnity under clause

10(v), at the fag end of the arbitration proceedings, without any pleadings

in that regard, in their final submissions agitated the issue that the

demurrage was in the nature of liquidated damages, to contend that

unless the Respondent proves that the damages are occurred to them by

making payment to vessel owner the Respondent is not entitled for the

said claim. However, in our clear opinion as the law in that regard would

stand that as we have considered above, these submissions could not have

availed to the benefit of the Appellant. This is for two fold reasons. The

Arbitral Tribunal has allowed the claim of the Respondent interpreting the

terms of the contract. For the purpose of interpretation of clause 10(v) of

the contract, the learned Arbitrator has taken into consideration the

intention of the parties which is covered not only in the words as they are

used in the agreement but also on the basis of the several facts which have

come on record on the basis of the evidence. It is by now well established

that when the contract is broken, the party who suffers a breach is entitled

to receive compensation for any loss which naturally would arrive in the

usual course of things from such breach. In the present case, the Appellant

knew when they entered into a contract with the Respondent, that a

PVR 101 app881-05.doc

particular loss is likely to result from such breach and therefore the

appellant agreed for payment of demurrage charges at the agreed rate. If

such is the situation, then, as their Lordships have observed in paragraph

46 of the decision in the case "Oil and Natural Gas Corporation Ltd. Vs.

SAW Pipes Ltd." there was no necessity of leading evidence for proving

damages, unless the Court arrives at the conclusion that no loss is likely to

occur because of such breach. This is surely not a case where the

Appellant has in any manner demonstrated that the

amount/compensation which was asked by the Respondent was not a

reasonable amount/compensation. There was no material to support such

a contention. The observations in paragraph 46 of the decision in the case

Oil and Natural Gas Corporation Ltd. Vs. SAW Pipes Ltd.(supra) as

noted by us above are therefore applicable in full force.

79. Thus, in our opinion, applying the well settled principle of

interference in an arbitration award, we may observe that when there are

two equally possible or plausible views of interpretation on a clause in the

contract, it was legitimate for the learned Arbitrator to accept the one or

the other interpretation. The parties being commercial men have also

understood the demurrage clause in the manner as it is writ large as borne

out from the facts. Thus, in this situation we cannot agree with the

contention as urged on behalf of the Appellant that the interpretation of

clause 10(v) as made by the learned Arbitrator and accepted by the

PVR 102 app881-05.doc

learned Single Judge, in any manner requires to be disturbed applying the

test of interference as permissible under Section 34 of the Arbitration and

Conciliation Act. It is well settled that the interpretation of the contract

was within the jurisdiction of the Arbitrator and unless there is a manifest

disregard of the contractual provision or the learned Arbitrator commits

an apparent error of law which goes to the very jurisdiction of the

Arbitrator, the Court would be loath to interfere in the arbitral award. We

are thus of the considered opinion that this is not one of the cases wherein

such manifest error or perversity in the award of the learned Arbitrator

has occurred.

80. As regards the counterclaim as made on behalf of the

Appellant, we may observe that though it was argued before the learned

Single Judge and the learned Single Judge has rejected the contention of

the appellant, no submissions were made in that regard before us.

However, in the written submissions some contentions have been urged

that the learned Arbitrator ought to have allowed the counterclaim. In

this situation, we do not propose to have any detail discussion on this

issue. In any event for sake of completeness , we may observe that we are

in complete agreement with the reasoning on the counterclaim as made

by the learned Arbitrator and also of the learned Single Judge. The issue

on counterclaim is as regards option cargo. It was completely a factual

issue. The learned Arbitrator has recorded a finding of fact that the

PVR 103 app881-05.doc

appellant was required to exercise an option in relation to the option

cargo which was not exercised by the appellant within the time allowed

by the contract. As rightly observed by the learned Single Judge, a finding

of fact could not have been disturbed in the limited jurisdiction under

Section 34 of the Arbitration Act in the absence of any perversity or error

apparent on the face of the record or that the finding suffers from the

violation of principles of natural justice. It was not a case of the appellant

that the learned Arbitrator has not applied his mind. The learned

Arbitrator has recorded a finding possible to the record, in the facts and

circumstances of the case. This findings therefore in any event cannot be

disturbed. The contention on the counterclaim is therefore, misconceived

and has been rightly rejected by the learned Single Judge.

81. Before concluding we may observe that the parameters of

jurisdiction in interference of Arbitral Award under Section 34 read with

Section 37 of the Arbitration Act are well settled. This Bench in a recent

decision in the case "Waverley Pvt. Ltd. Vs. Diversey India Pvt.Ltd."29

considering the decision of the Supreme Court in "M/s.Chebrolu

Enterprises Vs. Andhra Pradesh Backward Class Co-op. Finance Corpn.

Ltd." 30, in paragraph 11 held as under:-

"11. Therefore, taking overall view of the matter and considering the power and scope of Appellate Court under Section 37 of Arbitration Act and we have also noted that

30 (2015)12 SCALE 207

PVR 104 app881-05.doc

the reason provided by the learned Judge is well within the frame work of law and the record. Recently, the Supreme Court in M/s.Chebrolu Enterprises Vs. Andhra Pradesh

Backward Class Coop. Finance Corpn. Ltd. in Civil Appeal No.8918/2015 on 28.10.2015 has reinforced thus

"This Court or even the Appellate Court would not look into the finding of facts unless they are perverse." No case is made out to interfere with the impugned judgment."

82. In view of the above deliberation we may observe with

certainty that the learned Single Judge has appropriately dismissed the

Appellant's petition under Section 34 of the Arbitration Act. Resultantly,

the appeal fails and is accordingly rejected.

               (G.S.KULKARNI, J.)                       (ANOOP V. MOHTA, J.)
          
       







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter