Citation : 2016 Latest Caselaw 7184 Bom
Judgement Date : 14 December, 2016
1 jg.wp4258.15.odt
THE HIGH COURT OF JUDICATURE AT BOMBAY
: NAGPUR BENCH : NAGPUR.
WRIT PETITION NO. 4258 OF 2015
M/s. Sunflag Iron & Steel Company Limited
Through its Authorized Signatory
having its registered office at 33,
Mount Road, Sadar, Nagpur- 440001. ... Petitioner
VERSUS
Gurudatta Enterprises
Through its Proprietor
Mr. Tapankumar S/o Pramodnath Ojha,
Resident of Near Sunflag School,
Bhandara Road, Bhandara. ... Respondent
-------------------------------------------------------------------------------------------------
Shri A. C. Dharmadhikari, Advocate for the petitioner
Shri N. N. Thengre, Advocate for the respondent
------------------------------------------------------------------------------------------------------------------------
CORAM : PRASANNA B. VARALE, J.
JUDGMENT RESERVED ON : 7-3-2016
JUDGMENT PRONOUNCED ON : 14-12-2016
JUDGMENT
Rule. Rule made returnable forthwith.
2. The petitioner challenges the order passed by the learned
Civil Judge Senior Division, Bhandara dated 6-7-2015 in Regular
Darkhast No. 39/2004.
3. Brief facts giving rise to the present petition can be
summarized as follow.
2 jg.wp4258.15.odt
The petitioner - company engaged the respondent as work
contractor. Initially, the respondent - company was operating in the
name of Dharini Electricals. Subsequently, the respondent - company is
operating with the name of Gurudatta Enterprises. From year 1991 to
2004, the respondent - company was engaged by the petitioner as job
work contractor. The last contracts between the petitioner and
respondent was executed for the period from 1-7-2002 to 31-3-2003 and
from 1-3-2003 till 31-3-2004. The work contract rescinded with efflux
of time is the case of the petitioner - company. The respondent
instituted two suits against the petitioner-company, namely, Special
Civil Suit No. 112/2004 (old number) (new number 22/2009) for
permanent injunction and return of materials as per Schedule 'A' and 'B'
and another suit bearing no. 24/2009 for recovery of money. Special
Civil Suit No. 112/2004 was decreed partially and an order was passed
on an application thereby permitting the respondent-company to take
back the possession of the articles in Schedule 'A' and 'B'. The
respondent filed hakrasi form, Exhibit No. 1. The said proceeding was
registered as Regular Darkhast No. 39/2004. On an application seeking
review filed by the petitioner, the order below Exhibit 5 thereby
permitting the respondent to take possession of the articles in Schedule
A and B subject to production of list of articles by the respondent and
3 jg.wp4258.15.odt
verification by Security Department of the petitioner-company was
passed. As there was some dispute in respect of the material specified in
Schedule A and B, in view of an objection raised by the petitioner and in
view of an application submitted by the respondent, the order came to
be passed for appointment of the Commissioner. Learned trial Court
appointed Advocate Shri Raut as Commissioner and the Commissioner
was directed to trace the account of the petitioner-company from 1991
to 2004. On an application for amendment submitted by the petitioner,
order came to be passed dated 3-12-2005 thereby directing the
Commissioner to verify the accounts and records for 10 years i.e. from
1994 to 2004. Special Civil Suit No. 22/2009 (old number 112/2004)
was decided by the judgment and decree and thereby the petitioner-
company was directed to return the tools, articles and machinery 1 to 30
and A, B and C described in Commissioner's Report, Exhibit 179. The
respondent filed First Appeal No. 284/2014 in challenge to the
judgment and decree passed in Special Civil Suit No. 22/2009 and the
same is admitted by order dated 29-4-2015. The respondent filed an
application for attachment warrant in Regular Darkhast No. 39/2004.
The same was replied by the petitioner-company. On 1-7-2014, the
learned Executing Court allowed the application and directed only to
attach those articles which are specified in the judgment and decree
4 jg.wp4258.15.odt
dated 4-5-2013. Learned Executing Court gave directions in the said
order to refer the Commissioner's report. The respondent moved two
applications in Regular Darkhast No. 39/2004, one for grant of bailiff
and another for police protection. The petitioner contested the
applications by submitting that the respondent falsely made claim for
possession of heavy machinery which was neither part of judgment and
decree dated 4-5-2013 nor part of the report of the Commissioner. By
order dated 6-7-2015, learned Executing Court allowed the respondent
to take over possession of machine which belongs to the petitioner-
company is the submission of the petitioner.
4. Shri Dharmadhikari, learned counsel for the petitioner
referred to the various documents placed on record, namely, the
judgment and decree passed by the Court below, the report of the
Commissioner submitted to the Court, the darkhast application filed by
the respondent-company, certain interim orders passed by the lower
Court during the pendency of the suit and the final judgment and decree
passed in Special Civil Suit No. 22/2009. It was vehemently
submitted by the learned counsel Shri Dharmadhikari that the
documents, namely, the judgment and decree and the Commissioner's
report only referred to Schedule A and B and the articles under caption
5 jg.wp4258.15.odt
C and in these documents, there is nowhere mention of the machinery
claimed and sought to be recovered from the petitioner-company.
Shri Dharmadhikari, learned counsel then submitted that even though
the suit filed by the respondent is decided by judgment and decree i.e. in
favour of the respondent-company, the respondent had filed first appeal
challenging the said judgment and decree. It was the further submission
of Shri Dharmadhikari, learned counsel that the respondent-company
wanted to place reliance before the Court below on certain interim
orders to substantiate his claim. Shri Dharmadhikari, learned counsel
submitted that as the suit filed by the respondent was decided by
judgment and decree, the interim orders are merged in final order and
no reliance could have been placed on interim orders to support the
claim. Shri Dharmadhikari, learned counsel by inviting my attention to
the orders passed by the learned lower Court and placed on record
submitted that the learned trial Court observed in the order that all
articles referred to in Schedule A and B in the plaint filed by the
respondent were not found on the spot. Shri Dharmadhikari, learned
counsel then submitted that the respondent for the first time made
submissions in respect of the machinery when the applications were
moved by him in regular darkhast for grant of bailiff and police
protection. It was submitted by Shri Dharmadhikari, learned counsel
6 jg.wp4258.15.odt
that from the institution of suits i.e. from year 2004 till the decision of
the suit i.e. judgment and decree dated 4-5-2013, the respondent never
raised the claim in respect of the said machinery. It was the submission
of Shri Dharmadhikari, learned counsel that the learned Executing Court
while allowing the applications filed by the respondent exceeded its
jurisdiction. It was the submission of Shri Dharmadhikari, learned
counsel that it is the settled position of law that the Executing Court
possessed of only limited power i.e. the execution of the judgment and
decree and the Executing Court cannot travel beyond this power and
grant some relief to the decree holder which is not the part of the
judgment and decree. Shri Dharmadhikari, learned counsel placed
reliance on the judgment of the Apex Court in the case of Kanwar
Singh Saini Vs. High Court of Delhi reported in (2012) 4 SCC 307.
5. Per contra, Shri Thengre, learned counsel for the
respondent supported the order impugned in the petition. It was the
attempt of learned counsel Shri Thengre to submit before this Court that
the complete and necessary material is not placed before this Court by
the petitioner. It was the attempt of learned counsel Shri Thengre to
submit before this Court that as the lower Court passed an order in
respect of delivery of the articles and reference was made to the
7 jg.wp4258.15.odt
Commissioner's report and as the machinery claimed by the respondent
was purchased by the respondent and was kept in the premises, the
respondent was entitled to get back the said machinery. Shri Thengre,
learned counsel then submitted that as the lower Court being a fact
finding Court passed the order in favour of the respondent thereby
directing the petitioner to handover the machinery to the respondent
and this Court cannot substitute its opinion for fact finding. Thus, it was
the submission of Shri Thengre, learned counsel for the respondent that
the petition is unsustainable and untenable, as such, same be dismissed.
Shri Thengre, learned counsel also placed reliance on certain judgments.
6. Heard the learned counsel appearing for the parties at
length. I have also gone through the material placed on record. Perusal
of the copy of plaint in Civil Suit No. 112/2004 instituted by the
respondent which is the subject matter shows that the respondent -
plaintiff filed suit for permanent/mandatory injunction. The prayer in
the plaint reads thus :
(i) Grant permanent injunction restraining the defendant its agent or any person acting on behalf of the defendant company from engaging other contractor for contracting work of defendant till 31-12-2004 and till satisfing the outstanding dues of Plaintiff and till returning the machinery and appliances and records (fully described in Schedule A & B) to the Plaintiff. (emphasis supplied)
8 jg.wp4258.15.odt
(ii) ....
(iii) ....
(iv) ....
The copy of the Schedule A and B reads thus :
SCHEDULE A
__________________________________________________________
1. Standing Machine, 20mm to 75 mm capacity.
2. Wedling Transforma Machine, make I.O.L. capacity 2 Face, Oil Cool
3. Pulling & lefting Machine make Tfqr.
4. Chain block 5 ton capacity 2 Nos.
5. Cotugan Tourch 3 meter length 4 Nos.
6. Cotugan Tourch 18" length 4 Nos.
7. Reguletor 16 Nos.
8. Miscellaneous tools, tackles, safety appliances etc. as per register _______________________________________________________________
SCHEDULE B __________________________________________________________
1. Measurement Books.
2. Machinery Register.
3. Contract File.
4. Wages Register.
5. P.P.F. Register.
6. Account Register.
7. Bill & Voucher File.
8. All other records relating the contract work.
9. All the abovesaid property fully described in Schedule A & B are within possession and custody of defendant till today. _______________________________________________________________
Perusal of the material placed on record further shows that an
application was filed at the instance of the respondent sometime in the
month of May, 2004 for temporary injunction. The prayers in the said
application reads thus :
(i) Grant Temporary injunction restraining the Non- applicant its agent or any person acting on behalf of the Non-
9 jg.wp4258.15.odt
applicant company from engaging other contractor for contracting work of Non-applicant till 31-12-2004 and till satisfing the outstanding dues of Applicant and till returning
the machinery and appliances and records (fully described in Schedule A & B) to the Applicant.
(ii) Direct the Non-applicant to allow Plaintiff to work till
31-12-2004 as per renewal of licence in favour premises and take custody of all records and machinery full described in Schedule A & B.
(iii) Cost of the suit be awarded against the Non-applicant
and
(iv) any other relief as this Hon'ble Court may deem fit under
the facts and circumstances of the case be awarded against Non-applicant.
Perusal of the material shows that the petitioner had filed written
statement denying all the contentions raised by the respondent - plaintiff
including the details of Schedule A and B. Perusal of the order dated
2-7-2004 passed on the application for temporary injunction shows that
the application was partly allowed. It would be useful to refer to the
relevant observation of the learned lower Court.
10. The applicant is not made out strong prima facie case for grant of interim relief relates to execute job work contract with non-applicant company and restrained the non-applicant
from engaging other contractor ; but entitled to possession of the machinery, appliances, tools, tackles and registers from the custody of the non-applicant. For the reasons discussed above and my findings to point no. 1 to 3 I proceed to pass the following order.
ORDER
1. Application at Exh-5 is hereby partly allowed.
2. The defendant/non-applicant shall deliver the
10 jg.wp4258.15.odt
possession of the articles in Schedule 'A' and 'B' of the Plaint to the applicant.
3. The applicant shall pay the court fees as per rules for the possession of movable property described in schedule 'A' of the plaint.
4. Parties to bear their own costs.
As there were certain observations of the learned Joint Civil Judge
Junior Division, Bhandara in paragraph no. 9 of the order in respect of
production of list of articles by the applicant and verification by Security
Department of the petitioner-company and as same was not reflected in
the order dated 2-7-2004, the petitioner-defendant filed an application
seeking review. By order dated 17-3-2005, the application was allowed.
The clause (2) of the operative order dated 2-7-2004 was amended by
adding the words "subject to the production of the list of articles by the
applicant and verification by security department of the non-applicant
company".
7. Perusal of the material further shows that an application
was filed at the instance of the respondent-plaintiff for appointment of
the Commissioner. Learned lower Court i.e. Joint Civil Judge Junior
Division, Bhandara by observing that there is a grave dispute between
the plaintiff and defendant regarding the articles in schedule 'A' and 'B'
of the plaint and its verification by the Security Department passed the
11 jg.wp4258.15.odt
order thereby appointing Advocate Shri R. Y. Raut as Commissioner.
The Commissioner was directed to report as to what extent the plaintiff
is entitled for the delivery and possession of articles in schedule 'A' and
'B' of the plaint after due verification of the Security Department of the
non-applicant/Company. Then further order was passed on an
application seeking verification of the record thereby permitting the
Commissioner to verify ledger maintained by the security department of
the defendant company (petitioner herein) from year 1994 to 2004 and
to verify the relevant record of audit/account section from 1994 to 2004
regarding deduction of cost of machinery in installment from the year
1994 to 2004 as alleged by the plaintiff. (emphasis supplied) This
order passed by the Court below clearly shows that the Court has not
expressed any opinion in respect of the machinery being owned by the
respondent-company but the Court only refers that the machinery as
alleged by the plaintiff. Perusal of the Court Commissioner's report
placed on record at Annexure-P-13 shows that the Commissioner
referred to various vouchers. It may not be necessary to refer to all
these vouchers. It would be useful for our purposes to refer to the list of
articles. List of articles referred to certain articles. The Commissioner
further found that there were some articles which were referred to in
the receipts of articles submitted by the plaintiff. The Commissioner
12 jg.wp4258.15.odt
then in clear words states that those articles were not entered in the
security company register also. These articles are :
Hose pipe 30 met.
c) 28.12.02 Cutting torch 4 Nos.
The Commissioner then further states that property mentioned in
Schedule A and B not found there in standing machine hall there is
straightening machine its manufacturing year 32 y model-SM.65,
Capacity 25 met. Then the Commissioner states in the report that he
directed the defendant to produce articles mentioned in Schedule B i.e.
measurement book, machinery register, contract file, bill and voucher
file and record relating to contract work of plaintiff. The document is
placed on record at Annexure-P-14 i.e. the copy of invoice referring to
straightening machine delivered to the petitioner from one Bhambra
Engineering Works, Calcutta and receipt is also placed on record. It
shows that an amount of Rs. 8,92,495/- was paid by the petitioner-
company towards the said machine. Perusal of the copy of the judgment
and decree passed by learned Civil Judge Senior Division, Bhandara in
Special Civil Suit No. 22/2009 i.e. Old R.C.S. No. 112/2004 shows that
the suit is partly decreed and the Court further directed to return the
13 jg.wp4258.15.odt
tools, articles and machinery 1 to 30 and A, B and C which is fully
described in Commissioner Report Ex-179 within three months from the
date of order and the plaintiff shall take their custody within three
months failing which the defendant's company will not responsible for
loss or damage, if any, tools or machinery or articles.
8. Further perusal of the material shows that the respondent
himself had filed first appeal before this Court bearing Stamp No.
13193/2013 challenging the judgment and decree passed by learned
lower Court in Special Civil Suit No. 22/2009. Perusal further shows
that the applications were filed by the respondent for a special bailiff
and police protection. Perusal of the application for execution of the
decree dated 4-5-2013 through special bailiff shows that it is submitted
that there is a heavy machinery which is the part of decree and it would
require at least 4 days and 15 skilled labourers to remove the
machinery, as such, special bailiff be provided for 4 days for execution of
the decree. In the application seeking police protection, it is reiterated
that the machinery is heavy and the judgment debtor may cause
obstruction for removal of the machinery, as such, the police protection
be provided. By filing reply, the application is strongly opposed. It is
stated in the reply that the judgment debtor had not objected or
14 jg.wp4258.15.odt
obstructed to take back the articles as per the Commissioner's report but
the decree holder is asking for a specific machine without there being
any such reference of the said machine either in the decree or any
material to show that said machine belongs to the decree holder. The
order passed by the learned Civil Judge Senior Division, Bhandara dated
6-7-2015 impugned in the present petition shows that the learned Civil
Judge Senior Division refers to the objection raised by the petitioner,
namely, the decree holder is insisting upon custody of machine which is
not mentioned either in his plaint-schedule or in Commissioner's report,
therefore, there is resistance from judgment debtor company. Learned
Civil Judge Senior Division by observing that if one reads
Commissioner's report, Exhibit 179 which is part and parcel of decree, it
clearly states that the articles and machine belonging to decree holder
was not found in place where it was supposed to be and same were
found on some other place within the premises of judgment debtor
company. Learned Court below arises at a conclusion that the decree
holder was entitled for delivery of the said machine and allowed the
applications. In my opinion, observations of the learned Civil Judge
Senior Division, Bhandara in order dated 6-7-2015 are clearly erroneous
and contrary to the record. As stated above, the copy of schedule A and
B placed on record nowhere refers to the straightening machine. It
15 jg.wp4258.15.odt
would be necessary to state at the costs of repetition that the perusal of
the Commissioner's report clearly shows that the Commissioner referred
to certain vouchers and articles. The articles referred to by the
Commissioner under caption (a), (b) and (c) are two regulators, one
hose and the cutting torch. The Commissioner referred to straightening
machine but the straightening machine is neither part of articles referred
to in the list of articles by the Commissioner nor the articles captioned
under (a), (b) and (c). It would be also useful to refer to the statement
in the Commissioner's report which reads that I have visited the Bright
Bar section, Billet yard section, straightening machine section and
verified the property described in Scheduled A. It further makes clear
that the Commissioner is referred to various machinery in reference
specifically about the verification of the property described in
Schedule A. The Commissioner did not state that the straightening
machine is the part of the property described in Schedule A. The
material placed on record further shows that the respondent-defendant
nowhere gave any particulars of the said machine i.e. straightening
machine, such as, any receipt of purchase etc. On the contrary, the
documents placed on record shows that the machine was delivered to
the petitioner company from one Bhambra Engineering Works, Calcutta.
The invoice is placed on record i.e. the receipt of amount paid by the
16 jg.wp4258.15.odt
petitioner to the tune of Rs. 8,92,495/- is placed on record. It further
reveals that the judgment and decree dated 4-5-2013 refers to articles
and machinery 1 to 30 and A, B and C described in Commissioner's
report Exhibit 179. Further material placed on record along with the
submissions and pursis filed by the respondent shows that articles 1 to
30 are delivered to the respondent. The copy of superatnama is also
placed on record and it states that 32 articles having valued at
Rs. 4,460/- are handed over to the respondent-decree holder under a
superatnama. Learned counsel Shri Dharmadhikari placed reliance on
the judgment of Apex Court in the case of Kanwar Singh Saini Vs. High
Court of Delhi (cited supra) in support of his submission that the
interim order merges in final order. It would be useful to refer to the
following observations of the Apex Court in the said judgment.
17. Application under Order 39 Rule 2-A CPC lies only where disobedience/breach of an injunction granted or order complained of was one that is granted by the court under Order 39 Rules 1 & 2 CPC, which is naturally to enure during the pendency of the suit. However, once a
suit is decreed, the interim order, if any, merges into the final order. No litigant can derive any benefit from mere pendency of case in a court of law, as the interim order always merges in the final order to be passed in the case and if the case is ultimately dismissed, the interim order stands nullified automatically. (Vide: A.R. Sircar v. State of U.P]; Shiv Shanker v. UPSRTC, Arya Nagar Inter College v. Sree Kumar Tiwary, GTC Industries Ltd. v. Union of India and Jaipur Municipal Corpn. v. C.L. Mishra).
17 jg.wp4258.15.odt
I find considerable merit in the submissions of Shri Dharmadhikari,
learned counsel for the petitioner.
9. In view of the above referred detailed facts, I am unable to
accept the submissions of Shri Thengre, learned counsel for the
respondent. Shri Thengre, learned counsel though placed reliance on
judgments to submit that as in the impugned order, the lower Court had
undertaken the exercise of fact finding and this Court may not entertain
the petition as the fact finding of the lower Court attains finality.
Though there cannot be dispute on the proposition of law reflected in
the judgments relied on by Shri Thengre, learned counsel for the
respondent, I am of the opinion that in view of peculiar facts of the
present matter, judgments relied on by Shri Thengre, learned counsel
are of no help to him. As stated above, the order impugned in the
present petition is clearly on erroneous findings which is clearly in
contrast with the record and material. The order passed by the lower
Court is clearly unsustainable. In the result, writ petition is allowed.
The order impugned in the petition passed by learned Civil Judge Senior
Division, Bhandara dated 6-7-2015 is quashed and set aside.
JUDGE
wasnik
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!