Thursday, 30, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Redi Port Limited And Anr vs State Of Maharashtra And Anr
2016 Latest Caselaw 7180 Bom

Citation : 2016 Latest Caselaw 7180 Bom
Judgement Date : 14 December, 2016

Bombay High Court
Redi Port Limited And Anr vs State Of Maharashtra And Anr on 14 December, 2016
                                                          1                                  WP-2134-16(J)


                                                                               
                         IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                               
                             ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                       
                                    WRIT PETITION NO.2134 OF 2016


          REDI PORT LIMITED AND ANR                                ..  PETITIONERS




                                                                      
                             Versus
          STATE OF MAHARASHTRA & ANR                               ..  RESPONDENTS
                                              ...




                                                             
          Mr.D.J. Khambata, Senior Advocate with Gautam Ankad, Mr.Aditya 
                                           
          Mehta,   Vishesh   Malaviya,   Mr.Ashwin   Bhadang,   Ms.Madhavi   Doshi 
          i/b M/s.Federal & Rashmikant for the petitioners.
                                          
          Mr.S.G.Aney,   Senior   Advocate   with   Mr.Sanjay   Jain   and   Mr.Ishwar 
          Nankani, Mr.Sheelang Shah, Ms.Janaki Garde i/b Nankani Associates 
          for respondent no.2.
             

          Mr.A.I. Patel, Additional G.P. for State.
          



                                                     CORAM:  DR.MANJULA CHELLUR,CJ. 
                                                                   &  M.S. SONAK, J.

RESERVED ON: 25th October 2016 PRONOUNCED ON: 14th DECEMBER, 2016 JUDGMENT (Per Dr.MANJULA CHELLUR, CJ):-

1 State of Maharashtra, by virtue of powers conferred

under Section 5 of Indian Ports Act, 1908, came with a notification

to alter the existing limits of several ports as detailed in the

Tilak

2 WP-2134-16(J)

notification including the port at Redi. After deliberations in several

meetings right from 1996 to 2002, policy decision was taken to

privatize these ports so as to develop them as multi-purpose ports. In

the first phase, port at Redi was also included. The limits of Redi

Port came to be altered i.e. from one mile to ten miles on the

seaward side from the south bank of Mochimad creek. By

submitting necessary documents, the promoter of the petitioner no.1

through M/s.Earnest Shipping and Ship Builders Pvt.Ltd. approached

the authorities, requesting permission to develop Redi Port on Build,

Own, Operate, Share and Transfer basis. A notification came to be

issued by the Government of Goa, identifying and declaring the

Tiracol port limits within the tidal waters of River Tiracol east of

Meridian passing through Long.0730 41.5'. The proposal of

M/s.Earnest Shipping and Ship Builders came to be approved on 18th

August 2006, and ultimately, after several rounds of negotiation so

far as the terms of Concession Agreement, on 18th October 2008,

resolution was passed by State of Maharashtra, sanctioning the

execution of Concession Agreement with M/s.Earnest Shipping

Builders to develop an "All weather and multi-purpose port at Redi".


    Tilak





                                              3                                    WP-2134-16(J)


In pursuance of policy of ports privatization on 25 th February 2009,

Concession Agreement came to be executed. However, according to

petitioners, physical possession came to be handed over only on 8 th

April 2009.

2 By virtue of an Indenture of Lease between first

petitioner and the second respondent as lessee, an agreement came

to be executed for 50 years commencing from 25 th February 2009 on

18th December 2009. This is how the petitioner no.1 as the lessee,

has come into picture.

3 The first petitioner claims structurally and mechanically

it has revamped jetties sometime after April 2009. The petitioner

no.1 - Redi Port Limited (RPL) made an application for lease of the

Government lands which were earlier identified by Maharashtra

Maritime Board (for short "MMB"), and MMB requested the State of

Maharashtra for transfer of the said lands to MMB for development

of Redi Port. Apparently, an amount of Rs.4,58,47,000/- came to be

paid by the RPL to MMB.


    Tilak





                                              4                                    WP-2134-16(J)


    4                  The   petitioner   contends   that   as   per   the   Concession 




                                                                                    

Agreement, RPL filed a detailed project report with MMB along with

all supporting documents, as indicated above, on 22 nd April 2010.

Environmental Impact Assessment (EIA) request was issued by RPL

to L & T Ramboll Consulting Engineers Limited on 29 th June 2010.

Mean while, Government of Goa issued a notification altering the

limits of Tiracol port as a result of which Tiracol port extended onto

the seaward side of the river Tiracol and extended into the area that

has been demarcated as the limits of Redi Port as detailed and

demarcated on the map annexed at Exhibit-B to the rejoinder.

However, first petitioner claims that it learnt of this notification only

on 19th August 2016. Baseline surveys were initiated at Redi Port by

RPL in order to obtain environmental clearance in the month of May

2011. Draft Environmental Impact Assessment (EIA) report along

with Executive summaries were submitted by RPO to Maharashtra

Pollution Control Board (MPCB). On 9th May 2011, State of

Maharashtra and MMB approved detail project report (Phase I)

which was submitted by Board on 22nd April 2010. In the month of

2011 itself, MMD requested State of Maharashtra for transfer of the

Tilak

5 WP-2134-16(J)

lands to MMB for the purpose of development of Redi Port by

indicating urgency and necessity for such transfer for the purpose of

port privatization policy of State of Maharashtra. It is contended

that State of Maharashtra and MMP approved the Master Plan for

development of Redi Port during the period from 2014 - 2046

between 20th September 2011 to 20th October 2011. MMB, by its

letter dated 11th May 2012 requested the Principal Secretary (Ports)

of State of Maharashtra to publish a notification u/s.5 of the Indian

Ports Act to amend the existing port limits of Redi Port. This was in

terms of clause 3.5.1 of Concession Agreement.

5 Final EIA and EMP (Environment Management Report)

came to be submitted by RPL on 21st May 2012 to Maharashtra

Coastal Zone Management Authority (for short "MCZMA"). On 29 th

May 2012, additional documents were also submitted. Even a

presentation to the concerned Expert Appraisal Committee was made

on 3rd November 2012. Revision of draft notification correcting the

limits of the Redi port came to be made after consulting RPL by

Notification dated 30th January 2013, altering the limits and

Tilak

6 WP-2134-16(J)

declaring the new limits of Redi Port, indicating latitude and

longitude geographical coordinates. This again required

clarifications by RPL to MCZMA since MCZMA raised queries. This

again, took some time, according to the petitioners, for no fault of

them. Only in the year 2013, MMB de-notified the required land for

the purpose of acquiring the same for development of Redi Port

depending upon classification of various lands. On 27 th September

2013, a lease deed came to be executed between RPL and MMP in

respect of 730 acres of inter-tidal land to enable RPL to implement,

develop, design, construct, operate and maintain the Redi Port in

accordance with the provisions of Concession Agreement. It is

contended that a sum of Rs.11,06,25,000/- for the inter-tidal lease

agreement came to be paid by RPL. MCZMA recommended

Environmental Clearance for the project of MOEF on 24 th October

2013. Finally, report required for necessary clearance came to be

submitted by RPL only on 8th November 2013 between 20/11/2013

to 23/11/2013. Request of RPL for environmental clearance was

considered by MOEF in its 128 th meeting. It was intimated to the

RPL by MOEF that Government lands was not yet in possession of

Tilak

7 WP-2134-16(J)

RPL and RPL's proposal would be considered once those lands come

to the possession of RPL. This, again made the petitioners approach

MMB for transfer of lands. In turn, MMB requested the officials of

State of Maharashtra to initiate proceedings for diversion of said

government lands. According to the petitioners, they followed up

the matter with the State of Maharashtra and MMB on the release of

the said Government lands, therefore, requested for an extension of

Zero Date explaining the factual situation. Zero Date came to be

extended by MMB on 9th September 2014, and the same was

communicated accordingly.

6 According to petitioners, RPL addressed several letters,

representations to the State of Maharashtra and MMB and extension

of Zero Date and handing over of the said government lands, but the

same was delayed due to objections by local residents, occupants.

Therefore, even the proposal of RPL to purchase alternate lands did

not fructify. RPL even renewed the bank guarantee and submitted

further bank guarantee on 10th March 2015. However, this is

disputed by MMB.


    Tilak





                                                8                                    WP-2134-16(J)


    7                  On   21st  April   2015,   according   to   petitioner,   there   was 




                                                                                      

demand for payment of Rs.22.55 crore by MMB and this is nothing,

but arbitrary demand towards landing and shipping fees and port

dues. There was communication of coercive steps if the said

amounts were not paid. According to MMB, the amounts demanded

are to be computed based on the rates prescribed by MMB for multi-

purpose jetties in terms of notification dated 5 th April, but according

to RPL, the same is not applicable. Since Redi Port is a minor port

under State of Maharashtra, port privatization policy and concession,

and therefore, is under a multi-purpose terminal jetties. Apparently,

Arbitration Petition No.836/15 under section 9 of the Arbitration

and Conciliation Act came to be filed by RPL wherein interim relief

was granted, restraining MMB directly or indirectly, or taking any

coercive steps or restraining RPL from carrying out operations at

Redi Port. Appeal (L) No.470 of 2015 challenging the order dated

30th April 2015 was dismissed on 17th June 2015.

8 According to petitioners, MMB addressed a letter to State

of Maharashtra unilaterally seeking alternation of RPL's port limits

Tilak

9 WP-2134-16(J)

on 3rd April 2015, and the same came to the notice of the petitioner

for the first time on 18th August 2016 when it received a copy of the

letter from MMB. According to the petitioner, the statement of MMB

in this letter addressed to State of Maharashtra is false, so far as the

port limits of Tiracol port. According to them, it was only a pretext

for MMB to trouble the petitioners since Tiracol port limits had been

fixed in 2010 by the State of Goa and for RPL, it came to be re-fixed

much later i.e. 2013. The notification is dated 26 th November 2015

and came to RPL's knowledge only in the first week of August 2016.

This notification is with regard to alteration of limits of Redi Port.

According to the petitioner, the said alteration is shown in Exhibit-B

to the rejoinder was done in a clandestine and arbitrary manner by

MMB. The port limits came to be altered and re-fixed in the year

2013 after consultation and discussion with RPL, and both State of

Maharashtra and MMB kept RPL in the dark whilst issuing the

notification concerned. State of Maharashtra addressed a letter to

MMB enclosing a draft notification though in the month of

November 2015, but RPL learnt about the same on 18th August 2016.




    Tilak





                                                 10                                    WP-2134-16(J)


    9                  According   to   petitioner,   in   February   2016   itself,   it   had 




                                                                                        

informed the Divisional Forest Officer of State of Maharashtra that

RPL had selected non-forest land having Gat No.92/2 at

Sangameshwar, and requested the Officer to issue suitable

certificate. Request for RPL for compensatory afforestation came to

be accepted on 18th February 2016. Accordingly, it was accepted and

the clearance is awaited from Government of India in terms of letters

sent to the Government of India by State of Maharashtra and MMB.

10 In July 2016, RPL made a detailed representation to

MMB enumerating the various efforts undertaken by RPL to obtain

the said Government Lands and requested MMB to extend the Zero

Date by another 15 months so that it can obtain environment

clearance and achieve financial closure. Upon a praecipe filed by

MMB, a sole arbitrator was appointed by the High Court to

adjudicate upon the disputes between the parties under the

Concession Agreement, so far as the demand of authorities on the

basis of alleged multi-purpose terminal notification. Government of

India sought further details and information to take necessary action

Tilak

11 WP-2134-16(J)

in terms of letters addressed to Government of India in the month of

March, June and July so far as the issue of compensatory

afforestation.

11 The petitioner seems to have initiated correspondence

with MMB with regard to the notification dated 26th November 2015

by which State of Maharashtra had altered the limits of Redi Port. In

the joint meeting held between RPL and MMB, MMB made it clear

not to extend Zero Date on account of the non-payment of landing

and shipping fees and charges amounting to Rs.22.54 crores.

Several requests, according to the petitioner, were made to MMB as

well as Chief Minister of Maharashtra to withdraw notification dated

26th April 2015 allegedly issued unilaterally altering the port limits,

therefore, it necessitates extension of Zero Date. Mean while, a

status quo order with regard to possession of RPL came to be passed

by this Court on 25th August 2016 in the present Writ Petition.

12 It is contended on behalf of the petitioner that even after

filing of the Writ Petition, counsel appearing on behalf of State of

Maharashtra informed the Court that the representations of RPL for

Tilak

12 WP-2134-16(J)

the extension of Zero Date already filed, were pending before the

State and MMB, and sought liberty to consider the said

representations. Letters were addressed to Revenue and Forest

Department of State of Maharashtra, so far as request to comply with

the issues raised by Government of India regarding compensatory

afforestation which was sought by Union of India.

On 30th August 2016, in a meeting held by MMB, it was

resolved that the Concession Agreement stands terminated since

Zero Date has not been achieved, and MMB should take back

possession of Redi Port from RPL. According to the petitioners, in

total violation of directions of this Court to maintain status quo

regarding possession, officials of MMB visited the premises to draw

assets of the RPL and also to take possession of all the assets and

properties etc. Said attempt was continued only to trouble the

petitioners without even caring to consider the cargo lying in the

port premises belonging to third parties. This was informed to the

Court accordingly. Mean while, two letters were received from MMB

to collect or recover the landing and shipping fees of the cargo

Tilak

13 WP-2134-16(J)

handled between certain period, which again is the subject matter of

arbitration proceedings according to the petitioners. This ultimately,

compelled the petitioners to file Contempt proceedings in Contempt

Petition (L) No.73/16 in the above Writ Petition. Mean while,

District Mining Officer took steps against various mining companies

to remove their cargos from the Redi Port. According to petitioners,

the sole arbitrator by an interim order dated 19 th September 2016,

granted interim reliefs to RPL, pending arbitration, for a period of six

weeks from the date of award. Now, they learnt that State of

Maharashtra has allotted anchorage point within port limits of Redi

Port to one Kiranpani Port Pvt.Ltd, and the Anchorage Point is

situated very close to inter-tidal land leased to RPL. On 23 rd

September 2016, RPL received a letter from MMB that the

Concession Agreement stood automatically terminated as per clause

5.1 of the Concession Agreement due to the failure on the part of

RPL to achieve the Zero Date. They also indicated taking steps to

adhere to the directions of the State of Maharashtra as a

consequence of termination of the captioned 'Concession Agreement'.

According to the petitioners, termination of the Concession

Tilak

14 WP-2134-16(J)

Agreement is in gross violation and contempt of the orders of this

Court dated 30th April 2015 and 1st August 2016 in Arbitration

Petition No.836/15. The said termination, according to them, is

malafide, illegal, non-est, void, ab initio, and without authority in

law as MMB has only followed the directions of the State

Government since State of Maharashtra has no authority to issue

such direction, except directions on the question of policy of MMB.

The letter is nothing, but breach of statement made by MMB to the

Court during the pendency of the Writ Petition. According to the

petitioners, the conduct of the MMB and State of Maharashtra would

indicate that even till end of August, they were making attempts to

provide the government lands to RPL. It is further contended that

the proposed action of MMB on the directions of 1 st respondent -

State of Maharashtra, they are exposed to immense loss and

hardship since they have already invested amongst in excess of 55

crores on the execution of the project. Termination of RPL's

Concession Agreement in turn affect interest of various other third

parties who depend on the port managed by the petitioners,

especially the owners of the iron ore.


    Tilak





                                             15                                    WP-2134-16(J)




                                                                                    
    14                 As against this, the respondent no.2 through its Assistant 




                                                            

Secretary-cum-Law Officer has filed its affidavit-in-reply. According

to the respondents, Writ Petition itself is not maintainable.

Therefore, the petitioners are not entitled for any interim relief,

much less the relief sought in the Writ Petition. It is stated that the

petitioners have suppressed material facts and documents, and have

made false and misleading statements regarding entire Techno-

Economical Feasibility Study Report prepared by Consulting

Engineering Services Pvt. Ltd in 1997. The Techno-Economical

Feasibility Study Report prepared by L & T Ramboll Consulting

Engineers Ltd in the year 2007 at the instance of the petitioners, and

the entire detailed project report prepared by L & T Ramboll

Consulting Engineers Limited in 2010 was again prepared at the

instance of petitioners. According to them, even with regard to

location as notified by respondent no.2, by notification dated 30 th

January 2013, they are made on the misleading statements. They

further contend that the Writ Petition is aimed at adjudication of

contractual disputes which involves adjudication upon disputed

Tilak

16 WP-2134-16(J)

question of fact and the Writ Petition is aimed at avoiding

consequences of petitioners' failure to achieve Zero Date, as defined

in clause 4.2 of the agreement dated 25th February 2009. It is further

said that certain illegal operations are being attempted by the

petitioners from the two jetties of respondent no.2 at Redi Port after

the expiry of Zero Date, and therefore, the attempt is only to

perpetuate the illegal operations.

15 Under the guise of seeking reliefs with regard to

notification dated 26th November 2015 which is impugned in the

present Writ Petition, an attempt is made to seek extension of period

of achieving Zero Date, and in fact, it would be nothing but matters

which need to be decided in arbitration since they all refer to

contractual terms of the parties. Since several amounts are due from

petitioners, they are not entitled for any discretionary relief. State of

Maharashtra has coastal line stretching 720 kms long which consists

of 48 small size ports across the coastal line in Konkan region. It felt

the necessity to develop numerous small ports privately to maximize

amenities and meet global standards in order to improve the

Tilak

17 WP-2134-16(J)

industrial growth. Out of seven ports selected, Redi Port was one of

them, so far as first phase is concerned. Way back in 1934, this Redi

Port was notified. The jetties which are in existence were built

somewhere in the year 1981-82. Customs office was built here and

department of Customs has issued Landing and Shipping

declaration. Redi Port is largely used for exporting iron ore. So far

as the contention of the petitioners that in 1996, State of

Maharashtra notified policy decision to privatize and develop

multipurpose ports, they are not opposing or denying the same.

16 Since positive bids were not received to allocate global

tenders to attract international developments, first respondent

decided to allocate development rights of the ports, and at the

Memorandum of Understanding, on the basis of BOOT, M/s.Earnest

Shipping and Ship Builders Pvt.Ltd submitted proposal, and the

same was approved. Petitioner no.1 was incorporated as a special

purpose vehicle for the purpose of developing the Redi Port. Once

Redi Port being developed, second respondent MMB had an option

to acquire upto 11% equity stake in petitioner no.1. This would

Tilak

18 WP-2134-16(J)

have happened only if petitioner no.1 was able to achieve the Zero

Date.

17 Zero Date is introduced as per policy decision of

respondent no.1 which is clearly indicated in the policy documents.

Till Zero Date is not achieved, the conditions necessary to launch the

projects are not achieved. Hence, till such achievement, no rights

could be created in favour of proposed licensee. On 6 th July 2007

itself, in the letter of Intent issued in favour of M/s.Earnest Shipping

and Ship Builders Pvt.Ltd by State of Maharashtra, they were

directed to comply with achieving Zero Date and made clear that

extension of Zero Date is at the discretion of the respondent no.2. In

August 2007, petitioner no.1 came to be incorporated and furnished

a bank guarantee for Rs.5 crores which expired in 2010. No fresh

bank guarantee was issued and the same came to be given much

later in the month of March 2015. At the request of first petitioner,

Concession Agreement came to be executed, wherein there was a

request for transfer of two working jetties (MMD jetties), the land

owned by respondent (the leased land) and other assets and

Tilak

19 WP-2134-16(J)

facilities to the first petitioner.

18 By placing reliance on variuos clauses, they contend that

time was essence of the contract and all dates stipulated and

specified under the agreement had to be adhered to, unless

specifically and mutually extended by the parties. Non-achievement

would automatically result in termination of Concession Agreement

since environmental clearance and financial closure within the

prescribed 24 months period as stipulated under Concession

Agreement was not achieved inspite of extension of time limit to

achieve Zero Date. Termination would be the result. In the Board

meeting and as per the Controller and Audit General Report,

petitioner no.1 was held responsible in delaying the process of

getting environmental clearance of MOEF. Inspite of extending the

Zero Date upto 31st August 2016, the petitioners are not able to

achieve Zero Date. Hence, in terms of clause 5.1, Concession

Agreement would stand terminated and parties to the Concession

Agreement shall have no liability of any nature subject to clause 5.2.

According to respondents, achieving Zero Date was an integral and

Tilak

20 WP-2134-16(J)

fundamental obligation of the petitioners which was not complied

with. Petitioners were to prepare a detailed project report before

April 2010. Apart from placing relevant information, the petitioners

were bound to accurately and precisely delineate the entire Redi

Port proposed for development. Inspite of claiming requisite

expertise, petitioners never took steps to include the Tiracol port by

the State of Goa. The independent agency appointed by respondent

no.2 to study technical and economic viability, the DPR said to have

been prepared by L & T Ramboll is based on the information

furnished by petitioner no.1. The same is prepared without

accurately identifying the State borders between State of

Maharashtra and State of Goa. According to respondents, port limits

required for the development of Redi Port were deliberately and

willfully misled and misinformed by the petitioners. First petitioner

has consciously chose the project location Survey No.15, Village Redi

and Survey No.58 Village Kanyal for development which required

permissions and compliances from various authorities. The Board

approved the DPR Phase I on the representations, assurances and

delineation of the area identified by petitioners in the DPR, and

Tilak

21 WP-2134-16(J)

accordingly, port limits were identified and indicated by the

petitioners were notified. The numerous correspondence between

the parties and the authorities clearly indicate the same. Second

respondent obligations under the Concession Agreement were

always complied with so far as existing facilities, including assets etc.

297 Hectares of inter-tidal land was identified and lease deed was

executed on 9th September 2013. Application for environmental

clearance was never applied within the prescribed time. However,

petitioners started using the leased land and leased assets and again

declined to pay the charges, which again became subject matter of

dispute. After entering into the Concession Agreement and the

information collected from 2004 to 2008 prior to the Concession

Agreement, would clearly indicate that there is average loss of

Revenue as indicated in the reply. The petitioners sought so many

exemptions and refused to pay fee payable for various jetties.

19 The respondent no.2 was informed, that port limits as

proposed under the DPR by the petitioner no.1 on the basis of which

notification dated 30th January 2013 was issued, forms part of

Tilak

22 WP-2134-16(J)

territorial waters of Goa only in the month of August - September

2015. Since the port limits of Redi Port as notified encroached upon

the territorial limits of State of Goa, second respondent had to take

steps to alter the port limits within the Maharashtra State Territory.

Therefore, notification dated 26th November 2015 was issued. This

was very much within the authority of the second respondent to alter

the port limits. Said notification has not at all affected the

petitioners in any manner since they have never commenced the

work under the Concession Agreement. Therefore, they did not

raise any objection though they were aware of the notification dated

26th November 2015. Now, they are trying to project that off-late,

they acquired knowledge of the notification dated 26 th November

2015.

20 Second respondent has not violated any of the orders of

the Court. Every assistance and co-operation required was given to

petitioners by the respondent to obtain permissions, clearances from

various authorities. When the petitioners failed to achieve the Zero

Date inspite of extension of Zero Date achievement, they intended to

Tilak

23 WP-2134-16(J)

take back possession of the properties on expiry of Zero Date.

According to them, petitioners have committed default of obligations

and assurances.

21 All along, petitioners were aware of the breach of

obligations, but under the guise of impugned notification to

overcome their defects, have approached this Court, invoking writ

jurisdiction by interpreting several clauses of Concession Agreement,

for which petitioner has an alternative and efficacious remedy.

According to them, impugned notification has nothing to do with the

pre-requisites to achieve Zero Date and they are not at all inter-

linked to the notification. The challenge to the impugned

notification cannot be entertained in the absence of competent

authority in the State of Goa being made a party. Having failed to

obtain all necessary permissions within the period in terms of

Concession Agreement, petitioners are blaming the respondents for

the laches of the petitioners. The notification is dated 26 th November

2015 which is a public document, and the petitioners have

challenged the same on 22nd August 2016, just nine days prior to the

deadline to achieve Zero Date, only with an intention to seek

Tilak

24 WP-2134-16(J)

extension of Zero Date under guise of the impugned notification. It

was the duty and obligation of the petitioners to verify all the details

in all respects so far as the preparation of DPR. Having failed to do,

they cannot now blame the respondents for altering the port limits.

The alleged amount claimed to have been spent by the petitioners

alone, is mentioned, but they have never placed on record the

Revenue earned by them between 2009 to 2016. Alteration of port

limits has no hindrance of any nature to achieve Zero Date, and even

if such alteration affects the proposed development, it is a subject

matter of commercial dispute and not a dispute to be resolved under

Article 226 of the Constitution.

22 With the above facts and submissions at our command,

we proceed to dispose of the Writ Petition for the following reasons.

23 The salient features of Concession Agreement and

relevant clauses which are enumerated in the affidavit-in-reply of the second respondent read as under :-

(1) Clause 3.1 of the Concession Agreement, Petitioner No.1 shall pay a onetime licence fee of Rs.10 lakhs;



    Tilak





                                                 25                                    WP-2134-16(J)




(2) Clause 1.5 - Respondent No.2 has granted to the

Petitioner No.1 license to build a Multi-purpose, common user Port at Redi on BOOT basis for a period of 50 years;

(3) Clause 2(d) - Date of Commencement of Operations shall have the meaning specified in Section 21 of the Concession Agreement being the date on which "the Port"

as defined in clause 2(x) of the Concession Agreement being able to commence business.

(4) Clause 2(j) - Development Phase means the phase

between the Effective Date and the Zero Date. (5) Clause 2(l) - Effective Date means the date of signing

of the concession agreement i.e. 25.02.2009.

(6) Clause 2(n) - Financial Closure means the fulfilment

of all conditions precedent to the initial availability of funds under the Financing Documents and receipt of commitments for equity required for Phase I of the Project/immediate access to funds;

(7) Clause 2(x) - "Port" means the port proposed to be

developed in accordance with the terms of the Concession Agreement by Petitioner No.1;

(8) Clause 2(y) - Port limits means the limits of the Port as defined by the Indian Ports Act and as amended from time to time.

(9) Clause 3.4 - Petitioner No.1 was obligated to finance,

design and construct the Port within the time frame specified under the Concession Agreement and operate and maintain the Port Complex.

(10) Clause 3.5.1 - Respondent No.2 would demarcate port limits based on the 50 years plan provided in the approved Detailed Project Report (DPR) and it shall not alter or

Tilak

26 WP-2134-16(J)

modify the port limits to the prejudice of Petitioner No.1 as far as possible.

(11) Clause 3.5.2 - Respondent No.2 shall provide a list to

Petitioner No.1 of Government owned land required for the project as per the existing policy of the Government and the same would be valued at the market value as on the date of transfer of such land.

(12) Clause 3.5.2 - Respondent No.2 would request the Competent Planning Authority to notify the total land indicated in the DPR and approved by Respondent No.2 for

development of the Port and port related activities.

(13) Clause 4.2 - Petitioner No.1 was to achieve Zero Date within 24 months (ie by 24th February 2011) from the Effective Date (i.e. date of signing of the Concession

Agreement). The pre-requisites in order to achieve Zero Date, Petitioner No.1 was to :

(a) Obtain all Environmental Clearances from

the Ministry of Environment; and

(b) Achieve Financial Closure;

(14) Clause 5.1 - In the event Zero Date is not achieved within 24 months from Effective Date unless otherwise

agreed to, the Concession Agreement would stand terminated (which termination happened on 31st August 2016)

(15) Clause 5.2 - If Zero Date has not been achieved, Respondent No.2 may invoke the Development Guarantee.

(16) Clause 6.2.2 - Petitioner No.1 was required to submit the application for all Environmental Clearance within 14 months of the effective date i.e. by 24 th June 2010.


    Tilak





                                                27                                   WP-2134-16(J)


(However, Petitioner No.1 has submitted the Final EIA and other documents to the MOEF only on 29th May 2012) (Page

406 of Additional Affidavit filed by Petitioner No.1)

(17) Clause 6.2.4 - Petitioner No.1 was required to furnish a Construction Bank Guarantee.

(18) Clause 8 - Petitioner no.1 was to comply with all statutes and regulations of the Central or State

Governments.

(19) Clause 11.1 - Within 14 months of signing the Concession Agreement, Petitioner No.1 was required to

furnish a Detailed Project Report, inter alia, containing the Port Charges that are payable to Respondent No.2 based on

estimated volumes of cargo and the land requirement for the project over the licence period of 50 years.

(20) Clause 12.5 - Petitioner No.1 agreed to independently verify all details with regard to meteorological, geological and other conditions and would be liable for any defect, discrepancy, error or deficiency in

the information provided and no claim would be entertained based on any such defects including extension

of time for completing construction of the Port complex. The grievance in this Petition arises on account of default, discrepancy and error in the Petitioner's DPR.

(21) Clause 12.8 - Petitioner No.1 shall complete and submit all designs, drawings prepared by it to Respondent No.2 within a period of 6 months from the Zero Date.

(22) Clause 14.1 - Petitioner No.1 was solely liable to obtain all statutory clearances including Environmental Clearance from various Government authorities.

(23) Clause 16.6 - Petitioner No.1 was obligated to allow Respondent No.2 to inspect work carried out in the Port complex.

    Tilak





                                                  28                                    WP-2134-16(J)




               (24) Clause   19.2     -     Petitioner   No.1   was   to   provide   a 




                                                                                         

Development Guarantee of Rs.5,00,00,000/- upon signing of the Concession Agreement. The petitioners for some period

did not provide the Development guarantee.

(25) Clause 20 - Respondent No.2 was entitled to inspect project activities and operations of the Port and Petitioner

No.1 was to ensure unhindered access and offer necessary cooperation to carry out inspection of the Port complex.

(26) Clause 20.1.1 - The Date of Commencement of

Operations of the Port shall be the date of issue of Landing and Shipping Declaration by the Customs or the date of

expiry of scheduled construction period.

(27) Clause 27.1 - Petitioner No.1 was to provide a Performance Guarantee of Rs.1,00,00,000/-.

(28) Clause 38 - Petitioner No.1 was liable to pay a portion of the amount collected by it for the cargo handled at Port as per the scale of rates for providing services

starting from the date of commencement of commercial operations i.e. Rs.3/- per Tonne of cargo or Rs.36/- per

loaded TEU (20 foot Equivalent Unit) in case of Containers.

(29) Clause 64 - provided that all disputes shall be

referred to arbitration.

(30) Clause 85 - Specific project milestones and timeframe within which they were to be achieved were set out.

               (a)      Submission of DPR - 14 months.


               (b)      Submission of application for Environmental 
                        Clearance - 14 months.



    Tilak





                                              29                                 WP-2134-16(J)


               (c)      Obtaining of all clearances except 
                        Environmental Clearance - 24 months;




                                                                                  
                                                          
               (d)      Zero Date/Financial Closure - 24 months.

               (e)      Amendment of AOA and MOA of SPV 
                        i.e. Petitioner No.1;




                                                         
               (f)      Submission of detailed engineering design - 6 months  
                        from Financial Closure;

               (g)      Submission of application to Customs 




                                                 
                        Department for Declaration as Landing and 
                        Shipping site - 4 weeks from the completion 
                                     
                        of inspection of the Port;

               (h)     Completion of construction - 60      months;
                                    
               (i)     Date of normal transfer - 600 months.
       

    24                 The case brought on record clearly indicated the terms 
    



and conditions upon which the parties agreed to proceed with the

obligation and a several classes of concession agreement. It is

pertinent to point out that on account of State of Goa altering the

Tiracol port limits, it has caused impact on the limits of Redi port

which in turn has delayed the project is the stand of the petitioners

why they were unable to achieve the Zero date. Apparently, the

State of Goa is not made a party. According to the petitioners, only

in the month of August 2015 to September 2015, port limits got

Tilak

30 WP-2134-16(J)

extended in terms of notification dated 30th January 2013, and

became part of territorial waters of Goa. Whether notification issued

in November 2015 to ensure port limits of Redi port as notified

earlier to alter the Redi port limits, was the actual cause why the

petitioners were not able to comply with the condition of achieving

the zero date? Whether the notification of Government of Goa

extending the limits of Tiracol port came in the way of even

commencing the work under the concession agreement, and whether

there was delay on the part of the respondent authorities to comply

with their obligations so as to commence the work? These

controversial issues involve ascertainment of factual situation which

require a full-fledged trial. According to the respondent authorities,

notification dated 26th November 2015 never affected the rights of

the petitioners since they never commenced the work under the

concession agreement. This, depending upon the ascertainment of

facts, only can be decided.

25 It is placed on record certain measurement of inter-tidal

land was entitled and even lease documents were executed way back

Tilak

31 WP-2134-16(J)

in 2013. According to the respondent authorities, environmental

clearance application was to be applied within the prescribed time,

but they had never applied, and on the other hand, they were using

the leased land without paying the charges which again is the subject

matter of dispute between the parties. Whether delineation of the

area for the purpose of implementation of the project under the

concession agreement was delayed, which ultimately created

obstacles for the petitioner to achieve the zero date or the petitioners

were delaying project by not even commencing the substantial work

and however, made use of land leased to them, will again forms part

of exercise of ascertainment of facts. It is also contended on the part

of the respondent authorities that without seriousness to implement

the concession agreement in order to reach zero date, there were

unreasonable demands on the part of the petitioners which

ultimately delayed in reaching the Zero date. According to the

respondent authorities, the independent agency appointed by second

respondent so far as technical and economical viability said to have

been prepared by L & T Ramboll is based on the information

furnished by petitioner no.1. Therefore, if at all, any difficulty arose

Tilak

32 WP-2134-16(J)

in demarcating the limits of Redi port, it is on account of inaccurate

information furnished by the petitioners. The limits required for the

development of Redi port was deliberately and willfully misled by

the petitioners is the stand of the respondent authorities, and it is

further contended that on account of such misleading information, if

at all there was delay on the part of the respondent authorities, the

petitioners have to blame themselves and not the respondent

authorities. All these controversial issues between the parties again

depends upon the actual and factual ascertainment of material facts,

therefore, definitely, this Court, while exercising powers under

Article 226 of the Constitution of India, should not undertake such

exercise since alternate and efficacious remedy is available for the

petitioners is the stand of the respondents.

26 According to the respondents, the breaches and defaults

of obligations, representations and assurances by Petitioners under

the Concession Agreement include, but are not limited to:




    Tilak





                                               33                                  WP-2134-16(J)




                                                                                    

(a) failure to obtain Environment Clearance from the Ministry of Environment (Clause 4.2.1 and 14),

(b) failure to submit application for Environment Clearance within 14 months of Effective Date (Clause

6.2.2)

(c) failure to obtain Financial Closure {Clause 4.2.2 read with 2(n)}

(d) failure to achieve Zero Date despite extension

upto 31st August 2016 i.e. more than 5 years after the scheduled time frame of 24 months.

(e) misrepresentation of proper Project Location under clause 2.1 of the DPR.

(f) failure to pay Landing and Shipping Dues in

terms of Government Resolution dated 5th April 2011,

(g) unlawful payment of Landing and Shipping Dues in terms of Government Resolution dated 5th April 2011.

(g) unlawful payment of Landing and Shipping Dues at the rates provided under clause 38 of the Concession Agreement despite the Commencement of Operations as defined not having been achieved.

(h) failure to provide Construction Guarantee (Clause 19.1 read with clause 6.2.4)

(i) delay of almost 5 years in submission of second Development Guarantee after expiry of the first Development Guarantee in 2010 (Clause 19.2)

Tilak

34 WP-2134-16(J)

(j) failure to develop Redi Port as a multipurpose, all

weather port and design and construct within time frame as specified in the Concession Agreement (Clause

85),

(k) failure to obtain permissions for obtaining possession of S.No. 15 and 58 despite all assistance

rendered by Respondent No.2 (Clause 6.2.1),

(l) failure to collect and pay Port Dues under Section 33 of the Indian Ports Act, 1908 (Clause 8);

(m) failure to finance and construct Port within

stipulated time frame {Clause 3.4(b)}

(n) failure to perform all duties, obligations and

responsibilities under the Concession Agreement {Clause 3.4(e)}

(o) failure to transfer Leased Assets in good condition

to Respondent No.2 in accordance with the provisions of the Concession Agreement at the expiry of License

Period or early termination as the case may be {Clause 3.4(f)}.

(p) failure to accurately verify details and data on meteorological, geological and other conditions (Clause 12.5)

(q) Petitioner is liable for defects under the DPR (Clause 12.12);

27 In order to appreciate the stand of the parties and to

invoke plenary jurisdiction of this Court to grant prerogative writ

Tilak

35 WP-2134-16(J)

under Article 226 of the Constitution, one has to see what exactly is

the grievance raised, and the basis on which said grievance is

espoused and, ultimately, what relief the petitioner seeks at the

hands of this Court. The respondents have taken serious objection

to the maintainability of this Writ Petition on the ground that the

Writ Petition cannot be entertained under Article 226 of the

Constitution since there has to be investigation into factual details

with reference to the terms of contract and also conduct of the

parties. The grievance of the respondent authorities is that the

petitioners did not achieve the Zero Date in spite of several

opportunities given to them, and according to the petitioners, they

were not at fault in not achieving the Zero Date, but on account of

the various factors including the fact of extension of port limits in

terms of notification dated 30th January 2013, the extension of Zero

Date could not be reached.

28 It is beneficial to refer to the decision in State of Kerala

Vs. M.K. Jose, (2015)9 SCC 433, in order to appreciate the stand of

the parties, invoking jurisdiction under Article 226 of the

Tilak

36 WP-2134-16(J)

Constitution. In the case referred to above, several directions came

to be issued by the High Court with regard to the subject matter of

the work and the contract. Ultimately, a commission was allowed to

measure the completion of work under the contract. Their Lordships

in paragraph nos.20 and 21 analysed the circumstances in which the

action or the directions of the Division Bench of the High Court was

found fault in that particular case. In paragraph nos.20 and 21,

while coming to the conclusions, earlier judgments of the Apex Court

were analyzed, and ultimately, opined that the plenary jurisdiction of

the High Court to issue a prerogative writ, will not normally be

exercised by the Court to the exclusion of other available remedies

unless such action of the State or its instrumentality is arbitrary or

unreasonable so as to violate the constitutional mandate or for other

valid and legitimate reasons for which the Court thinks it necessary

to exercise plenary jurisdiction.

29 In the case of Whirlpool Corporation Vs. Registrar of

Trade Marks (1998) 8 SCC 1, and Nivedita Vs. Cellular Operators

Association of India, (2011) 14 SCC 337, it was held that having

Tilak

37 WP-2134-16(J)

regard to the facts of the case, the High Court in its discretion can

entertain or reject a Writ Petition. However, the High Court has

imposed upon itself certain restrictions, one of which is that if an

effective and alternative efficacious remedy is available, the High

Court would not normally exercise its jurisdiction. No doubt an

alternative remedy has been consistently held not to operate as a bar

where a Writ Petition has been filed for the enforcement of any of

the fundamental rights or where there has been a violation of the

principle of natural justice, or where the order or proceedings are

wholly without jurisdiction or the virus of an Act is challenged. But

none of the above circumstances exist in the present case.

30 In the light of the above circumstances, we have to

analyze what exactly is the grievance before this Court. It is not in

dispute that parties before us are to proceed with the project in

terms of the obligation and several clauses of concession agreement.

Whether there was justification on the part of the writ petitioner to

seek extension of Zero Date, beyond the time limit provided under

the agreement which was extended from time to time, and whether

Tilak

38 WP-2134-16(J)

there is violation of any obligation on the part of the respondent

authority which ultimately created obstacles in achieving the Zero

Date, or whether the conduct of the petitioner itself is responsible in

not achieving the Zero Date, are all matters which are required to be

investigated with reference to the facts and various other material

which the parties could tender before the Court in evidence.

In the light of above factual situation, for the reasons

mentioned above, we are of the opinion the Writ Petition deserves to

be dismissed, and is dismissed accordingly.

               (M.S.SONAK, J)                               CHIEF JUSTICE
    






    Tilak





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter