Citation : 2016 Latest Caselaw 1979 Bom
Judgement Date : 28 April, 2016
8-arbp606-16
vai
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
ARBITRATION PETITION NO.606 OF 2016
Oil & Natural Gas Corporation Limited )
a Corporation registered under the )
Companies Act, 1956 having its )
registered office at Jeevan Bharati, )
Tower-II, 124, Connaught Circus, )
New Delhi - 110 001 and having its )
Branch Office at Quadrant 1, 3rd Floor, )
NBP Green Heights, Plot No.C-69,
ig )
Bandra Kurla Complex, )
Bandra (East) - Mumbai - 400 051. ) ...Petitioner
....Versus....
International Certification Services )
Private Limited, a Company registered )
under the Companies Act, 1956, having )
its registered office at 22/23, Goodwill )
Premises, Swastik Estate, 178 CST )
Road, Kalina, Santacruz (East) )
Mumbai - 400 098. ) ...Respondent
Mr.Kevic Setalvad, Senior Counsel with Ms.Daisy Dubhash, Mr.J.P.
Kapadia, Mr.O.Mohandas and Mr.A. Khare i/b Little & Co. for the
Petitioner.
Mr.Vishal Kanade with Ms.Bhakti Nadkarni i/b Lex Firum for the
Respondent.
CORAM : R.D. DHANUKA, J.
DATE : 28TH APRIL, 2016.
ORAL JUDGMENT :-
1. By this petition filed under section 34 of the Arbitration &
8-arbp606-16
Conciliation Act, 1996 the petitioner has impugned the arbitral award
dated 26th October, 2015, recommending immediate withdrawal and
cancellation of ONGC letter dated 22nd April, 2014 regarding dealing
with the respondent and to permit the respondent herein to
participate in all ongoing and future tenders, wherever they are
qualified and to restore their business credibility. Some of the relevant
facts for the purpose of deciding this petition are as under :
2. The petitioner herein was the original respondent, whereas
the respondent was the original claimant in the arbitral proceedings.
3. The petitioner had invited bids for maintenance, painting of
its process platforms at Mumbai in the year 2008. M/s.J.K. Surface
Coating Pvt. Ltd. had submitted its bids. The bid of the said M/s.J.K.
Surface Coating Pvt. Ltd. was accepted by the petitioner on 8th May,
2009.The petitioner had also invited bids for hiring the services of a
third party for supervision, quality control and measurement of work
of maintenance, painting of the said offshore platforms of Mumbai
Offshore. The petitioner had accepted the bid of the respondent in
respect of the said work on 8th June, 2009. The petitioner entered into
a contract with the respondent on 7th July, 2009. It is not in dispute
that when the tender was opened, the tender amount was more than
Rs.1.00 crore. It is also not in dispute that in the year 2012, the work
for supervision and maintenance entered into between the parties
8-arbp606-16
was completed by the respondent.
4. It is the case of the petitioner that the respondent received
a vigilance complaint with regard to the work carried out by the
painting contractor i.e. M/s.J.K. Surface Coating Pvt. Ltd. The
petitioner accordingly initiated action against the said M/s.J.K.
Surface Coating Pvt. Ltd. based on such vigilance complaint. On 13 th
June, 2012, the petitioner addressed a letter to the respondent for
seeking explanation in respect of the alleged discrepancies in the
certification process undertaken by it. It was the case of the petitioner
that in view of the wrong certification of the invoices of the painting
contract by the respondent, the petitioner had made excess payment
of Rs.57,41,582/- to the painting contractor.
5. It is the case of the petitioner that on 10th July, 2013, the
Vigilance Department submitted its recommendation that the
petitioner may consider action against the respondent and the
painting contractor for recoveries of excess payment.
6. The petitioner thereafter started enquiry by nominating an
enquiry officer on 18th October, 2013 to enquire and investigate the
case against the respondent.. The enquiry officer thereafter issued a
show cause notice to the respondent. The respondent replied to the
said show cause notice and denied the allegations made therein. The
enquiry officer thereafter conducted an enquiry on 31 st December,
8-arbp606-16
2013 and recommended banning of all further business dealings with
the respondent and putting the respondent on a holiday for a period
of three years for the alleged gross violation of the provisions of the
scope of the work.
7. Based on such enquiry report, the competent authority of
the petitioner issued an order on 22nd April, 2014 against the
respondent stopping further business dealings with the respondent
for participation in future tenders of the petitioner for the period of
three years from the date of the issue of the said order.
8. On 18th December, 2014, the respondent invoked
arbitration as per clause 27 of the contract. The petitioner appointed
Dr.I.M. Chatterjee as a sole arbitrator on 10th April, 2014. The
respondent filed statement of claim before the learned arbitrator and
applied for refund of the amount recovered by the petitioner by
encashing the performance bank guarantee and also impugned the
letter dated 27th April, 2014 issued by the petitioner thereby
blacklisting the respondent from future contract for a period of three
years. The petitioner resisted the said claim by filing the written
statement. The learned arbitrator made an award on 26th October,
2015 and rejected the monetary claim made by the respondent. The
learned arbitrator however, recommended the impugned withdrawal
and cancellation of the letter dated 27th April, 2014 issued by the
8-arbp606-16
petitioner thereby dealing with all the business with the respondent
for a period of three years. This part of the impugned award is
impugned by the petitioner in this petition filed under section 34 of the
Arbitration & Conciliation Act, 1996.
9. Mr.Setalvad, learned senior counsel appearing for the
petitioner invited my attention to the various provisions of the contract
entered into between the parties and more particularly clauses 9, 10,
18.1 to 18.6 and 27.1. It is submitted by learned senior counsel that
admittedly the contract had expired by efflux of time. He submits that
the contract was not terminated on account of force majeure and also
on account of unsatisfactory performance. He submits that clauses
18.1 and 18.2 of the contract were thus not attracted in the facts and
circumstances of the present case. Reliance is placed on second part
of clause 18.6 which provides for consequence of termination. He
submits that since the contract was not terminated under clauses
18.1 and 18.2 which provided for termination of contract on expiry of
the contract and termination on account of force majeure, the
contractor could be put on holiday under clause 18.6. He submits that
there is no dispute that clause 34 which provided for "integrity pact"
was deleted.
10. Learned senior counsel for the petitioner also invited my
attention to four circulars issued by the petitioner which provided for
8-arbp606-16
procedure required to be followed for black listing a contractor and
action permitted under those circulars against such a contractor. He
submits that the action was initiated by the petitioner against the
respondent under those circulars and also under "integrity pact"
which provided for black listing such contractor for a period of three
years.
11. It is submitted that since the petitioner had taken action
against the respondent for black listing under the "integrity pact" and
based on such circulars, the cause of action, if any, arisen in favour
of the respondent was outside the scope of the contract and thus the
said prayer for impugning the action of black listing was not arbitrable
under the arbitration clauses recorded under clause 27.1 of the
contract.
12. The next submission of the learned senior counsel for the
petitioner is that clause 27.2 which provided for number of arbitrators
required to be appointed by the appointing authority would also
indicate that the arbitrator could be appointed only if the amount of
the claim was as prescribed under clause 2 of the said clause.
13. It is submitted by the learned senior counsel that the
learned arbitrator thus acted beyond the scope of his jurisdiction and
has decided the issue of blacklisting on the respondent which was not
permissible under clause 27.1 of the contract.
8-arbp606-16
14. The next submission of learned senior counsel is that the
fact that the learned arbitrator has rejected the claim for refund of
performance bank guarantee amount by rendering a finding against
the respondent that the work was not satisfactory, the learned
arbitrator could not have consequently passed an order for setting
aside the order of blacklisting against the respondent. The conclusion
drawn by the learned arbitrator is contrary to the findings recorded by
the learned arbitrator. He submits that the petitioner has no dispute
that the respondent could avail of any other remedy in law other than
invoking the arbitration agreement.
15. Mr.Kanade, learned counsel appearing for the respondent
on the other hand invited my attention to clauses 18.1 to 18.6, 27.1
and 34 of the arbitration agreement. It is submitted by the learned
counsel that admittedly the "integrity pact" clause recorded in clause
34 was deleted. He submits that admittedly the petitioner had taken
action of blacklisting against the respondent under "integrity pact". In
support of this submission, learned counsel for the respondent invited
my attention to some of the paragraphs of the impugned award in
which the submissions of both the parties were recorded by the
learned arbitrator. He submits that the contention of the petitioner
before the learned arbitrator was that clause 34 of the contract which
provided for "integrity pact" clause was deleted by mistake by the
8-arbp606-16
petitioner. He submits that the petitioner had applied for rectification
of the contract before the learned arbitrator based on the premise that
the said clause 34 was deleted by mistake.
16. It is submitted that since the action taken by the petitioner
was under clause 34, which was not part of the contract, the
respondent was entitled to invoke arbitration under clause 27.1 of the
contract. He submits that the question as to whether the petitioner
could take any action of blacklisting the respondent was the question
which would fall within the parameters of clause 27.1 as the same
was in connection with construction, meaning, operation, effect,
interpretation of the contract or breach thereof. He submits that the
disputes and differences arose between the parties as to whether the
petitioner could have banned the respondent under the provisions of
the said contract and thus the learned arbitrator had jurisdiction to
deal with such claims made by the respondent.
17. The next submission of learned counsel for the respondent
is that the petitioner had not raised an issue of jurisdiction before the
learned arbitrator that the claim made by the respondent was outside
the scope of contract or was outside the purview of arbitration
agreement recorded in clause 27.1 of the contract. He submits that
since the issue of jurisdiction was not raised before the learned
arbitrator, the said issue of jurisdiction cannot be allowed to be
8-arbp606-16
raised for the first time in this petition filed under section 34 of the
Arbitration & Conciliation Act, 1996.
18. Learned counsel for the respondent invited my attention to
the findings and observations made by the learned arbitrator while
granting the relief of setting aside the order of blacklisting the
respondent. He submits that the learned arbitrator has after
considering the pleadings and documents has rendered findings of
fact which findings being not perverse cannot be interfered by this
Court. He submits that the ig learned arbitrator has interpreted the
terms of the contract and has come to the conclusion that under the
provisions of the contract, the petitioner could not ban the respondent
in view of the deletion of clause 34 of the of the contract. He submits
that since the action on the part of the petitioner was beyond the
scope of contract, the said claim was arbitrable. It is submitted that
the interpretation of the learned arbitrator of the provisions of the
contract being a possible interpretation, this Court cannot substitute
the possible interpretation of the learned arbitrator with another
interpretation.
19. Mr.Setalvad, learned senior counsel for the petitioner in re-
joinder submits that the learned arbitrator could not have entertained
such claim. In support of this submission, he placed reliance on the
judgment of the Calcutta High Court in case of Vijay Singh Nahata
8-arbp606-16
vs. Union of India & Ors., AIR 1998 Calcutta, 153 and in particular
paragraphs 48 to 54. He submits that the challenge to an order
banning a contractor could be challenged only by way of writ petition
and not by filing arbitration proceedings.
20. A perusal of the contract entered into between the parties
indicates that clause 34 of the contract which provided for "integrity
pact" had been deleted admittedly when the contract was signed. The
said contact also provided that any modification to the contract had to
be in writing. Admittedly, there was no such amendment to clause 34
of the contract.
21. The question that arises for consideration of this Court is
whether the action of blacklisting taken by the petitioner against the
respondent by applying a non-existing provision was outside the
contract which action was based on the performance of the contractor
under the same contract awarded to the respondent and if so
whether such cause of action could be adjudicated upon by invoking
the arbitration agreement recorded in clause 27.1 of the contract.
22. It is not in dispute that the contract was terminated by
efflux of time. No action had been taken by the petitioner on account
of force majeure. It is not the case of the petitioner that the
respondent was banned by invoking clause 18.6 of the contract. A
perusal of the letter dated 22nd April, 2014 issued by the petitioner
8-arbp606-16
thereby banning the business dealings with the respondent for a
period of three years clearly indicates that the said order was based
on irregularity alleged to have been observed in the works in the
same contract which was subject matter of arbitration.
23. In my view, even if the validity period of contract had
expired upon completion of work between the parties, the dispute,if
any, having arisen out of the said contract in view of the banning
order issued by the petitioner based on the alleged unsatisfactory
performance of the respondent of the same contract, the arbitration
agreement will not come to an end and would continue to subsist for
adjudication of the dispute between the parties under the said
agreement. In my view, there is thus no substance in the submission
of the learned senior counsel for the petitioner that the claim
impugning banning order issued by the petitioner was outside the
scope of contract or outside the scope of arbitration agreement
recorded under clause 27.1 of the contract or that the arbitration
agreement did not survive after expiry of the contract.
24. In my view, since clause 34 of the contract was admittedly
deleted by the parties when the contract was awarded to the
respondent, the petitioner could not have taken any action against the
respondent under the said non-existent clause. The submission of the
petitioner made before the learned arbitrator for rectification of the
8-arbp606-16
contract based on the alleged mistake in deleting the said clause was
in my view, totally untenable and is rightly rejected by the learned
arbitrator.
25. A perusal of the record clearly indicates that the petitioner
did not raise any issue of jurisdiction before the learned arbitrator,
which is raised by the petitioner for the first time in this petition. It was
not the case of the petitioner that though the issue of jurisdiction was
raised by the petitioner before the learned arbitrator, the same is not
considered by the learned arbitrator. In my view, the issue of
jurisdiction thus not having been raised before the learned arbitrator,
the same cannot be allowed to be raised for the first time in the
present proceedings filed under section 34 of the Arbitration &
Conciliation Act, 1996.
26. Be that as it may, in my view, the challenge to the order of
banning issued by the petitioner was within the purview of jurisdiction
of the learned arbitrator under arbitration agreement recorded in
clause 27.1 of the contract. A perusal of the said clause clearly
indicates that the same is very wide and would include the disputes
or question arising out of its agreement which arose between the
parties. In my view, the claim of the respondent that the action of
banning was in breach of the contract would thus clearly fall within
the ambit of arbitration agreement. In my view, the learned arbitrator
8-arbp606-16
has thus acted within the jurisdiction by exercising his power under
clause 271. of the contract. There is thus no substance in this
submission made by the learned senior counsel for the petitioner.
27. Insofar as the submission of learned senior counsel for the
petitioner that mechanism of the arbitration could not be invoked also
under clause 27.2 is concerned, there is no substance in this
submission of the learned senior counsel. A claim upto Rs.5.00
crores could be adjudicated upon by a sole arbitrator to be appointed
by the petitioner.
28. A perusal of the judgment of the Calcutta High Court,
relied upon the learned senior counsel for the petitioner in case of
Vijay Singh Nahata (supra) indicates that the Calcutta High Court
had considered the issue of black listing in the writ petition. In my
view, the said judgment would not apply to the facts of this case and
would not assist the case of the petitioner.
29. A perusal of the award clearly indicates that the learned
arbitrator has dealt with the provisions of the contract and has dealt
with the submissions and pleadings of both the parties and has
rendered a finding of fact. In my view, the said finding of fact
rendered by the learned arbitrator is not perverse and thus cannot be
interfered with by this Court under section 34 of the Arbitration &
Conciliation Act, 1996.
8-arbp606-16
30. The learned arbitrator has interpreted the terms of the
contract and has held that in view of deletion of clause 34 of the
contract, the petitioner could not have taken any action of banning the
respondent in absence of such contract. The interpretation of the
learned arbitrator is not only possible interpretation but is correct
interpretation.
31. Insofar the submission of learned senior counsel for the
petitioner that since the learned arbitrator had rejected the claim for
refund of performance bank guarantee amount and thus the
conclusion drawn by the learned arbitrator is inconsistent with the
findings recorded by the learned arbitrator is concerned, it is not in
dispute that the respondent has not impugned the said finding. In my
view the action banning the contractor by the petitioner was an
independent action. The learned arbitrator on interpretation of the
terms of the contract having found that the said action was outside
the scope of contract, has rightly allowed the said claim.
32. In my view, the petition is devoid of merits and is
accordingly dismissed. No order as to costs.
(R.D. DHANUKA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!