Citation : 2016 Latest Caselaw 1562 Bom
Judgement Date : 16 April, 2016
ssm 1 app644.06-judgment.sxw
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 644 OF 2006
IN
ARBITRATION PETITION NO. 229 OF 1993
IN
AWARD NO. 77 OF 1993
M/s. Michigan Engineers Pvt. Ltd.,
D-7, Commerce Centre,
78, Javji Dadaji Road, Tardeo,
Bombay-400 084. .....Appellants.
(Original Respondents)
Vs.
Municipal Corporation of Greater Bombay, a Body Corporate, Constituted
The Bombay Municipal Corporation Act, 1888, having it's office at Mahapalika Building, Mahapalika Marg, Fort,
Bombay-400 001. ....Respondents.
(Original Petitioners)
Mr. Simil Purohit a/w Mr. Bagla Dandekar i/by Bagla Dandekar & Co.
for the Appellants.
Ms. Nikita Trivedi a/w Mr. R.Y.Sirsikar for the Respondents.
CORAM : ANOOP V. MOHTA AND G.S. KULKARNI JJ.
RESERVED ON : 18 FEBRUARY 2016.
PRONOUNCED ON : 16 APRIL 2016.
ssm 2 app644.06-judgment.sxw
JUDGMENT (PER ANOOP V. MOHTA, J.):-
The original Claimants-Appellants, by this Appeal, have
challenged Judgment dated 21 November 2005 passed by the learned
Judge in the Arbitration Petition whereby, the Arbitration Petition No.
229 of 1993 was partly allowed and thereby, modified the award to
the following extent-
". The directions contained in the award for making the
payment at the rate of Rs.7312/- per unit against item at serial No. 2 is set aside.
. Award stands modified to the above extent.
Respondent shall pay costs of this petition to the Petitioner as incurred by the Petitioner."
2 The learned sole Arbitrator, Mr. Justice V.D. Tulzapurkar,
(former Judge of the Supreme Court of India) has passed an award on
12 April 1993. The operative part of the same is as under:-
(a) It is declared that for items at Serial Nos. 2,3, 3(a) 4 and 5 specified in Tabular Statement in para 11 above
the Claimants are entitled to get additional payment at the enhanced/higher rates determined and specified by me in para 12 above against each such item after adjusting the payment already made by the Respondents a the Tender Rates.
(b) It is further declared that the Claimants are entitled to get interest at 13% p.a. on the amount that will
ssm 3 app644.06-judgment.sxw
become due for the said items under the declaration at
(a) above from the date when payment for concerned items became due till the date of this Award.
(c) In the circumstances, parties will bear and pay their
costs of this Arbitration.
3 Brief facts of the case are as under:-
In the month of April 1989, tenders were invited by the
Respondent-Municipal Corporation of Greater Bombay, (for short, "the
Corporation") for construction of fine screens, aerated grit chamber at
Bhandup and Ghatkopar being Contract Nos. 10/A and 11/A,
respectively. On 17 November 1989, the work order of said contract
was issued in favour of the Appellants. Under the said contract, the
two alternative methods were provided for completing the contract
and the option to choose any of them lay with the contractor. Though
the Appellants possessed the expertise, equipment and special
technique to complete the contract by adopting the alternative R.C.C.
Dispensable Conical Shoe method, by installation of stone columns of
the size of 400 mm diameter, but were compelled to complete the
work by another option by installing 750 mm diameter rammed stones
by adopting conventional boiler boring method. Accordingly, on 29
November 1989, work order issued by the Chief Engineer, Sewerage
ssm 4 app644.06-judgment.sxw
Project of Respondent Corporation to Appellants. On 15 December
1989, the work of both the contracts were commenced.
4 Cost of work in Contract No. 10/A was Rs. 3,12,60,215.61
with a contract period of 24 months exclusive of monsoon period
while that for Contract No.11/A was Rs. 5,92,94,471.96 with a
contract period of 30 months exclusive of monsoon period. The terms
and conditions of the contract were included in- General Conditions of
Contract for Civil Work (GCC), Bills of Quantities (BOQ), Technical
and Special Specifications, Drawings and all other documents
mentioned in definition of contract provided under clause 4(b) of
GCC. Under the contract, definite and precise sequence of
construction programme of work was required to be submitted by the
Appellants. As per the sequence of construction and programme of
work, the work of improving the bearing capacity of the ground and
controlling the settlement was required to be taken up first to achieve
results of certain items viz. item Nos. 1 to 5 of BOQ 9, which were
required to be executed by the Appellants at the first instance. There
are fixed schedule rates provided under various items of BOQ. BOQ
and schedule rates are part of the contract, as provided under the
ssm 5 app644.06-judgment.sxw
definition of contract under Clause 4(b) of GCC. The dispute involved
in the present Appeal is confined to item No. 2 of BOQ 9. Item No. 2
deals with installation of stone columns. The execution technology of
civil items has been specified in Technical Specifications Vol.3, Part I of
2. The technique for installation of stone columns has been
specifically provided under Section 02318A. Clause 1.1.2 of Section
02318A provided for two alternative methodologies for installation of
rammed stone columns viz. (i) by driving heavy casing tube of 750
mm diameter by using conventional boring piling method or by
employing bailor boring method or, (ii) by driving 400 mm diameter
closed ended tube by providing dispensable conical shoe at bottom.
As per the definition of contract provided under Clause 4(b) of GCC,
all the documents mentioned therein were specifically provided to be
complimentary to each other.
5 On 9 December 1989, a co-ordination meeting held
between the authorized representatives of Appellants and Respondent
Corporation, wherein Appellants' proposed methodology of driving
400 mm diameter closed ended tube by providing dispensable conical
shoe at bottom, was not accepted by Respondent Corporation since
ssm 6 app644.06-judgment.sxw
the same was not in conformity with BOQ. The Respondent
Corporation was constrained to refuse the proposed methodology
since the provisions of BOQ and technical specifications had to be
construed harmoniously in conjunction with each other and as per the
contract, it was incumbent for the Appellants contractor to install 750
mm diameter stone column. Thus, the execution methodology for
installation of 750 mm diameter column i.e. by using conventional
boring piling method or by employing bailor boring method as
provided under Clause 1.1.2 of Section 02318A of Technical
Specifications had to be employed by the Appellants contractor in
conformity with the contract.
6 A letter was issued by the Appellants to the Chief Engineer
of Consultants M/s. Binnie & Partners (India) Ltd. on 11 January
1990, proposing use of technique of concrete dispensable shoe for
installation of stone column. On 19 March 1990, a letter was issued
by the Chief Engineer (Sewerage Project) of Respondent Corporation
to Appellants explicitly refusing to accept the proposed methodology,
which was in deviation with the terms of the contract. By the said
letter, the Respondent Corporation made it clear that the stone column
ssm 7 app644.06-judgment.sxw
installed by the Appellants' proposed methodology, could be accepted
only on the condition that payment would be made by the Respondent
Corporation only under BOQ items existing in contract. If the said
condition regarding payment is not acceptable, the Appellants
contractor was at liberty to follow technical specification for 750 mm
diameter as provided in the contract.
7 On 29 March 1990, since the Appellants contractor was
not able to install even one trial stone column as per it's proposed
methodology, which was not in conformity with contract, letter
addressed by the Executive Engineer (Sewerage Project) of
Respondent Corporation to the Appellants advising it to follow
relevant technical specification for BOQ item for 750 mm dia. rammed
stone column.
8 On 24 May 1990, since no productive work was achieved
by the proposed methodology, a letter was issued by the Executive
Engineer (Sewerage Project) of the Respondent Corporation to
Appellants, calling upon the use of technique as per clause 1.1.2 of
Section 02318A for 750 mm diameter stone column. Since Appellants'
ssm 8 app644.06-judgment.sxw
proposed methodology was unsatisfactory, on 28 May 1990, a letter
was issued by the Executive engineer (Sewerage Project) of
Respondent Corporation to Appellants that the proposed methodology
was not acceptable to consultant and thus, in the interest of the
project, requesting for employing bailer boring method as per the
contract.
9 On 5 June 1990, since the Appellants failed to establish
proposed methodology to the satisfaction of technical specifications, a
letter was issued by the Chief Engineer (Sewerage Project) of the
Respondent Corporation to the Appellants requesting it to adopt bailer
boring method as per the contract. On 6 June 1990, a letter was
issued by the Chief Engineer (Sewerage Project) of the Respondent
Corporation to Appellants that the Appellants had never quoted a rate
for proposed methodology, which was in deviation with the contract.
On 27 November 1990, a letter was issued by the Appellants to the
Executive Engineer, Respondent Corporation requesting for payment
of Rs.10,970/0 per stone column. On 16 November 1991, a letter
was issued by the Appellants Contractor to the Municipal
Commissioner, Respondent Corporation for it's decision under Clause
ssm 9 app644.06-judgment.sxw
96 of the GCC in view of dispute regarding payment. On 22 April
1992, decision was taken by the Municipal Commissioner of
Respondent Corporation that claim submitted by the Appellants is not
admissible. As the Appellants were wrongfully denied to use the one
of the alternative method of which they had option, therefore, the
Appellants were required to put the additional cost for which the
Respondent required to pay the same as the Respondent refused to
pay. Therefore, the Respondent agreed to refer the said disputes and
differences for the Arbitration as per clause 96 and 97 of the GCC.
10 On 12 April 1993, the learned Arbitrator passed
declaratory Award whereby, the Appellants were declared as entitled
to get additional payment at the enhanced higher rate at 2/3 rd of the
rates claimed by them and further was declared entitled to get interest
of 18% per annum on the said enhanced amount from the date when
it became due till the date of award.
11 On 23 September 1993, the Respondents challenged the
said Award by filing the Arbitration Petition. On 21 November 2005,
the impugned Judgment/order was passed, and therefore, the present
ssm 10 app644.06-judgment.sxw
Appeal is filed on 18 January 2006.
12 The learned counsel appearing for the
Appellants/Claimants submitted that, the alternative which the
Claimants wanted to opt for, was not given any trial and was denied to
them by the Respondent Corporation for no valid reason and instead,
the Respondent Corporation foisted on them the expensive alternative
of installing rammed stone columns of 70 mm dia for which they must
compensate the Claimants. It is not possible to reject the claim
outright for absence of such material inasmuch as the Respondents
have received the benefit of getting the requisite number of rammed
stone columns of the size of 750 mm dia installed by wrongfully
denying the other alternative which was open to the Claimants namely
to install the same number of rammed stone columns of the size of
400 mm dia thereby, subjecting the Claimants to higher expenditure
and it was never the intention of the parties that the Claimants
should do so gratuitously.
13 The learned Arbitrator, in the facts and circumstances,
referring to the evidence so recorded by giving sufficient reasons and
ssm 11 app644.06-judgment.sxw
the material placed on record including rival contentions of the
Respondents, observed and held as under:-
"12 ......It is true that the Claimants should have placed
material on record regarding the actual expenditure incurred by them. But it is not possible to reject their claim outright for absence of such material inasmuch as the Respondents have received the benefit of getting
the requisite number of rammed stone columns of the size of 750 mm dia installed by wrongfully denying the other alternative which was open to the Claimants namely to install the same number of rammed stone
columns of the size of 400 m dia thereby subjecting the Claimants to higher expenditure and it was never the
intention of the parties that the Claimants should do so gratuitously. Not to grant any higher rate whatsoever would amount to the Respondents getting
unjust enrichment, apart from the Respondents going scot-free in spite of their wrongful denial of the alternative to the Claimants to which they were entitled. I am, therefore, of the opinion that on
quantum meruit basis the Claimants would be entitled
to claim additional payment at reasonably enhanced rate. In all the circumstances of the case, it would be reasonable to grant to the Claimants enhanced higher at 2/3rd of the rates claimed by them. Accordingly, I
fix the enhanced rate per unit at Rs. 7,312.00 against item at Serial No. 2, at Rs.686.00 against item at Serial No. 3, at Rs. 230.00 against item at Serial No. 3(a), at Rs. 7,312.00 against item at Serial No.4 and at Rs. 486.00 against item at Serial No.5 since
payment for these items at Tender Rates has already been made by the Respondents to the Claimants, the Respondents are directed to pay the difference between the Tender Rates and the rates specified by me above.
13. On the question of interest claimed by the Claimants, the Respondents have averred that the same cannot be
ssm 12 app644.06-judgment.sxw
allowed in view of the prohibition contained in Clause 85 of the General Terms and Conditions of the Contract. In my view, Clause 85 prohibits payment of
interest in routine case of delay arising in payment normal running bills. Here the entitlement to
additional expenditure is refuted altogether and the additional payment has become due ad the result of my adjudication. Therefore in view of the notice given by the Claimants that they shall claim interest at 18%,
the Claimants are entitled get interest at the rate form the date when payment for the concerned items became due till the date of this Award."
14 The learned counsel appearing for the Appellants has
pointed out various communication on record including,
communication dated 12 June 1990 whereby, the Appellants referring
to the decision of the Executive Engineer, as per clause 7 while dealing
with the aspect of deviation from the contract conditions, submitted
that, "However, if you feel that your decision is final then we request you
to put this matter for arbitration, as per the conditions in the contract at
the earliest". The proposal so stated, was accordingly proceeded
further for discussion. Admittedly, there was no stop notice and/or
indication to the Appellants not to complete the work as per the
available one method out of two. On the contrary, admittedly
Appellants proceeded and completed the work by choosing one of the
method by making rammed stone columns, which was part of the
ssm 13 app644.06-judgment.sxw
contract itself. The work was completed under the supervision and
direction and subject to the technical specification as per the
agreement. In case of dispute and/or doubt about the decision of the
Executive Engineer, it was permissible to refer the matter for
Arbitration. Such issue, as per the agreement, referable to the
Arbitration inspite of the decision of Executive Engineer and/or
concerned Officer, even as per the Arbitration Contract, the rate for
such work done by the Appellants are always subject to the final
decision of the Arbitral Tribunal. Having once adopted this
mechanism, which is permissible in law, the learned Arbitrator
therefore, in our view, rightly awarded the amount as recorded above,
on the quantum meruit basis, towards the additional payment at
enhanced reasonable rate. The reason therefore, so given and so
recorded above, in our view, is within the framework of law and the
record. There is no breach of any terms and conditions and therefore,
the award ought not to have been modified, as done in the present
case. There was no perversity and/or award was not contrary to the
record and/or the terms and conditions. The view expressed by the
learned Arbitrator was within the framework of law, as by consent the
Arbitrator was appointed to settle the issue, as there was no
ssm 14 app644.06-judgment.sxw
agreement with regard to the decision taken by the concerned Officer.
Both the parties agreed for the Arbitration and therefore, the decision
given by the learned Arbitrator, in our view, ought not to have been
interfered with and or modified. The learned counsel appearing for
the Respondents have placed on record the following judgments:-
a) Rajasthan State Mines & Minerals Ltd. Vs. Eastern Engineering Enterprises & Anr.1
"Award disregarding the terms of the contract is a
jurisdictional error. Arbitrator cannot award an amount which is ruled out or prohibited by the terms of the contract. If there is a specific bar in
the contract to the raising of a particular claim then the award passed in respect thereof is in excess of jurisdiction. Even if the claim is raised and referred to arbitration, such claim amount
cannot be awarded as the agreement is binding
between the parties and the arbitrator has to adjudicate as per the agreement. A deliberate departure or conscious disregard of the contract manifests the disregard of his authority or
misconduct on his part."
b) Steel Authority of India Limited Vs. Gupta Brothers Steel Tubes Limited2
"Where an arbitrator travels beyond the contract, the award would be without jurisdiction and would amount to legal misconduct and would become amenable for being set aside by the Court."
1 (1999) 9 SCC 283
2 (2009) 10 SCC 63
ssm 15 app644.06-judgment.sxw
c) K.P. Poulose Vs. State of Kerala & Anr.3
"Award passed by ignoring material documents
which throw abundant light on the controversy constitutes legal misconduct under Section 30(a) of
Arbitration Act, 1940.
d) Waverly Jute Mills Co. Ltd. Vs. Raymon & Co. (India) (P) Ltd.4
"If an award deals with a matter not covered by the agreement, it could be modified under Section 15(a) of the 1940 Act."
e) Indian Oil Corporation Ltd. Vs. Amritsar Gas Service &
Ors.5
"Award modified so that the relief granted would
be within the jurisdiction of the arbitrator."
f) The Upper Ganges Valley Electricity Supply Company Ltd.
Vs. The U.P. Electricity Board6
"The invalid part of the award being severable from that which is valid, there is no justification for setting aside the entire award."
g) J.C. Budhraja Vs. Chairman, Orissa Mining Corporation Ltd. & Anr.7
"Part of the award suffering from the vice of legal misconduct being severable from the rest of the
award, entire award is not liable to be set aside.
Amounts awarded by the arbitrator falling within
3 (1975) 2 SCC 236 4 AIR 1963 SC 90 5 (1991) 1 SCC 533 6 (1973) 1 SCC 254 7 (2008) 2 SCC 444
ssm 16 app644.06-judgment.sxw
jurisdiction can be severed from other portions of the award.
h) D.C.M. Ltd. Vs. Municipal Corporation of Delhi & Anr.8
"If the arbitrator has exceeded his jurisdiction, the award to that extent can be set aside."
i) Bombay Housing Board Vs. Karbhase Nail & Co.
Sholapur9
"In the absence of any agreement for the claimed rates, stipulated rates would apply and be binding
upon the parties."
j)
M/s. Alopi Parshad Vs. Union of India10
"Where the party has chosen to tie himself down by
the express terms of the contract, there is no scope for the arbitrator to award by applying principle of quantum meruit. The legal principle which forms the basis of the award in awarding the claim
amount, can be examined by the Court. Extra
rates by applying quantum meruit cannot be awarded where there are fixed contractual rates."
k) M/s. Patel Engineering Co. Ltd. Vs. Indian Oil
Corporation Ltd.11
"The arbitrator cannot award on the basis of quantum meruit where there are express terms of the contract."
l) Roopji & Sons Vs. Dyer Meaken & Co. Ltd.12
8 (1997) 7 SCC 123
9 (1975) 1 SCC 828
10 AIR 1960 SC 588
11 AIR 1975 Pat. 212
12 AIR 1930 All 545
ssm 17 app644.06-judgment.sxw
"Applicability of quantum meruit is excluded where party is bound by express terms of contract."
m) Associate Builders Vs. Delhi Development Authority13
"It is well settled law that an award which is not based on any evidence is necessarily perverse and liable to be set aside."
15 The above law position requires no discussion as settled.
We have to see the facts of this case. The Judgments so referred
above are on different facts and are distinguishable. In view of the
facts so recorded above and specifically reasoning given by the
learned Arbitrator, this case needs to be dealt with accordingly.
16 The Apex Court, in Food Corporation of India and Ors. Vs.
Vikas Majdoor Kamdar Sahakari Mandli Limited, 14 referring to Section
70 of the Contract Act, 1872, while dealing with the principle of
quantum meruit for the extra work and the reasonable payment
whether required to be granted or not, recorded that the payment
under this Section can also be claimed when the benefit has already
been availed by the other side and in para Nos. 19 and 20 recorded
13 (2015) 3 SCC 49 14 (2007) 13 SCC 544
ssm 18 app644.06-judgment.sxw
the said principle as under:-
"19 A person who does work or who supplies goods under a contract, if no price is fixed, is entitled to
be paid a reasonable sum for his labour and the goods supplied. If the work is outside the contract, the terms of the contract can have no application; and the contractor is entitled to be paid a reasonable price for such work as
was done by him.
20 If a party to a contract has done additional construction for another not intending to do it
gratuitously and such other has obtained benefit, the former is entitled to compensation for the additional
work not covered by the contract. If an oral agreement is pleaded, which is not proved, he will be entitled to compensation under Section 70. Payment under this
section can also be claimed for work done beyond the terms of the contract, when the benefit of the work has been availed of by the defendant."
17 This is the case where the Respondents admittedly, availed
the benefits and permitted the Claimants to work and complete the
construction and the decision of Executive Engineer was made subject
to Arbitration. The Arbitrator, therefore, was empowered to do so and
deal with the issue of payment for the work admittedly done by the
Appellants. The Arbitrator has taken a view based upon the
agreement between the parties and awarded the reasonable
compensation. We see no reason to interfere with the same by the
ssm 19 app644.06-judgment.sxw
learned Judge. [T.P. Geroge Vs. State of Kerala15]. This is not the case of
award which is contrary to settled law and/or record. Considering the
principle of Section 30 of Arbitration Act 1940 Arbitrator was not
obliged to give reasons, unless it stipulates in the agreement itself. In
the present case, the reasons are provided. There was no error
apparent on the face of record of the award to vitiate the decision of
the Arbitrator on the points. [Trustees of the port of Madras Vs.
Engineering Constructions Corporation Ltd.16].
18 The claim of high rate by the contractor for abnormal
increase in quantity of work, the power of Arbitrator to award the
higher rate is within the framework of law. [State of U.P. Vs. Ram Nath
International Construction Pvt. Ltd.17].
19 There is no case of misconduct made out after reading the
award so passed by the Arbitrator, on the contrary, the award is
reasoned one, based upon the contract terms between the parties and
the correspondence placed on record. The amount so awarded is not
15 AIR 2001 SC 816 16 1995 (5) SCC 531 17 AIR 1996 SC 782
ssm 20 app644.06-judgment.sxw
based upon any sort of loss and/or claim of liquidated damages. After
going through the record, as well as, the correspondence between the
parties, we are also convinced that the claim so awarded by the
learned Arbitrator was towards the work admittedly done and the
Respondents admittedly got the benefit out of it. The Respondents,
therefore, cannot deny the claim once agreed to refer the decision to
the Arbitrator on this issue. The Arbitrator, therefore, has
jurisdictional authority to pass and/or award reasonable
compensation beyond the rates so agreed, as sought to be contended
by the learned counsel appearing for the Respondents.
20 Having noted the Arbitration clause, in addition to above
clauses, the Executive Engineer's decision held to be final, as the issue
was referred by the parties to the Arbitral Tribunal. The Arbitrator has
power and authority to decide the monetary claim and rate to be paid,
as it was not decided and/or could not be decided by the Engineer,
therefore, in the present case, based upon the clauses and the
conditions, the award so passed by the learned Arbitrator is well
within the framework of law and the record. The submission that as
the decision of Executive Engineer was final and therefore the
ssm 21 app644.06-judgment.sxw
contractor was not entitled for any other amount than fixed for other
claims, is unacceptable, as it is contrary to the contract between the
parties itself. There is no clause pointed out that the decision of the
Executive Engineer shall not be questioned in any Arbitration
proceedings and cannot be subject matter of Arbitration dispute.
Therefore, the case is made out by the Appellants to interfere with the
order passed by the learned Single Judge, which is contrary to the
terms and conditions itself and against the settled principle of law in
this regard.
21 In the present case, therefore, we are inclined to observe
that the award so passed by the learned Arbitrator was not beyond the
terms of contract. It is not without jurisdiction and/or shows any
illegal misconduct. The award passed, based upon the material placed
on record, apart from the grant of reasonable compensation
considering the nature of admitted work done under the supervision
and control of the Respondents-Corporation. As the payment was
subject to Arbitral Tribunal decision, this itself means it is permissible
for the Arbitrator to award reasonable compensation, if the matter
does not fall and cover by the special agreement. We are inclined to
ssm 22 app644.06-judgment.sxw
observe that even in absence of agreement in claimants rates and
stipulated rates, if party agreed to refer the same issue for arbitral
tribunal to adjudicate the decision of Arbitral Tribunal, binds all
including the Respondents. The extension of principle of quantum
meruit, in the facts and circumstances, rightly made and therefore, the
award ought not to have modified as done by the learned Judge.
There was no express provision with this regard though two methods
were provided under the contract of payment. As directed and
permitted, the Appellants completed the work and agreed by both the
parties to refer the decision to the Arbitrator, itself means and shows
that there was no fixed contractual rights agreed and fixed by the
Appellants and/or by the parties, as there was no express terms of
contract in this regard and specifically about the rates. The decision
so taken by the learned Arbitrator, ought not to have been faulted
with, as the amount was not towards the liquidated damages and/or
compensation, but for the actual work done under the supervision of
the Respondents. The findings, therefore, so given by the learned
Arbitrator in no way can be stated to be perverse and/or required to
be interfered with by the learned Judge. [Associate Builders (supra)].
It is relevant to note that the Respondents never stopped and/or asked
ssm 23 app644.06-judgment.sxw
the Appellants not to work unless the rates are settled by agreement.
On the contrary, as recorded, permitted to work and/or proceeded
with the work by one method out of two so available with further
agreement to refer the Executive Engineers decision to the Arbitration.
Therefore, the issue of rate was not decided finally and/or agreed by
and between the parties and left for the Arbitrator to adjudicate the
same. The learned Arbitrator, as recorded, accordingly adjudicated
and awarded the reasonable compensation. We have gone though the
amount so awarded and the reasons so recorded in the same. Even
for that, we see there is no perversity based upon the commercial
contract and the amount so claimed, supported by the material on
record. The rate of interest so awarded, in the facts and
circumstances, of 18% p.a. also needs no interference. However,
considering the fact that though asked for 18% p.a. and by recording
further, this is not the case of routine payment based upon the normal
running bills though demanded 18% p.a., restricted to 13% p.a. on the
amount due for the said item, from the date when the payment for
concerned items become due till the date of this award. However,
considering the general trend and in view of the Judgments of the
Supreme Court, so referred above, we are inclined to restrict the
ssm 24 app644.06-judgment.sxw
interest @ 9% p.a. instead of 13%, so awarded.
22 The learned Judge, in our view, erred in holding that the
Appellants ought to have made the claim for damages, as there was a
breach of contract. The Arbitrator, as recorded, has granted 2/3 of
the claim of the Appellants by granting approved rate. The learned
Judge, ought not to have interfered with as there was no perversity.
The Arbitrator was within its jurisdiction to fix the rate in the items,
which was not provided in the contract. The award was for fixing the
responsibility of contract and was not for the breach of contract.
Therefore, there was no question of leading any evidence and/or
proof of damages. The view taken by the learned Judge was possible
and plausible, therefore, considering the provisions of the Arbitration
Act, 1940, it ought not to have been interfered with.
23 The amount so claimed by the Appellants was for items,
for which no rates were provided under the contact. The Respondents
compelled the Appellants to install 750 mm Diameter Stone with
conventional boring method and as the Petitioner admitted by
adopting second method, therefore, awarded 2/3 rate claimed by the
ssm 25 app644.06-judgment.sxw
Appellants. The learned Arbitrator, as discussed, on rate analysis
passed the award. The learned Judge failed to appreciate that the
claim made by the Appellants was determined the rate for items for
which the tender document of the Respondents provides, no rates.
There was no question of denying the work by the Appellants without
any payment and/or gratuitously. The legal entitlement for the work
tendered, is well recognized principle, specifically when the rates were
not agreed and/or made subject to the Arbitration and compelled the
contractor-Appellants to complete the work within a period. Such
claim of pro-rata rate for the work done, ought not to have interfered
with by the learned Judge. The Arbitration, itself was for the fixing
the reasonable rate based on the existing tender contract. The
adjudication, therefore, so done by the Arbitrator was well within the
purview and power of the Arbitrator, including the agreement
between the parties.
24 Having once observed above, we are not inclined to accept
the case of the Appellants with regard to the power of the learned
Judge to modify the award, as done by the learned Judge in the
present case. It is settled that the award can be modified by the
ssm 26 app644.06-judgment.sxw
Court under Section 34. The law is clear on this issue as declared by
the Supreme Court, as well as, by this Court. Considering the nature
of construction contract, we are inclined to reduce the rate of interest
from 9% p.a. instead of 13% p.a., as done by the Supreme Court also
in many such matters. This is also for the reasons that such pendency
of Court litigations should not be the reason to burden the interest
upon the Corporation only.
Therefore, the following order:-
ORDER
a) The impugned order of the learned Single Judge
dated 21 November 2005, modifying the Arbitral
award is set aside.
b) The award passed by the learned Arbitrator is
maintained in every respect, except the rate of
interest, which is to be restricted to 9% p.a. instead
of 13% p.a.. Rest of the award is maintained.
c) Appeal is allowed accordingly.
d) There shall be no order as to costs.
26 The learned counsel appearing for the Respondent seeks
ssm 27 app644.06-judgment.sxw
stay of execution of this Order. Considering the reason so recorded
and in the interest of justice, we are inclined to grant six weeks time.
The present order, therefore, will not be executed for six weeks from
today. Order accordingly.
(G.S. KULKARNI, J.) (ANOOP V. MOHTA, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!