Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Larsen And Toubro Limited vs State Of Maharashtra And 5 Ors
2015 Latest Caselaw 432 Bom

Citation : 2015 Latest Caselaw 432 Bom
Judgement Date : 14 October, 2015

Bombay High Court
Larsen And Toubro Limited vs State Of Maharashtra And 5 Ors on 14 October, 2015
Bench: M.S. Sanklecha
    Pvr                                     1/17                     wp2323-15L&T.doc

                IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                     ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                                 
                              WRIT PETITION NO.2323 OF 2015




                                                         
    Larsen & Toubro Limited.                                      ...Petitioner

           versus




                                                        
    1.State of Maharashtra & Others.
    2.Maharashtra State Electricity Distribution Co.Ltd.
    3.Himachal Energy Pvt.Ltd.
    4.Genus Power Infrastructure Pvt.Ltd.




                                               
    5.M/s.Genus Innovation Pvt.Ltd.
    6.Institute of Design Electrical Measuring Instruments.
                                    ig                            ...Respondents


                                            ---
                                  
    Mr.Aspi Chinoy, Senior Counsel with Mr.Chetan Kapadia with Mr.Sanchin
            

    Chandarana and Mr.Pritish Shetty i/b. M/s.M.K.Ambalal & Co., for the Petitioner.
         



    Mr.M.P.Jadhav, AGP for Respondent no.1.

    Mr.G.R.Joshi, Senior Counsel with Ms.S.Surve with Mr.Saurabh Pakale and
    Mr.Amy Jaiswal i/b. Little & Co., for Respondent No.2.





    Mr.Anupam Dighe with Mr.Vishal Jathar and Mr.Kiran Padalkar i/b. India Law
    Alliance, for Respondent No.3.

    Mr.Ghanshyam Upadhyay i/b. Law Juris, for Respondent Nos.4 and 5.





    Mr.V.P.Vaidya i/b. Mr.Mahendra Agavekar, for Respondent no.6.

                                            ---

                                         CORAM     :      M.S.SANKLECHA &
                                                          G. S. KULKARNI, JJ.
                                         DATE      :      14th OCTOBER,2015





     Pvr                                       2/17                       wp2323-15L&T.doc

    JUDGMENT : (PER G.S.Kulkarni, J.)




                                                                                     

1. This petition under Article 226 of the Constitution of India arises out

of a tender floated by respondent no.2 - the Maharashtra State Electricity

Distribution Company Ltd. for procurement of what is described as "LT AC

Single Phase 5-30 AMPS Static Energy Meters with IR Port" (for short 'the said

tender'). The petitioner impugns the letter of Award of the contract dated 2 nd

September, 2015 issued by respondent no.2 in favour of respondent nos.3 to 5.

The petitioner has also prayed for a direction to respondent no.2 to conduct

retesting of the meter as contemplated under the tender conditions by any other

NABL laboratory across the country and re-tender / float afresh the tender.

2. Respondent No.2 on 7th August, 2014 issued the tender in question

inviting bids for supply of the electricity meters 20 lakhs in quantity. The tender

document issued by respondent no.2 contains various instructions to the tenderers.

The bids were to be submitted in two parts, part one being the techno commercial

bid and part two being the price bid. Clause XXII of the tender conditions

stipulate that in case of tenderers whose techno commercial bid is acceptable,

their price bids will be opened. Clause XXVI of the conditions prohibits post

tender correspondence stating that the tenderers should note that no

correspondence shall be entertained or considered after the due date and time of

submission of tender unless otherwise sought by the purchaser. As a part of the

technical bid, the bidders were required to submit "sample meters". As regards

testing of the sample meters, the same is provided for in clause 3 of the 'Special

Pvr 3/17 wp2323-15L&T.doc

Terms and Conditions of Tender and Supply' as contained in 'Annexure A'(at page

59 of the paper book). This condition reads as under:-

"3. Tender sample meters at NABL Laboratories and at IT Section of MSEDCL (wherever applicable):

13 nos. of sample of Meters and 2 nos. of HHU (Along with the HHU driver Software & documentation etc.) of each offered type as per Cl.No.24 of Technical Specification of Single Phase Meters with IR Communication capability & 2

Sample of Meter Box as per Cl.No.7 of Annexure-III of Technical Specification of Single Phase Meters with IR Communication capability are to be submitted to EE(SM) in the office of the Chief Engineer (MM Cell), 1 st floor, Prakashgad, Bandra (E), Mumbai-51 on or before the time and date stipulated for submission of offer.

The Cl.No.24 of technical specification stands modified to this extent and other stipulations of Cl.No.24 of technical specification will remain unchanged.

Packing of tender samples:

"Sample meters shall be suitably packed in order to avoid damage during transit or handing. In case, the sample meters found damage, it shall be the bidder's sole

responsibility. Therefore, bidders should ensure that the meters packed are intact."

3. The tender document has also prescribed technical specifications in

respect of this procurement. Some of the clauses which are relevant are clauses

7.21, 7.22 and 7.23 (at page 80 of the paper book) and clauses 11.05 and 11.07

(at page 83 of the paper book). These clauses read thus:-

"7.21. The meter shall remain immune for the test of electromagnetic HF/RF defined under the test NO. 4.0 for EMI/EMC of IS 13779:1999 amended up to date.

7.22 For any higher signals than the present standards and MSEDEL

technical specifications indicated above, if the accuracy of meter gets effected, it shall record energy considering meters maximum current, reference voltage and U.P.F. during such tampering events for defined period of seven days. The same shall log the event with date and time stamping. The same shall be displayed in the scrolling mode. After that meter should record normal energy consumption.

7.23. The communication of energy meters shall not be effected considering the above feature stated in the clause 7.21 and 7.22.

11.05. The meter shall be immune to the magnetic field (AC/DC/Permanent up to 0.2 Tesla (except 0.2 Tesla AC). Under influence of any magnetic field AC/DC/permanent) more than 0.2 Tesla, if the accuracy of the meters gets

Pvr 4/17 wp2323-15L&T.doc

effected then the same shall be recorded as magnetic tamper event with date and time stamping and the meter shall record energy considering maximum value current (1max) at reference voltage and unity power factor.

11.07. The meter shall remain immune for the test of electromagnetic HF/RF defined under the test no.4.0 for EMI/EMC of IS 13779 : 1999 amended

up to date. For any \higher signals than the present standards and MSEL technical specifications indicated above, if the accuracy of meter gets affected, it shall record energy considering meters maximum currents ((1max) reference voltage & U.P.P. during such tampering events for defined period of seven days. The same shall log the events with date and time stamping. The same shall be displayed in

the scrolling mode. After that meter should record normal energy consumption. "

A perusal of these clauses makes it quite clear that the meters to be

supplied were required to be of a technical standard as prescribed under these

clauses.

4. Another relevant clause is clause no.24 which pertains to tender

sample providing that the offer of those eligible bidders shall only be considered if

the sample passes the test at NABL laboratory, as well as necessary certification

from the IT department for the offered sample. It also states that the results of the

NABL Lab. and the certification from IT Department for the offered sample shall

not be disputed and shall be binding on the bidder. It would be profitable to

extract this condition which reads thus:-

"24.00 TENDER SAMPLE Tenderer are required to submit 10 (ten) nos. of sample meters & 2 no. of sample

HHU of offered type along with required cables and 2 (Two) Nos. of meter enclosures as per technical specifications along with the HHC driver software & documentation, etc. to EE(SM) in the office of the Chief Engineer Material Management Cell, 1st Floor, Prakashgad, Bandra (E), Mumbai-400051, on or before the time & date stipulated for submission of offer for testing the sample meters in third party NABL Lab like ERDA, CPRI, CIPET, ERTL and testing the offered sample by our IT Department as per technical specifications. The offer of those eligible bidders shall only be considered if the sample passes the tests at

Pvr 5/17 wp2323-15L&T.doc

NABL Lab as well as necessary certification from our IT Department for the offered sample. The results of NABL lab and the certification from IT

Department for offered sample shall not be disputed and shall be binding on the bidder.

The required information such as Manufacturer's Name or Trade Name, Sr.No. ISI Certification No. etc. shall be on stickers to be affixed on outer portion of sample meters being submitted alongwith the offer. Such information shall not be

embossed or printed on any part of the sample meter. Out of these, two samples shall be without Ultrasonic welding to confirm constructional features.

Note: The HHU with GPRS embedded modem is to be submitted before

commencement of supply. However, HHU with modified protocol without GPRS

modem is to be supplied for evaluation at the time of bid submission along with meter sample."

5. The petitioner was one of the bidders alongwith the other bids

received from respondent nos. 3 to 5. On 12 th September, 2014 the petitioner

submitted its bid for the quantity of 10 lakhs meters out of the total tender

requirement of 20 lakhs meters. The petitioner also submitted samples of the

meters as per the tender requirement. The condition of the tender was that these

sample meters submitted by the bidders were required to pass the test in any one

of the two NABL laboratories. Respondent No.2 had nominated the Central

Power Research Institute, Bhopal (CPRI) and the ERTL Mumbai as the

Laboratories which would undertake the testing of the sample meters submitted by

the bidding parties.

6. It is not disputed between the parties that on 27 th November, 2014 a

test was conducted on the sample meter submitted by the petitioner in its technical

bid by the CPRI, Bhopal. This test was conducted in the presence of the

Pvr 6/17 wp2323-15L&T.doc

representative of the petitioner and respondent no.2. This test on the meters of the

petitioner failed.

7. On 14th November, 2014 the samples of all the bidders were

forwarded by respondent no.2 to the Laboratory at ERTL Mumbai. The petitioner

claims to have passed the test alongwith six other bidders including respondent

nos. 3 to 5. However, ERTL, Mumbai could not undertake one specific test

namely the Electro Magnetic HF test, due to facility limitations at ERTL,

Mumbai. It was therefore, decided by respondent no.2 to forward these meters to

another Laboratory namely the 'The Institute of Design Electrical Measuring

Instruments, Mumbai (IDEMI)' - Respondent No.7 and subject the samples to the

said Electro Magnetic HF test. This was permissible as per the policy of

respondent no.2 as contained in the resolution of Board of Directors taken in its

meeting held on 18th July, 2011, and thus a second testing was available to the

bidders to subject the meters to a test by another NABL laboratory. The IDEMI

laboratory on 14th July, 2015 conducted a test on the sample meters of the

petitioner and of other three bidders. During this test the representative of the

petitioner was present. In the test conducted on the meters of the petitioner and

the other bidders, the samples of the petitioner and the samples of the other

bidders namely Palmohan, Flash and HPL failed the test. Respondent no.3 passed

the Elector Magnetic HF test. The report of this test was forwarded by IDEMI to

respondent no.2 on 20th July, 2015.

8. As the samples of the petitioner failed on 14 th July, 2015 at IDEMI

Pvr 7/17 wp2323-15L&T.doc

Laboratory, the petitioner entered correspondence with respondent no.2 as also

with the Director of the IDEMI pointing out an anomaly in the test procedure

followed by IDEMI. The grievance of the petitioner was that for the test at

IDEMI the pulse sensor was kept inside the GTEM Cell. The pulse sensor being

an electronic circuit, there was a good possibility that a sensor is also getting

affected by HF field generated inside the GTEM cell. It was stated that in other

laboratories pulses are picked up through an optical cable that is immune to HF

fields being generated inside the GTEM. The petitioner requested respondent

no.2 to allow retesting of the meters and also requested IDEMI to change their

method of testing and bring the same in line with the procedure followed in other

laboratories. It is the petitioner's case that a similar representation was addressed

by a co-bidder namely Flash India Electronics Pvt. Ltd. It is noteworthy that the

petitioner took up the matter directly with the Principal Director of IDEMI by its

letter dated 23rd July, 2015 making a request to reconsider the test reports on its

above reasoning and re-calibrate the testing procedure.

9. In the meanwhile as respondent no.2 was in urgent need of the

meters to be supplied under the tender which as per respondent no.2 was already

delayed, respondent no.2 went ahead with the tender procedure and the

commercial bids of respondent nos.3 to 5 who were successful in the technical bid

came to be opened. Respondent No.3 emerged as a lowest bidder with a price of

Rs.733.05 lakhs, however respondent no.2 gave a counter offer to respondent no.3

to match the order price of Rs.695.46 lakhs which respondent no.3 agreed. It is

placed on record on behalf of respondent no.2 that the tender process was

Pvr 8/17 wp2323-15L&T.doc

thereafter completed by issuance of a letter of award (LOA) dated 1 st

September,2015 in favour of respondent no.3 to 5 and Work Order was issued in

their favour on 10th September 2015 for supply of 20 lakhs meters in the

proportion of 10.70 lakhs, 6 lakhs and 3.30 lakhs respectively by each of these

bidders.

10. In the meantime as a consequence of the repeated approach of the

petitioner to the IDEMI requesting to reconsider its failure report in relation to the

meters of the petitioner, the IDEMI addressed a letter a E-mail dated 13 th

August,2015 to respondent no.2 which reads as under:-

"Dear Sir,

. This is with reference to your work order no. SP/SM/IDEMI/T- 1003/0814/002867 dated 10.7.2015 for type testing of single phase IR meters as per technical specifications of tender No.SP/T-1003/0814, IDEMI has carried out samples of energy meters of 5 firms for test of immunity of EMHF fields as per IS 13779: 1999 (amended up to date) and as per MSEDCL tender specifications.

The testing was carried out in presence of all the firms representative and MSEDCL representative. During testing none of the representatives raised any

objection for test set up but after non compliance of their meters, three of the firms requested to carry out the testing using fiber optic cable.

In this matter, on request of the firms we have forwarded e-mail on 06.08.2015 to CE Stores that we are reviewing the matter. As per standards IS

13779 we have tested correctly. However, due to recent developments in the same area, the test to be carried out using fiber optic cable . After consultation with various experts in the fields we have come to the conclusion that we shall retest the energy meters using fiber optic method being followed by other laboratories.

. Hence, we request to carry out retest on same sample submitted by MSEDCL and request you to hold the test reports issued to MSEDCL dated 20.07.2015 and accordingly also request to recall the reports.

You may appoint your representatives for the retest and inform all the firms accordingly. The test can be carried out on suitable dates after mutual discussion.

Regards, C.M.Patil Assistant Director IDEMI "

(emphasis supplied)

Pvr 9/17 wp2323-15L&T.doc

11. On the basis of the above communication of the IDEMI to

respondent no.2, it is the contention of the petitioner that the test report as

submitted by the IDEMI on the test conducted on the sample meters of the

petitioner on 14th July,2015 is required to be discarded and the entire tender

process carried out on the basis of the said test report is required to be recalled and

a fresh decision on the technical bids is required to be taken by respondent no.2.

It is the case of the petitioner that the EM-HF test conducted by the IDEMI has

proved to be inappropriate as according to the petitioner this is conceded by

IDEMI in the above communication dated 13 th August,2015. It is urged on behalf

of the petitioner that in the said communication dated 13 th August,2015 of the

IDEMI, it had categorically stated that it would carry out re-test on the same

samples submitted by the bidders with a request to hold the test report issued to

respondent no.2 on 20th July, 2015 and accordingly, IDEMI had requested for

recall of the reports. It is therefore, submitted that when the testing authority itself

had recalled the reports, it was not proper for respondent no.2 to go ahead with the

tender procedure and make a award of the contract in favour of respondent nos.3

to 5. The decision of respondent no.2 to undertake a tender process contrary to

the communication dated 13th August,2015 of the IDEMI is arbitrary and illegal

and thus, is required to be interfered by this Court as prayed for in the Writ

Petition.

12. On behalf of respondent no.2 a reply affidavit has been filed to

oppose the admission of the petition to contend that the Writ Petition is wholly

Pvr 10/17 wp2323-15L&T.doc

misconceived and not maintainable. It is urged on behalf of respondent no.2 that

the petitioner has acted in complete breach of the tender conditions inasmuch as

contrary to clause XXVI of the tender conditions which prohibited

correspondence post submission of tender, the petitioner has entered into

correspondence with the tendering authority as also the testing laboratory. It is

submitted that Clause 7.21 of the Technical Specifications (supra) has prescribed a

specific condition that the meter shall remain immune for the test of electro

magnetic HF/RF defined under test No.4.0 for EMI /EMC of IS13779:1999

amended up to date and that according to this standard the IDEMI had tested the

sample meters of the petitioner and the test on the same had failed on 14 th July,

2015. A report to this effect came to be forwarded to the petitioner on 20 th

July,2015. It is submitted that the petitioner however, has adopted a novel method

whereby contrary to the tender norms the petitioner has sought to impose not only

on the IDEMI but also on respondent no.2 a different method of testing of the

sample meters. This was admittedly not to the expert knowledge of the IDEMI as

the IDEMI had applied the standard procedure known to it when the test were

conducted on the sample meter of the petitioner. It is submitted that it was not the

petitioner alone whose meter was subjected to the test conducted by the IDEMI

but also the same test was conducted on the sample meter submitted by

respondent no.3 and the sample meter of respondent no.3 passed the test. It is

submitted that the communication dated 13th August,2015 issued by IDEMI was at

the behest of the petitioner and admittedly as a result of a correspondence

undertaken post submission of the bid by the petitioner. It is submitted that even

the communication dated 13th August,2015 of the IDEMI categorically states that

Pvr 11/17 wp2323-15L&T.doc

the test conducted on the sample meters on 14 th July,2014 was as per the standard

IS13779 and that IDEMI has tested the meters correctly. It is therefore, submitted

that only because it is the petitioner's view that there are recent developments and

those ought to be taken into consideration, cannot render the test undertaken by

the IDEMI meaningless more particularly when the test were admittedly

undertaken by the IDEMI as per the prescribed IS standards.

13. The next contention as urged on behalf of respondent no.2 is that the

petition is clearly barred by delay and laches inasmuch as the petitioner has

approached this Court on 9th September,2015 which is after issuance of letter of

award in favour of respondent nos.3 to 5 and one day prior to the issuance of work

order that is on 10th September,2015. It is submitted that the writ petition was

served on respondent no.2 on 18th September, 2015 with a notice of hearing of the

petition for 30th of September,2015. It is submitted that in fact the first lot of the

meters to be supplied by respondent nos.3 to 5 are ready and a joint inspection for

delivery in that regard is being held between 5 th to 18th October,2015. It is the

contention of respondent no.2 that the petitioner if at all was to be aggrieved ought

to have approached this Court immediately after the tests were undertaken by

IDEMI on 14th July,2015. It is submitted that the supply under the tender in

question is in public interest affecting the supply of electricity to consumers and

thus, on the nature of the pleas as raised by the petitioner, this Writ Petition cannot

be entertained. In support of the submissions as made on behalf of respondent

no.2, reliance is placed on the decision of the Supreme Court in the case of

"Michigan Rubber (India) Limited. Vs. State of Karnataka & Ors, ((2012) 8

Pvr 12/17 wp2323-15L&T.doc

SCC 216)".

14. We have heard the learned Counsel for the parties as also we have

perused the pleadings and the documents as placed on record.

15. The tender in question is for procurement of electricity meters. As

urged on behalf of respondent no.2 the same constitutes an important procurement

in public interest. The petitioner being one of the bidders had submitted its

technical bid alongwith the sample meters. It is an admitted position that a test on

the meter submitted by the petitioner as undertaken by the CPRI Bhopal had

failed. This test was similar to the one undertaken subsequently by the IDEMI as

noted by us above. The petitioner admittedly had no grievance on the same. As

regards the test conducted by IDEMI the sample meter submitted by the petitioner

again failed the test. This test was undertaken by the IDEMI on 14 th July,2015 in

the presence of the representative of the petitioner. Only after this test failed, the

petitioner chose to approach respondent no.2 as also the IDEMI to complain about

the procedure being followed by the IDEMI in testing the petitioner's meter. The

petitioner's contention is that technological advancement of the nature as set out

in its letter dated 23rd July,2015 and 10th August,2015 ought to have been adopted

by the IDEMI. It appears to us that the petitioner was successful in persuading the

IDEMI to address an E-mail dated 13th August,2015 to respondent no.2 whereby

though the IDEMI completely approves the procedure adopted in the test

undertaken on 14th July,2015 to be correct still expresses its willingness to

reconsider the test and on that ground has requested that the report submitted by it

Pvr 13/17 wp2323-15L&T.doc

on 20th July,2015 in pursuance of the test conducted on 14 th July,2015 be recalled.

It is only on the basis of this communication dated 13 th August,2015 of the IDEMI

to respondent no.2, the petitioner has urged that the tender process which is

completed be scrapped. In our opinion, the petitioner is not correct in raising the

contentions as urged. This is for the reason that the meter submitted by the

petitioner was subjected to a standardized test as set out in clauses 7.21, 7.22 and

7.23 read with 11.5 and 11.7 (supra) of the tender specifications. It is an admitted

position that the test which was conducted by IDEMI was as per the prescribed

standard namely the IS13779:1999. In fact, the IDEMI itself has stated so in its

communication dated 13th August,2015 which is not disputed by the petitioner.

Further condition no.24 which pertains to tender sample also specifically provides

that the results of the laboratory as received by respondent no.2 shall not be

disputed and shall be binding on the bidder. The contention of the petitioner if

accepted, it would amount to introducing in the testing of samples a different

method which is not known either to the testing laboratory or recognized by the

tender conditions. This was definitely not permissible as a bidding party cannot

foist a condition contrary to the norms set out by the tendering authority which are

made applicable to all the bidders.

16. It is quite clear that the petitioner in violation of Clause XXIV of the

instructions to the tenderers entered into a correspondence not only with the

tendering authority but also with the third party namely the IDEMI which was

nominated laboratory to undertake the test on the sample meters submitted by the

bidding parties. This was wholly impermissible and in fact a serious breach of the

Pvr 14/17 wp2323-15L&T.doc

tender condition on the part of the petitioner and on this count alone the petitioner

ought to be non-suited. A party which itself in breach of tender condition under

which it is participating in the tender cannot turn around and seek reliefs to recall

a tender process as is sought to be done by the petitioner. We are in complete

agreement with the contentions as urged on behalf of respondent no.2 that

respondent no.2 has appropriately followed the prescribed procedure under the

tender by subjecting the test of the sample meters of all the bidders by the

prescribed laboratories. It is pertinent that the petitioner has not urged any

malafides against the tender process undertaken by respondent no.2 and it is only

on the basis of an alternative testing method as being canvassed on behalf of the

petitioner, the petitioner has sought recall of the tender process.

17. It is further clear from the record that there is absolutely no fault

whatsoever in the decision making process as undertaken by respondent no.2 in

awarding of the tender to respondent nos.3 to 5 much less any arbitrariness or

discrimination. The sample meter as submitted by the petitioner admittedly did

not pass the test as prescribed in the tender conditions. The very consequence of

this was that the technical bid of the petitioner had failed and the petitioner was

not entitled for opening of its price bid. We are also in agreement on the

submissions as made on behalf of respondent no.2 that the petitioner has

approached this Court belatedly and that the petitioner even otherwise is not

entitled to maintain the petition on the principles of delay and laches. This is

borne out by the fact that if the petitioner had any real grievance, it would have

definitely approached this Court immediately when the test on the sample meter

Pvr 15/17 wp2323-15L&T.doc

failed on 14th July,2015. This was for the reason that the tender condition would

not permit the petitioner to undertake any correspondence after submission of the

tender with the tendering authority much less with the third party i.e. the IDEMI.

The petitioner allowed the tender process to progress culminating into the award

of the tender to respondent nos.3 to 5 by issuance of the letter of award on 1 st

September, 2015 and the Work Order in that regard on 10 th September,2015. This

Writ Petition was filed on 9th September,2015 and served on the respondents on

18th September,2015. The petitioner was completely aware of the progress of the

tender and that the price bids would be opened after the technical report would be

received by respondent no.2 from IDEMI. However, the petitioner permitted the

tender process to go ahead. Moreover, as on date the respondent nos.3 to 5 who

are successful bidders have already kept ready part of the supplies to be made to

respondent no.2 under the tender. We cannot loose sight of the fact that the

supplies are electricity meters and on which is dependent the supply of electricity

to large number of consumers. What is at stake is definitely a public interest. It is

well settled that the delay in approaching the Court is required to be considered on

the facts as would fall for consideration in a particular case. There can be no

second opinion that there is a delay on the part of the petitioners to approach the

Court. This Writ Petition therefore, also ought to fail on the principles of delay

and laches.

18. Learned Senior Counsel for Respondent no.2 has appropriately

placed reliance on the decision of the Supreme Court in the case "Michigan

Rubber (India) Ltd." (supra) wherein the Supreme Court taking into

Pvr 16/17 wp2323-15L&T.doc

consideration catena of judgments has held that judicial review of an

administrative action would not be available when the decision relating to award

of contract is bonafide and is in public interest and that the Courts will not, in

exercise of power of judicial review, interfere even if procedural aberration and

error in assessment or prejudice to a tenderer is made out. The power of judicial

review will not be permitted to be invoked to protect private interest at the cost of

public interest or to decide contractual dispute. The tenderer with a grievance can

always seek damages in civil court inasmuch as a contract is a commercial

transaction, evaluating tenders and awarding contracts are essentially commercial

functions. The Supreme Court has laid down the following test before a Court

could interfere in a tender or contractual matter in exercise of power of judicial

review.

(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone;

OR Whether the process adopted or decision made is so arbitrary and irrational that the court can say: 'the decision is such that no responsible

authority acting reasonably and in accordance with relevant law could have reached';

(ii) Whether public interest is affected."

In our opinion, in the facts of the present case, the answers to the

above test as enunciated by the Supreme Court are totally in the negative. We

are more than satisfied that there is no breach whatsoever or any arbitrariness in

the tender process undertaken by respondent no.2 culminating into the award of

the tender in favour of respondent nos.3 to 5 as noted by us above, which in any

Pvr 17/17 wp2323-15L&T.doc

manner would justify the exercise of writ jurisdiction of this Court under Article

226 of the Constitution.

19. In the light of the above discussion, the Writ Petition fails and is

accordingly, rejected. In the facts and circumstances of the case, the parties shall

bear their own costs.




                                                   
                            (G.S.Kulkarni, J.)
                                    ig                      (M.S.Sanklecha, J.)
                                  
            
         







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter