Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pvt. Ltd. vs & Ors
2011 Latest Caselaw 63 Bom

Citation : 2011 Latest Caselaw 63 Bom
Judgement Date : 16 November, 2011

Bombay High Court
Pvt. Ltd. vs & Ors on 16 November, 2011
Bench: Dr. D.Y. Chandrachud, A.A. Sayed
Dmt                                  1                                         wp744-11




                                                                           
        IN THE HIGH COURT OF JUDICATURE AT BOMBAY




                                                   
               ORDINARY ORIGNAL CIVIL JURISDICTION




                                                  
                      WRIT PETITION NO. 744 OF 2011

      M/s. Silver Land Developers 




                                           
      Pvt. Ltd., & Ors.
                            ig                          ..  Petitioners.
             versus

      The Empowered Committee
                          
      & Ors.                                            ..  Respondents.
                                         .....
        


      Mr. Aspi Chinoy, Sr. Adv. with Mr. Vinay Sonpal and
     



                    Mr. B.R. Vishwakarma for the Petitioners.

      Mr. B.M. Chatterjee with Mr. Rajinder Kumar and Ms.





                    Anamika Malhotra for R. Nos. 1 & 2.

      Mr. Suresh Kumar for Respondent Nos. 3 & 4.
                                  ......





                             CORAM :  DR.D.Y.CHANDRACHUD &
                                        A. A. SAYED, JJ.

16 November 2011.

Dmt 2 wp744-11

ORAL JUDGMENT : (PER DR. D. Y. CHANDRACHUD, J.)

An order has been passed by the Empowered

Committee on 21 February 2011 holding that the Petitioners are

not entitled to the benefit of the Industrial Park Scheme 2002.

The Scheme has been notified by the Central Government in

exercise of powers conferred by clause (iii) of Sub-section (4) of

Section 80-IA of the Income Tax Act, 1961. The Petitioners in

these proceedings under Article 226 of the Constitution question

the legality of the order of the Empowered Committee.

2. Sub-section (1) of Section 80-IA provides that where

the gross total income of an assessee includes profits and gains

derived by an undertaking or an enterprise from a business

referred to in sub-section (4), the assessee would be allowed, in

accordance with the provisions, in computing the total income,

a deduction of an amount equal to hundred per cent of the

profits and gains derived from such business for ten

consecutive assessment years. Under sub-section (2) the

Dmt 3 wp744-11

assessee has an option to claim the deduction for any ten

consecutive assessment years out of fifteen years beginning

from the year in which the undertaking or the enterprise

develops an industrial park. Sub-section (4) of Section 80-IA

contains a description of the undertakings or enterprises to

which the provision applies. Clause (iii) of sub-section (4) as

it stood during the material period to which the controversy

relates was to the following effect :

"(iii) any undertaking which develops, develops and

operates or maintains and operates an industrial

park notified by the Central Government in

accordance with the scheme framed and notified by

that Government for the period beginning on the 1st

day of April, 1997 and ending on the 31st day of

March, 2006."

3. Under Section 80-IA (4) (iii) the Central Government

was empowered to notify a scheme. The Central Government

Dmt 4 wp744-11

has notified schemes from time to time. The Scheme to which

the present dispute relates is notified on 1 April 2002 and is

called the Industrial Park Scheme, 2002. Para 3 of the Scheme

provides for the period of operation and is to the following

effect :

"3. Period of operation of the scheme - This

scheme shall be applicable for any undertaking

which develops, develops and operates or maintains

and operates an Industrial Park for the period

beginning on the 1st day of April, 1997 and ending

on the 31st day of March, 2006. In a case, where

an undertaking develops an Industrial Park on or

after the 1st day of April, 1999 and transfers the

operation and maintenance of such Industrial Park

to another undertaking (transferee undertaking), the

benefits shall be allowed to such transferee

undertaking for the remaining period in the ten

consecutive assessment years in a manner as if the

Dmt 5 wp744-11

operation and maintenance were not so transferred

to the transferee undertaking.

Para 4 defines the objectives of an industrial park which

includes, inter alia, in sub-para (b) "an industrial park for

development of infrastructural facilities or built-up space with

comon facilities in any area allotted or earmarked for the

purposes of industrial use". The Scheme provides two modes

for the grant of approval; (i) automatic approval and (ii) non-

automatic approval. The case of the Petitioners is admittedly

governed by the non-automatic approval route. In such cases

para 7 of the Scheme stipulated that all applications which

were not eligible for automatic approval shall require the

approval of the Empowered Committee constituted by the

Central Government. The Empowered Committee was required

to consider each application on a case to case basis subject to

its complying with the statutory requirements as prescribed by

the Ministry of Finance under the Income Tax Act, 1961 and

other statutory rules/obligations. Para 9 of the Scheme lays

Dmt 6 wp744-11

down certain general conditions and is to the following effect :

"9. General conditions.-(1) In case the

commencing of the Industrial Model Town or

Industrial Park or Growth Centre gets delayed by

more than 1 year from the date indicated in the

application, fresh approval may have to be obtained

to get the benefits under the Act. This condition

also applies to the existing approvals under the

Industrial Park Scheme, which envisages

commissioning of the Parks, latest by March 31,

2002.

(2) The tax benefits under the Act can be availed

only after the number of units indicated in the

application, are located in the industrial park."

4. The Petitioners initially applied to the Government

of Maharashtra on 14 June 2005 for the registration of their

Dmt 7 wp744-11

project at Jogeshwari (West) Mumbai as a private Information

Technology Park under a resolution of the State Government.

The State Government issued a letter of intent on 8 July 2005.

On 27 September 2005 the Directorate of Industries of the

State Government drew the attention of the Petitioners to the

Industrial Park Scheme of 2002 notified by the Union

Government under Section 80-IA(4)(iii). On 27 December 2005

the Petitioners submitted an application to the Union Ministry

of Commerce and Industry for approval of their Information

Technology Park under the Scheme. The proposed area of

the Park was stated to be 8261-56 sq.mt. and it was proposed

that the total number of industrial units would be eight. The

expected date of commencement of the Industrial Park was

stated to be 15 March 2006. The proforma provided by the

Union Government clarified that the expected / actual date of

commencement would denote the date when all the

infrastructural facilities for the proposed number of industrial

units have been provided.

Dmt 8 wp744-11

5. The Union Government in the Ministry of

Commerce and Industry conveyed the approval of the

Government to the proposal of the Petitioners for setting up of

an industrial park in terms of the Industrial Park Scheme, 2002

on 24 July 2006. According to the approval, the expected date

of commencement was to be 15 March 2006. Para 3 stipulates

that the Industrial Park should be in operation during the

period for which the benefits under Section 80-IA (4)(iii) are to

be availed of. Para 5 (ii) of the letter which was in terms

of para 9 of the Scheme then contains the following stipulation

:

(ii) In case the commencement of the Industrial

Park is delayed by more than one year from the

date as indicated in Para 1 (xi) of this approval

letter, fresh approval shall be required under the

Industrial Park Scheme, 2002, for availing benefits

under Sub-Section 4 (iii) of Section 80-IA of the

Income Tax Act, 1961.

Dmt 9 wp744-11

6. On 26 October 2006 the Petitioners addressed a

communication to the Union Ministry of Commerce and

Industry stating that the project would require a likely period

of two months for completion. The Petitioners stated that in

view of the then existing circumstances they would be able to

accommodate three units in the I.T. Park and consequently

sought a change in the number of units allowed from eight to

three. The proposed area of the I.T. Park was maintained at

8261.56 sq. mt. and similarly there was no change in the

proposed allocable area. The expected date of completion

was set back from 15 March 2006 to 31 March 2006.

7. On 8 March 2007, the Petitioners submitted an

application for the grant of an occupation certificate. The

Municipal Corporation of Greater Mumbai issued an occupation

certificate on 2 June 2007. On 17 April 2007 the Union

Ministry of Commerce and Industry sought a status report

from the State Directorate of Industries on a number of issues

Dmt 10 wp744-11

including the status of the development of the project and the

date of commencement. In a response dated 29 May 2007

a status report was forwarded. The State Directorate of

Industries clarified to the Empowered Committee that the

Municipal Corporation of Greater Mumbai had found that the

Architects had submitted a building completion certificate on 8

March 2007 after completion of the work at site. The view of

the State Government on the actual completion of the work

was as follows :-

" The Municipal Corporation of Greater

Mumbai concludes that the Building under

reference was completed on 08/03/2007 and

thereafter, issued OC on 02/06/2007 on the basis

of application filed by the applicant on 08/03/2007

considering completion of Building on 08/03/2007.

In this case, as per the confirmation report

given by Brihanmumbai Mahanager Palika (now

Dmt 11 wp744-11

MCGM) Applicant / Developers have completed

building work on 08/03/2007, and thereby complied

with norms of Industrial Park Scheme, 2002. Hence,

it is recommended to consider the request of

applicant under the said scheme."

8. On 10 July 2007 an intimation was addressed to the

Petitioners by the Union Ministry of Commerce and Industry in

the following terms :

"The date of commencement of your park is

15-03-2006. With one year grace period the park

should start functioning before 14-03-2007.

However, the State Government report indicated

that construction work is at final stage of

Completion & Occupation Certificate is awaited.

2. You are requested to furnish the following

details to this Department at the earliest for further

Dmt 12 wp744-11

processing your case :

a. Whether the park has become function? If so,

b. How many units have been located in your

park as on 14-03-2007?

(emphasis supplied)

The communication, significantly refers to the fact that the I.T.

Park, as stated in the application, should have been completed

by 15 March 2006 and notes that a one year grace period

would entail that the park should have started functioning

before 14 March 2007. Queries were accordingly addressed to

the Petitioners to clarify as to when the park had actually

become functional. In a reply dated 25 July 2007, the

Petitioners stated that as on 14 March 2007 three units were

located in I.T. Park, namely, (1) M/s. Tata Consultancy Services

Ltd., (2) M/s. Polaris Software Lab Ltd. and (3) M/s. Bharti

Airtel Ltd.

Dmt 13 wp744-11

9. On 3 August 2007, the Union Government sought a

No Objection Certificate from the land owner to the effect that

only the Petitioners shall claim benefit under Section 80 IA.

The NOC was furnished on 14 August 2007. On 21 September

2007 the Petitioners addressed a communication to the Union

Government stating that subsequently an additional unit,

namely, of M/s. Citigroup Global Services Ltd. had been located

in the I.T. Park and permission was sought. On 12 November

2007 the Petitioners stated that they had anticipated that they

will be allotted three industrial units. However, they were in a

position to accommodate five units for which an amendment in

the approval was sought.

10. On 25 August 2008, the Union Government in the

Ministry of Commerce and Industry rejected the application of

the Petitioners on the ground that since the expected date of

commencement of the Industrial Park is after 31 March 2006,

the application was not covered by the Industrial Park Scheme

of 2002. The Petitioners were accordingly advised to apply to

Dmt 14 wp744-11

the appropriate authority under the subsequent Scheme of

2008. On 6 January 2009, an order was passed by the Union

Government in the Ministry of Commerce and Industry

reiterating that since the expected/actual date of

commencement of the Industrial Park was 15 February 2007 as

reflected in the application dated 19 November 2008, the

application was not covered by the Scheme of 2002. The view

taken was that the Industrial Park Scheme, 2002 was applicable

only to Industrial Parks set up between 1 April 1992 and 31

March 2006.

11. The initial order dated 6 January 2009 was set

aside by a Division Bench of this Court on 16 June 2009 on

the ground that an opportunity of being heard was not granted

to the Petitioners and the matter was referred back to the

Empowered Committee for a fresh decision. Upon remand, a

hearing took place before the Empowered Committee on 7

September 2009 during the course of which the Committee

noted that "the most crucial element here is the date of

Dmt 15 wp744-11

completion of the building." The Empowered Committee

noted the submissions of the Petitioners that the date of the

completion of the building should be reckoned from the date

of the application, for the grant of an occupation certificate

and not from the date of the issuance thereof. Accordingly, it

was decided that the matter should be referred to the State

Government to take a report from the Municipal Corporation

about (i) The date of the application for issuance of a

completion certificate; (ii) The date of the completion of the

building as per law. Following this reference, on 20 November

2009, a report was submitted by the State Government

clarifying that according to the Municipal Corporation the

building under reference was completed on 8 March 2007 and

that an occupation certificate was issue on 2 June 2007 on the

basis of the application considering the completion of the

building as on 8 March 2007. The Directorate of Industries of

the State Government recommended in the report that since

the Petitioners had completed the work of the building on 8

March 2007, they should be regarded as having complied with

Dmt 16 wp744-11

the norms of the Industrial Park Scheme, 2002.

12. Upon receipt of the report of the State Government,

a further hearing took place before the Empowered Committee

on 21 December 2009. During the course of the hearing, a

representative of the Central Board of Direct Taxes contended

that an industrial park which commences operation after 31

March 2006 and before 31 March 2009 shall be governed by

the Scheme of 2008. Hence, according to the CBDT, since the

Petitioners had commenced operation of the industrial park

after 31 March 2006 and even after allowing the grace period

of upto one year that should not extend later than 31 March

2006. The Empowered Committee took the view that the issue

of the grace period should be resolved first before the CBDT,

the Department of Revenue and the Department of Industrial

Policy and Promotion and a fresh meeting of the Committee

should be convened thereafter.

13. On 7 July 2010 the Empowered Committee came to

Dmt 17 wp744-11

the conclusion that the Petitioners should not be granted the

benefit of the Industrial Park Scheme, 2002. In taking this view

the Committee noted that it had obtained the views of the

Revenue Department and the Department of Legal Affairs.

According to the clarification issued by CBDT on 2 June 2008

para 9 (1) of the Scheme only provided a condition of re-

notification of the Industrial Park in case there was a delay in

completion of the park by more than one year. According to

the the Empowered Committee, this only meant that if there

was a delay of less than one year, there was no need of re-

notification but that would not extend the operation of the

Scheme beyond 31 March 2006. The Committee took the view

that when the Scheme of 2002 was notified on 1 April 2002,

Section 80-IA (4) (iii) only applied to undertakings which were

to commence operation by 31 March 2006. Hence, it was held

that Para 9(1) of the Scheme should not be interpreted in a

manner which would extend the scope of exemption beyond

what was intended in the main statute. In sum and

substance the view of the the Empowered Committee was that

Dmt 18 wp744-11

since the Petitioners had not commenced the industrial park by

31 March 2006, they were not entitled to the benefit of the

Scheme.

14. This second order of the the Empowered

Committee was set aside by a Division Bench of this Court on

18 October 2010 in a Writ Petition under Article 266 of the

Constitution on the ground that the Committee had relied

upon material which was not disclosed to the Petitioners.

Following the second order of remand, the Empowered

Committee convened fresh hearings and thereafter rejected the

application of the Petitioners for the benefit of the Scheme of

2002 by an order dated 21 February 2011.

15. The impugned order dated 21 February 2011 of the

the Empowered Committee takes note of the legal opinion of

the Department of Legal Affairs and of the view of the

Revenue Department according to which any industrial park

which commences after 31 March 2006 is not eligible to be

Dmt 19 wp744-11

considered under the Industrial Park Scheme, 2002 and that the

one year grace period cannot extend beyond 31 March 2006.

The claim of the Petitioners has been consequently rejected on

the ground that since the industrial park was not completed on

or before 31 March 2006, they were not eligible for approval

under the Scheme of 2002.

16.

The learned Senior Counsel appearing on behalf of

the Petitioners urged the following submissions in assailing the

order of the the Empowered Committee :

(i) Section 80-IA (4) (iii) does not mandate that

development of an industrial park should be

completed by 31 March 2006. Several schemes

have in fact been notified by the Central

Government from time to time and the intent to

give the benefit of a deduction for developing

infrastructural facilities continues to exist until date;

Dmt 20 wp744-11

(ii) Under Section 80-IA (4) (iii) a benefit is available to

(i) either an assessee who is a developer; or (ii) an

assessee who develops and operates an industrial

park; or (iii) an assessee who maintains and

operates an industrial park in accordance with the

Scheme notified by the Central Government. Para

9(1) of the Scheme does contemplate a situation

where the commencement of the industrial park is

delayed by more than one year from the date

indicated in the application in which case a fresh

approval has to be obtained to get the benefit

under the Act. This condition has been also

applied to existing approvals under the Industrial

Park Scheme which had envisaged the

commissioning of the park, latest by 31 March 2002.

Clause 5 (2) of the letter of approval that was

granted to the Petitioners was inserted specifically

with reference to the expected date of completion

of 15 March 2006 and was in terms of Para 9 of

Dmt 21 wp744-11

the 2002 Scheme;

(iii) The subsequent scheme which has been framed by

the Central Government in 2008 has liberalised the

provisions even further by merely requiring that

the undertaking shall begin to develop an industrial

park;

(iv) In the present case the entire project was

completed by 8 March 2007. The Empowered

Committee in the course of its hearing also noted

that the crucial date was 14 March 2007.

(v) In the circumstances, the view which has been

taken on Para 9 (1) of the Scheme by the the

Empowered Committee is unduly technical and

would defeat the public purpose underlied Section

80-IA (4). An infrastructural project requires

investment of considerable amount of time, effort

Dmt 22 wp744-11

and money and if the interpretation which has

been placed by the the Empowered Committee

were to be adopted, the benefit of the provision

would be denied to several projects where

approvals were granted within a period of one year

prior to 31 March 2006 when the Scheme was to

expire. In the present case itself, approval was

granted to the project on 24 July 2006. As a

matter of fact, queries under the Right to

Information Act have revealed that approvals have

been granted to at least fifty projects as late as

April 2007. This would suggest that it has been

the consistent stand of the the Empowered

Committee that the completion of the project on or

before 31 March 2006 has not been regarded as an

inviolable condition for availment of benefits.

17. On the other hand, learned Counsel appearing on

behalf of the Revenue submitted that :

 Dmt                              23                                          wp744-11




                                                                         
       (i)     Para 3 of the Scheme of 2002 postulates that the 




                                                 

development of the facility has to be completed by

31 March 2006;

(ii) The Scheme cannot override the provisions of

Section 80-IA (4) (iii);

(iii) Para 9 of the Scheme would apply only to those

cases where there is a delay in the commencement

of the project of the industrial park but when the

commencement does not fall back beyond 31 March

2006;

(iv) In the present case occupation certificate was

granted only on 2 June 2007 and even if a grace

period of one year were to be granted, that would

also expire on 15 March 2007 being the date on

which a period of one year would expire from the

Dmt 24 wp744-11

expected date of completion; and

(v) The number of units for which approval is sought

constitutes an essential requirement. The

Petitioners sought to reduce the number of units

for which approval was taken from eight to three

and thereafter to five.

18. The rival submissions now fall for determination.

The object and purpose of Section 80-IA is to grant a

deduction, while computing the total income of the assessee of

an amount equal to hundred per cent of the profits and gains

derived from an eligible business for ten consecutive

assessment years out of fifteen years beginning from the year

in which inter alia the assessee develops an industrial park or

facility. The eligible businesses to which the provisions are

attracted are specified in sub-section (4) of Section 80-IA. The

object and purpose of Section 80-IA was to provide an impetus

to the growth of infrastructure in the country. Clause (iii) of

Dmt 25 wp744-11

sub-section (4) of Section 80-IA makes eligible an undertaking

which (i) develops; or (ii) develops and operates; or (iii)

maintains and operates an industrial park notified by the

Central Government in accordance with the Scheme framed for

the period beginning on 1 April 1997 and ending on 31 March

2006. An undertaking is eligible if it has either developed; or

developed and operated; or operated and maintained an

industrial park in accordance with the Scheme. The first

aspect of the matter which needs emphasis is that clause (iii)

of Section 80-IA (4) requires that the Scheme has to be notified

for the period between 1st April 1997 and 31 March 2006. The

statutory provision does not contain a specific requirement to

the effect that the industrial park had to be developed on or

before 31 March 2006. The requirement is that the industrial

park has to be developed in accordance with the Scheme

framed by the Central Government for the period between 1

April 1997 and 31 March 2006. The Scheme which was framed

by the Central Government stipulated the requirement for the

grant of approval in those cases which did not fall in the

Dmt 26 wp744-11

automatic approval route. Para 3 of the Scheme lays down

the period of operation of the Scheme. Under Para 3 the

Scheme is to be applicable to any undertaking which develops,

develops and operates or maintains and operates an Industrial

Park for the period beginning on 1 April 1997 and ending on 31

March 2006. Therefore, undoubtedly it was as a result of Para

3 that a requirement to the effect that the undertaking should

develop an industrial park for the period commencing on 1

April 1997 and ending on 31 March 2006 came to be

introduced. The Scheme, however, stipulated in Para 9 (1) that

in case the commencement of the industrial park is delayed by

more than one year from the date indicated in the application,

a fresh approval would have to be obtained to get the benefit

of the Act. The last sentence of Para 9 (1) then clarified that

this condition would also apply to the existing approvals under

the Industrial Park Scheme which envisaged the commissioning

of the park, latest by March 31, 2002. Para 9 (1) took notice of

the fact that approvals were granted under the previous

Scheme which envisaged the commissioning of parks by 31

Dmt 27 wp744-11

March 2002. The new Scheme was notified on 1 April 2002.

If 31 March 2002 was to be treated as an absolute cut-off then

it is unlikely that the last sentence of Para 9(1) would provide

that the condition which was spelt out in the said Para would

also apply to existing approvals. Consequently Para 9 of the

Scheme did contemplate situations where the commencement

of an industrial park was delayed by more than one year from

the date indicated in the application. The Scheme provides

that in such cases, a fresh approval would have to be obtained

in order to obtain the benefits under the Act.

19. The course of proceedings before the Empowered

Committee reveals that the application filed by the Petitioners

for the grant of approval was allowed on 24 July 2006 noting

that the expected date of completion was 15 March 2006. The

letter of approval is significant because clause 5(2) of the letter

stipulates that in case the commencement of the park is

delayed by more than one year from the date as indicated in

Para 1 (11) - 15 March 2006 - a fresh approval would be

Dmt 28 wp744-11

required under the Industrial Park Scheme, 2002 for availing of

benefits under Section 80-IA (4) (iii). Obviously therefore, when

the the Empowered Committee granted its approval on 24 July

2006 it did so conscious of the circumstance that the expected

date of completion was 31 March 2006. The Empowered

Committee took note of the possibility that the commencement

of the industrial park may be delayed by more than one year

from this date. The letter thereafter proceeded to stipulate

that in such an event a fresh approval was required. This is

an important circumstance, which has a bearing on the manner

in which the provisions of the Scheme were construed by the

Empowered Committee. At least when it granted its approval

on 27 July 2006 the Empowered Committee did not treat the

requirement that the industrial park should commence on 15

March 2006 as inviolable. In this regard it would be necessary

to also take notice of the fact that the notified date of

commencement, as referred to in the format provided by the

Union Government, was defined as denoted as the date from

which industrial facility proposed for the units having been

Dmt 29 wp744-11

provided.

20. The next important circumstance which would have

a bearing on the issue before the Court is the manner in

which the Union Government in the Ministry of Commerce and

Industry construed the Scheme during the course of the

proceedings. On 10 July 2007 the Union Government in its

communication to the Petitioners noted that the date of

commencement of the park (as recorded in the application) was

15 March 2006. The Government noted that with a one year

grace period the park should start functioning before 14 March

2007. The Petitioners were, therefore, called upon to disclose

as to whether the park had become functional and if not how

many units had been located as on 14 March 2007. On

remand a hearing took place before the Empowered Committee

on 7 September 2009. During the course of hearing the

Committee observed that the most crucial element was whether

the completion of the building had taken place before or after

14 March 2007. The Empowered Committee was persuaded to

Dmt 30 wp744-11

change its view on the basis of the position which was adopted

by the CBDT which was also minuted during the course of a

hearing which took place on 21 December 2009. The

Committee was of the view that the issue of the grace period

should be first resolved between the CBDT, the Department of

Revenue and the Department of Industrial Policy and

Promotion and a fresh meeting of the Empowered Committee

should be convened. The affidavit in reply that is filed in

these proceedings contains an extract of a legal opinion which

was received from the Department of Legal Affairs. The

opinion of the Department of Legal Affairs, as set out in the

reply, was to the following effect:

"Para 9(1) of Industrial Park Scheme, 2002, only

provides a condition of re-notification of the

industrial park, in case of delay of completion of

industrial park by more than one year from the

date indicated in the application. It only means

that if there is a delay of one year or less, there is

Dmt 31 wp744-11

no need for re-notification. But it does not in any

case extend the operation of the scheme beyond

31st March, 2006. The intention of para 9 (1) is also

very clear. When Industrial Park Scheme, 2002 was

notified on 1.4.2002, the main section 80-IA[4(iii)]

only applied to undertakings which were to

commence operation by 31 st March, 2006. Thus,

para 9(1) of the scheme cannot be interpreted in a

manner which would extend the scope of

exemption beyond what was intended in the main

statute. Hence, if an industrial park has not

commenced operation by 31st March, 2006, it shall

not be governed by the provision of the Industrial

Park Scheme, 2002". (emphasis supplied).

The view which finds acceptance by the Department of Legal

Affairs postulates that when the Industrial Park Scheme of 2002

was notified on 1 April 2002, Section 80-IA(4)(iii) only applied

to undertakings which were to commence operations by 31

Dmt 32 wp744-11

March 2006. This conclusion is not a correct reading of

Section 80-IA(4)(iii). What Section 80-IA(4)(iii) postulated was

that the section would apply to any undertaking which

develops, develops and operates or maintains and operates an

industrial park notified by the Central Government in

accordance with a Scheme framed for the period beginning on

1 April 1997 and ending with 31 March 2006. The provision

does not contain a condition to the effect that the industrial

park must commence operation by 31 March 2006. As a

matter of fact, the provision applies to an undertaking which

either develops, or develops and operates or maintains and

operates an industrial park. Based on the opinion which was

formed by the Department of Legal Affairs, the Empowered

Committee accepted the contention of the Department that

Para 9 (1) cannot be interpreted in a manner which would

extend the scope of exemption beyond what was enacted in

the main statute. Now, undoubtedly, as a matter of first

principle, a scheme which constitutes a piece of subordinate

legislation, cannot override the provisions of the parent

Dmt 33 wp744-11

enactment. That is, however, not the case here. The statute

contemplated that a scheme would be notified for the period

between 1 April 1997 and 31 March 2006. The Scheme

contemplates that the industrial park should be developed,

developed and operated or be maintained and operated for the

period beginning on 1 April 1997 and ending on 31 March

2006. This stipulation in Para 3 of the Scheme must however

be read harmoniously with Para 9 which contemplates a

situation where the commencement of any industrial park is

delayed by more than one year from the date indicated in the

application in which event a fresh approval has to be granted.

This condition was also made applicable to existing approvals

under the Scheme which had envisaged the commissioning of

the park March by 31, 2002, prior to the enforcement of the

Scheme on 1 April 2002.

21. We find merit in the contention of the Petitioners

that if the position which has been adopted by the Empowered

Committee were to be accepted, that would result in virtually

Dmt 34 wp744-11

defeating the salutary public purpose which underlies Section

80-IA (4) (iii). Notice would have to be taken of the fact

that infrastructural projects require a considerable amount of

investment and a time lag is involved in the completion of the

project. The view of the Empowered Committee is that Para 9

of the Scheme would apply to a delay in a project beyond one

year but that the delayed date of completion should not in

any event fall beyond 31 March 2006. If this were to be

accepted as the correct interpretation, that will denude the

benefit of Section 80-IA to project where approvals were

granted a few months before 31 March 2006 and the

completion date spills over beyond that date. There is no

indication either in the statute or in the scheme that

Parliament or its delegate intended to deprive the assessee of

the benefit of Section 80IA(4)(iii). Para 9 of the Scheme would

would in fact indicate an intent not to deprive the benefit of

Section 80IA (4) (iii) save and except that if the commencement

of the project is delayed beyond one year a fresh approval

would have to be obtained to get the benefits under the Act.

Dmt 35 wp744-11

The Court cannot also ignore the fact that the intent of the

legislature and its executive is not to discontinue the benefits

available in law. The Union Government has further liberalised

the scheme in 2008 by requiring that the undertaking shall

begin to develop the industrial park by a stipulated date. In

this case, approvals had been granted on 24 July 2006 which

was several months after 31 March 2006 when the Scheme of

2002 was to expire.

22. During the course of the hearing, learned Counsel

appearing on behalf of the Revenue relied on the fact that

though the Petitioners had initially stated in their application

that they would have eight units in the industrial park, this

figure was sought to be reduced to three. Learned Counsel

submitted that Para 9(2) of the Scheme speaks that the tax

benefits under the Act can be availed of only after the number

of units indicated in the application are located in the

industrial park. In response to this, the attention of the Court

was drawn by the learned Counsel for the Petitioners to the

Dmt 36 wp744-11

fact that the Petitioners had in their original application stated

that there would be eight units; that the proposed area of the

industrial park would be 8261-56 sq. mt.; and that the

proposed allocable area of would be 6529.42 sq. mt. By their

further application dated 26 October 2006 the Petitioners

sought to alter the number of units from eight to three.

However, there was no change proposed either in the area as

declared earlier or in the allocable area. Learned Counsel

submitted that the Petitioners fulfilled in substance the object

and substance underlying the Scheme and the Department was

notified on 25 July 2007 that three units located in the park as

on 14 March 2007 were occupied by Tata Consultancy Services

Ltd., Polaris Software Lab. Ltd., and Bharti Airtel Ltd.

Subsequently, the Petitioners notified the Department that an

additional unit had been occupied by Citigroup Global Services

Ltd.

23. The application filed by the Petitioners for a

modification of the number of approved units was not allowed

Dmt 37 wp744-11

purely on the ground that the development of the industrial

park was completed beyond 31 March 2006. For the reasons

already indicated by us in the earlier part of this judgment, we

have come to the conclusion that the Respondents were not

justified in rejecting the application purely on the ground that

the development of the park was not complete by 31 March

2006. In holding thus, the Empowered Committee disabled

itself from exercising the power and jurisdiction which it had

under Para 9(1) of the Scheme.

24. The attention of the Court has also been drawn to

the fact that in fifty cases, approvals have been granted under

the Scheme of 2002 beyond 31 March 2006 and as a matter of

fact as late as in April 2007. Learned Counsel on behalf of the

Revenue has submitted that the Department would seek to

revoke those permissions which have been granted in other

cases. Be that as it may, for the reasons indicated earlier we

have come to the conclusion that the basis on which the

Empowered Committee has rejected the application filed by the

Dmt 38 wp744-11

Petitioners is contrary to law and would have to be set aside.

25. We, accordingly, dispose of this Petition by quashing

and setting aside the impugned order of the Empowered

Committee dated 21 February 2011. We direct in consequence

that the Empowered Committee shall consider the application

filed by the Petitioners including for the reduction of units

without holding the Petitioners to be disentitled on the ground

that has been found to be erroneous in the judgment of this

Court. The Committee, it is clarified, would be at liberty to

consider the application in accordance with the provisions of

law.

26. Rule is made absolute in the aforesaid terms.

There shall be no order as to costs.





                                              (Dr. D.Y. Chandrachud, J.)



                                                (A. A. Sayed, J.)





 Dmt          39                               wp744-11




                                          
                  
                 
                 
         
        
        
     







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter