Citation : 2011 Latest Caselaw 222 Bom
Judgement Date : 13 December, 2011
1 app-211-09.sxw
dgm
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO. 211 OF 2009
IN
SUIT NO. 3353 OF 1986
Jamnadas Mathradas .... Appellant
ig (Orig. Plaintiff)
vs
1 M/s.Baf Hira Builders Private Limited
2 N. L. Hiranandani
3 S. M. Bafna
4 Laxmi Builders .... Respondents
(Orig. Defendants)
Mr. Amar Talreja for the Appellant.
Mr. Gaurav Joshi i/by M/s. Vivek Kantawala & Co. for the
respondents.
CORAM: D.K. DESHMUKH &
ANOOP V. MOHTA, JJ.
JUDGMENT RESERVED ON : November 14, 2011
JUDGMENT PRONOUNCED ON : December 13, 2011
JUDGMENT: (Per Anoop V. Mohta, J.)
The Appellant (the Plaintiff) has challenged the judgment and
decree dated 24 October, 2008 whereby his Suit for specific
2 app-211-09.sxw
performance against all the Respondents has been dismissed in toto.
2 The Appellant attracted by Respondents 1 to 3's advertisement
dated 1 July 1979 alleged to have booked a two room kitchen flat
bearing Flat No.20-A, on the 4th floor of Building No.5 at Baf-Hira
Nagar, Marve Road, Malad (West), Mumbai and paid the earnest
money by a cheque on 2 July 1979 of Rs.5,500/- in favour of
Respondent No.1 and paid cash to one M/s.Laxmi Housing Agency,
alleged sole agent. The same were duly acknowledged.
3 On 3 November 1979 the Appellant enquired about the
agreement and the commencement of construction date. That was
followed by a communication of another letter dated 17 November
1981. On a communication from M/s. Laxmi Agency, the Plaintiff
visited the office also on 19 February 1981. As alleged an assurance
was again given by Respondents 1 to 3 that building's construction
would commence by 15 April 1981 and the work would be completed
in 18 to 20 months. The Appellant communicated on 23 August 1981
to the Respondents that they were bound by the original contract
terms and conditions, therefor not willing to modify the terms and
conditions of payment and consideration as informed in the meeting
3 app-211-09.sxw
dated 14 August 1981 by Respondents 1 to 3. The construction work
never commenced as stated by the Respondents. Advocate's notice
dated 18 October 1982 was sent by the Plaintiff to execute the
agreement. The Plaintiff thereafter also relied upon oral assurances as
contented, till July 1986. Respondents 1 to 3 had conveyed by an
agreement the property in favour of Respondent no.4 who had
commenced the construction on the site.
4 As noted Respondent no.4 was carrying out construction of the
building on the said plot, the Plaintiff, therefore, called upon
Respondent no.2 by notice dated 8 August 1986 to execute the
agreement. Respondent no.4 by Advocate's reply dated 4 September
1986 denied the knowledge of their agreement.
5 The Plaintiff insisted and claimed the right, based upon the offer
brochures by notice dated 15 September 1986 and ultimately filed the
Suit on 19 November 1986. There was no ad-interim order and/or
any protection and/or during the pendency of the Suit till its decision.
By the reasoned judgment and order, the learned Single Judge on
24.10.2008, after considering all the 14 issues together, dismissed
the Suit with costs and has held as under :
4 app-211-09.sxw
(a) The Plaintiff failed to prove that Defendant no.1 has
advertised to sell the flats at BAF-HIRA Nagar, Marve Road, Malad
(West), Mumbai 400 064 on 1.7.1979; (b) The Plaintiff failed to
prove that he had agreed to purchase one flat bearing No.75/A/20,
two room kitchen area about 450 sq.ft on 4th floor, building No.5, "A"
Wing at Bafna Nagar, Malad (West), Mumbai or any other such
number as per the advertisement given by defendant No.1; and is
ready and willing to pay the balance amount of price fixed for the flat
by defendant Nos. 1 to 3; (c)The Plaintiff failed to prove that in
pursuance to the contract to sell the flat as per advertisement, the
defendant no.1 accepted part of the sale price of Rs.5,500/- from the
plaintiff on 3.7.1979; (d) The plaintiff is not entitled to decree for
possession of the flat and for specific performance of the contract /
agreement of sale to him by defendants 1 to 3; (e) The Plaintiff is not
entitled to in lieu of decree for specific performance as loss and
damages for the breach of agreement committed by the defendants 1
to 3 for sale in favour of Plaintiff; (f) Defendant no.4 proved that
he was a bonafide purchaser of the building which was sold by
Defendant no.1 and (g)The Plaintiff failed to prove that the Suit is
5 app-211-09.sxw
within limitation and is bad for non-joinder of necessary parties.
6 After hearing both the parties and going through the documents
and considering the rival submissions so made and even after re-
visiting the issues so raised, we have to see whether case is made out
by the Appellant to interfere with the reasoned judgment and order
passed by the learned Single Judge by exercising the judicial
discretion, while dismissing the Suit for specific performance of the
contract.
7 First and foremost issue is about the limitation in view of Article
54 of The Limitation Act, 1963. Admittedly, the alleged
acknowledgment/agreement was entered into on 2 July 1979. The
amount of Rs.5,500/- was paid by a cheque to Respondent no.1
towards the earnest money through M/s. Laxmi Housing Agency,
alleged to be the sole agent. There was no details and description of
the flat as there was no constructed building. There was no specific
agreement entered into at any point of time. The building
construction was never commenced and/or completed by Respondent
no.1. After 3 November 1979 another letter was addressed by the
Appellant/Plaintiff on 17 January 1981 and a copy was also sent to
6 app-211-09.sxw
M/s. Laxmi Housing Agency referring to several telephonic
conversations. From January 1981 upto 14 August 1981 various
meetings, took place as alleged. By referring to letter dated 14
August 1981 and the meeting, the Appellant by telegram dated 23
August 1981, refused to accept the modification of the terms with
regard to cost and consideration of the flat and insisted for original
terms and conditions only. The Respondents 1 to 3 and M/s.Laxmi
Housing Agency never accepted and/or agreed to proceed on the
original terms and conditions at any point of time. The Appellant by a
by a notice dated 18 October 1982 again requested to execute the
agreement as per the original offer. Admittedly, no legal proceedings
were initiated by the Appellant except filing of the Suit on 19
November 1986, after exchanges of the legal notices between the
parties. If the Appellant agreed for the terms and conditions which
provide that the possession would be given within two years and later
on refused to accept the modified terms and conditions as admittedly
opposed by the communication/telegram and still waited for more
than three years and filed the Suit in the year 1986, in our view, is not
entitled for any relief in such Suit merely on the basis of alleged oral
assurances and communications. Once the agreement is in writing,
oral communication and/or modification, even if any, needs to be
7 app-211-09.sxw
substantiated by the parties one who wants to rely upon such oral
communication/agreement. The Appellant failed to prove the same.
The contention that the time was not fixed for performance and there
was no notice of refusal from the Respondents side, is unacceptable in
the facts and circumstances of the case specifically when there was no
specific agreement executed between the parties except the
payment/acknowledgment of earnest money based upon the offer.
The legal notice dated 18 October 1982 was sent by the Appellant to
the Respondents. Therefore even the last notice of 8 August 1986
could not save the limitation. The Suit as filed and as observed by
the learned Single Judge was time barred. The learned Judge by
giving detailed reasons rightly relied upon the material on record
including the telegram whereby the Appellant/plaintiff has insisted to
execute the agreement, based upon the original offer and even
threatened to take action for damages. The contents of the said
telegram are not in dispute. The Appellant had knowledge about the
intention of the Respondents, if any, not to perform their part of the
contract based upon offer conditions. There is no force in the
contention that the Suit as filed within a year from the last notice
dated 8 August 1986 on the basis of Motilal Jain vs. Ramdasi Devi,1
1 2000 (4) Civil L.J. 524 (SC): (2000) 6 SCC 420
8 app-211-09.sxw
is maintainable. The facts are totally different and distinct and
distinguishable. Merely because the Appellant had chosen to issue
notice asking the Respondents to execute the sale deed in the year
1986, in our view no way save the Suit as filed on 19 November 1986.
8 Importantly, the specific performance can be granted of
immovable property based upon the clear terms and conditions along
with the description of the property. In the present case, there was no
specific agreement between the parties except the alleged
acknowledgment of receipt of the earnest money. There was no
specific agreement executed at any point of time. There is sufficient
material on record to show that the Respondent never commenced the
construction immediately. Therefore, there was no occasion to fix
further price of flat and/or its instalment, if any. Therefore, there
was no final agreement for consideration of the flat. The construction
never took place within a span of two years. As noted, the Appellant
even failed to agree for modified terms and conditions including the
payment so proposed. The building no.5 was never constructed at
any point of time. As noted, the acknowledgment refers to flat in
building no.5. In view of this matter, as there is clear lacking of terms
and conditions as well as description of the property and as there
9 app-211-09.sxw
exists no such building no.5, apart from delay, and as there was no
interim order or protection operating in favour of the Appellant, at
any point of time and Respondent no.4 being subsequent purchaser,
completed the construction and third party rights have already been
created and there exists no such flat no.20 in building no.5, "A" Wing
as claimed and if the specific performance as claimed, even if any just
cannot be granted and as the leaned Judge has exercised the
discretion, we also see no reason to interfere with the judgment and
order so passed.
9 The Court cannot pass a judgment or decree which is un-
executable specially in a Suit for specific performance. Therefore,
whether there was valid and/or binding contract as the Appellant
based upon the offer/brochures made the payment through the
exclusive agent, which is also not proved, is also looses its importance
in the present facts and circumstances of the case. The readiness and
willingness which is also basic element of such Suit for specific
performance, as rightly observed by the leaned Single Judge, by giving
reason and we also confirm, after going through the material and
documents on record that the Appellant failed to prove that he was
ready and willing continuously before filing of the Suit and even
10 app-211-09.sxw
thereafter. The leaned Judge has rightly relied on N. P. Thirugnanam
vs. Dr. R. Jagan Mohan Rao, (1995) 5 SCC 115. The issue with
regard to readiness and willingness is always on the foundation of
valid and clear executable agreement. If there is no clear terms
agreed with regard to description of the property and also of
consideration, the submission with regard to the willingness and
readiness is also unacceptable.
10 Admittedly the construction was commenced by Respondent no.
4 with whom there was no agreement of the Appellant of any kind.
By agreement dated 24 August 1984, Respondent no.4 purchased the
property from Respondents 1 to 3. The third party rights have been
created even thereafter. The Suit was filed in the year 1986. The
Appellant's claim, therefore to grant a decree as prayed of specific
performance declaring the agreement/acknowledgment of the year
1979 valid and binding, in our view also cannot be granted.
11 Respondents 1 to 3, in view of above, was not in a position to
execute and/or give the possession of the alleged flat as the premises
itself was sold to Respondent no.4. There was no agreement and/or
challenged raised within limitation and no interim relief sought at the
11 app-211-09.sxw
appropriate stage, Respondent no.4 was also not in a position to give
possession of the flat as there was no specific agreement executed
between the Appellant and Respondent no.4, specially when
Respondent no.4, as noted above, was a bonafide purchaser of the
building. In totality, therefore, the dismissal of the Suit by the
learned Judge cannot be faulted with.
Once it is held that the Appellant/plaintiff is not entitled to
decree for possession of the flat and for specific performance of the
agreement of sale, the learned Judge, as the Appellant/plaintiff failed
to prove, by placing the material evidence in support of his alleged
loss and damages for the breach of the agreement by Defendants 1 to
3 and thereby rightly dismissed the claim of damages also.
13 Having once observed above that the Appellant/plaintiff failed
to prove his case and as not entitled for any decree for possession on
the basis of the agreement, and as the Suit itself is barred by the
limitation, there was no question of granting any compensation for the
breach as alleged, except refund of earnest money. There is no
question of any direction by invoking Section 151 of Code of Civil
Procedure (CPC) to provide any flat based upon the agreement
12 app-211-09.sxw
between the parties. The Appellant's readiness and willingness, as
relied, as was not continued at the relevant time, the same cannot be
accepted now at this appellate stage of the proceedings basically when
the Suit of specific performance as filed itself is dismissed by the
learned Judge with reasoned order.
14 Having once observed above, in our view also, based upon the
Ready Reckoner, the claimed compensation cannot be awarded. Here,
there is no question of denial of right to the Appellant on the basis of
alleged mere price rise, but in view of above reasoning itself. The
Appellant failed to prove the agreement dated 24 August 1984 was
bogus or sham document to defraud his claim and/or it was created
with malafide intention. The Appellant/plaintiff did not examine any
other witness in support of his allegations except his own testimony.
The Appellant also failed to prove that the Respondents have no better
title of the property. The Appellant was not entitled for specific
performance based upon vague, unclear agreement, specifically with
regard to the description of the property. Respondent no.4's reply
with whom never executed any agreement by the Appellant, the
denial, even if any, cannot bring the Suit within limitation based upon
the agreement of the year 1979 executed between the Appellant and
13 app-211-09.sxw
Respondents 1 to 3.
15 In view of above reasoning and as facts and circumstances are
distinct and distinguishable, the other citation so relied upon by the
Appellant, in our view also no way assist the Appellant to set aside the
judgment and decree passed by the learned Judge.
However, the learned counsel for Respondents, on instructions,
without prejudice to their rights and contentions expressed their
willingness to pay a lump sum amount of Rs.1,67,500/- towards
damages as prayed in prayer (e) and further ready to pay an interest
on the said amount from the date of the order, if any. The statement is
also made to make the payment of earnest amount of Rs.5,500/- as
prayed in prayer clause (d) with 10% interest per annum from 3 July
1979. The Appellant denied this offer. In our opinion, however, in
view of the statement, made on behalf of the Defendants-Respondents,
reliefs in terms of prayer clauses (d) and (e) of the plaint can be
granted to the Appellant. The appeal is dismissed. However, in view
of the statement made on behalf of the Defendants-Respondents, the
Defendants are directed to pay an amount of Rs.1,67,500/- with
interest at the rate of 10% per annum from the date of this order till
14 app-211-09.sxw
realisation. The Defendants-Respondents are also directed to pay Rs.
5,500/- with interest at the rate of 10% per annum from 3.7.1979 till
the date of payment. The payment be made within a period of four
weeks from today.
17 The Appeal is disposed of in the above terms. There shall be no
order as to costs.
(ANOOP V. MOHTA, J.) (D. K. DESHMUKH,J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!