Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Registered Office At Tel.Bhuvan vs Registered Under The Companies ...
2010 Latest Caselaw 46 Bom

Citation : 2010 Latest Caselaw 46 Bom
Judgement Date : 18 October, 2010

Bombay High Court
Registered Office At Tel.Bhuvan vs Registered Under The Companies ... on 18 October, 2010
Bench: Anoop V.Mohta
    ssm                                         1                                 arbp325.08.sxw


                    IN THE  HIGH COURT OF JUDICATURE AT BOMBAY




                                                                                        
                        ORDINARY ORIGINAL CIVIL JURISDICTION

                         ARBITRATION PETITION NO. 325  OF 2008




                                                                
    Oil & Natural Gas Corpn. Ltd.
    A public sector undertaking incorporated
    under the Companies Act, 1956 having its




                                                               
    Registered Office at Tel.Bhuvan, Dehradun
    India and its Mumbai regional Business Centre at 502,
    Bengal Chemicals Bhavan, Prabhadevi, Mumbai 400 025                  ....   Petitioner




                                                   
           Vs

    DOLPHIN Offshore Enterprises (I) Ltd.
                                
    Registered under the Companies Act, 1956
    having its registered office at 1001, Raheja
    Centre 214, Nariman Point, Mumbai-21                                 ....    Respondent
                               
    Mr.Pradeep Sancheti, Senior Counsel i/by M/s.Vyas & Bhalwal for the petitioner.
    Mr. V. K. Rambhadran for the respondent. 
          


                                         CORAM:   ANOOP V. MOHTA, J.

DATE : 18th October, 2010

JUDGMENT:-

Rule, returnable forthwith. By consent of the parties, heard finally.

2 The petitioner has challenged the Award dated 2nd April, 2008 ("the

Award") under Section 34 of the Arbitration & Conciliation Act, 1996 ("the Act")

passed by the Arbitral Tribunal.

3 The basic facts as per the petitioner are as under:-

     ssm                                            2                                   arbp325.08.sxw


    (a)     The petitioner is the owner of the Vessel named "Sindhu 14" (hereinafter 




                                                                                             
    referred to as "the vessel").  




                                                                    
    (b)     In response to the Tender Notice No.MRBC/MM/TECH/O and M/10(18) 

99 (`Tender') dated February 19, 1999 issued by the petitioner, the Respondent

submitted its bid for rendering the services of manning, running, operation,

victualising and maintenance for the aforesaid vessel. The bid of the Respondent

was accepted by the petitioner which was communicated to the Respondent by

the Letter of Intent (LOI) dated August 11, 1999 which was then eventually

culminated in Contract dated November 29, 1999 between the parties (the

contract).

(c) The vessel was handed over to the Respondent on August 22, 1999 by the

outgoing operator M/s. Seaspan Shipping Ltd. The Contract was valid for two &

half years with effect from August 22, 1999 till February 21, 2002.

(d) The Contract envisaged maintenance to seaworthiness by the Respondent

along with the other necessary incidental repairs and maintenance needed for

effective functioning of the vessel. The process of delivery of the said vessel by

the outgoing operator and taking over thereof by Respondent technically known

as "Handing over - Taking over" - (HOTO') was done under clause 3 of the

contract. The HOTO process and formalities thereto consisted of a Protocol

signed by both the parties. An independent survey Agency appointed by the

petitioner to evaluate the condition and to prepare a condition report. The

ssm 3 arbp325.08.sxw

Protocol provided for preparation of a list of defects in the hull, machinery and

equipment of the said vessel. The defects were noticed in the presence of the

representatives of both the parties and a list ("HOTO list") was prepared by the

independent surveyors Messrs Metcalf Hodkingon Pvt.Ltd., containing 221 defects

on August 22, 1999.

(e) After the HOTO list was prepared, petitioner desired to know the estimated

costs of rectification of the listed defects and vide contract

No.MRBC/LOG/MP/HOTO/ESTM/2000 dated March 23, 2000, the petitioner

appointed J. Basheer and Associates Surveyors Pvt.Ltd for the purpose of

estimation of cost for rectification of HOTO defects of the vessel as detailed in the

tender. The report of the said J. Basheer and Associates is of January 25, 2001.

(f) However the petitioner processed the invoice submitted by Respondent as

agreed in the contract which resulted in deduction of payment which was outside

the scope of the work contract.

(g) In the said arbitral proceedings, respondent sought for an award interalia

praying that the petitioner herein be directed to pay the Respondent a sum of Rs.

24,77,121 along with interest at the rate of 18% per annum from October 12,

2002 and also prayed for costs thereto.

4 There were eight claims raised by the respondent supported by the

documents. The petitioner resisted the same by placing on record documents as

well as relevant clauses of the Agreement between the parties. The learned

ssm 4 arbp325.08.sxw

Tribunal, considering the details of respective claims and the defence so raised

and after giving opportunity to both the parties, gave the findings on individual

claim and concluded in the following words:

"(A) The Oil and Natural Gas Corporation, the Respondents

herein are ordered and directed to pay to Dolphin Offshore

Enterprises (I) Ltd., the claimants herein, the sum of Rs.22,29,226.00

(Rupees twenty-two lacs twenty-nine thousand two hundred twenty-

six only) with interest thereon at the rate of 12% per annum from

12.10.2002 till payment or realisation whichever is earlier.

(B) Oil and Natural Gas Corporation Ltd., the Respondents herein

are ordered and directed to pay to Dolphin Offshore Enterprises (I)

Ltd., the Claimants herein the sum of Rs.5,00,000.00 (Rupees: Five

lacs only) towards costs of these proceedings."

By consent, the sum amount is corrected as Rs.21,60,606/-

5 The petitioner's submission with regard to the grant of interest inspite of

specific clauses of the Agreement has some force as the Supreme Court judgment

cited by the learned counsel appearing for the respondent is not applicable on

facts as well as the agreed clauses between the parties. In Sayeed Ahmed and

Company vs. State of Uttar Pradesh & ors., (2009) 12 SCC 26, the Supreme

Court has dealt with Sections 31(7) (a) and (b) and 34 of the Act. The relevant

portion of Sections 28(3) and 31(7) are as under:

"28. Rules applicable to substance of dispute.- (1) .....

     ssm                                             5                                  arbp325.08.sxw


                  (2) ............




                                                                                             
                  (3)        In   all   cases,   the   arbitral   tribunal   shall   decide   in 

accordance with the terms of the contract and shall take into account

the usages of the trade applicable to the transaction.

31. Form and contents of arbitral award. - (1) ...

(2) ....

(3) ......

(4) ...........

(5) .........

(6) ..........

(7) (a) Unless otherwise agreed by the parties, where and

insofar as an arbitral award is for the payment of money, the arbitral

tribunal may include in the sum for which the award is made

interest, at such rate as it deems reasonable, on the whole or any

part of the money, for the whole or any part of the period between

the date on which the cause of action arose and the date on which

the award is made.

(b) A sum directed to be paid by an arbitral award shall,

unless the award otherwise directs, carry interest at the rate of

eighteen per centum per annum from the date of the award to the

date of payment.

6 The relevant clauses of the Agreement are as under:

"22.0 ARBITRATION:

                 22.1        Except   as   otherwise   provided   elsewhere   in   the 




     ssm                                          6                                  arbp325.08.sxw


contract, if any dispute, difference, question or disagreement or

matter whatsoever shall, before or after completion or abandonment

of work or during extended period, hereafter arises between the

parties hereto or respective representative or assignees concerning

with the construction, meaning, operation or effect of the contract or

out of or relating to the contract or breach thereof shall be referred

to arbitration.

22.2 The reference to arbitration shall be to a arbitral

tribunal consisting of three arbitrators. Each party shall appoint one

arbitrator and the two appointed arbitrators shall appoint the third

arbitrator, who shall act as the presiding arbitrator.

                  22.3    ................
     



                  22.4    .................

                  22.5    It is a term of the contract that the cost of arbitration 





          will be borne by the parties in equal shares. 





                  22.6    It is also a term of the Contract that neither party to 

this agreement shall be entitled to the interest on the amount of

award.

                  22.7    ...............

                  22.8    Subject as aforesaid, the provisions of Arbitration and 

Conciliation Act, 1996 and any statutory modifications or re-

ssm 7 arbp325.08.sxw

enactments thereof and rules made thereunder for the time being in

force shall apply to the arbitration proceedings under this clause."

7 The above agreed clauses are clear to the effect that the parties agreed

that"Neither party to this agreement shall be entitled to the interest on the

amount of award". It is also agreed that subject to aforesaid, the provisions of

the Act shall apply to the arbitration proceeding between the parties. It is also

agreed that any dispute and difference or question or disagreement, before or

after completion and/or during extended period, between the parties, with the

construction, meaning, operation or effect of the contract or out of or relating to

the contract or breach thereof, shall be referred to arbitration. Therefore, it is

agreed that the arbitral Tribunal is empowered to decide the dispute, difference or

disagreement concerning construction, meaning, operation and effect of contract

or out of or relating to the contract and/or breach thereof. In view of above

specific agreed clauses, in my view, the arbitral Tribunal ought not to have

awarded the interest on the sum of Rs.22,29,226/- at the rate of 12% per annum

from 12.10.2002 till payment or realisation whichever is earlier as awarded, as it

was specifically agreed by both the parties that they shall not be entitled for any

interest on the amount of award.

8 It is necessary to consider basic notwithstanding/ non-obstante clause i.e.

"unless otherwise agreed by the parties" of Section 31(7) (a) of the Act. The

parties can agree to waive or restrict the interest and/or rate of interest on the

whole or any part of the money or for the whole or any part of the period between

ssm 8 arbp325.08.sxw

the date on which the cause of action arose and the date on which the award was

made or intent on the award amount. There is no bar for such agreement.

Therefore, if the parties in the present facts and circumstances of the case, agreed

as recorded above, they are not entitled for any interest on the amount of award.

There is no question of granting even 12% p.a. interest as awarded on the

awarded amount.

9 The arbitrator, in view of clause (b) of Sub-Section (7) of Section 31 of the

Act, in absence of otherwise agreed clause and if there is no bar, can award

interest up to the rate of 18% p.a.. The words in Section 31(7) (b) "unless the

award otherwise directs" are supports the agreed clause and in view of Section 28

(3) of the Act also, therefore, the arbitrator has no power to award any future

interest, from the date of the award. It is specifically permitted and/or

permissible under the Act itself, specially in view of rider of Section 31 (7) so

reproduced above. Therefore, if such contract/ agreement permits the parties not

to claim interest on the awarded amount, in my view, such debar clause ought not

have been overlooked by the arbitrator. The submission that the other part of

Section 31(7) (a) and (b) if read in isolation then the power of arbitrator to

award such interest is permissible as per the judgment of the Apex Court as

referred above, Sayyed Ahmed and Company (Supra), is unacceptable. Sections

31 (7) (a) & (b) and 28(3) need to read together. There is no question of reading

the same in isolation.



    10      In  Sayyed Ahmed and Company (Supra), there was no such clause for 





     ssm                                              9                                   arbp325.08.sxw


consideration. The question is the power and jurisdiction of the arbitrator to

award interest for the three periods viz. pre-reference period, pendent lite and

future period from the date of the award, but it is only when there is no express

bar in the contract regarding the award of interest. It is observed by the Apex

Court, in Sayyed Ahmed and Company (Supra).

"10. Ultimately, this Court made it clear that the arbitrator had the jurisdiction and authority to award interest for the three periods, namely, pre-reference period, pendente lite and future

period (from the date of award) if there was no express bar in the contract regarding award of interest - vide Irrigation

Deptt. Govt. of Orissa V. G.C. Roy, (1992) 1 SCC 508, Executive Engineer, Dhenkanal Minor Irrigation Division Vs. N.C. Budharaj, (2001) 2 SCC 721, as also the decision in Bhagawati Oxygen Ltd. Vs. Hindustan Copper Ltd., (2005) 6

SCC 462."

(Emphasis added)

11 The points relating to interest have been further summarized in State of

Rajasthan V. Ferro Concrete Construction (P) Ltd., (2009) 12 SCC 1, in the

following words.:-

(a) Where a provision for interest is made on any debt or damages, in any agreement, interest shall be paid in accordance with such agreement.

(b) Where payment of interest on any debt or damages is barred by express provision in the contract, no interest shall be awarded.

(c) Where there is no express bar in the contract and where there is also no provision for payment of interest then the principles of Section 3 of the Interest Act will apply and consequently interest will be payable;

(i) where the proceedings relate to a debt (ascertained

ssm 10 arbp325.08.sxw

sum) payable by virtue of a written instrument at a certain time, then from the date when the debt is

payable to the date of institution of the proceedings;

(ii) where the proceedings is for recovery of damages or for

recovery of a debt which is not payable at a certain time, then from the date mentioned in a written notice given by the person making a claim to the person liable for the claim that interest will be claimed.

(d) Payment of interest pendente lite and future interest shall not be governed by the provisions of the Interest Act, 1978, but by the provisions of Section 34 of the Code of Civil Procedure, 1908 or the provisions of law governing arbitration as the

case may be."

                                  ig                         (Emphasis added)
                                
    12     In the present case, the clause is comprehensive and bars interest on the 

awarded amount. Clause G1.09 in [Sayyed Ahmed (Supra)] bars interest under

any head in clear and categorical terms on the money or balance lying with the

Government or due and payable owing to any dispute or delay on the part of

Engineer in making payment and in other respect whatsoever. Those facts and

circumstance based upon the agreed terms in question, therefore, are distinct and

distinguishable, as the clauses in question are significantly different. Even

otherwise, the Act provides discretionary powers to the arbitrator to award such

interest. There is no question of exercising discretionary power in view of agreed

clause. The arbitrator, is bound by the agreed clause and he cannot go beyond

the same, in the present facts and circumstances, therefore, there is no question in

awarding any interest on the awarded amount.

13 The importance has already been given to the specific clauses/ agreed

ssm 11 arbp325.08.sxw

clauses of the agreement between the parties. Therefore, in view of the peculiar

clauses in question, I am of the view that the interest so awarded by the arbitrator

is unsustainable and without jurisdiction. The award needs to be set aside to that

extent as the part of the award can be modified and rest of the award can be

maintained, in view of the Full Bench Judgment. [R.S. Jiwani (M/s.), Mumbai

Vs. Ircon International Ltd., Mumbai, 2010 (1) Mh. L.J., 547.]

14 Section 31(7) (a) of the Act begins with a non-obstante clause i.e. "unless

otherwise agreed by the parties". This clause prevails overall other provisions of

interest in all the stages, by the Arbitrator. I am dealing with a specific agreement

clause and therefore, also the power of the Arbitrator to award interest in all the

stages. The obstante clause read with agreed clause govern and regulate the

power of the Arbitrator to grant interest. This non-obstante clause prevails over

the entire scheme of power of the arbitrator to grant interest at all stages.

15 It is made clear that the power of arbitrator to grant interest is regulated by

the agreement between the parties. This is no way control or regulate the power

of the Court to award interest once the award is made final in accordance with

law. This obstante clause and the agreed clause nowhere control the power of the

Court to award future interest or modify the interest rate or period or stage. But,

in view of the Scheme of the Act and specially of Section 28(1) and (31) (7), the

Court needs to consider the agreed clause between the parties while making the

award final and binding.

     ssm                                              12                                 arbp325.08.sxw


    16      "Such non-obstante clause needs to be interpreted widely to cover Section 




                                                                                              

31(7) (a) and (b) together. The provisions and the power to award interest is not

mandatory, but it is discretionary. The Arbitral Tribunal needs to exercise that

discretion judicially. The Tribunal should normally exercise its power to award

interest, but subject to overriding contractual right to interest, if any. The right to

interest, therefore, is subject to contract/agreement between the parties, which

they are permitted and free to execute or agree under the Act itself. Such

agreement shall have precedence over the default provision of Section 31(7)(a)

and (b) of the Act. There is no conflict between the power of Arbitrator to

award interest and a contractual right to claim particular rate of interest and/or

from the particular period and/or to waive or debar from claiming any interest on

any amount even at all stages to the rate of interest under the Act.

17 As noted, Section 31(7) (a) begins with a non-obstante clause as referred

above. This clause, in my view, govern Section 31(7)(a) & (b) both. As the

parties are free to agree on the power of the Tribunal in respect of the award of

interest, such power cannot be restricted only to Section 31(7) (a), the provision

permit, in my view, the parties to agree on the powers of the Tribunal in regard to

the award of interest for Section 31(7)( (b) also. In the present case, as noted

above, the parties agreed accordingly covering Section 31(7) (a) and (b) both.

This contractual agreement restricting the interest is well within the frame work

of law and there is no conflict of such contractual right with Section 31(7) (a) and

(b). The freedom to enter into such type of agreement with regard to the interest

is well within the UNCITRAL Model Law and Rules, scheme and recognised power

ssm 13 arbp325.08.sxw

even under Section 49(1) of the English Arbitration Act, 1996.

18 The object of awarding post/future-interest is always to get the awarded

amount as early as possible and/or to avoid delay in making payment towards the

awarded amount specially when the Award attains finality. The respondents

and/or a party against whom Award is passed may delay the proceeding and/or

payment. Once the Award is final and/or attains finality as per the provisions of

the Act, the Court in a given facts and circumstances, in spite of above clauses

may pass or award and/or grant future or post-award interest for early recovery of

the amount so awarded and/or protect the interest of the party in whose favour

award is passed or the future loss as he may not be in a position to utilise

awarded amount from the date of confirmation and/or final award till the

execution and/or realization of the same.

19 Another challenge was raised with regard to the claim at Serial No.7

towards the operation and maintenance charges while the vessel was waiting for

instructions from ONGC. Item No. VI, Clause 12 of the agreement provides open

ended time for revamping 60% compensation for the same. The Petitioner

deducted 40% operation and maintenance charges though the vessel was waiting

for revamping and was non-operational during 104 days, but 60% of the daily

rate was paid. The claim, therefore, was raised for unpaid balance. There is a

material on record, as observed by the learned Arbitral Tribunal that during 104

days, the said vessel with complete crew on board was waiting for finalization of

the tender and the award of the contract for revamping. The Respondent

ssm 14 arbp325.08.sxw

themselves on their own could not have kept the fully ready and manned vessel

for such period. For want of instructions, the Respondent could not have even

moved the vessel to the revamping yard. The learned Tribunal, in my view, rightly

considered the word "revamping" to include waiting for instructions of

revamping. Clause 12 of the agreement (down time) provides that the master

and crew of the vessel as well as the base staff are to be fully involved in the

revamping of the vessel. Having once entered into the contract in question and

compel other parties to keep everything ready and involved, subject to

instructions and as they could not proceed with, the submission that it no way

covers waiting for revamping, as rightly rejected by the Tribunal. The Petitioner

denied the claims of the Respondent only because of their own inaction as they

unable to give instructions and/or finalize the contract within the reasonable time

and kept the fully manned vessel waiting. The Petitioner cannot claim benefit of

their own wrong. It is not the case that the Respondent were not ready and fully

and/or failed to complete their steps within the time prescribed. In such type of

contract, it is expected that both the parties will complete and perform their part

within reasonable time. When time period is prescribed, it is always with the

clear understanding that both the parties will act within the framework of it.

Therefore, on the basis of undisputed position on record, and as the Petitioner

caused waiting, they cannot deny the right of the payment so claimed by the

Respondent for keeping the vessel ready and the crew involved. In my view also,

the reasoning so given is well within the purview of law and cannot be stated to

be absurd or beyond the overall scope of the contract. The interpretation so given

by the Tribunal to the clause, in the facts and circumstances, is possible and

ssm 15 arbp325.08.sxw

reasonable and therefore, needs no interference.

20 The Tribunal has further rightly observed referring to clause 5.1 of the

agreement that the vessel was not expected to operate offshore but waited for to

be moved to the revamping yard. Therefore, submission with regard to the class

certificate in no way sufficient to discard the claims so raised by the Respondent.

There was no question of operation with all certificates and clearances as rightly

observed. There is a clear finding given that the vessel was operational for the

purpose of carrying itself for revamping and participating for revamping.

Therefore, costs so incurred during this waiting period, need to be compensated

and has rightly awarded by the Arbitral Tribunal. In all, considering the facts and

circumstances and the agreement clauses between the parties, the view so taken,

cannot be stated to be unjust, perverse or contrary to law.

21 Another submission was raised that no proper and previous approval was

taken for various repairs and replacements which were not listed in HOTO and/or

without giving list and estimation of the same for approval. The learned Tribunal

after considering Section 70 of the Contract Act and considering the nature of

contract between the parties and as it was for to carry out repairs and

replacements of the vessel and as the fact of repairs or replacements and the

materials so used were not denied, the Petitioner cannot deny the claims of the

Respondent so raised; and as it was done without any objections and as it was

necessary to repair and replace the same under the contract. The learned Tribunal

has rightly granted claims on the principle "where the person for whom the act

ssm 16 arbp325.08.sxw

was done accepted and enjoyed the benefits although there was no request for the

act on his part" which in the present case, is not in dispute. The submission that

the work was not in the list of HOTO and therefore, was not under the contract, in

the facts and circumstances, therefore, not acceptable, in view of the claim Nos.

1,4,5,6 and 8 specially, when other claim Nos. 2,3 and 7 were duly proved.

22 There are various facets of costs of the proceedings, which may include

"cost of the reference", "cost of the arbitration proceeding", "cost of the parties".

The parties in the present case agreed to share the cost of the arbitration. The

Arbitral Tribunal, in the present case, considering the facts and circumstances of

the case, awarded the cost of Rs.5,00,000/- (Rupees five lacs) in favour of the

winning party and against the losing party. Such grant of award is well within the

frame work of law even as per Section 31 (8) of the Act. Such after event award

of cost cannot be equated with the arbitration costs which the parties have agreed

to share equally; they must have incurred and shared already till the date of the

award. The lump sum amount so awarded towards the costs, therefore, needs no

interference. To award the costs, is entirely in the discretion of the Court, so also

the tribunal. It cannot be claimed as a matter of right. The cost awarded by the

Court while awarding the claim in favour of winning party cannot be shared

equally with the loosing party based upon the agreement in question. The share

of costs of Arbitration as per clause 22.5 has nothing to do with the present costs

so awarded. This was in addition to the expenses and/or costs of the Arbitration

which party agreed to share equally. No other challenge raised.

     ssm                                           17                                  arbp325.08.sxw


    23    I have observed in Jigar Vikamsey Vs. Bombay Stock Exchange Limited,  




                                                                                            

[2010(1) Bom. C.R. 908], considering the various judgments of the Supreme

Court revolving around Section 34 of the Act as under:-

"11 The Petition is under Section 34 of the Act. The Apex Court

recently in G. Ramchandra Reddy & Company v. Unin of India &

anr., (2009) 6 SCC 414 and in Madhya Pradesh Housing Board v.

Progressive Writers and Publishers, (2009) 5 SCC 678, while

dealing with both the Arbitration Acts and considering the principles

to challenge the Arbitral Award has re-iterated the following points :

(a) The re-appraisal of the evidence by the Court is not

permissible (Ispat Engineer Foundary Works vs. Steel Authority of

India, (2001) 6 SCC 347). An Award of an Arbitrator need to be

read as a whole to find out the implication and meaning thereof of

the reasons. The Court, however, does not sit in Appeal over the

Award.

(b) The interference, where reasons are given would still be less,

unless there exists a total perversity and/or the Award is based on a

wrong proposition of law.

(c) Even if two views are possible on an interpretation of central

clause, that would not be justification in interfering with the Award

specially when the view so taken is possible/plausible one (Sudarshan

Trading v. Allied Construction (2003) 7 SCC 396). [ G.

          Ramchandran   (Supra)   ]      But   the   interpretation   of   the   clause  





     ssm                                           18                                  arbp325.08.sxw


which is wholly contrary to law should not be upheld by the Court.

[Numaligarh Refinery Ltd v. Daehim Industrial Co. Ltd., 2007(10)

SCALE 577/(2007) 8 SCC 466 ]

(d) The jurisdiction of the Court to interfere with an Award made

by an Arbitrator is limited, unless there is an error apparent on the

face of the Award and/or jurisdictional error and/or legal mis-

conduct. [ Numaligarh Refinery Ltd (supra).

(e) The wrong point of law and apparent, improper and incorrect

findings of facts which are demonstratable on the face of the material

on record, may be treated as grave error and/or legal misconduct.

(g) "From the above decisions, the following principles emerge:

          (a)     An award, which is
        

          (i)     contrary to substantive provisions of law; or
     



          (ii)    the provisions of the Arbitration and Conciliation Act, 1996; 

          or 

(iii) against the terms of the respective contract; or

(iv) patently illegal; or

(v) prejudicial to the rights of the parties;

is open to interference by the court under Section 34(2) of the Act.

(b) The award could be set aside if it is contrary to :

          (a)     fundamental policy of Indian law; or

          (b)     the interest of India; or

          (c)     justice or morality.




     ssm                                                19                                     arbp325.08.sxw


           (c)       The   award   could   also   be   set   aside   if   it   is   so   unfair   and  




                                                                                                    

unreasonable that it shocks the conscience of the court.

(d) It is open to the court to consider whether the award is

against the specific terms of contract and if so, interfere with it on

the ground that it is patently illegal and opposed to the public policy

of India." [ Delhi Devedlopment Authority vs. R.S.Sharma & Co.-

(2008) 13 SCC 80 ].

In view of above settled principles of law, the judgments cited by

the parties in support of their respective submission on law need

no further discussion. The facts are totally distinct and

distinguishable."

24 In view of above itself, I am interfering and modifying so far as the order of

interest on the awarded amount till realization by the arbitral tribunal in

following words:-

The petitioner to pay 18% interest from the date, the award has attained

finality, till the realization of same, if the Petitioner fails to make the payment

from the date of final order under the Act.

    25         The rest of the award is maintained.



    26         The arbitration petition is partly allowed and disposed of accordingly.  No 

    costs.  

                                                                  (ANOOP V. MOHTA, J.)





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter