Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Siemens Ltd. & Anr vs Mumbai Railway Vikas Corporation ...
2010 Latest Caselaw 255 Bom

Citation : 2010 Latest Caselaw 255 Bom
Judgement Date : 7 December, 2010

Bombay High Court
Siemens Ltd. & Anr vs Mumbai Railway Vikas Corporation ... on 7 December, 2010
Bench: Dr. D.Y. Chandrachud, Anoop V.Mohta
                                                  1                            wpl-2449-10.sxw


    dgm




                                                                                       
                  IN THE  HIGH COURT OF JUDICATURE AT BOMBAY

                       ORDINARY ORIGINAL CIVIL JURISDICTION




                                                               
                           WRIT PETITION  NO. 2449  OF 2010




                                                              
    1  Siemens Ltd. & anr.                                              ....   Petitioners
          vs
    1  Mumbai Railway Vikas Corporation Ltd. & anr.                     ....    Respondents




                                                 
                                
    Mr.   Aspi   Chinoy,   Sr.   Advocate   with   Mr.   V.   R.   Dhond   with   Mr.   Shailesh 
    Mendon with Mr. Shahezdad Kazi i/by Negandhi Shah & Himayatullah for 
    the petitioners.
                               
    Mr.   Nitin   Thakkar,   Sr.   Advocate   with   Ms.   Usha   Srivastava   i/by   Consulta 
    Juris for respondent no.1. 

    Mr. Suresh Kumar with Mr. Deepak Rai for respondent no.2. 
          
       



                                                   CORAM: DR. D.Y. CHANDRACHUD &
                                                                 ANOOP V. MOHTA, JJ.

DATE : December 07, 2010

ORAL JUDGMENT (Per Dr. D. Y. Chandrachud, J.):

Leave to amend in terms of the draft amendment tendered is granted.

Amendment be carried out during the course of the day.

2 MUTP-II is a project aided by the World Bank and is being

implemented by the First Respondent. The First Respondent floated a

tender for the supply of 72 trains, each of 12 coaches. The bids are to be

opened this morning. The First Petitioner has not been permitted to bid in

2 wpl-2449-10.sxw

view of a settlement that was entered into by the First Petitioner with the

World Bank under which the First Petitioner agreed to voluntarily desist

from bidding for any World Bank aided project, across the world, for a

period of two years and to make a financial commitment of US Dollars 100

million over fifteen years to support anti-corruption work. This followed,

what the World Bank described as the Petitioner's, "acknowledged past

mis-conduct in its global business and a World Bank investigation into

corruption in a project in Russia involving a Siemens subsidiary". The

decision of the World Bank was communicated to the Union Ministry of

Finance which, in turn, informed the First Respondent of the debarment by

a letter dated 24 August 2009.

3 The position as it exists is that the First Petitioner is debarred from

bidding for the project in question. Tenders have been invited under the

MUTP-II project of the First Respondent, which is entirely aided and

financed by the World Bank. The First Respondent is, therefore, obligated

not to entertain a bid of a bidder who is precluded from bidding until 31

December 2010. These facts are adverted to in a World Bank letter dated

31 July 2009 to the Joint Secretary in the Department of Economic Affairs,

Union Ministry of Finance of the Government of India.

4 The Petitioners seek to challenge a communication of the First

Respondent dated 3 June 2010 stating that under the guidelines issued by

the Union Ministry of Finance and the World Bank, the bid documents for

3 wpl-2449-10.sxw

this bid could not be issued to the First Petitioner. The First Respondent

had sought a clarification from the World Bank by a letter dated 11

November 2010. The World Bank informed the First Respondent by its

letter dated 15 November 2010 that it had nothing further to add. On 18

November 2010 the World Bank responded to a representation by the

Petitioner and found no reason to make an exception from the voluntary

restraint imposed under the settlement agreement. The World Bank, in its

letter to the Petitioner furnished the following reasons for not making an

exception:

"While we recognize the potential benefits that may accrue to the borrower and the project if Siemens were allowed to bid, in our view, it has not been established that the loss of those potential benefits would constitute `disproportionate harm' to the borrower, as required by the settlement

agreement. We would note, among other things, that there are a number of other potential bidders that have expressed

interest in the tender, so that the borrower has not been deprived of a competitive process, nor is there any indication from the borrower itself that Siemens' absence from the bidding would have a material adverse effect on project

implementation. Indeed, our borrower has not communicated any concern to us in connection with this tender or Siemens' participation, which we would view as a sine qua non for any exception. We are also conscious of the precedent that an exception would create for future bidding as the voluntary

restraint period draws to a close."

The World Bank stated that the question as to whether the deadline for the

bid should be extended is a matter for the borrower to decide. The First

Respondent has declined to extend the deadline for the submission of bids.

                                                     4                             wpl-2449-10.sxw


    5      Counsel for the Petitioners has adverted to the averments made in 




                                                                                          

paragraph 19 of the Petition and submitted that there is an element of

public interest involved in extending the time for the submission of bids.

Among the factors to which a reference has been made is that (i) the

Petitioner has successfully completed three years of project experience, in

integrating over the Chassis, IGBT traction EMU units on trains; (ii) the

Petitioner already has two dedicated units at Kalwa and Nashik which no

other competitor possesses for manufacturing the equipment/trains for

which tenders have been invited; (iii) other bidders would either have to

set up a new facility or to incur import costs; (iv) the bid submitted by the

Petitioner in an earlier tender was substantially lower, envisaging a saving

of nearly Rs.120 crores and (v) the petitioner is in a position to supply the

final product within twelve to fourteen months.

6 The only relief that has been sought in these proceedings, at the

hearing,is that this Court should direct the First Respondent to extend the

dead line for the submission of bids to a date beyond 31 December 2010, in

order to facilitate the Petitioner to submit a bid. The jurisdiction under

Article 226 of the Constitution of India is invoked on the ground that

having regard to the experience and the past performance of the Petitioner

it is in the public interest to extend the deadline for submission of bids. That is

the only relief which Learned Senior Counsel pressed at the hearing.

    7      We have already noted the circumstance that the MUTP-II   project 





                                                   5                             wpl-2449-10.sxw


under which bids have been invited is entirely funded by the World Bank.

The Petitioner is under a voluntary agreement of restraint not to bid for any

project financed by the World Bank globally until 31 December 2010. The

World Bank, while evaluating a representation submitted by the Petitioner

noted that it was unable to come to a conclusion that the First Respondent

would suffer disproportionate harm by excluding the Petitioner from the

bidding process. That was on the basis of several other potential bidders

having expressed interest in the tender and that the First Respondent

would not be deprived of a competitive process. The World Bank was of the

view that the exclusion of the Petitioner would not have a material adverse

effect on the implementation of the project. These are of course

observations of the World Bank and by no means conclude the Court on the

question as to whether it is in the public interest to grant relief in terms

prayed for extending the deadline for submission of bids. The views of

the World Bank do not bind the Court, particularly when it is exercising its

jurisdiction under Article 226 of the Constitution of India.

8 During the course of the hearing, counsel on behalf of the First

Respondent, on a query by the Court, stated that four bidders have

submitted their bids by the dead line which expired at 11 am this morning.

These bidders are (i) M/s.Alstom, Transport SA, France in joint venture

with BHEL, (ii) Sumitomo Corporation of Japan in joint venture with

Mitsubishi, (iii) M/s.Zhuzhou CSR Times Electric Co.Ltd., China and (iv)

6 wpl-2449-10.sxw

Bombardier, Germany. We have allowed the statement which has been

placed by the counsel for the First Respondent to be taken on record.

These facts would indicate that a competitive process of bidding has not

suffered as a result of the exclusion of the Petitioner. Whether, as a matter

of fact, the bids that have been received by the First Respondent meet the

technical criteria and if so, whether they are commercially viable is a

matter which is to be evaluated in the public interest by the First

Respondent. The relief that is sought in these proceedings is fairly

exceptional because a bidder who is admittedly not entitled to bid until 31

December 2010 seeks a direction from the Court compelling the bid inviting

authority to extend the deadline for the submission of bids. Ordinarily

the Court would not exercise the jurisdiction under Article 226 to grant

relief of this nature. On the basis of material on the record, we are of the

view that no case has been made out for an order of the Court for the

extension of time to submit bids. Several bidders, including among them,

those with a global presence are involved in the bidding process. There is

no justification for the Court to direct the extension of the time prescribed

for submitting bids, if only to enable a party which is not qualified to bid at

this time to bid at a future date. Besides any such direction will only delay

the implementation of a public project. The Petitioner has not questioned,

in the submissions at the hearing, the ground for its debarment under what

is described as a settlement on voluntary restraint.

                                                 7                           wpl-2449-10.sxw


    9          For these reasons, we decline to entertain the petition.     The Petition 




                                                                                    
    is dismissed.  There shall be no order as to costs. 




                                                            
            


               (ANOOP V. MOHTA, J.)                   ( DR.D.Y. CHANDRACHUD,J.)




                                                           
                                               
                                
                               
          
       







 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter